Method for carrying out operation and maintenance on power grid assets based on large reasoning model

By collecting multi-source data and constructing a power grid topology, an optimization reasoning model based on power physics constraints is introduced to generate a maintenance action sequence that conforms to the feasible domain of the power grid maintenance period. This solves the problem of the difficulty in unifying the modeling of multi-source data and topology, realizes intelligent operation and maintenance of power grid assets, and improves the scientificity and security of the solution.

CN121120032AActive Publication Date: 2025-12-12CHENGDU SUN HIGH-TECH CO LTD

Patent Information

Application Number
CN202511661028.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-11-13
Publication Date
2025-12-12
Estimated Expiration
2045-11-13

AI Technical Summary

Technical Problem

Existing technologies struggle to unify multi-source data with power grid topology modeling. Single-device predictions neglect cascading effects, leading to an underestimation of systemic risks. Data-driven results lack physical constraints. Maintenance plans fail to form a closed-loop linkage with feasible time zones, reserve capacity, and dispatch approval. The generated operation sequences cannot suppress risk propagation along paths while meeting safety boundaries, making it difficult to implement stably in engineering practice.

Method used

Multi-source operational data of power grid assets are collected, a power grid topology is constructed, and the data is mapped to the attribute space of power grid topology nodes and edges. Power physical constraints are introduced and the inference model is optimized to generate a maintenance action sequence that conforms to the feasible domain of power grid maintenance period and can minimize risk transmission. The model is optimized through chain inference loss function to predict the chain effect of equipment failure.

Benefits of technology

Significantly improve the scientific and rational nature of maintenance plans, effectively reduce systemic risks, realize the transformation of power grid asset operation and maintenance from experience-driven to intelligent decision-making, improve the efficiency and accuracy of plan generation, and ensure the safety and economy of maintenance execution.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN121120032A_ABST
    Figure CN121120032A_ABST
Patent Text Reader

Abstract

The invention belongs to the field of electric power, and provides a method for performing operation and maintenance on power grid assets based on a large reasoning model, comprising the following steps: collecting multi-source operation data of the power grid assets; constructing a power grid topological structure, and forming a power grid operation state diagram; performing targeted training and optimization on the pre-trained reasoning model to ensure that the running state prediction output by the reasoning model meets the electrical feasible region; enabling the reasoning model to automatically avoid maintenance schemes which do not accord with the load curve, the reserve capacity and the scheduling approval in the reasoning process; optimizing the inference model through a chain type inference loss function, so that the inference model can predict the linkage effect of the equipment fault; and based on an output result of the reasoning model, generating a maintenance action sequence which accords with a feasible region of the power grid maintenance period and can minimize risk conduction. According to the method, the operation and maintenance efficiency of the power grid assets is improved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application belongs to the field of electric power, and particularly relates to a method for performing operation and maintenance of power grid assets based on a reasoning large model. BACKGROUND

[0002] With the continuous expansion of the scale of the power grid and the increasing penetration of new energy, the operating state is jointly influenced by the coupling of device health, external environment and network topology. Operation and maintenance not only needs to identify single-device hidden dangers, but also needs to consider physical constraints such as power flow balance, power conservation and short-circuit safety, and is influenced by time period constraints such as load curve, standby capacity and dispatching approval window. With the rapid growth of multi-source data such as online monitoring, weather and historical work orders, how to uniformly express heterogeneous data and power grid topology, and how to make the reasoning results directly converted into executable maintenance sequences become key requirements.

[0003] In the prior art, common means include periodic maintenance and state-based maintenance, relying on SCADA and online monitoring for threshold alarm and trend analysis, using offline calculation of power flow and short circuit to check the safety boundary before and after maintenance, using experience rules or expert systems to generate power-off and power-on operation tickets and operation sequences, and implementing maintenance through manual coordination or simple scheduling to select low-load windows. Some data-driven methods can perform life estimation and fault prediction, and some methods structure work order texts to assist decision-making. Some systems introduce a hierarchical approval process and resource constraint management for parallel jobs.

[0004] The prior art still has deficiencies, mainly manifested in that multi-source data and power grid topology are difficult to be uniformly modeled, single-device prediction ignores chain transmission leading to underestimation of systemic risks, data-driven results lack physical constraints and appear unexecutable operating states, maintenance plans fail to form a closed-loop linkage with time period feasible region, standby capacity and dispatching approval, and generated operation sequences cannot meet safety boundaries while suppressing risk propagation along the path, making it difficult to be stably implemented in engineering practice. SUMMARY

[0005] In order to solve the problems in the prior art, the present application provides a method for performing operation and maintenance of power grid assets based on a reasoning large model, comprising the following steps: Collecting multi-source operating data of power grid assets, the data including device state monitoring data, operating environment parameters and historical maintenance records; Constructing a power grid topology structure, mapping the multi-source operating data to the attribute space of power grid topology nodes and edges to form a power grid operating state graph; The pre-trained inference model is trained and optimized, in the training process, power physical constraints are introduced, and power flow balance, power conservation and short-circuit current electrical equations are taken as constraint conditions to ensure that the operation state prediction output by the inference model meets the electrical feasible region; the power grid maintenance period constraint is converted into a feasible region embedding vector and input to the inference model as a condition, so that the inference model automatically avoids the maintenance scheme inconsistent with the load curve, standby capacity and dispatch approval in the inference process; a risk transmission chain model is established, the influence of potential faults is propagated along the power grid topology path, and the inference model is optimized through a chain inference loss function, so that it can predict the cascading effect of equipment failure; Based on the output result of the inference model, a maintenance action sequence that meets the power grid maintenance period feasible region and can minimize risk transmission is generated to guide the operation and maintenance of power grid assets.

[0006] Further, the historical maintenance work order and maintenance record are digitally processed, and the converted data is indexed with the device number as the index key, and the device operation monitoring data and environmental data are established in a unified index relationship, and stored in the central maintenance database.

[0007] Further, the power grid topology structure refers to a graph structure formed by taking power grid equipment as nodes and the electrical connection relationship between devices as edges; The nodes include transformers, buses, circuit breakers, disconnectors, cables and transmission line endpoints, and the edges include lines, bus connections and switch access relationships; The attribute space refers to a set of numerical or categorical features attached to the nodes and edges, used to store operation data related to nodes or edges.

[0008] Further, the device monitoring data is stored in a real-time database, and the device number is used as the unique index identifier. By comparing the node number in the topology file with the device number in the database, data binding is achieved.

[0009] Further, a node list and an edge list are generated according to the topology file, and an index relationship is established; the data in the monitoring database and the environmental database are filled into the attribute set of the corresponding nodes and edges according to the index number; the filled node attributes and edge attributes are stored as node attribute matrix and edge attribute matrix respectively.

