A BIM-based project progress and project payment management system and method

Through the BIM-based project progress and project payment management system, the problem of untimely data updates and disconnected management measures in BIM technology is solved, efficient management and accurate settlement of engineering projects are achieved, and management efficiency and settlement reliability are improved.

CN113591188BActive Publication Date: 2024-10-25GUANGZHOU INSTITUTE OF BUILDING SCIENCE CO LTD +1
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202110843917.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-07-26
Publication Date
2024-10-25
Estimated Expiration
2041-07-26

AI Technical Summary

Technical Problem

The application of BIM technology in construction project management has problems such as untimely data updates and disconnected management measures, resulting in poor data flow and affecting the management efficiency of project progress and project payment.

Method used

Design a BIM-based project progress and project payment management system, including a BIM model management module, project progress management module, material management module and project payment management module. Through the interconnection of these modules, the division and progress tracking of engineering projects can be realized. , material management and payment plan settings to ensure closed-loop data flow and information accuracy.

Benefits of technology

It improves the efficiency of project progress and project payment management, reduces the workload of managers, provides a reliable basis for project payment settlement, and reduces the occurrence of project disputes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113591188B_ABST
    Figure CN113591188B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of construction project management, and specifically discloses a BIM-based project progress and project payment management system and method, the system includes a BIM model management module, a project progress management module, a material management module and a project payment management module, the BIM model management module is used to establish a complete BIM model of the project, divide the project into a number of construction areas and sub-projects, and calculate the project quantity information for the construction areas and sub-projects; the project progress management module is used to set the project plan progress, generate the identification code of the current transportation, and obtain the actual progress of the project; the material management module is used to obtain the material entry information and the material exit information; the project payment management module sets the payment plan and settles the project payment. The present invention can obtain the real situation of the project, so that the relevant information forms a closed-loop circulation, reduces the workload of management personnel, improves management efficiency, and reduces project disputes.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of construction project management, and in particular to a BIM-based project progress and project payment management system and method. Background Art

[0002] Progress management is not only an important part of construction project management, but also an important part of reflecting the competitiveness of construction companies in the industry. In the process of engineering construction, the management level of project progress and project payment affects the construction cost and also determines the profit level of the construction company. Faced with the fiercely competitive construction market, how to improve the efficiency and level of project progress and project payment management and avoid the cost increase caused by material backlog, waste and progress delays has become an important issue facing construction companies.

[0003] The emergence of BIM (Building Information Modeling) provides a new tool for the management of construction projects. BIM technology can provide a complete and actual construction project information database for construction projects by establishing a virtual three-dimensional model of the construction project and combining other digital technology means. The BIM-based prefabricated building construction process data collaborative management system published in the invention patent application CN106600239A realizes the tracking and management of the production, storage, transportation and assembly of prefabricated building components by disassembling the BIM model into a prefabricated building component model and assigning coding information to each component; the building intelligent construction progress management method proposed in the invention patent application CN109872127A manages the construction progress by comparing the planned progress of the BIM model with the actual progress. However, in general, the current application of BIM technology in construction project management still faces problems such as untimely update of BIM model data and disconnection from management measures. The data flow problem has become an objective obstacle to the deep integration of BIM and construction project management.

[0004] Therefore, people in this field are in urgent need of finding a new technical solution to solve the above problems. Summary of the invention

[0005] In view of the technical problems in the prior art, the present invention provides a BIM-based project progress and project payment management system and method.

