The invention discloses a multilayer heterogeneous oil
reservoir water injection development balanced production well completion perforation optimization method, and relates to the technical field of oil and gas
field development engineering. The method comprises the steps that S1, basic parameters of a multilayer oil reservoir are collected, and
engineering constraints are determined; s2, performing numerical
simulation on perforation near-well flow of the multi-layer oil reservoir based on basic parameters of the multi-layer oil reservoir and the
engineering constraint, and establishing a
skin coefficient inversion
library; s3, a preset
skin coefficient of each layer in the multi-layer oil reservoir is set, and water
injection rate distribution of each layer of the multi-layer oil reservoir under the general water injection condition is calculated based on the preset
skin coefficient; s4, on the basis of the water injection amount distribution, calculating the water drive
leading edge advancing speed of the
oil phase and the water phase; s5, on the basis of the water drive
front edge advancing speed of each layer, the water drive
front edge advancing speed variance of each layer in the multi-layer oil reservoir is determined; and S6, the steps S3-S5 are repeated, the preset skin coefficient set when the advancing speed variance of the water drive
front edge of each layer is minimum is obtained, and the optimal perforation parameter combination at the moment is obtained.