A satellite testing method, a testing terminal and a computer storage medium

By obtaining satellite transportation and testing information, determine the test plan and test during transportation, solve the problem of lack of effective testing methods in traditional satellite transportation, and improve the test efficiency of satellite and the reliability of transportation processes.

CN114577260BActive Publication Date: 2025-01-28ZHEJIANG GEESPACE TECH CO LTD +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202210168495.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-02-23
Publication Date
2025-01-28
Estimated Expiration
2042-02-23

AI Technical Summary

Technical Problem

The lack of effective testing methods during traditional satellite transportation has led to repeated testing of satellites at the launch site, which cannot meet the testing needs of large-scale satellites, affecting the development cycle and quantity.

Method used

By obtaining the transportation information and testing information of the satellite, the test plan is determined, and the satellite is tested during the transportation, including the star meter testing, cable test, and wireless testing to generate test results.

Benefits of technology

The efficient testing of satellites during transportation has been achieved, reducing the repeat testing session of the launch field, and improving the test efficiency of satellite testing and the reliability and guarantee of the transportation process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114577260B_ABST
    Figure CN114577260B_ABST
Patent Text Reader

Abstract

The present application relates to a satellite testing method, a testing terminal and a computer storage medium. The testing method includes: obtaining the transportation information and testing information of the satellite; determining the testing plan of the satellite according to the transportation information and the testing information; testing the satellite according to the testing plan and generating test results. The satellite testing method, testing terminal and computer storage medium provided in the present application can test, power and monitor the environment of the satellite during transportation, improve the reliability and security of the satellite transportation process, reduce repeated testing links at the satellite launch site, and improve the testing efficiency of the satellite.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the field of satellite testing technology, and in particular, relates to a satellite testing method, a testing terminal and a computer storage medium. Background Art

[0002] Satellite development is divided into three major stages: final assembly, integration, and testing and experimentation. The most critical of these is the testing and experimentation stage, which accounts for the largest proportion of the satellite development process. After the satellite is developed at the manufacturing plant, it enters the factory state and will be transported from the manufacturing plant to the launch site. If the satellite can be tested during transportation, the satellite development cycle can be shortened and the number of satellites developed can be increased.

[0003] The traditional satellite transportation process only has the ability to detect temperature and humidity and pack materials for vibration reduction. After arriving at the launch site, the satellite needs to be retested. However, due to the large number of satellites in a single batch, it is difficult to find the time and space to carry out the test at the launch site. Therefore, a new test method must be adopted to avoid and reduce repeated tests at the launch site. Summary of the invention

[0004] In response to the above technical problems, the present application provides a satellite testing method, a testing terminal and a computer storage medium to improve the testing efficiency of the satellite and the reliability and security of the transportation process.

[0005] The present application provides a satellite testing method, including: obtaining transportation information and test information of a satellite; determining a test plan for the satellite based on the transportation information and the test information; testing the satellite according to the test plan, and generating a test result.

[0006] In one implementation, the transportation information includes transportation time and transportation distance; the test information includes the definition of the test interface and the communication method of the test.

[0007] In one embodiment, the step of determining the test plan for the satellite based on the transportation information and the test information includes: determining the test items for the satellite based on the definition of the test interface and / or the communication method of the test; determining the number of tests for each test item based on the transportation distance; and determining the test cycle and test timing for each test item based on the number of tests and the transportation time.

[0008] In one embodiment, the step of testing the satellite according to the test plan and generating a test result includes: testing the satellite according to the test items, wherein the test items include a star catalog test, a wired test, and a wireless test; if the satellite passes the star catalog test, the wired test, and the wireless test, the satellite test is qualified; if the satellite fails any one of the star catalog test, the wired test, and the wireless test, the satellite test is unqualified; wherein the order of test priority from high to low is the star catalog test, the wired test, and the wireless test.

[0009] In one embodiment, the step of testing the satellite according to the test plan and generating test results includes: generating remote control instructions for each satellite according to the test items of each satellite; combining and framing the remote control instructions for each satellite, and sending the remote control instructions to the corresponding satellite by broadcasting; setting the telemetry timing of each satellite, obtaining the telemetry data of each satellite according to the telemetry timing, and packaging the telemetry data; analyzing the telemetry data to generate test results for the corresponding satellite; wherein the test items include at least one of power supply and distribution test, attitude and orbit control test, comprehensive electronic test, and load test.

