A jig to prevent concrete cores from falling, and a method for forming through holes in a floor slab.
The concrete core fall prevention jig with a diameter-expanding member efficiently supports and recovers concrete cores during through-hole formation, addressing inefficiencies in existing devices by providing stable and quick recovery in narrow spaces.
Patent Information
- Application Number
- JP2022122808
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2022-08-01
- Publication Date
- 2026-08-25
- Estimated Expiration
- 2042-08-01
AI Technical Summary
Existing concrete core fall prevention devices require time-consuming steps like embedding anchors and connecting means, making them inefficient for preventing concrete cores from falling during through-hole formation in existing structures, especially in narrow spaces.
A concrete core fall prevention jig with a rotatably attached expanding member that changes diameter positions, allowing it to support and recover concrete cores by expanding below the slab, and multiple expanding members at different heights for stable support.
Efficiently prevents concrete cores from falling into inaccessible spaces by supporting and recovering them, even in narrow areas, facilitating quick and stable recovery.
Smart Images

Figure 0007910842000001 
Figure 0007910842000002 
Figure 0007910842000003
Abstract
Description
Technical Field
[0001] The present invention relates to a concrete core fall prevention tool and a method for forming through holes in a floor slab.
Background Art
[0002] There are cases where ground improvement is carried out under an existing structure existing in a river, sea area, ground below the groundwater level, etc. (in this specification, these areas are collectively referred to as "water areas"). For example, in a box culvert that forms a main line for taking in and flowing rainwater and sewage, when a new structure is constructed above the box culvert, it is necessary to enhance the ground strength under the box culvert. Therefore, ground improvement will be constructed under the box culvert while supplying the main lines of rainwater and sewage. When constructing ground improvement under an existing structure in such a water area, when the width of the existing structure is long, there is a limit to the method of inserting the improvement rod obliquely from the side of the existing structure, and there is a risk of an area that cannot be improved. Therefore, a construction can be carried out in which through holes are formed in the upper floor slab and the lower floor slab constituting the existing structure, and the improvement rod is inserted into the ground under the existing structure through each through hole to perform ground improvement.
[0003] In this construction method, since it is ground improvement under an existing structure in a water area, when through holes are formed in the upper floor slab and the lower floor slab of the existing structure, it is important to take water stop measures to prevent groundwater from entering the main line or, conversely, to prevent sewage, etc. from leaking into the ground. However, for example, if there is a space for flowing sewage, rainwater, etc. in the existing structure, and this space is below the floor slab in which the through hole is formed and is a narrow space where people cannot enter, when the concrete core generated when the through hole is formed falls into this narrow space, the fallen concrete core cannot be recovered, and there is a problem that the concrete core that has fallen into the rain main line, sewage main line, etc. remains.
[0004] Here, Patent Document 1 proposes a concrete fall prevention device for a core drill that drills holes in concrete using a cylindrical core bit, which prevents the drilled concrete from falling when drilling. Specifically, it comprises a concrete anchor embedded in the concrete at an appropriate location and positioned inside the core bit when the concrete is drilled by the core bit, and a connecting means positioned inside the core bit that connects the upper wall of the core bit to the concrete anchor. After drilling the concrete, the concrete is suspended by the connecting means and the concrete anchor to prevent it from falling. [Prior art documents] [Patent Documents]
[0005] [Patent Document 1] Japanese Patent Application Publication No. 11-320548 [Overview of the project] [Problems that the invention aims to solve]
[0006] According to the concrete fall prevention device for a core drill described in Patent Document 1, it is possible to prevent concrete from falling after drilling. However, this device requires the step of embedding a concrete anchor in the appropriate place in the concrete prior to drilling with the core bit, and further requires the step of connecting the upper wall of the core bit and the concrete anchor with a connecting means placed inside the core bit. Therefore, it is an undesirable fall prevention measure as it is time-consuming.
[0007] The present invention aims to provide a concrete core fall prevention jig and a method for forming through holes in a floor slab, which can efficiently prevent the fall of concrete cores generated during the formation of through holes when sealing through holes in the floor slab of an existing structure. [Means for solving the problem]
[0008] To achieve the above objective, one embodiment of the concrete core fall prevention jig according to the present invention is: A concrete core fall prevention jig for supporting and recovering concrete cores generated when a through-hole is formed by drilling through a concrete slab that forms an existing concrete structure using a drilling rod, Rods and, The rod material is rotatably attached to the aforementioned rod material and has an expanding member that changes its position between a reduced diameter position and an expanded diameter position, When the fall prevention jig is inserted into a relatively small diameter pre-hole formed in the floor slab prior to the formation of the through-hole, the diameter-expanding member is in a reduced-diameter position, and changes its position to an expanded-diameter position when the diameter-expanding member protrudes below the floor slab. The formed concrete core is supported by the diameter-enlarging member in an enlarged diameter position.
