Safety Risk Control Method

A systematic risk management method using task generation and mobile terminals addresses manual inspection gaps, ensuring comprehensive risk control and stable production operations.

CN115099566BActive Publication Date: 2025-07-15ZIJIN MINING GROUP CO LTD +1
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202210553959.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-05-20
Publication Date
2025-07-15
Estimated Expiration
2042-05-20

AI Technical Summary

Technical Problem

In the prior art, risk monitoring during production operations is likely to lead to missed inspection items, which poses safety hazards.

Method used

By obtaining production task information, it generates work tasks and is assigned to relevant personnel for execution, and then generates inspection tasks and is assigned to inspection personnel. During the inspection, hidden dangers are found to generate rectification tasks. After the rectification, the acceptance person will review it to form a closed-loop management.

Benefits of technology

Effectively prevent the missed inspection items, ensure the stable progress of production operations, and improve the accuracy and efficiency of safety risk control.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115099566B_ABST
    Figure CN115099566B_ABST
Patent Text Reader

Abstract

The present invention discloses a safety risk control method and medium. The method includes: obtaining production task information, generating corresponding work tasks according to the production task information, and allocating the work tasks so that relevant personnel can execute the work tasks according to the allocation results; generating inspection tasks according to the work tasks and allocating the inspection tasks to corresponding inspectors; the inspectors conduct inspections according to the inspection tasks, and when potential hazards are found during the inspection process, generate corresponding rectification tasks and send the rectification tasks to corresponding rectifiers; the rectifiers conduct rectification according to the rectification tasks and send the rectification results to the accepters so that the accepters can review the rectification results; it can effectively allocate the risk control work during the production operation process, prevent the omission of inspection items, and ensure the stable progress of production operations.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of safety management, and particularly relates to a safety risk control method, a computer-readable storage medium, and a computer device. Background Art

[0002] During the production operation process of an enterprise, in order to ensure the safety of production operation, it is often necessary to conduct necessary safety risk training for operators before they start their operations, and conduct corresponding risk monitoring during the production operation to avoid the occurrence of hazards.

[0003] In the related art, during risk monitoring, most often managers directly conduct risk investigation on the operation site based on experience; this method is likely to lead to the omission of inspection items to be inspected, and further lead to potential safety hazards in the production operation process. Summary of the Invention

[0004] The present invention aims to solve at least one of the technical problems in the above technologies to some extent. For this reason, one object of the present invention is to propose a safety risk control method, which can effectively allocate the risk control work in the production operation process, prevent the omission of inspection items to be inspected, and ensure the stable progress of production operation.

[0005] The second object of the present invention is to propose a computer-readable storage medium.

[0006] The third object of the present invention is to propose a computer device.

[0007] To achieve the above object, an embodiment of the first aspect of the present invention proposes a safety risk control method, including the following steps: obtaining production task information, generating corresponding work tasks according to the production task information, and allocating the work tasks so that relevant personnel can execute the work tasks according to the allocation results; generating inspection tasks according to the work tasks, and allocating the inspection tasks to corresponding inspectors; the inspectors conduct inspections according to the inspection tasks, and when potential hazards are found during the inspection process, generate corresponding rectification tasks, and send the rectification tasks to corresponding rectifiers; the rectifiers conduct rectification according to the rectification tasks, and send the rectification results to the accepter so that the accepter can review the rectification results.

[0008] According to the security risk control method of the embodiments of the present invention, first, production task information is obtained, and corresponding work tasks are generated according to the production task information, and the work tasks are allocated so that relevant personnel can execute the work tasks according to the allocation results; then, inspection tasks are generated according to the work tasks, and the inspection tasks are allocated to corresponding inspectors; then, the inspectors conduct inspections according to the inspection tasks, and when potential hazards are found during the inspections, corresponding rectification tasks are generated, and the rectification tasks are sent to corresponding rectifiers; then, the rectifiers carry out rectification according to the rectification tasks and send the rectification results to the accepters so that the accepters can review the rectification results; thereby effectively allocating the risk control work during the production operation process, preventing the omission of inspection items, and ensuring the stable progress of the production operation.