[0010] In one embodiment, the step of testing the satellite according to the test plan and generating a test result includes: timing a cyclic test on the satellite according to the test period and the test timing; if the satellite test passes and the cyclic test timing ends, executing the step of generating a test result; if the satellite test passes and the cyclic test timing has not ended, continuing to test the satellite.

[0011] In one embodiment, the testing method also includes: obtaining the power of the satellite; when the power of the satellite is lower than a first threshold, supplying constant current to the satellite; when the power of the satellite reaches a second threshold, supplying power to the satellite in a shadow entry and exit mode; when the power of the satellite reaches a third threshold, stopping power supply to the satellite; wherein the first threshold is less than the second threshold, and the second threshold is less than the third threshold.

[0012] In one embodiment, the testing method further includes: obtaining environmental parameters of the storage environment of the satellite, wherein the environmental parameters include at least one of temperature, humidity, vibration, and cleanliness; automatically controlling the environmental parameters when the absolute value of the difference between the collected value and the target value of the environmental parameter is greater than a preset value; after the environmental parameters are automatically controlled, if the absolute value of the difference between the collected value and the target value of the environmental parameter is still greater than the preset value, generating an alarm message.

[0013] The present application also provides a test terminal, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps of the above-mentioned test method when executing the computer program.

[0014] The present application also provides a computer storage medium, wherein the computer storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the above-mentioned test method are implemented.

[0015] The present application provides a satellite testing method, a testing terminal and a computer storage medium, which can test, power and monitor the environment of the satellite during transportation, improve the reliability and security of the satellite transportation process, reduce repeated testing links at the satellite launch site, and improve the testing efficiency of the satellite. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a flow chart of the testing method provided in Example 1 of the present application;

[0017] Figure 2 It is a specific flow chart of the testing method provided in Example 2 of the present application;

[0018] Figure 3 is a schematic diagram of the structure of the test system provided in Example 3 of the present application;

[0019] Figure 4 This is a schematic diagram of the structure of the test terminal provided in Example 3 of the present application. DETAILED DESCRIPTION

[0020] The technical solution of the present application is further elaborated in detail below in conjunction with the accompanying drawings and specific embodiments of the specification. Unless otherwise defined, all technical and scientific terms used in this application have the same meaning as those commonly understood by technicians in the technical field of this application. The terms used herein in the specification of this application are only for the purpose of describing specific embodiments and are not intended to limit this application. "And / or" used herein includes any and all combinations of one or more related listed items.

[0021] Figure 1 Schematic diagram of the test method provided in Example 1 of the present application. Figure 1 As shown, the testing method of the present application may include the following steps:

[0022] Step S101: Obtaining transportation information and test information of the satellite;

[0023] Optionally, the transportation information includes transportation time and transportation distance; the test information includes the definition of the test interface and the communication method of the test.

[0024] Step S102: Determine a satellite test plan based on the transportation information and the test information;

[0025] In one embodiment, step S102 includes:

[0026] Determine the satellite test items based on the definition of the test interface and / or the communication mode of the test;

[0027] Determine the number of tests for each test item based on the transportation distance;

[0028] Determine the test cycle and test timing for each test item based on the number of tests and transportation time.

[0029] Optionally, the definition of the test interface includes defining the test interface as any one of a power supply and distribution test interface, an attitude and orbit control test interface, an integrated electronic test interface, and a load test interface; the test communication method includes any one of a satellite connection, a wired connection, and a wireless connection; according to the length of the transportation distance, the number of tests that must be completed for each test item is determined; according to the number of times each test item must be completed and the limited transportation time, combined with the test duration of each test item, each test item is scheduled to determine the test cycle and test start time of each test item.

[0030] Furthermore, according to the satellite test items, the test cycle of each test item and the test timing matching database plan, the test configuration parameters corresponding to each test item are selected and loaded to form a final test plan.

[0031] Step S103: Test the satellite according to the test plan and generate test results.

[0032] In one embodiment, step S103 includes:

[0033] Testing the satellite according to the test items; optionally, the test items include star table test, wired test, and wireless test;

[0034] If the satellite passes the star table test, wired test and wireless test, the satellite test is qualified;

[0035] If the satellite fails any of the star table test, wired test, and wireless test, the satellite test fails;

[0036] Among them, the order of test priority from high to low is star table test, wired test and wireless test.