[0009] According to this embodiment, when a through-hole is formed in the floor slab, the concrete core generated is supported by a fall prevention jig, and by lifting the fall prevention jig, the concrete core can be recovered above the existing structure, thereby efficiently preventing the concrete core from falling into the interior of the existing structure. Therefore, even if there is a narrow space below the floor slab that is inaccessible to people, it becomes possible to recover the concrete core generated when a through-hole is formed without dropping it into this narrow space. In this fall prevention jig, an expanding member is rotatably attached to a rod, and the expanding member changes its position between a contracted position and an expanded position. When the fall prevention jig is inserted through a relatively small diameter pre-hole formed in the floor slab prior to the formation of the through-hole, the expanding member is in the contracted position, and when the expanding member extends below the floor slab, the expanding member changes its position to the expanded position. This makes it possible to insert the fall prevention jig through the smallest possible pre-hole while supporting a concrete core that is larger than the hollow space of the pre-hole with the fall prevention jig.
[0010] Furthermore, in another embodiment of the bottom cover for closing through holes in a floor slab according to the present invention, The aforementioned diameter-expanding member is characterized in that it is biased from the rod member via an elastic material to assume an expanded diameter position.
[0011] According to this embodiment, since the diameter-expanding member is biased from the rod member to an expanded position via an elastic member, when the diameter-expanding member extends below the floor slab, the diameter-expanding member can be quickly changed to an expanded position.
[0012] Furthermore, another embodiment of the bottom cover for closing through holes in the floor slab according to the present invention is: The invention is characterized in that multiple diameter-enlarging members are rotatably attached to the same height position on the aforementioned rod.
[0013] According to this embodiment, by rotatably attaching multiple diameter-expanding members to the same height position on the rod, it becomes possible to stably support the falling concrete core with multiple diameter-expanding members. For example, this can be done by providing two diameter-expanding members at diagonal positions (180 degrees apart) on the rod, three diameter-expanding members at 120-degree intervals, or four diameter-expanding members at 90-degree intervals.
[0014] Furthermore, another embodiment of the bottom cover for closing through holes in the floor slab according to the present invention is: The aforementioned rod material is characterized in that multiple enlarged diameter members are rotatably attached at multiple height positions of the rod material.
[0015] According to this embodiment, since multiple diameter-expanding members are rotatably attached at multiple height positions on the rod, for example, if the multiple diameter-expanding members in the upper section malfunction and do not expand, the multiple diameter-expanding members in the lower section will expand and be able to support the falling concrete core.
[0016] Furthermore, one embodiment of the method for forming through holes in a floor slab according to the present invention is: A method for forming through-holes in a concrete slab, comprising drilling through the slab to form an existing concrete structure using a drilling rod, Rods and, Prepare a fall prevention jig having an expanding member that is rotatably attached to the bar and changes its posture between a reduced-diameter posture and an expanded-diameter posture in a preparation step. In a prior guide hole forming step, a prior guide hole having a relatively small diameter compared to the through hole formed in a subsequent step is formed at a position where the through hole is formed in the floor slab. With respect to the prior guide hole, insert the fall prevention jig with the expanding member in a reduced-diameter posture, change the posture to an expanded-diameter posture when the expanding member protrudes below the floor slab, and support the concrete core generated when the floor slab is drilled through to form a through hole with the expanding member located below, and pull up and recover the concrete core through the through hole. It is characterized by having a through hole forming step.
[0017] According to this aspect, when forming a through hole in the floor slab, the concrete core generated is supported by the fall prevention jig, and the fall prevention jig is pulled up to recover the concrete core above the existing structure, thereby efficiently preventing the concrete core from falling inside the existing structure. Therefore, even when there is a narrow space where people cannot enter below the floor slab, it is possible to recover the concrete core generated when forming the through hole without dropping it into this narrow space.
Advantages of the Invention
[0018] According to the concrete core fall prevention jig of the present invention and the method for forming a through hole in the floor slab, when closing the through hole in the floor slab of an existing structure, the fall of the concrete core generated during the formation of the through hole can be efficiently prevented.
Brief Description of the Drawings
[0019] [Figure 1] It is a diagram showing an example of an existing structure in a water area to which a ground improvement method under an existing structure is applied. [Figure 2] It is a process diagram of an example of a ground improvement method under an existing structure. [Figure 3] Following FIG. 2, it is a process diagram of an example of a ground improvement method under an existing structure. [Figure 4] Following Figure 3, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 5] Following Figure 4, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 6] This figure illustrates a fall prevention jig according to an embodiment and an example of a method for forming a through-hole in a floor slab, showing both the state in which the fall prevention jig passes through the through-hole and the state in which it protrudes from the through-hole. [Figure 7] Following Figure 5, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 8] Following Figure 7, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 9] Following Figure 8, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 10] Following Figure 9, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 11] Following Figure 10, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 12] Following Figure 11, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 13] Following Figure 12, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 14] Following Figure 13, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 15] Following Figure 14, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 16] Following Figure 15, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 17] Following Figure 16, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 18] Following Figure 17, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 19A] This is a perspective view of an example of a bottom cover that closes a through-hole in a floor slab. [Figure 19B]This diagram shows both the state in which the bottom cover passes through the through hole and the state in which it is in close contact with the underside of the floor slab. [Figure 20] Following Figure 18, this is a process diagram illustrating an example of a ground improvement method for existing structures. [Figure 21A] This is a process diagram explaining the test construction. [Figure 21B] Following Figure 21A, this is a process diagram explaining the test construction. [Figure 21C] Following Figure 21B, this is a process diagram explaining the test construction. [Figure 21D] Following Figure 21C, this is a process diagram explaining the test construction. [Figure 21E] Following Figure 21D, this is a process diagram explaining the test construction. [Figure 21F] Following Figure 21E, this is a process diagram explaining the test construction. [Figure 21G] Following Figure 21F, this is a process diagram explaining the test construction. [Figure 21H] Following Figure 21G, this is a process diagram explaining the test construction. [Modes for carrying out the invention]
[0020] The concrete core fall prevention jig and the method for forming through holes in the floor slab, according to the embodiment, will be described below with reference to the attached drawings. In this specification and drawings, substantially identical components may be denoted by the same reference numerals to avoid redundant explanations.
