Construction progress management method and system based on BIM space ternary mapping
By using the ternary mapping technology based on the BIM model in building construction, the physical space is divided and topological logical relationships are constructed, which solves the problems of dynamic adaptability and plan disconnection in construction progress management, realizes multi-level dynamic management and conflict coordination, and improves the efficiency of construction progress management.
Patent Information
- Application Number
- CN202511196715.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-08-26
- Publication Date
- 2025-10-03
AI Technical Summary
In the existing construction progress management scheme, the relationship is static and one-way, which makes it difficult to adapt to dynamic changes in construction. On-site progress feedback is delayed, resulting in disconnected conflicts in multi-level plans and chaotic spatial operations.
By dividing the physical space and constructing spatial topological logical relationships through component information based on the BIM model, a ternary closed-loop mapping relationship between WBS construction tasks, BIM model components and physical space is established to dynamically manage the progress of the overall construction control plan.
It realizes multi-level dynamic closed-loop management of the overall construction control plan, effectively handles schedule disconnection conflicts and team operation chaos, and improves the efficiency of construction progress management.
Smart Images

Figure CN120746210A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of building construction progress management, and in particular to a construction progress management method and system based on BIM space ternary mapping. Background Art
[0002] In the construction progress management scenario, BIM technology has been widely used in progress planning. Existing solutions generally only associate the work breakdown structure (WBS) with BIM components to manage work progress. These existing solutions have many problems: First, the association relationship is static and one-way, which makes it difficult to adapt to dynamic changes in construction; second, the on-site progress feedback lags during the plan execution phase, which may lead to disconnections and conflicts between multi-level plans; third, when multiple teams work in the same space, the lack of dynamic verification of spatial topology logic can easily lead to spatial conflicts and process confusion. Currently, no effective solution has been proposed for the problem of how to improve the efficiency of construction progress management based on building information modeling in related technologies. Summary of the Invention
[0003] The embodiments of the present application provide a construction progress management method and system based on BIM space ternary mapping, so as to at least solve the problem in the related art of how to improve the efficiency of construction progress management based on building information modeling.
[0004] In a first aspect, an embodiment of the present application provides a construction progress management method based on BIM space ternary mapping, the method comprising: Based on the component information of the BIM model, physical spaces with practical construction significance are divided and spatial topological logical relationships between the physical spaces are constructed; Based on the physical space and spatial topological logical relationship, a ternary closed-loop mapping relationship is constructed between the WBS construction task, the BIM model component and the physical space; Based on the current construction master control plan and the ternary closed-loop mapping relationship, the construction progress of the construction master control plan is managed.
[0005] In some embodiments, based on the component information in the BIM model, dividing the physical spaces with construction task significance and constructing the spatial topological logical relationship between the physical spaces includes: Parsing the BIM model in the BIM model library to extract component information of each model component in the BIM model, wherein the component information includes geometric information and non-geometric information; Dividing the BIM model based on the component information of the model components to obtain a physical space with actual construction significance, wherein the physical space includes rooms, floor areas, and functional areas; Based on the component information of the model components, a spatial topological logical relationship between the physical spaces is constructed, wherein the spatial topological logical relationship includes an adjacent relationship, an inclusion relationship, and a connectivity relationship.
[0006] In some embodiments, based on the physical space and the spatial topological logical relationship, constructing a ternary closed-loop mapping relationship between the WBS construction task, the BIM model component, and the physical space includes: Binding each WBS construction task to at least one BIM model component through a preset matching rule to obtain a first mapping matching relationship; Based on the physical space and the spatial topological logical relationship, determining the BIM model components contained in each physical space to obtain a second mapping matching relationship; Based on the first mapping matching relationship and the second mapping matching relationship, a ternary closed-loop mapping relationship among the WBS construction tasks, the BIM model components and the physical space is obtained.
[0007] In some embodiments, each WBS construction task is bound to at least one BIM model component by a preset matching rule to obtain a first mapping matching relationship, including: The preset matching rules include component type matching rules and component coding rules; If the preset matching rule is a component type matching rule, the type of the required BIM model component is determined according to the work content and requirements of the WBS construction task, and then the corresponding BIM model component is matched from the BIM model according to the type and bound to obtain a first mapping matching relationship; If the preset matching rule is a component coding rule, a unique type code or component code is assigned to each BIM model component, and then the WBS construction task is bound to the corresponding component according to the code to obtain a first mapping matching relationship.
[0008] In some embodiments, determining the BIM model components contained in each physical space based on the physical space and the spatial topological logical relationship to obtain the second mapping matching relationship includes: Based on the spatial topological logical relationship, the BIM model components contained in each physical space are determined through a spatial inclusion relationship judgment algorithm, that is, the physical space is used as a geographic fence of the BIM model components to determine the BIM model components of each physical space, and a second mapping matching relationship is obtained.
