The invention discloses a
constructed wetland construction method for
tail water lifting of an urban domestic
sewage treatment
plant, and particularly relates to the technical field of
sewage treatment, and the
constructed wetland construction method comprises the following steps: S1,
landform reconstruction and diversion
system construction; s2, layered construction of the composite anti-seepage structure; s3, precise configuration of gradient plants; s4, constructing an anti-
impact hydraulic
system; s5, establishing an ecological cooperation
system; and S6, implementing a dynamic operation and maintenance mechanism. Uniform distribution of
water flow is achieved through optimization of a flow guide structure, long-acting anti-seepage is guaranteed through a composite anti-seepage layer, gradient
plant communities construct a three-dimensional purification network, the
pollutant removal efficiency is remarkably improved, an anti-
impact system is integrated with an intelligent regulation and control module, water quantity fluctuation of 30% or above can be rapidly responded, and the
water quality is improved. The three-level ecological cooperation system realizes
pollution interception-deep purification-ecological restoration whole
process control, and the intelligent operation and
maintenance system improves the management precision by three times and reduces the operation cost by more than 40% through a real-time monitoring and prediction model.