[0006] The present invention includes a BIM-based project progress and project payment management system, including a BIM model management module, a project progress management module, a material management module and a project payment management module, wherein:

[0007] The BIM model management module is connected to the project progress management module; the BIM model management module is used to establish a complete BIM model of the project; and, according to the current status of the project, project management requirements and project division strategy, divide the project into several construction areas and sub-projects; and, according to the BIM model, calculate the engineering quantity information for the construction areas and sub-projects;

[0008] The project progress management module is connected with the BIM model management module, the material management module and the project payment management module; the project progress management module is used to set the project plan progress at different time nodes for each construction area and each sub-item; and, collect and review the material entry declaration information, and generate the identification code of the current transportation after the successful review; and, collect and review the material exit declaration information, and generate the identification code of the current transportation after the successful review; and, collect statistics on the material entry information and material exit information in each construction area or sub-item, and compare them with the engineering quantity information calculated by the BIM model management module to obtain the actual progress of the corresponding construction area or sub-item;

[0009] The material management module is connected to the project progress management module; the material management module is used to obtain the corresponding material entry declaration information or material exit declaration information by scanning the identification code; and, obtain the material entry information and the material exit information; and, compare the material entry information with the material entry declaration information, compare the material exit information with the material exit declaration information, and if the comparison results are consistent, the material entry information and the material exit information are recorded;

[0010] The project payment management module is connected to the project progress management module; the project payment management module is used to set payment plans under different project plan progress according to the construction contract; and, after the actual progress of the project reaches the project plan progress, the project payment is settled according to the corresponding payment plan.

[0011] Furthermore, the BIM model management module is also used to:

[0012] Adjust the BIM model according to the actual progress of the project, and update the visual progress of the project in the BIM model.

[0013] Furthermore, the project progress management module is also used to:

[0014] Compare the actual progress of the project with the planned progress of the project at the corresponding time node. If the actual progress of the project lags behind the planned progress of the project, an alarm will be issued.

[0015] Furthermore, the material entry declaration information includes at least the material type, quantity, license plate number of the transport vehicle, and driver information; the material exit declaration information includes at least the material type, quantity, license plate number of the transport vehicle, and driver information.

[0016] Furthermore, the material management module includes an access control management submodule, a code scanning submodule, a material type identification submodule, a material weighing submodule and a material information collection module, wherein:

[0017] The access control management submodule is connected to the material information collection module. The access control management submodule is used to identify the license plate number of the transport vehicle and match it with the license plate number of the transport vehicle in the corresponding material entry declaration information or material exit declaration information. If the match is successful, the access control is opened;

[0018] The code scanning submodule is connected to the material information collection module, and is used to scan the identification code to obtain the corresponding material entry declaration information or material exit declaration information;

[0019] The material type identification submodule is connected to the material information collection module. The material type identification submodule is used to obtain the types of incoming materials and the types of outgoing materials;

[0020] The material weighing submodule is connected to the material information collection module. The material weighing submodule is used to obtain the weight of incoming materials and the weight of outgoing materials;

[0021] The material information collection module is connected to the access control management submodule, the code scanning submodule, the material type identification submodule, and the material weighing submodule respectively. The material information collection module is used to compare the type and weight of incoming materials with the material entry declaration information, and to compare the type and weight of outgoing materials with the material exit declaration information, and if the comparison results are consistent, the type and weight of incoming materials, the type and weight of outgoing materials and the license plate number of the transport vehicle are collected.

[0022] Furthermore, the project progress management module collects statistics on the material entry information and material exit information in each construction area or sub-project as follows:

[0023] The project progress management module collects statistics on the types and weights of incoming materials, and the types and weights of outgoing materials in each construction area or sub-project.

[0024] Furthermore, the payment plan includes the payment terms and payment ratios in the construction contract.

[0025] Furthermore, the BIM model management module calculates the engineering quantity information for the construction area and sub-projects according to the BIM model as follows:

[0026] The BIM model management module extracts the types of materials required for the construction area or sub-projects in the BIM model, and calculates the demand for each type of material.