[0010] Further, the power flow balance refers to the balance relationship that should be met between the power injected at each node and the branch power in the power system, to ensure that the system operation state and power distribution are consistent; The power conservation refers to the balance between the injected power and the outgoing power at any node, and the power cannot increase or disappear without reason; The short-circuit current refers to the maximum value of branch current of the power system when a fault occurs, which is determined by the grid topology and impedance, and is an important parameter for testing the safety of equipment operation. The electrical feasible region refers to a state set jointly limited by electrical constraint equations, and only the operating state falling into the set is considered as an effective state conforming to the electrical law.

[0011] Further, the grid maintenance period constraint refers to a maintenance allowed window jointly determined by system operating conditions and dispatching rules, including load curve constraints, reserve capacity constraints, and dispatching approval constraints. The load curve constraint refers to the condition that the grid limits part of the equipment shutdown during the high load period, the reserve capacity constraint refers to the condition that sufficient reserve power capacity must be maintained in the system during equipment maintenance, and the dispatching approval constraint refers to the condition that the maintenance scheme needs to be approved by the dispatching department before implementation under the premise of conforming to the operating safety boundary. The feasible region embedding vector refers to the condition channel that converts the above constraint conditions into numerical form through a feature method and inputs the reasoning model in the form of a vector.

[0012] Further, the conduction coefficient of each edge is calculated, a monotone decreasing mapping of impedance modulus value, a monotone increasing mapping of power relative to rated value, and a monotone increasing mapping of environmental stress factor are weighted combined, and the result is limited in the interval of zero to one through compression mapping to obtain a weighted topology matrix; then a finite step propagation calculation is performed to accumulate the influence from upstream nodes layer by layer to obtain the risk intensity distribution of all nodes in the grid, and finally a chain reasoning loss function is constructed with reference to the theoretical conduction result.

[0013] Further, the chain reasoning loss function is: Let the grid contain N nodes, W be an edge weight matrix of size N x N, and element represent the conduction coefficient from node i to node j, with a value range of 0 to 1, s be a seed vector of size N, and element represent the initial influence value at node i, 0 < θ < 1 be a propagation attenuation factor, K be an upper bound of the number of propagation steps, and T be a reference conduction matrix calculated from electrical equations and historical samples. Define the propagation prediction vector of the model: , Define the theoretical propagation vector: , The chain reasoning loss function is: , wherein, and are non-negative weight coefficients used to balance node-level consistency and multi-step path consistency, denotes the k-th power of matrix W, measuring the cumulative effect of path propagation with length k, denotes the two-norm, denotes the k-th power of theoretical propagation matrix, reflecting the propagation result of path with length k under the theoretical model.

[0014] Further, the maintenance action sequence refers to a set composed of a series of ordered maintenance operation steps, which include one or more combinations of load transfer, switch operation, device de-parallel operation, on-site maintenance, test verification, and device restoration.

[0015] The present application can ensure that the output result is both consistent with the engineering implementability and can effectively control the cascading risk in the maintenance scheme generation link by combining the power grid operation data, physical constraint conditions, and reasoning large model. In this process, the inference ability of the reasoning model is no longer limited to the single-point state of the device, but realizes the optimization at the system level through topological propagation and time period feasible region constraints. The beneficial effects of the method are reflected in the following aspects: Firstly, the present application can significantly improve the scientificity and rationality of the maintenance scheme. Since the constraint conditions of electrical physical equations and the time period feasible region of the power grid are introduced in the reasoning process, the maintenance action sequence output by the model always remains consistent with the power flow balance, power conservation, and dispatching approval window, thereby avoiding the unimplementable scheme caused by ignoring physical laws or external limitations in traditional methods.

[0016] Secondly, the present application can effectively reduce the systemic risk. By establishing a risk transmission chain model and propagating the potential fault impact along the power grid topology path, the reasoning model can not only predict the operation risk of the device itself, but also identify the cascading effect, preferentially cut off the high-risk transmission path, and finally generate a maintenance sequence that can minimize the risk diffusion. This mechanism enables the maintenance process to not only solve the device hidden danger, but also ensure the stability of the overall power grid.

[0017] In summary, the implementation of the present application can realize the transformation of power grid asset operation and maintenance from experience-driven to intelligent decision-making, not only improving the efficiency and accuracy of scheme generation, but also ensuring the safety and economy of maintenance execution, providing a strong support for building a highly reliable modern power grid. BRIEF DESCRIPTION OF DRAWINGS

[0018] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the prior art, the following will briefly introduce the drawings needed to be used in the embodiments. Obviously, the drawings in the following description are only some embodiments of the present application, and other drawings can also be obtained by those skilled in the art without creative labor.

[0019] Figure 1 is the main flowchart of the present application; Figure 2 is the schematic diagram of power grid operation state; Figure 3 is the schematic diagram of reasoning model avoidance; Figure 4 is the schematic diagram of risk transmission. DETAILED DESCRIPTION

[0020] In order to make the objectives, technical solutions and beneficial effects of the present application clearer and more apparent, the present application will be further described in detail below in conjunction with embodiments. It should be understood that the following embodiments are only used to illustrate the present application, and are not used to limit the protection scope of the present application.

[0021] As shown in Figure 1 , the present embodiment provides a method for performing operation and maintenance of power grid assets based on a reasoning large model, which can combine the operation characteristics of power grid assets and the electrical physical constraint conditions to perform targeted training and optimization on a pre-trained reasoning model, so as to generate an intelligent maintenance scheme conforming to the operation rules and maintenance conditions of the power grid. The method as a whole includes the following stages: In the process of operation and maintenance of power grid assets, the device state is comprehensively affected by multiple factors, including real-time monitored electrical quantity parameters, dynamic conditions of external operating environment, and historical maintenance and fault conditions. If only relying on a single source of data, it is often difficult to accurately reflect the overall operation state of the device, thereby causing the reasoning model to lack the mastery of global information in the subsequent training and application process. In order to improve the understanding ability of the reasoning large model to the operation rules of the power grid assets, it is necessary to establish a comprehensive data input basis to ensure that the model can simultaneously perceive the internal state of the device, the external operating conditions and the historical evolution trajectory. For this purpose, multi-source operation data of the power grid assets are collected, including device state monitoring data, operating environment parameters and historical maintenance records.

[0022] The device state monitoring data refers to real-time parameters obtained by sensors, protection devices and monitoring systems installed on power grid devices, typical parameters including voltage, current, power, temperature, oil pressure, partial discharge intensity, etc.

[0023] The operating environment parameters refer to external conditions in the external environment of the power grid device that may affect its operation, typical parameters including air temperature, humidity, rainfall, wind speed, air salt fog content and geographical altitude.