[0009] In some embodiments, managing the construction progress of the current construction master control plan based on the ternary closed-loop mapping relationship includes: Based on the construction project requirements and the ternary closed-loop mapping relationship, the current construction master control plan is divided and compiled to generate corresponding monthly construction plans; Based on the construction team information and the ternary closed-loop mapping relationship, the monthly construction plan is divided and compiled to generate corresponding construction team plans; Based on the construction progress of the construction team plan, the construction progress of the monthly construction plan and the construction master control plan are managed.
[0010] In some embodiments, based on the construction project requirements and the ternary closed-loop mapping relationship, the current construction master control plan is divided and compiled to generate corresponding monthly construction plans, including: Based on the WBS construction tasks involved in the current construction master control plan, the corresponding BIM model components and the physical space to which the BIM model components belong are determined through the ternary closed-loop mapping relationship; Based on the construction project requirements and the physical space, the WBS construction tasks are divided and compiled, a corresponding monthly construction plan is generated, and the start time, end time and dependency relationship of each monthly construction plan are set.
[0011] In some embodiments, based on the construction team information and the ternary closed-loop mapping relationship, the monthly construction plan is divided and compiled to generate the corresponding construction team plan, including: In the monthly construction plan, the physical space that the construction team is responsible for is determined based on the construction team information, and the BIM model components and WBS construction tasks contained in the physical space are determined through the ternary closed-loop mapping relationship; Based on the actual situation of the construction site and the BIM model components, the WBS construction tasks are divided and compiled, the corresponding construction team plan is generated, and the plan-related information of the construction team plan is calculated.
[0012] In some embodiments, managing the construction progress of the monthly construction plan and the overall construction control plan based on the construction progress of the construction team plan includes: Based on the actual construction progress and expected completion time of each construction team plan, the progress deviation of the construction team plan is calculated, and based on the progress deviation, the construction progress of the corresponding monthly construction plan and the overall construction control plan are controlled step by step.
[0013] In a second aspect, an embodiment of the present application provides a construction progress management system based on BIM spatial ternary mapping, the system being used to execute the method described in the first aspect above, the system comprising a spatial topology mapping module and a dynamic planning collaboration module; The spatial topology mapping module is used to divide the physical space with actual construction significance according to the component information of the BIM model, and to establish the spatial topology logical relationship between the physical spaces; The spatial topology mapping module is used to construct a ternary closed-loop mapping relationship between the WBS construction task, the BIM model component and the physical space according to the physical space and the spatial topology logical relationship; The dynamic plan collaboration module is used to manage the construction progress of the construction master control plan based on the current construction master control plan and the ternary closed-loop mapping relationship.
[0014] Compared with the related art, the embodiment of the present application provides a construction progress management method and system based on BIM space ternary mapping, wherein the method divides the physical space with actual construction significance through component information based on the BIM model, and constructs the spatial topological logical relationship between the physical spaces; based on the physical space and the spatial topological logical relationship, constructs the ternary closed-loop mapping relationship between the WBS construction task, the BIM model component and the physical space; based on the current construction master control plan and the ternary closed-loop mapping relationship, manages the construction progress of the construction master control plan, realizes the multi-level dynamic closed-loop management of the construction master control plan by using the ternary closed-loop mapping relationship, can effectively deal with the disconnection and conflict between the actual construction progress and the expected progress, effectively coordinate the possible process confusion and operation conflict between multiple construction teams, and solves the problem of how to improve the construction progress management efficiency based on the building information model. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings: Figure 1 is a flowchart of the steps of the construction progress management method based on BIM space ternary mapping according to an embodiment of the present application; Figure 2 is a structural diagram of a parsed BIM model according to an embodiment of the present application; Figure 3 is a schematic diagram of a ternary closed-loop mapping relationship according to an embodiment of the present application; Figure 4 1 is a flowchart of collaborative feedback for the compilation of a multi-level plan according to an embodiment of the present application; Figure 5 Schematic diagram of the internal structure of an electronic device according to an embodiment of the present application. DETAILED DESCRIPTION
[0016] In order to make the purpose, technical solutions and advantages of this application more clearly understood, the present application is described and illustrated below in conjunction with the accompanying drawings and examples. It should be understood that the specific embodiments described herein are merely used to explain this application and are not intended to limit this application. Based on the embodiments provided in this application, all other embodiments obtained by those of ordinary skill in the art without making any creative efforts are within the scope of protection of this application.
[0017] Obviously, the drawings described below are merely examples or embodiments of the present application. Those skilled in the art can, without inventive effort, apply the present application to other similar scenarios based on these drawings. Furthermore, it is also understood that, although the effort involved in such a development process may be complex and lengthy, for those skilled in the art related to the content disclosed in this application, changes in design, manufacturing, or production based on the technical content disclosed in this application are merely conventional technical means and should not be construed as an insufficiency of the content disclosed in this application.