[0027] The present invention also provides a method for managing project progress and project payment based on BIM, comprising:

[0028] Establish a complete BIM model for the project;

[0029] Divide the project into several construction areas and sub-projects according to the current status of the project, project management requirements and project division strategy;

[0030] Calculate the quantity information for the construction area and sub-projects based on the BIM model;

[0031] Set the project schedule at different time nodes for each construction area and each sub-project;

[0032] Set up payment plans for different project schedules according to the construction contract;

[0033] Collect and review the declaration information of incoming materials, and generate the identification code of the current transportation after successful review, or collect and review the declaration information of outgoing materials, and generate the identification code of the current transportation after successful review;

[0034] Scan the identification code to obtain the corresponding material entry declaration information or material exit declaration information;

[0035] Obtain material entry information and material exit information;

[0036] Compare the material entry information with the material entry declaration information, and compare the material exit information with the material exit declaration information, and if the comparison results are consistent, record the material entry information and material exit information;

[0037] Collect statistics on the material entry and exit information in each construction area or sub-project, compare with the engineering quantity information, and obtain the actual progress of the corresponding construction area or sub-project;

[0038] After the actual progress of the project reaches the planned progress, the project payment will be settled according to the corresponding payment plan.

[0039] Furthermore, the BIM-based project progress and project payment management method also includes:

[0040] Compare the actual progress of the project with the planned progress of the project at the corresponding time node. If the actual progress of the project lags behind the planned progress of the project, an alarm will be issued; and

[0041] Adjust the BIM model according to the actual progress of the project, and update the visual progress of the project in the BIM model.

[0042] The project progress and project payment management system and method based on BIM of the present invention uses BIM model as a carrier, relies on BIM model to generate several construction areas and sub-projects, and obtains the actual progress of the project in the corresponding construction area or sub-project through the management and statistics of material entry information and material exit information, so as to compare it with the planned progress of the project, and know the real situation of the project, so that the relevant information in the system forms a closed-loop circulation, which reduces the workload of management personnel and improves management efficiency. On the other hand, after the actual progress of the project reaches the planned progress of the project, the project payment is settled according to the corresponding payment plan, which provides a reliable reference and basis for the settlement of the project payment and reduces project disputes. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0044] Figure 1 This is a structural composition diagram of a BIM-based project progress and project payment management system according to an embodiment of the present invention;

[0045] Figure 2 This is a structural composition diagram of a material management module in a BIM-based project progress and project payment management system according to an embodiment of the present invention;

[0046] Figure 3 The following is a flowchart of a method for managing project progress and project payment based on BIM according to an embodiment of the present invention (I);

[0047] Figure 4 This is a step flow chart (II) of the BIM-based project progress and project payment management method according to an embodiment of the present invention. DETAILED DESCRIPTION

[0048] The following will be combined with the accompanying drawings in the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work belong to the protection scope of the present invention.

[0049] The present invention provides a BIM-based project progress and project payment management system, such as Figure 1 As shown, the management system includes a BIM model management module 10, a project progress management module 20, a material management module 30 and a project payment management module 40, wherein:

[0050] The BIM model management module 10 is connected to the project progress management module 20; the BIM model management module 10 is used to establish a complete BIM model of the engineering project; and, according to the current status of the project, project management requirements and project division strategy, divide the engineering project into several construction areas and sub-projects; and, calculate the engineering quantity information for the construction areas and sub-projects according to the BIM model.

[0051] The project progress management module 20 is connected with the BIM model management module 10, the material management module 30 and the engineering payment management module 40; the project progress management module 20 is used to set the engineering plan progress at different time nodes for each construction area and each sub-item; and, collect and review the material entry declaration information, and generate the identification code of the current transportation after the review is successful; and, collect and review the material exit declaration information, and generate the identification code of the current transportation after the review is successful; and, the material entry information and material exit information in each construction area or sub-item are counted and compared with the engineering quantity information calculated by the BIM model management module 10, and the actual progress of the engineering of the corresponding construction area or sub-item is obtained. The material entry declaration information and the material exit declaration information are generated by the transporter and applied to the project progress management module 20 of this system, and the project progress management module 20 then reviews the material entry declaration information and the material exit declaration information.