[0021] [Method for improving the ground beneath an existing structure, a jig for preventing the fall of concrete cores according to the embodiment, and a method for forming through holes in a floor slab] Referring to Figures 1 to 20, an example of a ground improvement method beneath an existing structure will be described, and within this, referring to Figure 6, an example of a concrete core fall prevention jig and a method for forming through holes in a floor slab according to the embodiment will be described. Here, Figure 1 is a diagram showing an example of an existing structure located in a body of water to which the ground improvement method beneath the existing structure is applied, and Figures 2 to 5, 7 to 18, and 20 are, in order, process diagrams of an example of the ground improvement method beneath the existing structure. Furthermore, Figure 6 is a diagram illustrating an example of a fall prevention jig according to the embodiment and a method for forming a through-hole in the deck slab, showing both the state in which the fall prevention jig passes through the through-hole and the state in which it protrudes from the through-hole. In addition, Figure 19A is a perspective view of an example of a bottom cover that closes the through-hole in the deck slab, and Figure 19B shows both the state in which the bottom cover passes through the through-hole and the state in which it is in close contact with the underside of the deck slab.
[0022] The existing structure C, which is the target of the ground improvement work shown in Figure 1, is a linear, reinforced concrete box culvert embedded in the ground G beneath the riverbed. This box culvert C has an upper slab S1 (an example of a slab), a lower slab S3, and left and right side walls W1, and has a partition wall W2 inside, with an intermediate slab S2 further located in the area to the right of the partition wall W2.
[0023] The space (hollow) between the upper slab S1 and the middle slab S2 is the sewer main space C1, the space between the middle slab S2 and the lower slab S3 is the management space C2, and the space in the left region of the partition wall W2 is the rainwater main space C3.
[0024] Furthermore, the sewer main space C1 is a narrow space inaccessible to people, and sewer water flows through it at all times. On the other hand, the management space C2 is accessible to administrators and is used for managing the sewer and rainwater main lines. The method for performing ground improvement on the ground G1 below this box culvert C will be explained below.
[0025] In detail, the ground G1 below the rainwater main space C3 and the ground below the management space C2 will be improved separately, but the following explanation will focus on the method of improving the ground G1 below the management space C2. The ground improvement of the ground G1 below the rainwater main space C3 will be carried out using substantially the same method. Note that the existing structure whose ground below is subject to improvement is not limited to the box culvert shown in the illustration, but can include various concrete structures. In addition, the body of water where the ground to be constructed is located may be a river as shown in the illustration, or it may be a sea area. Furthermore, the existing structure may be an underwater structure that protrudes into the water, and the ground below it may be subject to improvement.
[0026] In Figures 2 and beyond, only the right-hand region of the bulkhead W2 under construction is shown. Furthermore, to facilitate understanding of the drawings, the sewer lines in the sewer main space C1 are omitted from the illustration. Additionally, a work platform exists above the river in the box culvert C. Drilling equipment such as boring machines are installed on this work platform to perform rotary press-in of the first penetration rod R1, and similarly, ground improvement is carried out using ground improvement equipment installed on the work platform. However, the illustrations of this work platform, drilling equipment, and ground improvement equipment are omitted.
[0027] As shown in Figure 2, the first penetration rod R1 is driven in the X2 direction while rotating in the X1 direction from above the upper slab S1 to a point midway through the thickness of the upper slab S1. As an example, a φ406 mm casing can be applied to the first penetration rod R1.
[0028] By rotating and pressing the first penetration rod R1 into the upper slab S1 to an intermediate position without water and then curing it, a watertight structure (primary watertight structure) is formed between the first penetration rod R1 and the upper slab S1. For example, if the thickness of the upper slab S1 is about 500 mm, the first penetration rod R1 is driven in about 50 mm.
[0029] Next, as shown in Figure 3, non-shrink mortar M1 (an example of a waterproofing material) is filled into the interior of the first penetration rod R1. After filling with non-shrink mortar M1, the first penetration rod R1 is slightly pulled up, causing the non-shrink mortar M1 to spread outward through the penetration groove formed by the first penetration rod R1. Subsequently, by lowering the first penetration rod R1 and returning its tip to the penetration groove, a waterproofing structure (secondary waterproofing structure) is formed, as shown in Figure 3, in which the areas inside and outside the first penetration rod R1 are waterproofed with non-shrink mortar M1.
[0030] In this way, by forming a watertight structure (secondary watertight structure) using non-shrink mortar M1, the intrusion of groundwater into the interior of the first penetration rod R1 can be suppressed in combination with the primary watertight structure described above (the above describes the upper deck penetration process).