[0018] References to "embodiments" in this application mean that a particular feature, structure, or characteristic described in connection with the embodiment may be included in at least one embodiment of the application. The appearance of this phrase in various places in the specification does not necessarily refer to the same embodiment, nor does it refer to independent or alternative embodiments that are mutually exclusive of other embodiments. It is understood, both explicitly and implicitly, by those skilled in the art that the embodiments described in this application may be combined with other embodiments unless there is a conflict.
[0019] Unless otherwise defined, technical or scientific terms used herein shall have the ordinary meaning as understood by persons of ordinary skill in the art to which this application belongs. The terms "a," "an," "an," "the," and similar expressions used herein do not denote quantitative limitations and may refer to either the singular or the plural. The terms "comprise," "include," "have," and any variations thereof, used herein, are intended to cover non-exclusive inclusions. For example, a process, method, system, product, or apparatus comprising a series of steps or modules (units) is not limited to the listed steps or units but may also include steps or units not listed, or may include other steps or units inherent to the process, method, product, or apparatus. The terms "connected," "connected," "coupled," and similar expressions used herein are not limited to physical or mechanical connections but may include electrical connections, whether direct or indirect. As used herein, "plurality" means two or more. "And / or" describes an association between associated objects, indicating that three possible relationships exist. For example, "A and / or B" may mean: A exists alone; A and B exist simultaneously; or B exists alone. The character " / " generally indicates that the objects before and after are in an "or" relationship. The terms "first", "second", "third", etc. involved in this application are only used to distinguish similar objects and do not represent a specific order for the objects.
[0020] The present invention provides a construction progress management method based on BIM space ternary mapping. Figure 1 This is a flowchart of the steps of the construction progress management method based on BIM space ternary mapping according to an embodiment of the present application, such as Figure 1 As shown, the method includes the following steps: Step S102: Based on the component information of the BIM model, physical spaces with actual construction significance are divided and spatial topological logical relationships between the physical spaces are constructed; Step S102 specifically includes the following steps: Step S1021: parsing the BIM model in the BIM model library to extract component information of each model component in the BIM model, wherein the component information includes geometric information and non-geometric information; Step S1022: dividing the BIM model based on the component information of the model components to obtain a physical space with actual construction significance, wherein the physical space includes rooms, floor areas, and functional areas; Step S1023: constructing spatial topological logical relationships between physical spaces based on the component information of the model components, wherein the spatial topological logical relationships include adjacent relationships, inclusion relationships, and connectivity relationships.
[0021] It should be noted that Figure 2Schematic diagram of the structure of the BIM model according to the embodiment of the present application. Figure 2 As shown, in step S1021, it is necessary to import these BIM models in the BIM model library and parse them to accurately extract the geometric information and non-geometric information of all components (constituent entities) in the model, wherein the geometric information includes coordinates, size, and shape, and the non-geometric information includes type and system; Figure 2 As shown, in step S1022 and step S1023, the physical space with actual construction significance (such as Figure 2 In the example, space-001 and space-002 are represented by a physical space, including rooms, floor areas, functional areas, etc., and a topological logical relationship is established between the spaces, including adjacent, contained, connected, etc.
[0022] Step S104: constructing a ternary closed-loop mapping relationship between WBS construction tasks, BIM model components, and physical space based on the physical space and spatial topology logical relationship; Step S104 specifically includes the following steps: Step S1041: Bind each WBS construction task to at least one BIM model component using a preset matching rule to obtain a first mapping matching relationship; Specifically, in step S1041, the preset matching rules include component type matching rules and component coding rules; If the preset matching rule is a component type matching rule, the type of the required BIM model component is determined according to the work content and requirements of the WBS construction task, and then the corresponding BIM model component is matched from the BIM model according to the type and bound to obtain a first mapping matching relationship; If the preset matching rule is a component coding rule, a unique type code or component code is assigned to each BIM model component, and then the WBS construction task is bound to the corresponding component according to the code to obtain a first mapping matching relationship.
[0023] It should be noted that Table 1 is an example table for constructing a mapping between WBS and BIM model components according to an embodiment of the present application. For the binding of WBS construction tasks → BIM model components, each WBS task item is directly associated with one or more target components (as shown in Table 1, taking Revit modeling software as an example) through preset matching rules (such as component type matching rules and component coding rules). The preset matching rules include component type matching rules, component coding rules, etc., among which the component type matching rules refer to determining the type of required components based on the work content and requirements of the WBS task, and then matching the corresponding type of components from the BIM model; the component coding rules refer to assigning a unique type code or component code to each BIM component, and the WBS task item is directly associated with the corresponding component through the code. Through the binding method in step S1041, the precise association mapping between the WBS construction task and the BIM model component is achieved, ensuring the accuracy of the subsequent construction progress control using the ternary closed-loop mapping relationship.