[0009] In addition, the security risk control method proposed according to the above embodiments of the present invention may also have the following additional technical features:

[0010] Optionally, the work task includes work content and work location, and a corresponding two-dimensional code is set in the work location. Wherein, the control method further includes: obtaining the scanning information of the two-dimensional code by the mobile terminal of the management personnel, and sending corresponding random inspection content to the mobile terminal of the management personnel according to the scanning information; obtaining the random inspection items input by the management personnel through their mobile terminals, and generating random inspection tasks according to the random inspection items so that the management personnel can conduct corresponding random inspections according to the random inspection tasks.

[0011] Optionally, the allocation of the work tasks includes: sending the work tasks to corresponding team leaders, and obtaining the team member IDs input by the team leaders and the work content corresponding to each team member ID; allocating corresponding work content to the team member IDs according to the input of the team leaders.

[0012] Optionally, the relevant personnel execute the work tasks according to the allocation results. After the allocation of the work content is completed, the team leader establishes a pre-shift meeting; obtains the self-face information collected by each team member, and generates pre-shift meeting attendance information corresponding to the team members according to the self-face information; obtains the face information of each team member collected by the team leader, and generates pre-shift meeting verification attendance information according to the face information collected by the team leader; determines the information of the attendees according to the pre-shift meeting attendance information and the pre-shift meeting verification attendance information; during the progress of the pre-shift meeting, obtains corresponding pre-shift meeting information, where the pre-shift meeting information includes pre-shift meeting location information, pre-shift meeting text information, pre-shift meeting recording information, and pre-shift meeting picture information.

[0013] Optionally, the execution of the work tasks by the relevant personnel according to the allocation result includes: before the relevant personnel enter the work location in a network-free environment, downloading the corresponding safety inspection template according to the allocation result to download the safety inspection template to the mobile terminal of the relevant personnel; after the relevant personnel enter the work location in the network-free environment, collecting safety inspection data according to the safety inspection template through their own mobile terminal, and after leaving the work location in the network-free environment, uploading the safety inspection data to the server through a network connection.

[0014] Optionally, generating an inspection task according to the work task and assigning the inspection task to the corresponding inspector includes: obtaining the information on the number of inspectors, and splitting the work task according to the information on the number of inspectors to obtain multiple work task groups; generating an inspection route corresponding to the work task group according to the work location corresponding to each work task in any work task group, generating an inspection time period according to the work tasks in the work task group, and generating an inspection task according to the work task group, the inspection route and the inspection time period; establishing an association between the inspection task and the corresponding inspector ID.

[0015] To achieve the above object, a second aspect embodiment of the present invention proposes a computer-readable storage medium, on which a safety risk control program is stored, and when the safety risk control program is executed by a processor, the safety risk control method as described above is implemented.

[0016] According to the computer-readable storage medium of the embodiment of the present invention, by storing the safety risk control program, when the processor executes the safety risk control program, the safety risk control method as described above is implemented, so as to effectively allocate the risk control work in the production operation process, prevent the omission of inspection items, and ensure the stable progress of the production operation. Description of the Drawings

[0017] Figure 1 It is a schematic flowchart of the safety risk control method according to the embodiment of the present invention. Detailed Embodiment

[0018] The embodiments of the present invention will be described in detail below. The examples of the embodiments are shown in the drawings, where the same or similar reference numerals denote the same or similar elements or elements having the same or similar functions throughout. The embodiments described below with reference to the drawings are exemplary and are intended to explain the present invention and should not be construed as limiting the present invention.

