The invention discloses a structure and method for controlling
dam break flood peak flow of a barrier dam, belongs to the field of disaster prevention and reduction
engineering, and provides a structure and method capable of effectively controlling the
dam break flood peak flow of the barrier dam. According to the structure for controlling the
dam break flood peak flow of the barrier dam, steel
pipe piles are arranged on the positions, on the two sides of a drainage channel, of the lower middle portion of the barrier dam respectively, the steel
pipe piles on each side are closely arranged on the outer sides of side
bank slope lines corresponding to side banks of the corresponding drainage channel in the state of flood peak flow in the period from dam break to 20 years, and the inner ends of the steel
pipe piles at least penetrate into the positions 10m below side
bank slope lines corresponding to the side banks of the corresponding drainage channel in the state of flood peak flow in the period from dam break to 20 years. According to the structure and method,
erosion expansion speed of the two banks of the drainage channel can be decreased through
erosion resistance of steel pipe
pile protection slopes on the two sides, protective
cement paste reinforcement stone cages on the two sides and outlet
impact-resistant
cement paste reinforcement stone cages, so that the dam break time of the barrier dam is delayed, the maximum flood peak flow of dam break is effectively reduced, and the purposes of disaster prevention and reduction are achieved.