The invention relates to a tunnel single-layer lining embedded
grating steel frame structure and a construction method thereof, and belongs to the technical field of
highway engineering. The structure is composed of a primary support, a film spraying waterproof layer, a secondary lining and embedded
grating steel frames, the embedded
grating steel frames are embedded into the primary support and the secondary lining respectively, the effects of transmitting
shear stress and coordinating deformation are achieved, the primary support and the secondary lining form a combined beam stress state, and the overall rigidity and
bearing capacity of the lining structure are remarkably improved. During construction, the arrangement distance of the grating steel frames is determined through theoretical calculation, and it is ensured that the anti-shearing requirement is met. The method has the advantages of being convenient and fast to construct, high in safety and good in economical efficiency, the lining thickness and the number of reinforcing bars can be effectively reduced, the
engineering cost is reduced, meanwhile, the method adapts to
tunnel engineering of different surrounding rock grades, the problem that in traditional single-layer lining, shearing force transmission between a primary support and a secondary lining is insufficient is solved, an innovative solution is provided for tunnel lining structure design, and the method is worthy of popularization and application. The method has important
engineering application value and popularization prospect.