[0052] The material management module 30 is connected to the project progress management module 20; the material management module 30 is used to obtain the corresponding material entry declaration information or material exit declaration information by scanning the identification code; and, obtain the material entry information and material exit information; and, compare the material entry information with the material entry declaration information, compare the material exit information with the material exit declaration information, and record the material entry information and material exit information when the comparison results are consistent. The information recorded by the material management module 30 will be used by the project progress management module 20 to calculate the actual progress of the construction area or sub-project, so strict control of the material entry information and material exit information will help improve the calculation accuracy of the actual progress of the project.

[0053] The project payment management module 40 is connected to the project progress management module 20; the project payment management module 40 is used to set payment plans under different project plan progress according to the construction contract; and, after the actual progress of the project reaches the project plan progress, the project payment is settled according to the corresponding payment plan. In this embodiment, the payment plan may include the payment conditions and payment ratios in the construction contract. For example, the payment conditions are that the payment is made only after the actual progress of the project in the corresponding construction area or sub-project reaches a certain percentage, and the payment ratio is the percentage of the full amount of the project payment paid to the construction party according to the set ratio when the payment conditions are met. The specific percentage value is specifically agreed upon when signing the construction contract and is not limited here. The project payment management module 40 of this embodiment settles the project payment according to the corresponding payment plan after the actual progress of the project reaches the project plan progress, which provides a reliable reference and basis for the settlement of the project payment and reduces engineering disputes.

[0054] In the process of reviewing the material entry declaration information, the project progress management module 20 of this embodiment shall collect the material entry declaration information, which shall at least include the type and quantity of the material, the license plate number of the transport vehicle, the driver information, etc. If relevant information is available, an identification code for the current transportation is generated for the material entry declaration information, so that the type and quantity of the incoming material, the license plate number of the transport vehicle, the driver information, etc. can be uniquely matched with the identification code, so that the material management module 30 can compare the material entry information with the material entry declaration information, thereby ensuring that the information of the incoming material is accurate and complete. The project progress management module 20 processes the material exit declaration information in the same way as the material entry declaration information, and the material exit declaration information also includes at least the type and quantity of the material, the license plate number of the transport vehicle, the driver information, etc., which will not be repeated here in this embodiment. The materials in this embodiment are not limited to building materials, but can also include related machinery and tools, such as tower crane parts, concrete mixer trucks, dump trucks, etc.

[0055] Specifically, Figure 2 As shown, the material management module 30 of the embodiment of the present invention includes a door access management submodule 301, a code scanning submodule 302, a material type identification submodule 303, a material weighing submodule 304 and a material information collection module 305, wherein:

[0056] The access control management submodule 301 is connected to the material information collection module 305. The access control management submodule 301 is used to identify the license plate number of the transport vehicle and match it with the license plate number of the transport vehicle in the corresponding material entry declaration information or material exit declaration information. If the match is successful, the access control is opened. The embodiment of the present invention divides the field and the outside of the field through the access control. The transport vehicle must pass through the access control to enter and exit the field. Only when the license plate number of the transport vehicle is used to declare the identification code, the access control can be opened to allow the vehicle to enter and exit, otherwise the transport vehicle cannot be released.

[0057] The code scanning submodule 302 is connected to the material information collection module 305. The code scanning submodule 302 is used to scan the identification code to obtain the corresponding material entry declaration information or material exit declaration information. The code scanning submodule 302 of this embodiment can be implemented by a device with a code scanning function to obtain the material entry declaration information or material exit declaration information corresponding to the identification code.

[0058] The material type identification submodule 303 is connected to the material information collection module 305, and is used to obtain the types of incoming materials and the types of outgoing materials. The material type identification submodule 303 of this embodiment can be implemented by a camera and a product combination with an image analysis function, and the camera takes a photo of the material carried by the transport vehicle, and then analyzes the photo to obtain the type of the material carried by the transport vehicle.