[0031] Next, as shown in Figure 4, a relatively small-diameter single pipe P is inserted into the first penetration rod R1 in the X3 direction, and a pilot hole Ha is formed by drilling through the upper deck slab S1.
[0032] As shown in Figure 5, a fall prevention jig 10 is inserted into the pre-hole Ha in the X4 direction, and its lower part is extended out through the pre-hole Ha into the sewer main space C1.
[0033] Here, with reference to Figure 6, the configuration and operation of the fall prevention jig 10 will be explained. The fall prevention jig 10 is a jig that prevents the concrete core CO generated when forming a through hole H1 (the first through hole H1 shown in Figure 7) in the upper floor slab S1 from falling onto the upper surface of the middle floor slab S2.
[0034] The fall prevention jig 10 includes, for example, a metal rod 11 and a plurality of metal diameter-expanding members 15 that are rotatably attached to the rod 11.
[0035] The rod 11 is formed from a hollow pipe, and three storage grooves 11a are provided at the left and right positions along its longitudinal direction. The lower ends of two diameter-expanding members 15 are rotatably mounted on a pivot shaft 13 located inside the rod 11, and each diameter-expanding member 15 is constantly biased to expand relative to the rod 11 via an elastic material 16 such as a coil spring.
[0036] In the illustrated example of the fall prevention jig 10, a pair of diameter-expanding members 15 are rotatably attached to three locations along the longitudinal direction of the rod 11.
[0037] When the fall prevention jig 10 passes through the pre-hole Ha made of the single pipe P, as shown in Figure 6, at least a portion of each enlarged diameter member 15 is housed in the housing groove 11a of the rod member 11, becoming the fall prevention jig 10A in a reduced diameter position, and is inserted through the inside of the single pipe P in the downward direction X4.
[0038] On the other hand, when the lower part of the fall prevention jig 10 extends below the single pipe P (below the upper floor slab S1), the diameter-expanding member 15, which is constantly biased to expand by the elastic material 16, rotates in the X5 direction via the pivot axis 13 and expands outward, and the pair of diameter-expanding members 15 expand to a larger diameter than the preceding guide hole Ha, resulting in the fall prevention jig 10B in an expanded diameter position.
[0039] Thus, when the fall prevention jig 10 is inserted into the preceding guide hole Ha, it is in a reduced diameter position as the fall prevention jig 10A, and when it extends below the upper floor slab S1, it changes its position to an expanded diameter position as the fall prevention jig 10B.
[0040] Here, a pair of diameter-expanding members 15 are rotatably provided at multiple different positions (three in the illustrated example) along the longitudinal direction (height direction) of the rod 11. For example, if the pair of diameter-expanding members 15 at the top malfunction and fail to expand, the pair of diameter-expanding members 15 in the center can expand and support the falling concrete core CO. Also, if the pair of diameter-expanding members 15 in the center are damaged or otherwise fail to expand during use, the pair of diameter-expanding members 15 at the bottom can expand and support the falling concrete core CO.
[0041] In this way, by providing multiple sets of diameter-expanding members 15 rotatably at different height positions on the rod member 11, even if some of the diameter-expanding members 15 malfunction or break, the concrete core CO can be reliably supported by the other sets of diameter-expanding members 15.
[0042] Furthermore, the process of preparing this fall prevention jig 10 is a preparation process (fall prevention jig preparation process), and the process of forming the pre-hole Ha in the upper floor slab S1 is a pre-hole formation process.
[0043] Figure 5 shows the state in which the lower part of the fall prevention jig 10 protrudes into the sewer main space C1, resulting in the fall prevention jig 10B in an expanded diameter position.
[0044] Next, as shown in Figure 7, a first drilling rod R2 (an example of a drilling rod) is placed inside the first penetration rod R1 in the upper slab S1, and the first drilling rod R2 is rotated in the X6 direction while drilling through in the X7 direction. As an example, a φ355 mm casing can be applied to the first drilling rod R2.
[0045] By drilling a first drilling rod R2 through the upper slab S1, a first through-hole H1 is formed in the upper slab S1, and a concrete core CO is generated during the formation of the first through-hole H1. By supporting the generated concrete core CO with an expanded-diameter fall prevention jig 10B, it is possible to prevent the concrete core CO from falling onto the upper surface of the middle slab S2. Thus, the process of forming the first through-hole H1 and supporting and recovering the concrete core CO with the expanded-diameter fall prevention jig 10B constitutes the through-hole formation process.
[0046] As previously mentioned, the sewer main space C1 is a narrow space inaccessible to people, making it impossible to recover the concrete core CO if it falls onto the upper surface of the intermediate slab S2. Thus, the fall prevention jig 10 is effective when forming a through hole in the slab (upper slab S1) above a narrow space inaccessible to people.
[0047] Furthermore, by forming the preliminary guide hole Ha with the smallest possible diameter, the first drilling rod R2 can be positioned between the pipe P forming the preliminary guide hole Ha and the first penetration rod R1 to form the first through hole H1. Even when a pipe P forming a small-diameter preliminary guide hole Ha is used, the fall prevention jig 10 can pass through the inside of the small-diameter pipe P by changing its orientation to a reduced-diameter fall prevention jig 10A (the above describes the upper slab penetration process).