[0024] The historical maintenance records refer to work order data, fault logs and maintenance reports formed by the power grid operation department in the past maintenance and fault handling process, which can reflect the deterioration trend, hidden danger position and common fault mode of the device.

[0025] In the implementation process, first, a plurality of types of sensor networks are deployed at the end of the power grid equipment, the sensors including voltage sensors, current transformers, temperature sensors, oil pressure sensors, partial discharge sensors, vibration sensors, etc., and the sensors are connected with remote terminal units through local acquisition modules. The remote terminal units are used for preprocessing the original signals collected by the sensors, including noise filtering, preliminary outlier rejection, and data compression, and transmitting the processed monitoring data to a central data platform in real time through communication links such as optical fiber private lines, microwave communication, or wireless public network private networks. In this way, the device operating parameters can be preliminarily cleaned and standardized at the acquisition end, reducing the subsequent processing burden.

[0026] Then, an external meteorological database and an environmental monitoring system are called, the meteorological database being a national or regional meteorological information platform accessed by the power grid dispatching department, which can provide meteorological data such as temperature, humidity, wind speed, rainfall, and ice and snow load. The environmental monitoring system is an environmental sensing device deployed in the power grid operation area, which can collect external parameters related to electrical equipment operation such as air salt spray concentration, pollutant concentration, altitude, and soil humidity. The meteorological data and environmental monitoring data are written into the central data platform according to a fixed sampling period, and a spatial mapping relationship is established with the power grid equipment in the corresponding area.

[0027] Further, historical maintenance work orders and repair records are digitized, which are usually stored in the form of paper archives or unstructured electronic documents. To ensure consistency with real-time data in subsequent processing, first, the optical character recognition method or text structured annotation method is used to convert such materials into a standardized data format. The converted data is indexed by device number, and a unified index relationship is established with the operation monitoring data and environmental data of the device, and stored in the central maintenance database. The database can support multi-dimensional queries, including quick retrieval by device, time, fault category, or maintenance measures.

[0028] After the above multi-source data is collected into the central data platform, it is standardized by a unified data access module. The data access module first converts the data formats from different sources, converting data of multiple sampling frequencies and unit systems into a unified standard system. For example, time scale normalization is performed on meteorological data collected at intervals of minutes and current monitoring data collected at intervals of seconds. Subsequently, based on a unified timestamp mechanism, the various types of data are aligned to eliminate time deviations caused by inconsistent sampling intervals. Finally, a mapping table is established using a unified naming specification to address differences in data naming rules between different monitoring systems and maintenance systems, so that data from different sources can be consistently stored and called.

[0029] Specifically, in the operation scenario of a certain 220kV main transformer, the real-time collected oil temperature data is 85℃, the winding current data is 620A, the external environment temperature is 35℃, the humidity is 78%, and the historical maintenance record shows that the main transformer has occurred twice sleeve discharge fault in the past three years. Through the above data collection and unified processing, the operation status of the main transformer can be completely described in the power grid operation state diagram, which provides effective support for the subsequent training and optimization of the reasoning model.

[0030] In the process of power grid operation and maintenance, power grid assets do not operate in isolation, and the operation status of a single device is often affected by its position in the topology, the connection mode with adjacent devices, and the overall power flow distribution of the system. If only single device data is used as input, it is easy to ignore the systemic risk and chain effect. Therefore, it is necessary to build a topology structure that can reflect the relationship between devices and the overall operation constraints, and map the multi-source data of different sources to the topology nodes and edges, so as to form a power grid operation state diagram that can fully describe the operation characteristics of the power grid. Therefore, the power grid topology structure is constructed, and the multi-source operation data is mapped to the attribute space of the power grid topology nodes and edges to form the power grid operation state diagram.

[0031] In the present application, the power grid topology structure refers to a graph structure formed by taking power grid devices as nodes and electrical connection relationship between devices as edges, which can reflect the coupling relationship between devices in the power grid.

[0032] The nodes include transformers, buses, circuit breakers, disconnectors, cables and transmission line endpoints, and the edges include line, bus tie and switch access relationship. The attribute space refers to a set of numerical or categorical features attached to the nodes and edges, used to store operation data related to the nodes or edges.

[0033] The power grid operation state diagram refers to a graph data model with state information formed by combining the topology structure and the attribute space, used to describe the overall operation of the power grid at a specific time.

[0034] In the specific implementation process, first, the topology connection relationship of the power grid devices is obtained, which can reflect the physical access mode and electrical connection logic of various devices in the power grid. This relationship is usually derived from the main wiring diagram or power network model file maintained by the power grid dispatching control system. The main wiring diagram represents the connection mode between transformers, buses, switches and lines in a graphical manner, and the network model file stores the connection attributes and operation parameters between devices in a structured data manner. By analyzing the above files, the set of device nodes and the connection relationship between nodes can be obtained, thereby forming the initial topology framework of the power grid.

[0035] Then, the device node number is corresponded with the device number of the multi-source operation data, ensuring that each node in the topology can establish a mapping relationship with its monitoring data. Specifically, the device monitoring data is usually stored in a real-time database, and the device number is used as a unique index identifier. By comparing the node number in the topology file with the device number in the database, data binding can be achieved. For example, when the topology file contains a main transformer node numbered T1, the device monitoring data numbered T1, such as oil temperature, current, and partial discharge signal, can be found in the operation database, and the data is attached to the attribute set of node T1.

[0036] Further, the attributes of the line side are set as transmission power, current, impedance and other parameters. The transmission power and current are collected in real time by the line monitoring device or the online monitoring system, and the impedance value is provided by the design archives or historical test data. When establishing the attributes of the side, external condition attributes need to be attached to the side in combination with meteorological and environmental data to reflect the influence of the external environment on the line operation capacity. For example, when the line is in a high-temperature, strong-wind or high-humidity environment, its current-carrying capacity will change, so a correction factor needs to be introduced in the attribute set of the side to adjust the rated operation capacity of the line.

[0037] The mapping process is realized by a topology modeling module, which is a functional component for processing power grid multi-source heterogeneous data. This module can convert data from different sources into a unified data structure. The implementation of this module is as follows: first, generate a node list and an edge list according to the topology file, and establish an index relationship; second, fill the data in the monitoring database and the environmental database into the attribute sets of the corresponding nodes and edges according to the index number; finally, store the filled node attributes and edge attributes as a node attribute matrix and an edge attribute matrix respectively, wherein the node attribute matrix is used to describe the operation state of each device, and the edge attribute matrix is used to describe the transmission characteristics and external influences of the lines and switches. The node attribute matrix and the edge attribute matrix are stored together with the topology connection relationship as a graph data structure for subsequent reasoning model calling and processing.