[0059] The material weighing submodule 304 is connected to the material information collection module 305, and is used to obtain the weight of the incoming materials and the weight of the outgoing materials. The material weighing submodule 304 in this embodiment can be implemented by an intelligent floor scale. For example, the vehicle carrying the materials is first weighed as a whole, and after the vehicle is unloaded, the empty vehicle is weighed again. The weight of the incoming materials can be obtained by subtracting the values ​​of the two weighings. Similarly, if the materials need to be transported outward, the empty vehicle is weighed first, and after the loading is completed, the vehicle carrying the materials is weighed as a whole. The weight of the outgoing materials can be obtained by subtracting the values ​​of the two weighings.

[0060] The material information collection module 305 is connected to the access control management submodule 301, the code scanning submodule 302, the material type identification submodule 303, and the material weighing submodule 304 respectively. The material information collection module 305 is used to compare the type and weight of incoming materials with the material entry declaration information, and to compare the type and weight of outgoing materials with the material exit declaration information, and if the comparison results are consistent, the type and weight of incoming materials, the type and weight of outgoing materials and the license plate number of the transport vehicle are collected. The types of incoming materials, the weight of incoming materials, the types of exiting materials, and the weight of exiting materials will be used by the project progress management module 20 to count the material incoming information and material exiting information in each construction area or sub-item of the project. Specifically, the project progress management module 20 counts the types of incoming materials, the weight of incoming materials, the types of exiting materials, and the weight of exiting materials in each construction area or sub-item of the project, and then compares them with the project quantity information calculated by the BIM model management module 10 to obtain the actual progress of the project in the corresponding construction area or sub-item of the project.

[0061] In this embodiment, the material information collection module 305 will count the weight of the same type of materials used for construction. For example, if the construction party first transports a certain weight of a certain material into the site, and then transports a certain weight of the material out of the site, the weight of the material used for construction is obtained by subtracting the exit weight from the entry weight. Preferably, in order to manage materials more effectively, the weight of the incoming materials must be greater than the weight of the exit materials, otherwise the access control management submodule 301 will not release the vehicle.

[0062] If the project construction also deploys a smart construction site system, the BIM-based project progress and project payment management system in this embodiment can be combined with the smart construction site system to jointly control smart weighing scales, access control, vehicle gates, etc.

[0063] Specifically, in this embodiment, based on the above-mentioned embodiment, the BIM model management module 10 calculates the engineering quantity information for the construction area and sub-items according to the BIM model: the BIM model management module 10 extracts the types of materials required for the construction area or sub-items in the BIM model, and calculates the demand for each type of material. The project progress management module 20 counts the types of incoming materials, the weight of incoming materials, the types of outgoing materials, and the weight of outgoing materials in each construction area or sub-item, and compares them with the demand for each type of material calculated by the BIM model management module 10 to obtain the actual progress of the corresponding construction area or sub-item.

[0064] Specifically, the BIM model management module 10 of the embodiment of the present invention is also used to adjust the BIM model according to the actual progress of the project, and update the visual progress of the project in the BIM model. Managers can learn about the actual progress of the project through the visual progress, and at the same time, the relevant information in the system forms a closed-loop circulation, which reduces the workload of managers and improves management efficiency.

[0065] Specifically, the project progress management module 20 in the embodiment of the present invention is also used to compare the actual progress of the project with the planned progress of the project at the corresponding time node, and if the actual progress of the project lags behind the planned progress of the project, an alarm prompt is issued. Through the alarm prompt, management, construction and other related personnel are informed that the actual progress of the project is lagging behind, so that the progress of the project can be accelerated in time, the production and construction can be completed as planned, and the losses caused by project delays can be avoided.

[0066] The BIM-based project progress and project payment management system in the embodiment of the present invention uses the BIM model as a carrier, relies on the BIM model to generate several construction areas and sub-projects, and obtains the actual progress of the project in the corresponding construction area or sub-project through the management and statistics of material entry information and material exit information, so as to compare it with the planned project progress and learn the actual situation of the project progress, so that the relevant information in the system forms a closed-loop circulation, which reduces the workload of management personnel and improves management efficiency. On the other hand, after the actual progress of the project reaches the planned progress of the project, the project payment is settled according to the corresponding payment plan, which provides a reliable reference and basis for the settlement of the project payment and reduces project disputes.