[0024] Table 1
[0025] Step S1042: Based on the physical space and the spatial topological logical relationship, determine the BIM model components contained in each physical space to obtain a second mapping matching relationship; Specifically, step S1042 determines the BIM model components contained in each physical space based on the spatial topological logical relationship through the spatial inclusion relationship judgment algorithm, that is, the physical space is used as the geographical fence of the BIM model components to determine the BIM model components of each physical space and obtain the second mapping matching relationship.
[0026] It should be noted that for the attribution of physical space to BIM model components, each physical space determines the set of all BIM model components it contains through spatial topological logical relationships. Specifically, using the spatial topological logical relationships established above, the physical space is used as a geographic fence for BIM model components. The spatial inclusion relationship judgment algorithm is used to determine the BIM components contained in each physical space, thereby accurately determining the attribution relationship between physical space and BIM model components, ensuring the accuracy of subsequent construction progress control using the ternary closed-loop mapping relationship.
[0027] Step S1043: Based on the first mapping matching relationship and the second mapping matching relationship, a ternary closed-loop mapping relationship among the WBS construction task, the BIM model component, and the physical space is obtained.
[0028] It should be noted that Figure 3 is a schematic diagram of a ternary closed-loop mapping relationship according to an embodiment of the present application, such as Figure 3As shown, the first mapping matching relationship is the mapping matching relationship between WBS construction tasks and BIM model components, and the second mapping matching relationship is the mapping matching relationship between physical space and BIM model components. By using these two sets of mapping matching relationships, a ternary closed-loop mapping relationship between the three can be constructed: WBS construction tasks - BIM model components - physical space.
[0029] Step S106: managing the construction progress of the construction master control plan based on the current construction master control plan and the ternary closed-loop mapping relationship.
[0030] Step S106 specifically includes the following steps: Step S1061: Based on the construction project requirements and the ternary closed-loop mapping relationship, the current construction master control plan is divided and compiled to generate corresponding monthly construction plans; Specifically, step S1061 determines the corresponding BIM model components and the physical spaces to which the BIM model components belong through a ternary closed-loop mapping relationship based on the WBS construction tasks involved in the current construction master control plan; Based on the construction project requirements and physical space, the WBS construction tasks are divided and compiled, the corresponding monthly construction plan is generated, and the start time, end time and dependency relationships of each monthly construction plan are set.
[0031] It should be noted that step S1061 is one of the steps in dynamically coordinating plans using a ternary closed-loop mapping relationship. Specifically, the construction master control plan (level 1 plan) is developed by the project management team based on the overall project objectives, key milestones, and overall resource constraints. The construction master control plan clearly defines the project's macro timeframe, key milestones, and overall resource budget. Figure 4 : is a flowchart of collaborative feedback of multi-level plan preparation according to an embodiment of the present application, such as Figure 4 As shown in the figure, the monthly construction plan (secondary plan) is based on the construction project requirements (such as project logic, resource constraints and engineering experience), combined with the ternary closed-loop mapping relationship (such as Figure 4 As shown in the figure, the ternary closed-loop mapping relationship between WBS, BIM, and physical space in the BIM model space topology mapping is used to automatically introduce physical space to construct the spatial fence of BIM components. In order to subdivide the WBS construction tasks and corresponding BIM components of the first-level plan in dynamic plan collaboration and generate the corresponding second-level plan), the overall construction control plan is divided and compiled to refine the spatial tasks. The determined monthly construction plan clearly defines the time window (planned start and end dates) and scope of each spatial task (such as "air conditioning installation in room 101").
[0032] It should be further explained that when the general construction control plan triggers the execution of the division and compilation instructions, the system automatically starts the constraint verification process, calls the BIM model components bound to the task from the mapping rule library, and filters out the physical space to which the above components belong based on the ternary closed-loop mapping relationship. Operations on the bound components are only allowed within the filtered physical space. Through the above process, a strong constraint chain of "WBS task → target component → limited space" is formed to ensure the spatial uniqueness and component accuracy of task execution.
[0033] Step S1062: Based on the construction team information and the ternary closed-loop mapping relationship, the monthly construction plan is divided and compiled to generate corresponding construction team plans; Specifically, step S1062 determines the physical space that the construction team is responsible for based on the construction team information in the monthly construction plan, and determines the BIM model components and WBS construction tasks contained in the physical space through a ternary closed-loop mapping relationship; Based on the construction team information and BIM model components, the WBS construction tasks are divided and compiled, the corresponding construction team plan is generated, and the planning-related information of the construction team plan is calculated.