[0048] Next, as shown in Figure 8, the first drilling rod R2 is used as the second penetration rod, and the second penetration rod R2 is driven in the X9 direction while rotating it in the X8 direction from above the subfloor slab S2 to a position midway through the thickness of the subfloor slab S2. Here, as shown in the illustrated example, instead of using the first drilling rod R2 as the second penetration rod, a second penetration rod different from the first drilling rod R2 may be used.
[0049] By rotating and pressing the second penetration rod R2 into the intermediate slab S2 in a waterless state up to an intermediate position and then curing it, a watertight structure (primary watertight structure) is formed between the second penetration rod R2 and the intermediate slab S2. For example, if the thickness of the intermediate slab S2 is about 500 mm, the second penetration rod R2 is driven in about 50 mm.
[0050] Next, as shown in Figure 9, non-shrink mortar M2 (an example of a waterproofing material) is filled into the interior of the second penetration rod R2. After filling with non-shrink mortar M2, the second penetration rod R2 is slightly lifted, causing the non-shrink mortar M2 to spread outward through the penetration groove formed by the second penetration rod R2. Subsequently, by lowering the second penetration rod R2 and returning its tip to the penetration groove, a waterproofing structure (secondary waterproofing structure) is formed, as shown in Figure 9, where the areas inside and outside the second penetration rod R2 are waterproofed with non-shrink mortar M2. Note that since sewage is present in the sewer main space C1, if it is not possible to slightly lift the second penetration rod R2 in this manner, it is not necessary to lift the second penetration rod R2.
[0051] In this way, by forming a watertight structure (secondary watertight structure) using non-shrink mortar M2, the intrusion of sewage into the interior of the second penetration rod R2 can be suppressed in combination with the primary watertight structure described above (the above describes the intermediate floor slab penetration process).
[0052] Next, as shown in Figure 10, a second drilling rod R3 is placed inside the second penetration rod R2 in the subfloor slab S2, and the second drilling rod R3 is rotated in the X10 direction while drilling through in the X11 direction. As an example, a φ318 mm casing can be applied to the second drilling rod R3.
[0053] By drilling through the intermediate slab S2 with the second drilling rod R3, a second through-hole H2 is formed in the intermediate slab S2, and concrete core CO is generated during the formation of the second through-hole H2. The generated concrete core CO falls onto the upper surface of the lower slab S3. However, since the management space C2 is large enough for a person to enter, the fallen concrete core CO can be collected by a worker.
[0054] If it is desired to prevent the concrete core CO from falling, a preliminary guide hole can be formed in the sub-slab S2 before the second drilling rod R3 is drilled through, using the same method as in Figures 4 and 5, and the fall prevention jig 10 can be applied (this completes the sub-slab penetration process).
[0055] Next, as shown in Figure 11, the second drilling rod R3 is used as the third penetration rod and is driven in the X13 direction from above the lower slab S3 to a point midway through the thickness of the lower slab S3 while rotating the third penetration rod R3 in the X12 direction. Here, as shown in the illustrated example, instead of using the second drilling rod R3 as the third penetration rod, a third penetration rod different from the second drilling rod R3 may be used.
[0056] By rotating and pressing the third penetration rod R3 into the lower slab S3 in a waterless state up to an intermediate position and then curing it, a watertight structure (primary watertight structure) is formed between the third penetration rod R3 and the lower slab S3. For example, the third penetration rod R3 is driven in about 50 mm.
[0057] Next, as shown in Figure 12, non-shrink mortar M3 (an example of a waterproofing material) is filled into the interior of the third penetration rod R3. After filling with non-shrink mortar M3, the third penetration rod R3 is slightly pulled up, causing the non-shrink mortar M3 to spread outward through the penetration groove formed by the third penetration rod R3. Subsequently, by lowering the third penetration rod R3 and returning its tip to the penetration groove, a waterproofing structure (secondary waterproofing structure) is formed, as shown in Figure 12, in which the areas inside and outside the third penetration rod R3 are waterproofed with non-shrink mortar M3.
[0058] In this way, by forming a watertight structure (secondary watertight structure) using non-shrink mortar M3, in combination with the primary watertight structure described above, it is possible to prevent groundwater that has seeped in from below the lower slab S3 from entering the management space C2 when a through hole (third through hole) is formed in the lower slab S3 (this concludes the lower slab penetration process).
[0059] Next, as shown in Figure 13, the third drilling rod R4 is positioned inside the third penetration rod R3 in the lower slab S3, and the third drilling rod R4 is rotated in the X14 direction while drilling through in the X15 direction. As an example, a φ267mm casing can be applied to the third drilling rod R4.
[0060] By drilling through the lower slab S3 with the third drilling rod R4, a third through-hole H3 is formed in the lower slab S3. If it is desired to recover the concrete core generated during the formation of the third through-hole H3, a preliminary guide hole can be formed in the lower slab S3 before drilling through with the third drilling rod R4, using the same method as in Figures 4 and 5, and the fall prevention jig 10 can be inserted into the ground G1 below (this concludes the lower slab penetration process).
