The invention belongs to the technical field of deep foundation pit supporting, and discloses a deep foundation pit gushing water emergency plugging anchor rod and a construction method thereof.The deep foundation pit gushing water emergency plugging anchor rod comprises an anchor rod body, and a conical head is fixed to the head of the anchor rod body; a quick-setting
cement bag is connected to the periphery of the anchor rod body on the rear side of the conical head, and quick-setting
cement is contained in the quick-setting
cement bag; the outer side of the quick-setting cement bag and the periphery of the anchor rod body are wrapped with a water-soluble isolating membrane; the outer side of the water-soluble isolating membrane is wrapped with a
super absorbent resin layer, and the
super absorbent resin layer is used for absorbing water to expand and block the anchor rod
drill hole. When water bursts suddenly in the anchor rod
drill hole, the
super absorbent resin layer swells rapidly after meeting water to fill a gap between the hole wall of the anchor rod
drill hole and the anchor rod body, meanwhile, the quick-setting cement bag can be broken through
extrusion, the quick-setting cement and the
bursting water are mixed to generate
cement paste to fill the outer side of the conical head, finally, a solidified body is formed, and through double plugging, the water
bursting effect is improved. The gap between the anchor rod body and the anchor rod
drill hole is filled, the anchor rod
drill hole can be blocked in time, the hole collapse risk is reduced, and meanwhile the blocking efficiency is improved.