[0067] The present invention also includes a BIM-based project progress and project payment management method, such as Figure 3 As shown, the following steps are included:

[0068] Step S01: Establish a complete BIM model of the project.

[0069] The BIM model can be established by combining existing technologies with the specific content of the engineering project, which is not limited in this embodiment.

[0070] Step S02: Divide the project into several construction areas and sub-projects according to the current status of the project, project management requirements and project division strategy.

[0071] Step S03: Calculate the engineering quantity information for the construction area and sub-projects according to the BIM model.

[0072] Steps S01 to S03 of this embodiment are all implemented by the BIM model management module 10 in the aforementioned BIM-based project progress and project payment management system embodiment of the present invention. The relevant instructions for the implementation of steps S01 to S03 can be referred to the aforementioned embodiment and will not be repeated here.

[0073] Step S04: Set the project schedule at different time nodes for each construction area and each sub-project.

[0074] Step S04 of this embodiment is implemented by the project progress management module 20 in the aforementioned BIM-based project progress and project payment management system embodiment of the present invention. The relevant instructions for the implementation of this step can be referred to the aforementioned embodiment and will not be repeated here.

[0075] Step S05: Setting payment plans under different project schedules according to the construction contract.

[0076] Step S05 of this embodiment is implemented by the project payment management module 40 in the aforementioned BIM-based project progress and project payment management system embodiment of the present invention. The relevant instructions for the implementation of this step can be referred to the aforementioned embodiment and will not be repeated here.

[0077] The implementation of this step is not necessarily limited to being performed after step S04. The implementation of steps S01 to S05 can be regarded as the preparatory work done before the construction of the project, while steps S06 to S11 are implemented during the construction of the project, specifically:

[0078] Step S06: collecting and reviewing the material entry declaration information, and generating an identification code for the current transport after the review is successful, and collecting and reviewing the material exit declaration information, and generating an identification code for the current transport after the review is successful.

[0079] Step S06 is correspondingly implemented by the project progress management module 20 in the aforementioned BIM-based project progress and project payment management system embodiment of the present invention. The relevant instructions for the implementation of this step can be referred to the aforementioned embodiment and will not be repeated here.

[0080] Step S07: Scan the identification code to obtain the corresponding material entry declaration information or material exit declaration information.

[0081] Step S08: Obtain material entry information and material exit information.

[0082] Step S09: Compare the material entry information with the material entry declaration information, and compare the material exit information with the material exit declaration information, and if the comparison results are consistent, the material entry information and the material exit information are recorded.

[0083] Steps S07 to S09 of this embodiment are all implemented by the material management module 30 in the aforementioned BIM-based project progress and project payment management system embodiment of the present invention. The relevant instructions for the implementation of steps S07 to S09 can be referred to the aforementioned embodiment and will not be repeated here.

[0084] Step S10: Collect statistics on the material entry information and material exit information in each construction area or sub-item of the project, compare them with the project quantity information, and obtain the actual progress of the project in the corresponding construction area or sub-item of the project.

[0085] Step S10 is correspondingly implemented by the project progress management module 20 in the aforementioned BIM-based project progress and project payment management system embodiment of the present invention. The relevant description of the implementation of this step can be referred to the aforementioned embodiment and will not be repeated here.

[0086] Step S11: After the actual progress of the project reaches the planned progress of the project, the project payment is settled according to the corresponding payment plan.

[0087] Step S11 is implemented by the project payment management module 40 in the aforementioned BIM-based project progress and project payment management system embodiment of the present invention. The relevant instructions for the implementation of this step can be referred to the aforementioned embodiment and will not be repeated here.