[0061] By sequentially executing the above steps, the first through-hole H1, the second through-hole H2, and the third through-hole H3 are formed at vertically corresponding positions in the upper slab S1, the middle slab S2, and the lower slab S3.
[0062] Next, a wing bit of, for example, φ250 mm is inserted into the ground G1 below the box culvert C through the first through-hole H1, the second through-hole H2, and the third through-hole H3 from above, and by excavating to the ground improvement depth, an installation hole Hg for installing the improvement rod Ra is created, as shown in Figure 14.
[0063] Next, as shown in Figure 14, while lifting and removing the third drilling rod R4, the improvement rod Ra is inserted in the X16 direction to the installation hole Hg, and the improvement rod Ra is installed at the ground improvement depth. Then, while rotating the improvement rod Ra, a slurry of (ultra) high pressure and (large) flow rate is injected laterally in the X17 direction from its tip, performing a (ultra) large-diameter high-pressure injection mixing method (an example of ground improvement).
[0064] This high-pressure injection mixing method creates, for example, a large-diameter pile ground improvement body GI in the ground G1 below the lower slab S3 in the right-hand region of the bulkhead W2 of the box culvert C, as shown in Figure 15.
[0065] Here, in addition to the illustrated example, other ground improvement methods such as chemical grouting methods that can be used to perform ground improvement by applying the improvement rod Ra may also be applied (ground improvement process).
[0066] After constructing the ground improvement body GI, a φ250mm wing bit or similar is reinserted into the third through-hole H3, and the ground improvement body that has entered the third through-hole H3 is re-drilled to clean the inside of the hole.
[0067] Next, a fiberscope is inserted into the third through-hole H1 to check the construction status of the ground improvement body GI. Then, as shown in Figure 16, the second drilling rod R3 is withdrawn and removed, and non-shrink mortar M4 (an example of a sealing material) is filled into the third through-hole H3 of the lower slab S3. The top cover L1 is then placed on the upper surface of the lower slab S3 to seal the non-shrink mortar M4, and the top cover L1 is fixed to the lower slab S3 with anchor bolts A. Here, although not shown in the illustration, it is desirable to ensure watertightness by interposing a packing between the upper surface of the lower slab S3 and the top cover L1.
[0068] Next, the second through-hole H2 on the underside of the intermediate floor slab S2 is closed with the lower cover L2, and the lower cover L2 is fixed to the intermediate floor slab S2 with anchor bolts A. The lower cover L2 can be attached to the underside of the intermediate floor slab S2 by a worker from inside the management space C2. Here, although not shown in the diagram, it is desirable to ensure watertightness by interposing a packing between the underside of the intermediate floor slab S3 and the lower cover L2.
[0069] Next, as shown in Figure 17, while the first drilling rod R2 is withdrawn and removed, non-shrink mortar M5 (an example of a sealing material) is filled into the second through-hole H2 through the filling hole provided in the lower cover L2, thereby sealing the second through-hole H2.
[0070] Next, when closing the first through-hole H1 of the upper slab S1, workers cannot enter the sewer main space C1 and attach the bottom cover to the underside of the upper slab S1. Therefore, by applying the bottom cover 20 shown in Figures 19A and 19B, the area below the first through-hole H1 of the upper slab S1 is closed, as shown in Figure 18.
[0071] As shown in Figure 19A, the bottom cover 20 has a plurality (three in the illustrated example) of dividing plates 21A, 21B that are connected to each other in a foldable manner, a fixing jig 23 fixed to the upper surface of the central dividing plate 21A, and a suspension member 33 attached to the fixing jig 23 via an intermediate member 31. Here, the number of dividing plates may be two or four or more.
[0072] The fixing jig 23 comprises a fixing part 23a fixed to the central dividing plate 21A and a rotating part 23b that rotates relative to the fixing part 23a, with one end of the intermediate member 31 fixed to one end of the rotating part 23b. The fixing part 23a and the rotating part 23b can be formed by a knuckle joint.
[0073] For example, the upper end of the rotating part 23b has a screw groove, and one end of an intermediate member 31 of a predetermined length (for example, the length of the first through hole H1), made of, for example, a steel bar, is screwed into this screw groove. The other end of the intermediate member 31 is screwed into one end of a high nut 32, and one end of a suspension member 33, made of, for example, a steel bar, is screwed into the other end of the high nut 32. This suspension member 33 is suspended from a work platform or the like above the box culvert C.
[0074] The divided plates 21A and 21B are connected to each other by multiple hinges 22 (two in the illustrated example), and the left and right divided plates 21B rotate upward in the Y1 direction relative to the central divided plate 21A.
[0075] Furthermore, the three divided plates 21A and 21B have a circular shape in plan view, and the fixing part 23a is fixed to the centroid position T of the three divided plates 21A and 21B. Because the shape in plan view is circular, in the illustrated example, the fixing part 23a is fixed to the center of the circle.
[0076] On the other hand, in the illustrated example of the bottom cover 20, a counterweight 27 is attached to one side of the back surface of the divided plate 21A at an offset position. As shown in Figure 19B, when the bottom cover 20 is inserted through the first through hole H1, the left and right divided plates 21B come into contact with the wall surface of the first through hole H1 and rotate, rising towards the central divided plate 21A, and furthermore, the counterweight 27 rotates the entire three divided plates 21A and 21B around the rotating part 23b in the Y2 direction, resulting in an oblique position.