[0034] It should be noted that step S1062 is also one of the steps for performing dynamic planning collaboration using the ternary closed-loop mapping relationship. Figure 4 As shown, the ternary closed-loop mapping relationship among WBS, BIM, and physical space in the BIM model space topology mapping is used to generate a space task package organized by physical space, which contains the corresponding BIM model components and WBS construction tasks, as well as a unique associated QR code; the physical space that the construction team is responsible for is determined based on the construction team information (for example, the construction team scans the QR code of the physical space through a mobile device, the system pushes the corresponding task package, and the scan activates the action to confirm the receipt of the task package); and then combined with the actual situation of the construction site (such as labor, materials, environment, etc.), as shown Figure 4As shown, in dynamic planning collaboration, the third-level plan is associated with the corresponding second-level plan to generate the corresponding construction team plan (third-level plan). Its time window is limited to the time window of the corresponding second-level plan, and the planning-related information of the construction team plan is calculated. The specific calculation rules are as follows: ① Input and obtain data: extract the remaining planned duration and remaining project volume of the WBS construction task from the monthly construction plan; then obtain the current cumulative completion rate and actual consumed working hours; retrieve the preset standard labor efficiency value (unit: project volume / person-day) from the quota database; ② Generate the default team number: calculate the minimum positive integer that satisfies "standard labor efficiency value * number of people * remaining planned duration ≥ remaining project volume", and round up if it is not an integer; ③ Generate the default target completion rate: calculate the sum of the current cumulative completion rate and the incremental value, and the incremental value is "standard labor efficiency value * default team number * number of days in the planning cycle ÷ remaining project volume" (number of days in the planning cycle: 1 day for daily planning and 7 days for weekly planning). If the result exceeds 100%, only 100% is taken; It is further necessary to explain that if Figure 4 As shown, the construction team plan also includes a default indicator calculation and decision-making support mechanism. Specifically, the first is the manual review and adjustment process: the system pre-populates the plan form with the default team size and target completion rate. The team then adjusts the parameters based on a four-dimensional set of on-site factors, including available labor allocation, material arrival schedule, construction environment interference, and process connection technical conditions. Second, real-time support for auxiliary decision-making: ① Construction period pressure warning: Based on the user-adjusted team size and target completion rate, the construction period is predicted by reverse deduction (remaining construction volume ÷ standard labor efficiency value ÷ adjusted team size). When the predicted construction period is greater than the remaining planned construction period, an overdue days alarm is automatically generated (overdue days = predicted construction period - remaining planned construction period); ② Component construction volume verification: In response to the user's operation of selecting components in the BIM model: the percentage of the total weight of the selected component set to the total weight of the current spatial task (the component weight is determined by the construction volume or complexity) is automatically calculated, and the theoretical working time requirement of the selected component is output (this percentage * remaining construction volume ÷ standard labor efficiency value); ③ Historical work efficiency benchmarking: Display the historical work efficiency reference data set (minimum, average, maximum), calculate the planned work efficiency value and compare it with the historical reference value, and output the quantitative result (for example, "the current value reaches 92% of the historical average").
[0035] In addition, if Figure 4As shown, the construction team plan also features a backend spatial simulation mechanism. After the team submits its plan, the system automatically triggers a backend spatial feasibility simulation to check for physical or resource conflicts between WBS construction tasks. If approved, an execution instruction is issued; if not, a conflict alert is issued, triggering a conflict detection and two-way adjustment mechanism. The construction team plan also features a conflict detection and two-way adjustment mechanism: it continuously monitors and immediately responds to submissions or updates to construction team plans (third-level plans). Conflicts (such as advances, delays, and scope changes) between the constraints (time windows) set by the third-level plan (planned time) and its associated second-level plan (monthly plan) are automatically detected. Approved (or authorized) and reasonable changes to team plan details allow for upward adjustments to the corresponding second-level plan (for backward compatibility). Alternatively, if there is a significant discrepancy between the team plan and the overall objectives of the second-level plan, batch adjustments to the second-level plan are made, and the parent (e.g., the first-level plan) is promptly notified of potential impacts.
[0036] Step S1063: Manage the construction progress of the monthly construction plan and the overall construction control plan based on the construction progress of the construction team plan.
[0037] Specifically, step S1063 calculates the progress deviation of the construction team plan based on the actual construction progress and expected completion time of each construction team plan, and based on the progress deviation, controls the construction progress of the corresponding monthly construction plan and the overall construction control plan step by step.