[0038] In the above manner, the organic combination of the power grid topology structure and the multi-source operation data can be realized, so that the operation data not only exists in the form of isolated numerical values, but also is embedded in the topology structure as the attributes of nodes or edges, thereby forming a power grid operation state graph that can reflect the overall operation characteristics of the power grid.

[0039] Specifically, as shown in Figure 2 In a regional power grid, there are the following devices: The main transformer T1 has a rated voltage of 220 kV, and the real-time monitoring parameters are oil temperature 85°C, winding current 620 A, and historical maintenance records show that there have been two sleeve discharge faults in the past three years.

[0040] Bus B1, real-time monitoring voltage is 219 kV, current load power is 150 MW.

[0041] Transmission line L1, connecting main transformer T1 and bus B1, monitoring current is 550 A, impedance is 0.23 Ω. The ambient temperature recorded by the environmental monitoring system is 35 °C, and the wind speed is 2.8 m / s, which will correct the current-carrying capacity of the line.

[0042] Transmission line L2, extending from bus B1 to external substation node B2, monitoring current is 430 A, impedance is 0.31 Ω, external environmental humidity is 78%, which will affect the insulation safety of the line.

[0043] External substation B2, voltage is 220 kV, load power is 180 MW, no major fault events in historical operation records.

[0044] In constructing the power grid operation state diagram, main transformer T1, bus B1 and external substation B2 are respectively taken as nodes, and transmission lines L1 and L2 are taken as edges. The nodes and edges are attached with corresponding attribute information, forming a graph structure with attributes.

[0045] The pre-trained inference model refers to a deep learning model that has completed basic training on a large-scale data set and has general pattern recognition and logical reasoning capabilities. Such models learn universal laws through multi-modal data or large-scale time series data in the pre-training stage, thereby showing strong generalization ability in different tasks. The optional implementation of the pre-trained inference model includes but is not limited to the general large model DeepSeek model, GPT model, LLaMA model, as well as the graph neural network model for graph structure analysis and the Transformer model for time series prediction.

[0046] Since the above pre-trained inference model has mastered basic capabilities such as time series pattern, spatial topological relationship and semantic understanding in the training process, and power grid asset operation and maintenance data naturally have time series, topological and semantic properties, the power grid specific operation data can be mapped to the input space of such models, and the power grid exclusive physical constraints and operation rules can be introduced through retraining or fine-tuning. This can quickly realize the migration and adaptation to the power grid operation and maintenance scene on the basis of the existing reasoning ability, avoiding the high data and computing cost required for training the model from scratch.

[0047] If the general pre-trained model is used directly without targeted training and optimization, the output result may not conform to the electrical physical law, may not meet the power grid maintenance period constraint, and may lack the judgment of the risk conduction effect between devices, resulting in the generated maintenance scheme lacking implementability and professionalism. Therefore, targeted training and optimization are needed on the basis of the pre-trained model, so that the model has the understanding ability of the operation characteristics of the power grid assets while maintaining the general inference ability, and can generate a maintenance scheme that conforms to the electrical law, the dispatching requirements and the system risk constraints.

[0048] In power grid operation and maintenance, the device operating state not only depends on the monitoring data, but also is strictly constrained by the physical law of the power system. If the inference model only relies on data-driven in the training process without considering the electrical law, it may produce prediction results that violate the principles of power flow distribution, power conservation or short-circuit current calculation, thereby leading to the infeasibility of the maintenance recommendations in actual implementation, and even introducing new system risks. Therefore, it is necessary to introduce power physical constraints in model training, so that the inference model learns data features while always following the basic rules of power grid operation. To this end, in the training process, the power physical constraints are introduced, and the power flow balance, power conservation and short-circuit current electrical equations are used as constraint conditions to ensure that the operating state prediction output by the inference model meets the electrical feasible region.

[0049] The power flow balance refers to the balance relationship that should be met between the power injected at each node and the branch power in the power system, which is used to ensure that the system operating state and power distribution are consistent.

[0050] The power conservation refers to the fact that at any node, the sum of the injected power and the outgoing power remains balanced, and there is no case of power increasing or disappearing without reason.

[0051] The short-circuit current refers to the maximum value of the branch current when the power system fails, which is determined by the topology and impedance of the power grid, and is an important parameter for testing the safety of device operation.

[0052] The electrical feasible region refers to the state set defined by the above electrical constraint equations. Only the operating state falling into this set is considered to be an effective state that conforms to the electrical law.

[0053] In the implementation process, first, a loss function structure with power physical constraints is established for the inference model in the training data processing stage. The loss function not only includes a conventional prediction error term for measuring the deviation between the model output and the actual monitoring data, but also further introduces the residuals of power flow balance, power conservation and short-circuit current, etc. electrical equation as additional constraint factors to participate in optimization together. In this way, the inference model is driven by two factors during the learning process. On the one hand, it approximates the actual observation data, and on the other hand, it strictly follows the physical laws of the power system, thereby ensuring that the model obtained during training converges to a unified state between prediction ability and physical rationality.

[0054] For the power flow balance constraint, at each node of the power system, the active power and reactive power injected by the node should be equal to the algebraic sum of the power flowing in or out through adjacent branches. During training, first, the node voltage amplitude and voltage phase angle parameters predicted by the model are used to solve the power flow of each branch according to the power flow calculation formula, and then the calculated branch power is aggregated to the corresponding node to construct the node power balance equation. By comparing the predicted node power with the theoretical balance condition, the residual obtained is the power flow balance residual, which is introduced as a constraint term into the loss function. During the iterative optimization process, the model parameters will be continuously adjusted under the action of the constraint term, so that the prediction result gradually approaches the power flow balance condition, avoiding states that do not conform to the power distribution rules of the power grid.

[0055] For the power conservation constraint, at any node of the power system, the injected power and the outgoing power must strictly maintain the conservation relationship. To achieve this, the injected power of the node predicted by the inference model and the outgoing power of the adjacent lines are differentiated, and the power conservation residual is obtained after squaring or weighting the difference. This residual is set as a penalty term in the loss function, prompting the model to avoid outputting results that do not satisfy the power conservation law during training. In this way, it can effectively ensure that the node energy exchange process conforms to the electrical physical laws, thereby improving the feasibility of the overall prediction.

[0056] For the short-circuit current constraint, when a fault occurs in the power system, the size of the short-circuit current is determined by the network topology and branch impedance. In the implementation, first, a node impedance matrix is constructed based on the power grid topology, and the theoretical short-circuit current under the condition of short-circuit at a specific node is calculated according to the electrical theory method, which is taken as the reference result. Then, the predicted short-circuit current value obtained by the inference model is compared with the reference value, and the deviation between the two is calculated to form the short-circuit current constraint residual. This residual is written into the loss function as an additional constraint term and repeatedly participates in parameter updating during the training iteration process, forcing the model to correct the prediction result of the short-circuit current during the learning process, so that the prediction gradually converges to a range consistent with the electrical theory.

