Pile foundation construction method in continuous water pond environment

By constructing a working platform and water passage in a continuous pond environment and utilizing topographical differences for drainage, the high construction cost and long cycle of existing technologies have been solved, achieving efficient and economical pile foundation construction.

CN122406750APending Publication Date: 2026-07-17CCCC FOURTH HARBOR ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
CCCC FOURTH HARBOR ENG CO LTD
Filing Date
2026-06-15
Publication Date
2026-07-17

AI Technical Summary

Technical Problem

When carrying out pile foundation construction in a continuous pond environment, existing technologies require the complete pumping and backfilling of the entire pond, resulting in high construction costs and long construction periods.

Method used

The main construction access road was constructed by filling the longitudinal embankment along one side of the pond, and construction proceeded from the lower end of the pond to the upper end. The access road was used to fill the pond body to build a working platform, and water passages were excavated between the pond bodies. The terrain differences were used to drain water, reducing the amount of backfill soil and water pumping. A mud pit was reserved for mud circulation, and the water passages were sealed to control the water flow.

Benefits of technology

It reduces construction costs and time, and provides an efficient and economical pile foundation construction solution by optimizing the construction process and utilizing topographic differences for drainage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN122406750A_ABST
    Figure CN122406750A_ABST
Patent Text Reader

Abstract

本发明涉及桩基工程领域,具体涉及一种连续水塘环境下的桩基施工方法,包括以下步骤:沿连续水塘一侧的纵向塘埂填筑出主施工便道;以第一个塘体作为当前塘体,对当前塘体进行抽水作业,通过主施工便道在当前塘体中填筑出作业平台;在当前塘体与相邻下一级塘体之间的横向塘埂上开挖出过水通道,使下一级塘体中的水能够排向当前塘体中,通过主施工便道在下一级塘体中填筑出对应的作业平台;将下一级塘体作为当前塘体,重复前一步骤直至全部塘体对应的作业平台均完成填筑,完成桩基施工。本发明能够降低回填的土方量和抽水量,进而大大节省了施工成本和施工周期,为连续水塘环境下的桩基施工提供了一种高效、经济的解决方案。