[0038] It should be noted that regarding the dynamic collection and processing of construction team progress plans, once a team activates a task package, the system locks associated components based on a ternary mapping rule library. The target component is highlighted on the mobile progress reporting interface. The team then clicks or boxes to select completed components. The system then calculates the task completion rate based on the component's weighted quantity and updates it in real time to the BIM model and plan libraries. Furthermore, the system continuously monitors the overall deviation between the secondary plan and actual construction progress. When the deviation exceeds a preset threshold (e.g., time deviation > 3 days, quantity progress deviation > 5%, or a threat to the critical path), the secondary plan is adjusted (by rescheduling nodes and reallocating resources), and a risk alert is issued to the primary plan. The system also continuously monitors WBS construction tasks currently underway or about to be constructed within the same physical space. Based on ternary mapping rules, task progress, dependencies, and BIM model coordinate data, it detects physical space conflicts (coordinate collisions) and process logic conflicts (dependencies, progress, and time overlaps). It then provides warnings, coordination suggestions, or automatically triggers fine-tuning instructions to ensure smooth construction.
[0039] Through the above steps in the embodiment of the present application, multi-level dynamic closed-loop management of the construction master control plan is achieved by utilizing the ternary closed-loop mapping relationship, which can effectively deal with the disconnection and conflict between the actual construction progress and the expected progress, effectively coordinate possible process confusion and operation conflicts between multiple construction teams, and solve the problem of how to improve the construction progress management efficiency based on the building information model.
[0040] The preferred embodiment of the present application provides a construction progress management method based on BIM space ternary mapping, and the method of the preferred embodiment includes the following steps: Step 1: Model processing: Obtain the basement BIM model and extract the spatial coordinates and boundaries of each room. Associate each sub-project of the mechanical and electrical installation (such as piping and duct installation) with BIM components and map them to the corresponding room spaces. For example, associate all fire protection piping components in room R001 with the WBS item "Fire Protection Pipe Installation."
[0041] Step 2: Generate a secondary plan: The system automatically lists the required mechanical and electrical installation tasks for each room (for example, room R001 requires fire protection piping and cable tray installation). Based on this list of tasks, planning engineers create a secondary (monthly) plan in the project management software, setting the start and end times and dependencies for each task.
[0042] Step 3: Team task collection and three-level plan generation: The construction team uses the mobile app to enter the basement room R001. They click the spatial positioning button in the app, and the app automatically obtains the current location. The system displays the tasks to be performed in the room (fire protection pipe installation, cable tray installation). The preferred embodiment uses positioning means to determine the corresponding physical space, while step S1062 of the above embodiment uses scanning a QR code to determine. There are many ways to determine the physical space, which will not be detailed here. The team leader selects the "Fire Protection Pipe Installation" task. Based on the pipe length (project quantity) associated with the task and the work efficiency data for "Pipeline Installation" in the quota library (for example, each person can install 20 meters per day), the system automatically calculates the required working days (for example, 100 meters requires 5 man-days) and generates a three-level plan (weekly plan / team plan).
[0043] Step 4: Progress verification: Teams report their progress daily in the app (for example, "20 meters completed today"). The system automatically calculates progress deviations (planned completion minus actual completion) and uses the BIM 3D collision engine to verify spatial topology. It checks to see if other teams are performing conflicting tasks in the same space (for example, ceiling installation and plumbing work at the same height) and checks process logic (for example, piping installation should be completed before wall plastering).
[0044] Step 5: Plan revision: When the deviation exceeds a threshold (e.g., a 10% delay in progress) or a spatial conflict is detected, the system triggers a correction mechanism: it recalculates the installation duration for the remaining piping in that room (taking into account the current progress and remaining work load) and automatically adjusts the start time of subsequent related tasks in the secondary plan. Simultaneously, the system pushes a conflict alert to the relevant teams.
[0045] It should be noted that the steps shown in the above process or the flowchart in the accompanying drawings can be executed in a computer system such as a set of computer-executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.
[0046] The embodiment of the present application provides a construction progress management system based on BIM spatial ternary mapping, the system is used to execute the method of the first aspect above, the system includes a spatial topology mapping module and a dynamic planning collaboration module; The spatial topology mapping module is used to divide the physical space with practical construction significance according to the component information of the BIM model, and to build the spatial topology logical relationship between the physical spaces; The spatial topology mapping module is used to construct a ternary closed-loop mapping relationship between WBS construction tasks, BIM model components and physical space based on the logical relationship between physical space and spatial topology; The dynamic planning collaboration module is used to manage the construction progress of the construction master control plan based on the current construction master control plan and the ternary closed-loop mapping relationship.
[0047] Through the spatial topology mapping module and dynamic plan collaboration module in the embodiments of the present application, multi-level dynamic closed-loop management of the construction master control plan is achieved by utilizing the ternary closed-loop mapping relationship, which can effectively deal with the disconnection and conflict between the actual construction progress and the expected progress, and effectively coordinate possible process confusion and operation conflicts between multiple construction teams, thereby solving the problem of how to improve the efficiency of construction progress management based on the building information model.
[0048] It should be noted that the above modules can be functional modules or program modules, and can be implemented through software or hardware. For modules implemented through hardware, the above modules can be located in the same processor; or the above modules can be located in different processors in any combination.