[0077] These measures make it possible to minimize the planar area of the three divided plates 21A and 21B as they pass through the first through-hole H1, thereby facilitating their passage through the first through-hole H1.
[0078] Furthermore, as shown in Figure 19A, a sealing material 25 is provided on the upper surfaces of the three divided plates 21A and 21B to close or surround the lower opening of the first through hole H1 and to adhere tightly to the lower surface of the upper floor slab S1. Here, the sealing material 25 is made of a waterproof rubber sheet or the like.
[0079] Furthermore, on the upper surfaces of the three divided plates 21A and 21B, four alignment pins 26 are provided that protrude upward at multiple locations corresponding to the downward opening of the first through hole H1 (four locations on a virtual circle VC that simulates the downward opening of the first through hole H1).
[0080] As shown in Figure 19B, when the first through-hole H1 is inserted downward in the Y5 direction and the three divided plates 21A and 21B protrude below the lower surface of the upper floor slab S1, two of the divided plates 21B spread out to the sides. Subsequently, when the three divided plates 21A and 21B are lifted by the suspension member 33, the four alignment pins 26 that protrude upward fit into the downward opening of the first through-hole H1, thereby positioning the three divided plates 21A and 21B at predetermined positions on the lower surface of the upper floor slab S1.
[0081] This allows the sealant 25 to adhere tightly to the underside of the upper deck slab S1 while the lower opening of the first through hole H1 is closed by the three divided plates 21A and 21B. The tight adhesion of the sealant 25 to the underside of the upper deck slab S1 ensures watertightness.
[0082] Furthermore, the process of preparing this bottom cover 20 is a preparation process (bottom cover preparation process), and the process of closing the lower opening of the first through hole H1 with the three divided plates 21A and 21B is an opening closing process.
[0083] Following the opening closing process, the first through-hole H1 is filled from above with non-shrink mortar M6 (an example of a sealing material) via the first penetration rod to close it. Figure 20 shows the state after the first through-hole H1 has been closed with non-shrink mortar M6 and the first penetration rod R1 has been pulled up and removed.
[0084] Until the non-shrink mortar M6 achieves its predetermined strength, the three divided plates 21A and 21B are suspended from the work floor by the suspension member 33. As shown in Figure 20, an overcut portion M6a is provided above the non-shrink mortar M6, and as the overcut portion M6a hardens, it locks into the upper surface of the upper deck slab S1. The intermediate member 31 and the high nut 32 are embedded in the non-shrink mortar M6, and the frictional force of these and the locking structure of the overcut portion M6a maintain the close contact position of the three divided plates 21A and 21B with the lower surface of the upper deck slab S1, preventing the bottom cover 20 from falling off.
[0085] The tall nut 32 is located at the upper end of the non-shrink mortar M6, and after the non-shrink mortar M6 has developed its strength, the suspension member 33 can be rotated to remove it from the tall nut 32 and retrieve it. Alternatively, the tall nut 32 may be positioned on the outside of the non-shrink mortar M6, and the suspension member 33 and tall nut 32 may be rotated together to remove them from the intermediate member 31 and retrieve them (this completes the through-hole closing process).
[0086] Thus, in this method of performing ground improvement on the ground G1 below the box culvert while forming through holes in each of the multiple slabs constituting the box culvert C, it becomes possible to perform ground improvement while preventing both the leakage of sewage and other contents into the ground G within the box culvert C and the infiltration of groundwater into the box culvert C.
[0087] [Test construction] Next, the test construction carried out by the inventors will be described with reference to Figures 21A to 21H. Here, Figures 21A to 21H are, in order, process diagrams of the test construction.
[0088] First, as shown in Figure 21A, a concrete slab was fabricated. The fabricated concrete slab was supported by two H-shaped steel beams and raised by 0.3 m. A test pressure box was installed on the top surface of the concrete slab via a packing and secured with anchor bolts.
[0089] Next, as shown in Figure 21B, a work platform was set up around the concrete slab, and a boring machine was installed on it. This work platform simulates an actual work platform.
[0090] Next, as shown in Figure 21C, a φ400 mm casing was attached to the φ90 mm boring rod of the boring machine, and a hole was drilled in the concrete slab.
[0091] Next, as shown in Figure 21D, a φ400 mm casing was inserted into the upper 10 to 15 mm area of a 500 mm thick concrete slab without water and fired, and non-shrink mortar was filled inside the casing.
[0092] Next, as shown in Figure 21E, the test pressure box and lid, and the lid and a φ400mm casing were fixed in place to seal the connection, and pressurized water at 0.2 MPa was supplied from the ball valve section. This simulates the water pressure based on the actual groundwater level in the construction plan area.
[0093] Next, as shown in Figure 21F, a φ350mm casing was inserted into a φ400mm casing, and a hole was drilled through the concrete slab. The water leakage situation at that time was then observed. The observation revealed that no water leakage was detected under the condition of pressurized water at 0.2 MPa.
[0094] As shown in Figure 21G, a retrieval hinge for concrete core retrieval (to prevent it from falling) is attached to the lower inner end of the φ350mm casing, and the concrete core was retrieved simultaneously when the casing was lifted. This retrieval hinge simulates a fall prevention jig.