[0057] During the training iteration process, the model is repeatedly executed through forward propagation and backward update, while minimizing the prediction error term and the electrical equation constraint residual. Finally, in the state of convergence, the model can not only give the prediction results close to the monitoring data, but also ensure that these prediction results are located within the electrical feasible region. Through this training method, the inference model not only accurately captures the trend of the device running state, but also always maintains consistency with the electrical physical law, thereby providing reliable data support for power grid operation and maintenance decision-making.

[0058] In a certain regional power grid, there is a 220kV main transformer T1, a section of bus B1, two transmission lines L1 and L2, and an external substation B2. The specific situation is as follows: Main transformer T1: the predicted winding current is 620A, the oil temperature is 85℃, and the historical maintenance record shows that there have been two sleeve discharge faults in the past three years.

[0059] Bus B1: the predicted voltage is 219kV, and the predicted power injection is 150MW.

[0060] Transmission line L1: connecting the main transformer T1 and the bus B1, the predicted transmission current is 550A, and the impedance is 0.23Ω. When the external air temperature is 35℃ and the wind speed is 2.8m / s, the current-carrying capacity is corrected to 530A.

[0061] Transmission line L2: connecting bus B1 and external substation B2, the predicted transmission current is 430A, and the impedance is 0.31Ω. When the external humidity is 78%, the insulation safety margin decreases by 5%.

[0062] External substation B2: the predicted voltage is 220kV, and the load power is 180MW.

[0063] In this operating state, the prediction results of the inference model will be subjected to the following constraint tests: Power flow balance constraint: the power injection of bus B1 node 150MW should be equal to the sum of the power flow of L1 and L2 lines. If the difference is not zero, a power flow residual is formed and is subjected to constraint in the loss function.

[0064] Power conservation constraint: the predicted injection power of T1 node must be equal to the power flowing out of L1, and the injection power of B2 node must be equal to the power flowing out of L2. If they are not equal, a conservation residual is formed.

[0065] Short-circuit current constraint: assuming that a single-phase ground fault occurs at B1 node, the theoretical short-circuit current is 9.8kA based on impedance matrix calculation, while the model prediction result is 10.3kA. The deviation between the two is recorded as a short-circuit residual and is subjected to the loss function.

[0066] The model adjusts parameters to make the prediction result meet the electrical feasible region by minimizing the weighted sum of the prediction error, the power flow residual error, the power conservation residual error and the short-circuit current residual error in the process of training iteration.

[0067] In the process of power grid operation and maintenance, the maintenance behavior is not only affected by the equipment state, but also affected by the system load change, the spare capacity configuration and the maintenance period approved by the dispatching department and other external constraints. If the reasoning model is only based on the equipment operating state and historical data for reasoning without considering the above constraints, the maintenance scheme may be generated which does not conform to the actual operating conditions, for example, proposing the suggestion of shutting down the key equipment in the peak load period, or arranging a large range of maintenance in the case of insufficient spare capacity. Although such scheme is feasible at the data level, it cannot be executed in actual operation, and even may cause system operation risk. In order to ensure that the output result of the reasoning model has engineering implementability, it is necessary to convert the power grid maintenance period constraint into a form that can be processed by the model and embedded in the reasoning process, so as to fundamentally avoid the scheme that does not conform to the conditions. Therefore, the power grid maintenance period constraint is converted into a feasible region embedding vector and input as a condition to the reasoning model, so that the reasoning model automatically avoids the maintenance scheme that does not conform to the load curve, the spare capacity and the dispatching approval in the reasoning process.

[0068] The power grid maintenance period constraint refers to the maintenance allowed window determined by the system operating conditions and the dispatching rules, including the load curve constraint, the spare capacity constraint and the dispatching approval constraint.

[0069] The load curve constraint refers to the condition that the power grid limits part of the equipment shutdown in the high load period, the spare capacity constraint refers to the condition that sufficient spare power capacity must be maintained in the system during equipment maintenance, and the dispatching approval constraint refers to the condition that the maintenance scheme needs to be approved by the dispatching department before implementation under the premise of conforming to the operating safety boundary.

[0070] The feasible region embedding vector refers to the condition channel that converts the above constraint conditions into numerical form through the feature method and inputs the reasoning model in the form of a vector.

[0071] In the specific implementation process, first, the load curve of the power grid operation is time series segmented. The load curve refers to the function of the total power of the system changing with time within a certain time range, which usually has obvious periodicity and regularity, such as peak in the daytime, valley at night and transition stage of gradually rising or falling load. In the present application, the load curve of a day is divided into several periods, such as peak period, valley period and transition period. For each period, the representative load level parameters are extracted, including the maximum load, the minimum load and the average load, and the parameter values are mapped into interval vectors after being numerized. The interval vector is used as the feature expression of the load curve to identify the load state of different time periods.

[0072] Secondly, the standby capacity is calculated in real time. The standby capacity refers to the additional power capacity that can be provided in the power grid operation after removing the normal load, including rotating standby capacity and cold standby capacity. In the implementation process, the current operating state and output upper limit of each power generation unit or standby device are first obtained, and then the standby capacity value of each time period is calculated. The calculated standby capacity is compared with the preset minimum standby demand value. If the standby capacity is greater than or equal to the minimum demand, it is identified as sufficient capacity, and if the standby capacity is less than the minimum demand, it is identified as insufficient capacity. The identification information is further converted into binary or numerical feature input to reflect the safety margin of the power grid in the time period.

[0073] Further, the dispatch approval constraint is encoded. The power grid maintenance must be approved by the dispatch department and is limited by the approval window and the approval priority. The approval window refers to the specific time range allowed by the dispatch department for maintenance, and the approval priority refers to the sorting principle of the dispatch department for different maintenance tasks when multiple maintenance applications exist at the same time. In the implementation process, the approval plan provided by the dispatch system is first read, and the approval status is marked as a numerical label, such as approval status marked as 1 and unapproved status marked as 0. The time range corresponding to the approval window is mapped to the time period index. The approval priority is converted into a level code, such as priority 1 representing the highest priority and priority 3 representing a lower priority. After the above steps, the dispatch constraint feature label that can be directly input into the model is formed.

[0074] After the interval vector of the load curve, the sufficiency identification of the standby capacity, and the feature label of the dispatch approval constraint are uniformly processed, they are combined into a multi-dimensional embedding vector. The multi-dimensional embedding vector can represent the load condition, standby margin, and dispatch approval situation in the vector space at the same time. The embedding vector is continuously updated with real-time data of the power grid operation in the time dimension to ensure that the model always reasons based on the latest operating environment.