[0049] This embodiment provides an electronic device, including a memory and a processor, wherein the memory stores a computer program, and the processor is configured to run the computer program to perform the steps in any one of the above method embodiments.
[0050] Optionally, the electronic device may further include a transmission device and an input / output device, wherein the transmission device is connected to the processor, and the input / output device is connected to the processor.
[0051] Optionally, the electronic device may also include a processor, a memory, a network interface, a display screen and an input device connected via a system bus. The processor of the electronic device is used to provide computing and control capabilities. The memory of the electronic device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The network interface of the electronic device is used to communicate with an external terminal via a network connection. When the computer program is executed by the processor, a construction progress management method based on BIM space ternary mapping is implemented. The display screen of the electronic device may be a liquid crystal display or an electronic ink display screen, and the input device of the electronic device may be a touch layer covering the display screen, or a button, trackball or touchpad provided on the housing of the electronic device, or an external keyboard, touchpad or mouse.
[0052] It should be noted that the specific examples in this embodiment can refer to the examples described in the above embodiments and optional implementation modes, and this embodiment will not be repeated here.
[0053] In addition, in conjunction with the construction progress management method based on BIM spatial ternary mapping in the above embodiments, embodiments of the present application may provide a storage medium for implementation. The storage medium stores a computer program; when the computer program is executed by a processor, it implements any of the construction progress management methods based on BIM spatial ternary mapping in the above embodiments.
[0054] In one embodiment, Figure 5 is a schematic diagram of the internal structure of an electronic device according to an embodiment of the present application, such as Figure 5 As shown, an electronic device is provided, which can be a server, and its internal structure can be as shown in FIG. Figure 5 As shown. The electronic device includes a processor, a network interface, an internal memory, and a non-volatile memory connected via an internal bus, wherein the non-volatile memory stores an operating system, a computer program, and a database. The processor is used to provide computing and control capabilities, the network interface is used to communicate with external terminals via a network connection, the internal memory is used to provide an environment for the operation of the operating system and the computer program. When the computer program is executed by the processor, it implements a construction progress management method based on BIM spatial ternary mapping, and the database is used to store data.
[0055] Those skilled in the art will understand that Figure 5The structure shown in the figure is only a block diagram of a part of the structure related to the solution of the present application, and does not constitute a limitation on the electronic device to which the solution of the present application is applied. The specific electronic device may include more or fewer components than shown in the figure, or combine certain components, or have a different component arrangement.
[0056] Those skilled in the art will understand that all or part of the processes in the above-mentioned embodiments can be implemented by instructing the relevant hardware through a computer program. The computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to memory, storage, database or other media used in the embodiments provided in this application may include non-volatile and / or volatile memory. Non-volatile memory may include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory may include random access memory (RAM) or external cache memory. By way of illustration and not limitation, RAM is available in many forms such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), Synchronous Link DRAM (SLDRAM), Rambus direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM), etc.
[0057] Those skilled in the art should understand that the various technical features of the above-described embodiments can be combined arbitrarily. In order to make the description concise, not all possible combinations of the various technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0058] The above-described embodiments merely represent several implementation methods of the present application. While the descriptions are relatively specific and detailed, they should not be construed as limiting the scope of the present invention. It should be noted that a person skilled in the art could make various modifications and improvements without departing from the spirit of the present application, all of which fall within the scope of protection of the present application. Therefore, the scope of protection of the present patent application shall be determined by the appended claims.
Claims
1. A construction progress management method based on BIM space ternary mapping, characterized in that: The method comprises: Based on the component information of the BIM model, physical spaces with practical construction significance are divided and spatial topological logical relationships between the physical spaces are constructed; Based on the physical space and spatial topological logical relationship, a ternary closed-loop mapping relationship is constructed between the WBS construction task, the BIM model component and the physical space; Based on the current construction master control plan and the ternary closed-loop mapping relationship, the construction progress of the construction master control plan is managed.
2. The method according to claim 1, characterized in that Based on the component information in the BIM model, physical spaces with construction task significance are divided and the spatial topological logical relationships between the physical spaces are constructed, including: Parsing the BIM model in the BIM model library to extract component information of each model component in the BIM model, wherein the component information includes geometric information and non-geometric information; Dividing the BIM model based on the component information of the model components to obtain a physical space with actual construction significance, wherein the physical space includes rooms, floor areas, and functional areas; Based on the component information of the model components, a spatial topological logical relationship between the physical spaces is constructed, wherein the spatial topological logical relationship includes an adjacent relationship, an inclusion relationship, and a connectivity relationship.