[0095] Next, as shown in Figure 21H, a steel plate was attached to the underside of the concrete slab to seal the through-hole, non-shrink mortar was filled into the φ400mm casing, and the φ400mm casing was removed to seal the through-hole.
[0096] This series of test constructions verified that, under conditions where a predetermined water pressure is applied, it is possible to achieve a series of construction methods that completely seal through-holes in concrete slabs with non-shrink mortar while preventing water leakage.
[0097] Furthermore, other embodiments may be used in which other components are combined with the configurations listed in the above embodiments, and the present invention is not limited in any way to the configurations shown herein. In this regard, modifications can be made without departing from the spirit of the present invention, and can be appropriately determined according to the application form. [Explanation of Symbols]
[0098] 10: Fall prevention jig 10A: Drop prevention jig in reduced diameter position 10B: Fall prevention jig in expanded diameter position 11: Bar material 11a: Storage groove 13: Rotating shaft 15: Diameter-enlarged material 16: Elastic material 20: Bottom lid 21,21A,21B:Dividing plate 22: Hinge 23: Fixing jig 23a: Fixed part 23b: Rotating part 25: Sealant 26: Alignment pin 31: Intermediate member (steel bar) 32: High nut 33: Lifting member (steel bar) C: Existing structure (box culvert) C1: Main sewer space C2: Management space C3: Stormwater main space S1: Upper floor slab (floor slab) S2: Middle floor version S3: Lower floor version W1: Exterior wall W2: Bulkhead G: Ground G1: Lower ground (ground beneath existing structures) R1: First penetration rod R2: First drilling rod (second penetration rod, drilling rod) R3: Second drilling rod (third penetration rod) R4: Third drilling rod Ra: Improved rod P: Single tube M1, M2, M3: Water-stopping material (non-shrink mortar) M4, M5, M6: Sealing material (non-shrink mortar) M6a: Overcut section H1: 1st through hole (through hole) H2: 2nd through hole H3: 3rd through hole Ha: Leading hole Hg: Installation hole CO: Concrete Core GI: Ground improvement body L1: Upper lid L2: Lower lid A: Anchor bolt T: Center of gravity position VC: Virtual Yen
Claims
1. A concrete core fall prevention jig for supporting and recovering concrete cores generated when a through-hole is formed by drilling through a concrete slab that forms an existing concrete structure using a drilling rod, Rods and, It has an enlarged diameter member, The diameter-expanding member is rotatably attached at its lower end to a pivot axis provided on the rod, and its orientation can be changed between a reduced diameter position and an expanded diameter position. When the fall prevention jig is inserted through a relatively small diameter pre-hole formed in the floor slab prior to the formation of the through hole, the diameter-expanding member is in the reduced-diameter position with its upper end facing the rod, and when the diameter-expanding member extends below the floor slab, the diameter-expanding member rotates around the pivot axis and changes its position to the expanded-diameter position with its upper end spreading outward. Multiple diameter-enlarging members are rotatably attached to the same height position of the aforementioned rod, and multiple diameter-enlarging members are rotatably attached at multiple height positions of the aforementioned rod, A concrete core fall prevention jig characterized in that the formed concrete core is supported by a plurality of diameter-enlarging members in an enlarged position at one of the plurality of height positions.
2. The concrete core fall prevention jig according to claim 1, characterized in that the diameter-expanding member is biased from the rod member via an elastic member to assume an expanded diameter position.
3. A method for forming through-holes in a concrete slab, comprising drilling through the slab to form an existing concrete structure using a drilling rod, Rods and, A fall prevention jig having an enlarged diameter member, The preparation step involves preparing the fall prevention jig, wherein the lower end of the diameter-expanding member is rotatably attached to a pivot axis provided on the rod, allowing it to change its orientation between a reduced diameter position and an expanded diameter position, and multiple diameter-expanding members are rotatably attached at the same height position on the rod, and multiple diameter-expanding members are rotatably attached at multiple height positions on the rod, respectively. A preliminary guide hole formation step is performed in which a preliminary guide hole, which has a relatively smaller diameter than the through hole to be formed in a later step, is formed at the position where the through hole will be formed in the aforementioned floor slab. A method for forming a through-hole in a floor slab, comprising the steps of: inserting the diameter-expanding member into the aforementioned pre-drilled hole in the aforementioned reduced-diameter position with its upper end facing the rod side, passing the fall prevention jig through the aforementioned pre-drilled hole; when the diameter-expanding member extends below the floor slab, rotating the diameter-expanding member around the pivot axis to change its position to the expanded-diameter position with its upper end spreading outwards; and when the floor slab is drilled through with the drilling rod to form a through-hole, the resulting concrete core is supported by a plurality of diameter-expanding members in the expanded-diameter position at one of the plurality of height positions below, and the concrete core is pulled up and recovered through the through-hole.
Citation Information
Patent Citations
Recovery device for core of main pipe
JP1986172992A
Concrete drop preventive device for core drill
JP1999320548A
Building boring device, suspended attachment, and building boring construction method
JP2011099300A
Concrete member cutting device
JP2015214105A
Core extractor and core drop arrester
JP2017087419A