[0075] When the inference model receives the embedding vector, the model automatically calls the constraint information in the internal reasoning path generation stage. In the candidate maintenance scheme generation process, any scheme that does not meet the feasible region conditions described by the embedding vector will be directly excluded. For example, when the load is in the peak period, the standby capacity is insufficient, and the dispatch is not approved, even if the device state shows a potential fault, the model will not output the maintenance action scheme for that period, but will automatically postpone the maintenance to a period that meets the load curve trough, sufficient standby capacity, and dispatch approval. Finally, the model only generates maintenance action sequences within the feasible region conditions, thereby ensuring the engineering implementability and operational safety of the output results.

[0076] As Figure 3As shown, in a certain regional power grid, there is a 220 kV main transformer T1, a section of bus B1, and two transmission lines L1 and L2, which are connected to external substations B2 and regional load centers, respectively. The system operation data and constraint conditions are as follows: Load curve data: The load curve provided by the dispatching system shows that the load is maintained at 180 MW to 200 MW during the daytime 9:00-21:00, which is the peak period; the load decreases to 110 MW to 130 MW during the night 23:00-6:00, which is the valley period; and the load is in a gradually rising or falling state during the remaining time, which is the transition period. According to the segmentation rule, the peak, valley, and transition periods are mapped to interval vectors, with the peak period recorded as [0.8-1.0], the valley period recorded as [0.4-0.6], and the transition period recorded as [0.6-0.8].

[0077] Backup capacity data: During the peak period, the backup capacity is only 15 MW, while the minimum backup requirement specified by the dispatching is 20 MW, so it is marked as insufficient capacity. During the night low valley period, the backup capacity is 35 MW, which is greater than the minimum backup requirement, so it is marked as sufficient capacity. This capacity state is converted into a binary feature, with sufficient capacity marked as 1 and insufficient capacity marked as 0.

[0078] Dispatch approval data: The dispatching system approval plan shows that the 23:00-5:00 period on weekdays is the approved maintenance window, with priority 1 for critical equipment emergency maintenance and priority 3 for routine maintenance tasks. This period is marked as an available maintenance window, with the approval status coded as 1, the time period index as the night low valley interval, and the priority marked as 3.

[0079] By constructing a multi-dimensional embedding vector [load interval vector, backup capacity identifier, approval status and priority] from the above information, for example, at the night 23:00 time, the embedding vector is [0.4-0.6, 1, (1, 3)]. When the inference model receives this embedding vector, it will automatically identify it as a low load, sufficient capacity, and approved period when generating a maintenance plan, thereby allowing the output of a maintenance plan for the main transformer T1. If inference is performed at 10:00 during the day, the embedding vector is [0.8-1.0, 0, (0, -)], at which time the inference model will automatically exclude all maintenance plans, even if the T1 device status shows potential risks, the model will delay the maintenance recommendation to avoid unreasonable maintenance actions in periods of high load and insufficient capacity.

[0080] In the process of power grid operation and maintenance, the potential failure of a single device is often not limited to itself, but can also be transmitted to adjacent devices and downstream systems through the power grid topology, thereby triggering a series of cascading effects. If the inference model only makes isolated predictions for a single device without considering the risk transmission on the topology path, the generated maintenance scheme may underestimate the overall risk, leading to cascading failures during operation, and even causing large-scale power outages. Therefore, it is necessary to establish a risk transmission chain model to propagate the impact of potential failures along the power grid topology path, and optimize the inference model through a chain inference loss function, so that it can predict the cascading effects of device failures.

[0081] The risk transmission chain model refers to a path propagation model constructed on the power grid topology structure, which can simulate the transmission relationship between potential failures among devices and lines.

[0082] The chain inference loss function refers to, in the training process of the inference model, in addition to considering the prediction error of the device itself, the residual error of the result after the transmission of the fault influence on the topology path is calculated, and the chain constraint is applied to the loss function, so as to force the model to consider both the local device state and the system-level risk transmission characteristics when optimizing parameters.

[0083] In the specific implementation process, first, the power grid topology structure is modeled to form a set of node and edge relationships, the node is used to represent the electrical equipment such as transformer, bus, line end, circuit breaker, and the edge is used to represent the physical connection relationship between devices. Secondly, the initial impact value of the potential failure is set as a seed signal and injected into the fault device node, and propagated to the downstream in turn according to the topology connection. In the propagation process, a transmission coefficient is assigned to each edge, which is determined by the line impedance, the real-time power of the line and the environmental stress factor. Through the iterative propagation process, the risk intensity value of each node downstream under the influence of the fault is obtained. Then, the risk transmission prediction result generated by the inference model is compared with the theoretical transmission result calculated according to the electrical equation and historical samples, the residual error is calculated and written into the chain inference loss function. The chain inference loss function acts simultaneously with the conventional defined prediction error in the training process, so that the model considers both the single-point prediction correctness and the consistency of the cascading effect when updating parameters, thereby realizing the accurate characterization of the system-level risk.

[0084] For the convenience of understanding, the related terms are explained as follows. The initial impact value of potential fault refers to a non-negative quantity used to start the propagation calculation at the fault device node, indicating the fault injection strength of the node. The conduction coefficient refers to a proportional factor for transmitting the fault impact along the topology edge, with a value range of zero to one, and the greater the value, the easier the risk is transmitted along the edge. The risk intensity value refers to the quantitative value of the chain risk obtained by each node after the propagation ends. The theoretical conduction result refers to the benchmark propagation result obtained according to the power flow sensitivity, impedance parameter and historical outage sample, which is used as a reference for comparison in training. The chain reasoning loss function refers to a loss term for measuring the deviation between the predicted propagation result and the theoretical propagation result, and can be superimposed with path consistency constraints or stability constraints to improve the physical rationality of training convergence.

[0085] In the specific implementation process, first, the node set and edge set are parsed from the main wiring diagram or network model file derived from the dispatching system, a weighted adjacency matrix is constructed, and the consistency binding of device number and topology number is completed. Then in the fault diagnosis stage, the seed node and its initial impact value are determined according to the device state indicator, and the value is loaded into the propagation initial value vector. Further, the conduction coefficient of each edge is calculated, which is weighted combined by using a monotone decreasing mapping of impedance modulus value, a monotone increasing mapping of power relative rated value and a monotone increasing mapping of environmental stress factor, and the result is limited in the interval of zero to one through compression mapping to obtain a weighted topology matrix. Then, a limited step propagation calculation is performed, the influence from upstream nodes is accumulated layer by layer, and the risk intensity distribution of all nodes in the network is obtained. Finally, taking the theoretical conduction result as a reference, a chain reasoning loss function is constructed, and the prediction error and the chain loss are minimized in each training iteration, so that the model simultaneously meets the consistency constraints of data fitting and topology chain.