3. The method according to claim 1, characterized in that Based on the physical space and spatial topological logical relationship, constructing a ternary closed-loop mapping relationship between the WBS construction task, the BIM model component and the physical space includes: Binding each WBS construction task to at least one BIM model component through a preset matching rule to obtain a first mapping matching relationship; Based on the physical space and the spatial topological logical relationship, determining the BIM model components contained in each physical space to obtain a second mapping matching relationship; Based on the first mapping matching relationship and the second mapping matching relationship, a ternary closed-loop mapping relationship among the WBS construction tasks, the BIM model components and the physical space is obtained.
4. The method according to claim 3, characterized in that By presetting matching rules, each WBS construction task is bound to at least one BIM model component, and the first mapping matching relationship obtained includes: The preset matching rules include component type matching rules and component coding rules; If the preset matching rule is a component type matching rule, the type of the required BIM model component is determined according to the work content and requirements of the WBS construction task, and then the corresponding BIM model component is matched from the BIM model according to the type and bound to obtain a first mapping matching relationship; If the preset matching rule is a component coding rule, a unique type code or component code is assigned to each BIM model component, and then the WBS construction task is bound to the corresponding component according to the code to obtain a first mapping matching relationship.
5. The method according to claim 3, characterized in that Based on the physical space and the spatial topological logical relationship, determining the BIM model components contained in each physical space, and obtaining the second mapping matching relationship includes: Based on the spatial topological logical relationship, the BIM model components contained in each physical space are determined through a spatial inclusion relationship judgment algorithm, that is, the physical space is used as a geographic fence of the BIM model components to determine the BIM model components of each physical space, and a second mapping matching relationship is obtained.
6. The method according to claim 1, characterized in that Based on the current construction master control plan and the ternary closed-loop mapping relationship, managing the construction progress of the construction master control plan includes: Based on the construction project requirements and the ternary closed-loop mapping relationship, the current construction master control plan is divided and compiled to generate corresponding monthly construction plans; Based on the construction team information and the ternary closed-loop mapping relationship, the monthly construction plan is divided and compiled to generate corresponding construction team plans; Based on the construction progress of the construction team plan, the construction progress of the monthly construction plan and the construction master control plan are managed.
7. The method according to claim 6, characterized in that Based on the construction project requirements and the three-way closed-loop mapping relationship, the current construction master control plan is divided and compiled to generate corresponding monthly construction plans, including: Based on the WBS construction tasks involved in the current construction master control plan, the corresponding BIM model components and the physical space to which the BIM model components belong are determined through the ternary closed-loop mapping relationship; Based on the construction project requirements and the physical space, the WBS construction tasks are divided and compiled, a corresponding monthly construction plan is generated, and the start time, end time and dependency relationship of each monthly construction plan are set.
8. The method according to claim 7, characterized in that Based on the construction team information and the ternary closed-loop mapping relationship, the monthly construction plan is divided and compiled to generate the corresponding construction team plan, including: In the monthly construction plan, the physical space that the construction team is responsible for is determined based on the construction team information, and the BIM model components and WBS construction tasks contained in the physical space are determined through the ternary closed-loop mapping relationship; Based on the actual situation of the construction site and the BIM model components, the WBS construction tasks are divided and compiled, the corresponding construction team plan is generated, and the plan-related information of the construction team plan is calculated.
9. The method according to claim 8, characterized in that Based on the construction progress of the construction team plan, managing the construction progress of the monthly construction plan and the overall construction control plan includes: Based on the actual construction progress and expected completion time of each construction team plan, the progress deviation of the construction team plan is calculated, and based on the progress deviation, the construction progress of the corresponding monthly construction plan and the overall construction control plan are controlled step by step.
10. A construction progress management system based on BIM space ternary mapping, characterized in that: The system is used to perform the method according to any one of claims 1 to 9, the system comprising a spatial topology mapping module and a dynamic planning collaboration module; The spatial topology mapping module is used to divide the physical space with actual construction significance according to the component information of the BIM model, and to establish the spatial topology logical relationship between the physical spaces; The spatial topology mapping module is used to construct a ternary closed-loop mapping relationship between the WBS construction task, the BIM model component and the physical space according to the physical space and the spatial topology logical relationship; The dynamic plan collaboration module is used to manage the construction progress of the construction master control plan based on the current construction master control plan and the ternary closed-loop mapping relationship.
Citation Information
Patent Citations
Method and system for automatically hooking BIM (Building Information Modeling) model and planned task
CN118364783A
BIM-based building engineering construction optimization management method and management platform
CN118862237A
Construction progress analysis and regulation system based on BIM model
CN120338727A
System and method for location-based construction scheduling
WO2024022566A1
Building model management method and system, and electronic device
WO2025123627A1
Cited By
BIM model and WBS hitching diagnosis method and system
CN121031125A
Engineering project management auxiliary decision-making method based on domain knowledge enhancement
CN121544086A
An engineering project management auxiliary decision-making method based on domain knowledge enhancement
CN121544086B