[0088] Specifically, Figure 4 As shown, the BIM-based project progress and project payment management method of the embodiment of the present invention also includes the following steps:

[0089] Step S12: Compare the actual progress of the project with the planned progress of the project at the corresponding time node. If the actual progress of the project lags behind the planned progress of the project, an alarm prompt is issued.

[0090] Step S12 of this embodiment is implemented by the project progress management module 20 in the aforementioned BIM-based project progress and project payment management system embodiment of the present invention. The relevant description of the implementation of this step can refer to the aforementioned embodiment and will not be repeated here. The implementation of this step is implemented when the actual project progress is obtained in step S10.

[0091] Step S13: Adjust the BIM model according to the actual progress of the project, and update the visual progress of the project in the BIM model.

[0092] Step S13 of this embodiment is implemented by the BIM model management module 10 in the aforementioned BIM-based project progress and project payment management system embodiment of the present invention. The relevant description of the implementation of this step can refer to the aforementioned embodiment and will not be repeated here. The implementation of this step is implemented when the actual project progress is obtained in step S10, and it is not implemented in any order with step S12.

[0093] The BIM-based project progress and project payment management method of the embodiment of the present invention uses the BIM model as a carrier, relies on the BIM model to generate several construction areas and sub-projects, and obtains the actual progress of the project in the corresponding construction area or sub-project through the management and statistics of material entry information and material exit information, so as to compare it with the planned project progress and learn the actual situation of the project progress, so that the relevant information in the system forms a closed-loop circulation, which reduces the workload of management personnel and improves management efficiency. On the other hand, after the actual progress of the project reaches the planned progress of the project, the project payment is settled according to the corresponding payment plan, which provides a reliable reference and basis for the settlement of the project payment and reduces project disputes.

[0094] The present invention is further described above with the aid of specific embodiments. However, it should be understood that the specific description here should not be construed as limiting the essence and scope of the present invention. Various modifications made to the above embodiments by ordinary technicians in the field after reading this specification are all within the scope of protection of the present invention.

Claims

1. A BIM-based project progress and project payment management system, characterized in that: It includes BIM model management module, project progress management module, material management module and project payment management module, among which: The BIM model management module is connected to the project progress management module; the BIM model management module is used to establish a complete BIM model of the engineering project; and, according to the current status of the project, project management requirements and project division strategy, the engineering project is divided into a number of construction areas and sub-projects; and, according to the BIM model, the engineering quantity information of the construction areas and the sub-projects is calculated; The project progress management module is connected with the BIM model management module, the material management module and the engineering payment management module; the project progress management module is used to set the engineering plan progress at different time nodes for each construction area and each sub-item; and, collect and review the material entry declaration information, and generate the identification code of the current transportation after the successful review; and, collect and review the material exit declaration information, and generate the identification code of the current transportation after the successful review; and, collect statistics on the material entry information and material exit information in each construction area or sub-item, and compare them with the engineering quantity information calculated by the BIM model management module to obtain the actual progress of the corresponding construction area or sub-item; The material management module is connected to the project progress management module; the material management module is used to obtain the corresponding material entry declaration information or material exit declaration information by scanning the identification code; and, obtain the material entry information and the material exit information; and, compare the material entry information with the material entry declaration information, compare the material exit information with the material exit declaration information, and if the comparison results are consistent, the material entry information and the material exit information are recorded; The engineering payment management module is connected to the project progress management module; the engineering payment management module is used to set payment plans under different engineering plan progress according to the construction contract; and settle the engineering payment according to the corresponding payment plan after the actual progress of the project reaches the engineering plan progress; The material entry declaration information at least includes the material type, quantity, license plate number of the transport vehicle, and driver information; the material exit declaration information at least includes the material type, quantity, license plate number of the transport vehicle, and driver information; The material management module includes an access control management submodule, a code scanning submodule, a material type identification submodule, a material weighing submodule and a material information collection module, wherein: The access control management submodule is connected to the material information collection module. The access control management submodule is used to identify the license plate number of the transport vehicle and match it with the license plate number of the transport vehicle in the corresponding material entry declaration information or material exit declaration information. If the match is successful, the access control is opened; The code scanning submodule is connected to the material information collection module, and the code scanning submodule is used to scan the identification code to obtain the corresponding material entry declaration information or material exit declaration information; The material type identification submodule is connected to the material information collection module, and the material type identification submodule is used to obtain the types of incoming materials and the types of outgoing materials; The material weighing submodule is connected to the material information collection module, and is used to obtain the weight of incoming materials and the weight of outgoing materials; The material information collection module is connected to the access control management submodule, the code scanning submodule, the material type identification submodule, and the material weighing submodule respectively. The material information collection module is used to compare the type and weight of the incoming materials with the material entry declaration information, and to compare the type and weight of the outgoing materials with the material exit declaration information, and if the comparison results are consistent, the type and weight of the incoming materials, the type and weight of the outgoing materials and the license plate number of the transport vehicle are collected.