[0086] To ensure the clarity of implementation, a specific chain reasoning loss function is given. Let the power grid contain N nodes, W be the edge weight matrix of size N x N, and the element represent the conduction coefficient from node i to node j, with a value range of 0 to 1, s be the seed vector of size N, and the element represent the initial impact value at node i, 0 < θ < 1 be the propagation attenuation factor, K be the upper bound of the number of propagation steps, and T be the benchmark conduction matrix calculated from the electrical equation and historical samples. The propagation prediction vector of the model is defined as , The theoretical propagation vector is defined as , The chain reasoning loss function is , wherein, and are non-negative weight coefficients used to balance node-level consistency and multi-step path consistency. The meanings of the above symbols are as follows, represents the k-th power of the matrix W, and measures the cumulative effect of path propagation with a length of k, represents the two-norm, represents the k-th power of the theoretical propagation matrix, and reflects the propagation result of a path with a length of k under a theoretical model.

[0087] Through the above scheme, the trained inference model can accurately reflect the cascading propagation relationship of fault influence on the topology while maintaining single-point prediction accuracy, reduce the probability of underestimating systemic risk, and improve the global rationality when generating the maintenance action sequence.

[0088] As shown in FIG. 1, Figure 4 In a certain regional power grid, a simplified topology including a main transformer T1, a bus B1, and an external substation B2 is constructed. A transmission line L1 connects T1 and B1, and a transmission line L2 connects B1 and B2. The initial impact value of a potential fault is injected into T1, and the seed risk is set to 1.0. The propagation coefficients are calculated according to the impedance, load, and environmental stress. The propagation coefficient of L1 is set to 0.72, and the propagation coefficient of L2 is set to 0.64. The propagation attenuation factor is set to 0.8, and the propagation step number is set to 2. The amount propagated to B1 in the first step is 0.8*0.72, and the predicted risk of B1 is 0.576. The amount propagated along the path T1→B1→B2 in the second step is 0.8*0.8*0.72*0.64, and the predicted risk of B2 is 0.295. Based on the theoretical contrast estimated by the power flow sensitivity and historical samples, the theoretical risk of B1 is set to 0.560, and the theoretical risk of B2 is set to 0.270. The node-level residuals are obtained, and the residual of B1 is 0.016, and the residual of B2 is 0.025. During training, the above residuals and path component residuals are jointly counted into the chain inference loss, and are minimized synchronously with the conventional defined prediction error, so that the model approximates the electrically reasonable cascading propagation result while meeting the physical constraints.

[0089] In the process of power grid operation and maintenance, although the inference model can predict the potential fault of the equipment and the risk propagation situation at the topology level, if the result is not converted into an executable operation sequence, the maintenance measures cannot be implemented in engineering practice. The maintenance behavior must meet the time window approved by the dispatch, maintain sufficient standby capacity, and avoid conducting unstable factors on the path where the risk is easy to expand. If the model only outputs the risk score without giving the specific action sequence, the operation and maintenance personnel will have difficulty operating accordingly, and even may implement unreasonable maintenance tasks in the peak load or critical operation stage, thereby causing more serious cascading risks. Therefore, based on the output result of the inference model, a maintenance action sequence that meets the feasible region of the power grid maintenance period and can minimize risk propagation is generated to guide the operation and maintenance of the power grid assets.

[0090] The maintenance action sequence refers to a set composed of a series of ordered maintenance operation steps, including load transfer, switch operation, device outage, on-site maintenance, test verification, and device restoration.

[0091] The power grid maintenance time period feasible region refers to an allowed time range formed after considering load curve constraints, reserve capacity constraints, and dispatch approval constraints, which ensures that the operations performed within this range will not negatively affect system operation stability.

[0092] The risk propagation minimization refers to, when generating the action sequence, preferentially arranging maintenance operations that can effectively cut off high-risk propagation paths to reduce the likelihood of cascading effects.

[0093] In the specific implementation process, first, the inference model outputs the list of potential faulty devices, risk propagation paths, and risk intensity evaluation values, and extracts the feasible region information of the current operating period. Second, according to the time window of the feasible region, divide the candidate maintenance time period, and directly eliminate the time period that does not meet the dispatch approval or is insufficient in reserve capacity. Third, in the remaining candidate time period, sort the priority of potential faults, and preferentially handle devices that have a greater impact on system-level risks. Then, based on the topology path analysis results, arrange the maintenance action sequence that can quickly weaken the risk propagation, such as first performing load transfer, then isolating the fault node, and finally implementing maintenance in the isolated environment. Finally, arrange these actions in chronological order to form an action sequence that meets the constraint conditions.

[0094] In a preferred implementation, the maintenance action sequence introduces priority weights during generation, and devices that have the greatest impact on core nodes or important loads are preferentially included in the early part of the sequence, which has the beneficial effect of being able to more quickly reduce the overall risk level of the system.

[0095] In another preferred implementation, the generation of the maintenance action sequence combines resource allocation information, including personnel, tools, and parallel work capacity, to avoid generating actions that cannot be executed in the case of insufficient resources or unsuitable on-site conditions, which has the beneficial effect of ensuring that the maintenance plan is not only safe and feasible, but also practical.

[0096] In another preferred implementation, the maintenance action sequence adopts a rolling generation mechanism, forming an initial sequence before plan execution, and dynamically adjusting it during execution in combination with real-time operating data, which has the beneficial effect of enhancing the adaptability and robustness of the maintenance plan, and being able to respond to load fluctuations or emergencies.

[0097] The maintenance action sequence generated by the above method not only meets the constraints of dispatch approval and spare capacity, but also effectively cuts off the potential risk transmission path, controls the system operation risk during maintenance, and finally forms a maintenance plan that has both engineering implementability and improved overall operation safety.

[0098] In a specific example, the scenario of the main transformer T1, the bus B1, the external substation B2 and the lines L1 and L2, the inference model predicts that T1 has a potential insulation deterioration fault, and the risk is transmitted to B2 along L1 and L2, causing the risk of downstream load to increase. In the dispatch-approved night low-load window, the generated maintenance action sequence includes the following steps: first, transfer part of the load to the standby power supply path before the beginning of the window; second, split T1 and perform a safety grounding measure; third, the on-site personnel perform sleeve and oil sample detection on T1; fourth, implement insulation defect treatment and sealing reinforcement; fifth, remove the grounding and gradually restore the switch after completing the maintenance; sixth, restore the original topology and monitor the stability of the power flow. The sequence successfully cuts off the high-risk transmission path under the premise of ensuring sufficient spare capacity and dispatch approval conditions, significantly reduces the system risk metric, and embodies the implementability and beneficial effects of the method in engineering practice.