[0037] In one embodiment, step S103 includes:

[0038] Generate remote control instructions for each satellite according to the test items of each satellite; optionally, the test items also include at least one of power supply and distribution test, attitude and orbit control test, comprehensive electronic test, and load test;

[0039] Combine the remote control commands of each satellite into frames and send the remote control commands to the corresponding satellites by broadcasting;

[0040] Set the telemetry timing of each satellite, obtain the telemetry data of each satellite according to the telemetry timing, and package the telemetry data;

[0041] Analyze the telemetry data and generate test results for the corresponding satellite.

[0042] Exemplarily, a star table connection, a wired connection and a wireless connection are established with the satellite respectively; if normal communication with the satellite can be achieved through the star table connection, the wired connection and the wireless connection, the satellite passes the star table test, the wired test and the wireless test, and the satellite test is qualified; if normal communication with the satellite cannot be achieved through the star table connection, the wired connection or the wireless connection, the satellite test is unqualified.

[0043] Exemplarily, the test items of satellite A are power supply and distribution and attitude and orbit control tests, and the test items of satellite B are attitude and orbit control, integrated electronics and payload tests. Corresponding remote control instructions are generated according to the test items of satellite A and satellite B respectively, and the remote control instructions of satellite A and satellite B are combined and framed and sent to satellite A and satellite B respectively through broadcasting; satellite A and satellite B are tested according to their respective remote control instructions and generate corresponding telemetry data; the telemetry timing of satellite A and satellite B is set to 1 and 2 respectively, then the telemetry data of satellite A is obtained first, and then the telemetry data of satellite B is obtained, and the telemetry data of satellite A and satellite B are packaged; if the power supply and distribution and attitude and orbit control tests are passed, the satellite A test is qualified; if the attitude and orbit control, integrated electronics and payload tests are passed, the satellite B test is qualified.

[0044] Exemplarily, the test items of satellite C are the attitude and orbit control test under the star chart connection, the comprehensive electronics and payload test under the wired connection, and the power supply and distribution test under the wireless connection, and the star chart connection, wired connection and wireless connection are established with the satellite respectively; if under the star chart connection, satellite C passes the attitude and orbit control test; under the wired connection, satellite C passes the comprehensive electronics and payload test; under the wireless connection, satellite C passes the power supply and distribution test, then satellite C passes the star chart test, the wired test and the wireless test, and the satellite C test is qualified; if one of the attitude and orbit control test under the star chart connection, the comprehensive electronics and payload test under the wired connection, and the power supply and distribution test under the wireless connection fails, then the satellite C test fails.

[0045] In one embodiment, step S103 includes:

[0046] Perform satellite cycle test timing according to the test cycle and test timing;

[0047] If the satellite test is qualified and the loop test timing is over, the step of generating the test result is executed;

[0048] If the satellite test passes and the loop test timing has not ended, the satellite will continue to be tested.

[0049] Optionally, if the satellite test has always been qualified during each test timing process, the test results are uniformly generated at the end of the cyclic test timing to save test resources; if the satellite test fails during any test timing process, the test results and alarm information are generated in time to promptly feedback the abnormal situation.

[0050] It is worth mentioning that the testing method of the present application also includes: obtaining the power of the satellite; when the power of the satellite is lower than a first threshold, supplying constant current to the satellite; when the power of the satellite reaches a second threshold, supplying power to the satellite in a shadow entry and exit mode; when the power of the satellite reaches a third threshold, stopping power supply to the satellite; wherein the first threshold is less than the second threshold, and the second threshold is less than the third threshold.

[0051] Optionally, before powering the satellite, the output voltage, output current, voltage threshold of overvoltage protection, current threshold of overcurrent protection, and shadow entry and exit mode sequence of the power supply device are set; in the process of powering the satellite, the output voltage and output current of the power supply device are monitored, and if the output voltage is higher than the preset voltage, and / or the output current is higher than the preset current, the power supply device is turned off and an alarm message is generated; the power is calculated by current integration, and when the satellite power reaches the standard, the power supply device is turned off and the power supply to the satellite is stopped. Among them, the shadow entry and exit mode is a mode set to simulate the charging ability of the satellite in the state of entering and exiting the earth's shadow in space.