2. The BIM-based project progress and project payment management system according to claim 1, characterized in that: The BIM model management module is also used for: The BIM model is adjusted according to the actual progress of the project, and the visual progress of the project in the BIM model is updated.

3. The BIM-based project progress and project payment management system according to claim 1, characterized in that: The project progress management module is also used for: The actual progress of the project is compared with the planned progress of the project at the corresponding time node. If the actual progress of the project lags behind the planned progress of the project, an alarm is issued.

4. The BIM-based project progress and project payment management system according to claim 1, characterized in that: The project progress management module collects statistics on the material entry information and material exit information in each construction area or sub-project as follows: The project progress management module collects statistics on the types and weights of incoming materials, and the types and weights of outgoing materials in each construction area or sub-project.

5. The BIM-based project progress and project payment management system according to claim 1, characterized in that: The payment plan includes the payment terms and payment ratios in the construction contract.

6. The BIM-based project progress and project payment management system according to claim 1, characterized in that: The BIM model management module calculates the engineering quantity information for the construction area and the sub-projects according to the BIM model as follows: The BIM model management module extracts the types of materials required for the construction area or the sub-projects in the BIM model, and calculates the demand for each type of material.

7. A method for managing project progress and project payment based on BIM, characterized in that: Using the BIM-based project progress and project payment management system as described in any one of claims 1 to 6, the method includes: Establish a complete BIM model for the project; Divide the project into several construction areas and sub-projects according to the current status of the project, project management requirements and project division strategy; Calculate the engineering quantity information for the construction area and the sub-projects according to the BIM model; Set the project schedule at different time nodes for each construction area and each sub-project; Set up payment plans for different project schedules according to the construction contract; Collect and review the declaration information of incoming materials, and generate the identification code of the current transportation after successful review, or collect and review the declaration information of outgoing materials, and generate the identification code of the current transportation after successful review; Scan the identification code to obtain the corresponding material entry declaration information or material exit declaration information; Obtain material entry information and material exit information; Compare the material entry information with the material entry declaration information, compare the material exit information with the material exit declaration information, and if the comparison results are consistent, record the material entry information and the material exit information; Collect statistics on the material entry and exit information in each construction area or sub-project, compare them with the engineering quantity information, and obtain the actual progress of the corresponding construction area or sub-project; After the actual progress of the project reaches the planned progress of the project, the project payment will be settled according to the corresponding payment plan.

8. The BIM-based project progress and project payment management method according to claim 7, characterized in that: Also includes: Compare the actual progress of the project with the planned progress of the project at the corresponding time node, and issue an alarm if the actual progress of the project lags behind the planned progress of the project; as well as The BIM model is adjusted according to the actual progress of the project, and the visual progress of the project in the BIM model is updated.

Citation Information

Patent Citations

  • Assembly type building construction full process data cooperation management system based on BIM

    CN106600239A

  • Intelligent building construction progress management method

    CN109872127A

  • Field construction material intelligent management method based on BIM