[0099] The part of the module structure of the present application which is not specifically defined shall be subject to the content described in the prior art. The prior art mentioned in the foregoing background section and the specific embodiment section of the present application can be used as a part of the present application to understand the meaning of some technical features or parameters.

Claims

1. A method for performing operation and maintenance of power grid assets based on a reasoning large model, characterized in that, The method comprises the following steps: Collecting multi-source operation data of power grid assets, the data comprising equipment state monitoring data, operation environment parameters and historical maintenance records; Constructing a power grid topology structure, mapping the multi-source operation data to the attribute space of the nodes and edges of the power grid topology structure, and forming a power grid operation state graph; Training and optimizing the pre-trained inference model, in the training process, introducing power physical constraints, taking the power flow balance, power conservation and short-circuit current electrical equations as constraint conditions to ensure that the operation state prediction output by the inference model meets the electrical feasible region; converting the power grid maintenance period constraint into a feasible region embedding vector and inputting it into the inference model as a condition to make the inference model automatically avoid maintenance schemes that do not match the load curve, standby capacity and dispatch approval in the inference process; establishing a risk transmission chain model to propagate the impact of potential faults along the topology path of the power grid, and optimizing the inference model through a chain inference loss function to enable it to predict the cascading effect of equipment failure; Based on the output results of the inference model, generating a maintenance action sequence that meets the power grid maintenance period feasible region and can minimize risk transmission, for guiding the operation and maintenance of power grid assets.

2. The method for operation and maintenance of power grid assets based on the reasoning large model according to claim 1, characterized in that, Digitizing historical maintenance work orders and maintenance records, and storing the converted data in the central maintenance database with the equipment number as the index key, and establishing a unified index relationship with the equipment operation monitoring data and environment data.

3. The method for operation and maintenance of power grid assets based on the reasoning large model according to claim 1, characterized in that, The power grid topology structure refers to a graph structure formed by taking power grid equipment as nodes and the electrical connection relationship between devices as edges; The nodes include transformers, buses, circuit breakers, disconnectors, cables and transmission line endpoints, and the edges include lines, bus connections and switch access relationships; The attribute space refers to a set of numerical or categorical features attached to the nodes and edges, used to store operation data related to the nodes or edges.

4. The method for operation and maintenance of power grid assets based on the reasoning large model according to claim 1, characterized in that, The equipment monitoring data is stored in a real-time database, with the equipment number as the unique index identifier. By comparing the node number in the topology file with the equipment number in the database, data binding is achieved.

5. The method for operation and maintenance of power grid assets based on the reasoning large model according to claim 4, characterized in that, According to the topology file, a node list and an edge list are generated, and an index relationship is established; the data in the monitoring database and the environment database are filled into the attribute set of the corresponding nodes and edges according to the index number; the filled node attributes and edge attributes are stored as a node attribute matrix and an edge attribute matrix, respectively.

6. The method for operation and maintenance of power grid assets based on the reasoning large model according to claim 1, characterized in that, The power flow balance refers to the balance relationship that should be met between the power injected at each node and the branch power in the power system, to ensure that the system operation state and power distribution are consistent; The power conservation refers to the fact that at any node, the sum of the injected power and the outgoing power remains balanced, and there is no power increase or disappearance without reason; The short-circuit current refers to the maximum value of the branch current when a fault occurs in the power system, which is determined by the topology and impedance of the power grid and is an important parameter for testing the safety of equipment operation; The electrical feasible region refers to the state set defined by the electrical constraint equations, and only the operation state falling into this set is considered to be an effective state that meets the electrical rules.

7. The method for operation and maintenance of power grid assets based on the reasoning large model according to claim 1, characterized in that, The power grid maintenance period constraint refers to a maintenance allowable window determined by system operation conditions and dispatching rules, including a load curve constraint, a reserve capacity constraint, and a dispatch approval constraint; The load curve constraint refers to a condition that the power grid limits part of the device shutdown during a high load period, the reserve capacity constraint refers to a condition that sufficient reserve power capacity must be maintained in the system during device maintenance, and the dispatch approval constraint refers to a condition that a maintenance scheme needs to be approved by the dispatch department before being implemented on the premise of meeting the operation safety boundary; The feasible region embedding vector refers to a condition channel in which the constraint conditions are converted into numerical forms by a feature method and input into a reasoning model in a vector manner.

8. The method for operation and maintenance of power grid assets based on the reasoning large model according to claim 1, characterized in that, The conductance coefficient of each edge is calculated, a weighted combination of a monotone decreasing mapping on the impedance modulus value, a monotone increasing mapping on the power relative rated value, and a monotone increasing mapping on the environmental stress factor is performed, and the result is limited in the interval of zero to one through a compression mapping to obtain a weighted topology matrix; then a finite step propagation calculation is performed to accumulate the influence from upstream nodes layer by layer to obtain a risk intensity distribution of nodes in the whole network, and finally a chain reasoning loss function is constructed with reference to a theoretical propagation result.

9. The method for operation and maintenance of power grid assets based on the reasoning large model according to claim 1, characterized in that, The chain reasoning loss function is: Let the power grid contain N nodes, W be an edge weight matrix of size N x N, element represent the conduction coefficient from node i to node j, with a value range of 0 to 1, s be a seed vector of size N, element represent the initial influence value at node i, 0 < θ < 1 be a propagation attenuation factor, K be an upper bound of the propagation step number, and T be a reference conduction matrix calculated from the electrical equation and historical samples; A propagation prediction vector of the model is defined as: , A theoretical propagation vector is defined as: , The chain reasoning loss function is: , wherein, and are non-negative weight coefficients balancing node-level consistency with multi-step path consistency, denotes the k-th power of the matrix W, measuring the cumulative effect of the propagation of paths of length k, denotes the two-norm, denotes the k-th power of the theoretical propagation matrix, reflecting the propagation result of paths of length k under the theoretical model.

10. The method for operation and maintenance of power grid assets based on a reasoning large model according to claim 1, characterized in that, The maintenance action sequence refers to a set composed of a series of ordered maintenance operation steps, and the operations include one or a combination of load transfer, switch operation, device disconnection, on-site maintenance, test verification, and device recovery.

Citation Information

Patent Citations

  • Power distribution network reconstruction coordination maintenance model considering voltage deviation

    CN114297828A

  • Power grid fault power protection maintenance plan making method, device, equipment and medium

    CN118504939A

Cited By

  • Graph neural network and large model fused power grid power flow online calculation method and equipment

    CN121456258A