[0052] It is worth mentioning that the test method of the present application also includes: obtaining environmental parameters of the satellite's storage environment, wherein the environmental parameters include at least one of temperature, humidity, vibration, and cleanliness; when the absolute value of the difference between the collected value of the environmental parameter and the target value is greater than the preset value, the environmental parameter is automatically controlled; after the environmental parameter is automatically controlled, if the absolute value of the difference between the collected value of the environmental parameter and the target value is still greater than the preset value, an alarm message is generated. Optionally, the corresponding environmental data is collected through a temperature and humidity sensor, a vibration sensor, and a cleanliness sensor; the temperature and humidity are controlled by a heating device; the vibration is controlled by a vibration reduction device; and the cleanliness is controlled by a fresh air device.

[0053] The test method provided in Example 1 of the present application determines the test plan of the satellite through the transportation information and test information of the satellite, and tests the satellite according to the test plan to generate test results, thereby realizing the testing of the satellite during the transportation process, reducing the repeated testing links at the satellite launch site, and improving the testing efficiency of the satellite; during the transportation process, the satellite can also be automatically powered on and the environment monitored, thereby improving the reliability and security of the satellite transportation process.

[0054] Figure 2 This is a schematic diagram of the specific flow of the test method provided in Example 2 of this application. Figure 2 As shown, the test method of this application includes:

[0055] Step S201: Obtaining transportation information and test information of the satellite;

[0056] Step S202: Determine whether the database solution is matched successfully;

[0057] If the database solution matches successfully, step S203 is executed: determining whether the test configuration parameters are loaded successfully;

[0058] If the database solution fails to match and / or the test configuration parameter fails to load, the process returns to step S201;

[0059] If the test configuration parameters are loaded successfully, step S204 is executed: determining whether the star catalog test passes;

[0060] If the star table test passes, then step S205 is executed: determining whether the wired test passes;

[0061] If the wired test passes, then step S206 is executed: determining whether the wireless test passes;

[0062] If the wireless test passes, then step S207 is executed: determining whether the cyclic test timing is over;

[0063] If the cycle test timing has not ended, return to step S204;

[0064] If the cyclic test timing ends, or any one of the star table test, wired test, and wireless test fails, step S208 is executed: generating a test result.

[0065] The implementation method of this embodiment refers to the first embodiment and will not be described in detail here.

[0066] The test method provided in Example 2 of the present application performs cyclic testing on the satellite during transportation, and can provide timely feedback when the test results are abnormal. When the test results are normal, the test results can be uniformly generated at the end of the cyclic test timing, thereby improving the timeliness and effectiveness of the test situation feedback, reducing the repeated testing links at the satellite launch site, and improving the testing efficiency of the satellite.

[0067] Figure 3 Schematic diagram of the structure of the test system provided in the third embodiment of the present application. Figure 3 As shown, the test system of the present application includes a test terminal, a measurement and control device, a power supply device and an environmental control device. Optionally, the test terminal is connected to the measurement and control device and the power supply device through 5G-IOT; the measurement and control device is connected to the environmental control interface and the test interface through the PXIe bus, and is respectively connected to the environmental control device and the satellite through the environmental control interface and the test interface; the power supply device is connected to the power supply interface through a wired cable, and is connected to the satellite through the power supply interface. Optionally, the measurement and control device is used to test and control the satellite according to the test instructions and environmental control instructions of the test terminal; the power supply device is used to power the satellite according to the power supply instructions of the test terminal; the environmental control device is used to collect environmental data of the satellite storage environment, and send the environmental data to the test terminal through the measurement and control device. Optionally, the measurement and control device is respectively provided with N environmental control interfaces and N test interfaces (1<N≤30, the typical value is 8), the number of power supply devices is m*N (1≤m≤24, the typical value is 2), and the power supply interface is set to N. When the satellite needs to be powered and / or tested, the test terminal controls the robotic arm to connect the satellite to the power interface and / or the test interface; the environmental control interface independently connects the environmental control device of each satellite.

[0068] The structural diagram of the test terminal is as follows: Figure 4 As shown, the test terminal includes: a processor 110, a memory 111, and a computer program 112 stored in the memory 111 and executable on the processor 110. When the processor 110 executes the computer program 112, the steps in the above-mentioned test method embodiments are implemented, for example Figure 1 Steps S101 to S103 are shown.

[0069] The test terminal may include, but is not limited to, a processor 110 and a memory 111. Those skilled in the art will appreciate that Figure 4 It is only an example of a test terminal and does not constitute a limitation of the test terminal. It may include more or fewer components than shown in the figure, or a combination of certain components, or different components. For example, the test terminal may also include input and output devices, network access devices, buses, etc.

[0070] The processor 110 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or any conventional processor, etc.

[0071] The memory 111 may be an internal storage unit of the test terminal, such as a hard disk or memory of the test terminal. The memory 111 may also be an external storage device of the test terminal, such as a plug-in hard disk, a smart media card (SMC), a secure digital (SD) card, a flash card, etc. equipped on the test terminal. Furthermore, the memory 111 may also include both an internal storage unit and an external storage device of the test terminal. The memory 111 is used to store the computer program and other programs and data required by the test terminal. The memory 111 may also be used to temporarily store data that has been output or is to be output.

[0072] The present application also provides a computer storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps of the above-mentioned test method are implemented.

[0073] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0074] In this document, the terms "comprises," "comprising," or any other variations thereof, are intended to cover a non-exclusive inclusion of elements other than those listed and may also include additional elements not expressly listed.

[0075] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.

Claims

1. A satellite testing method, characterized in that: include: Obtain satellite transportation and testing information; Determining a test plan for the satellite according to the transportation information and the test information; Testing the satellite according to the test plan and generating test results; The testing of the satellite according to the test plan and generating a test result includes: Generate remote control instructions for each satellite according to the test items of each satellite; Combine the remote control commands of each satellite into frames and send the remote control commands to the corresponding satellites by broadcasting; Set the telemetry timing of each satellite, obtain the telemetry data of each satellite according to the telemetry timing, and package the telemetry data; Analyze the telemetry data and generate test results for the corresponding satellite.

2. The satellite testing method according to claim 1, characterized in that: The transportation information includes transportation time and transportation distance; the test information includes the definition of the test interface and the communication method of the test.

3. The satellite testing method according to claim 2, characterized in that: The step of confirming the test plan for the satellite based on the transportation information and the test information includes: determining the test items for the satellite based on the definition of the test interface and / or the communication method of the test; determining the number of tests for each test item based on the transportation distance; and determining the test cycle and test timing for each test item based on the number of tests and the transportation time.

4. The satellite testing method according to claim 3, characterized in that: The step of testing the satellite according to the test plan and generating a test result includes: testing the satellite according to the test items, wherein the test items include a star catalog test, a wired test, and a wireless test; if the satellite passes the star catalog test, the wired test, and the wireless test, the satellite test is qualified; if the satellite fails any one of the star catalog test, the wired test, and the wireless test, the satellite test is unqualified; wherein the order of test priority from high to low is the star catalog test, the wired test, and the wireless test.

5. The satellite testing method according to claim 3, characterized in that: The test items include at least one of power supply and distribution test, attitude and orbit control test, comprehensive electronic test and load test.

6. The satellite testing method according to any one of claims 4 to 5, characterized in that: The step of testing the satellite according to the test plan and generating a test result includes: performing a cyclic test timing on the satellite according to the test period and the test timing; if the satellite test passes and the cyclic test timing ends, executing the step of generating a test result; if the satellite test passes and the cyclic test timing has not ended, continuing to test the satellite.

7. The satellite testing method according to claim 1, characterized in that: The testing method also includes: obtaining the power of the satellite; when the power of the satellite is lower than a first threshold, supplying constant current to the satellite; when the power of the satellite reaches a second threshold, supplying power to the satellite in a shadow entry and exit mode; when the power of the satellite reaches a third threshold, stopping power supply to the satellite; wherein the first threshold is less than the second threshold, and the second threshold is less than the third threshold.

8. The satellite testing method according to claim 1, characterized in that: The testing method also includes: obtaining environmental parameters of the satellite's storage environment, wherein the environmental parameters include at least one of temperature, humidity, vibration, and cleanliness; automatically controlling the environmental parameters when the absolute value of the difference between the collected value and the target value of the environmental parameter is greater than a preset value; after the environmental parameters are automatically controlled, if the absolute value of the difference between the collected value and the target value of the environmental parameter is still greater than the preset value, generating an alarm message.

9. A test terminal, characterized in that: The test terminal includes a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the computer program, the steps of the satellite test method according to any one of claims 1 to 8 are implemented.

10. A computer storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the satellite testing method according to any one of claims 1 to 8 are implemented.

Citation Information

Patent Citations

  • Online transport state monitoring device and method for transformer

    CN108981793A