[0019] In the related art, when conducting risk monitoring, it is mostly only the management personnel who directly conduct risk investigation on the operation site based on experience; this method is prone to omission of inspection items to be inspected, and then leads to potential safety hazards in the production operation process; according to the safety risk control method of the embodiment of the present invention, first, production task information is obtained, and corresponding work tasks are generated according to the production task information, and the work tasks are assigned, so that relevant personnel can execute the work tasks according to the assignment results; then, inspection tasks are generated according to the work tasks, and the inspection tasks are assigned to corresponding inspectors; then, the inspectors conduct inspections according to the inspection tasks, and when potential hazards are found during the inspection process, corresponding rectification tasks are generated, and the rectification tasks are sent to corresponding rectifiers; then, the rectifiers conduct rectification according to the rectification tasks, and send the rectification results to the accepters, so that the accepters can review the rectification results; thus, the risk control work in the production operation process is effectively assigned, the omission of inspection items to be inspected is prevented, and the stable progress of production operation is ensured.

[0020] In order to better understand the above technical solution, the exemplary embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. Although the exemplary embodiments of the present invention are shown in the drawings, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided so that the present invention can be more thoroughly understood and the scope of the present invention can be completely conveyed to those skilled in the art.

[0021] In order to better understand the above technical solution, the above technical solution will be described in detail below in combination with the accompanying drawings of the specification and specific implementation manners.

[0022] Figure 1 It is a schematic flowchart of the safety risk control method according to the embodiment of the present invention. As Figure 1 shown, the safety risk control method includes the following steps:

[0023] S101, obtain production task information, generate corresponding work tasks according to the production task information, and assign the work tasks, so that relevant personnel can execute the work tasks according to the assignment results.

[0024] That is to say, first, production task information (for example, the location where the production task is carried out, the relevant processes of the production task, required work types, personnel configuration, work content, etc.) is processed, and then corresponding work tasks are generated according to the production task information; then, the work tasks are assigned to relevant personnel, so that after receiving the work tasks, the relevant personnel can execute the work tasks for production.

[0025] Among them, there are various ways to generate corresponding work tasks according to the production task information.

[0026] As an example, first obtain the task type of the production task, and based on the task type, obtain the corresponding task template, and obtain the user's click operation to determine the work items in the task template. It can be understood that after determining the work items, each work item is a work task.

[0027] As another example, a release template for work tasks can be preset. Specifically, the release template can include work task number, work task name, risk level, initiating unit, work period, operation location, operation responsibility, and operation description, etc.; then, obtain the input information of relevant managers for the release template, and generate each work task according to the input information. It should be noted that for some high-risk work, a work ticket mechanism and an audit mechanism can be added to the release template; to ensure that the next process is started only when the previous process has been completed through the work ticket mechanism; at the same time, ensure the safe operation of the process through the audit mechanism.

[0028] Among them, there can be various ways to allocate work tasks.

[0029] As an example, after obtaining the production task information, split the production task according to the processes in the production task information to form multiple work tasks, and then allocate them to the corresponding workers according to the types of work to which the work tasks belong (that is, classify the workers according to their functions to form multiple types of workers); to complete the allocation of work tasks.

[0030] As another example, allocating the work tasks includes: sending the work tasks to the corresponding team leaders, and obtaining the team member IDs input by the team leaders and the work content corresponding to each team member ID; allocating the corresponding work content to the team member IDs according to the input of the team leaders.

[0031] Among them, there can be various ways for relevant personnel to execute work tasks according to the allocation results.

[0032] As an example, relevant personnel directly perform relevant operation operations according to the text guidance or voice guidance or video guidance in the work task, and upload the corresponding operation results after the operation is completed to complete the execution of the work task.

[0033] In some embodiments, to ensure safe production, the relevant personnel perform the work tasks according to the allocation results, including: after completing the allocation of work content, the team leader establishes a pre-shift meeting; obtains the personal face information collected by each team member, and generates the pre-shift meeting check-in information corresponding to the team member according to the personal face information; obtains the face information corresponding to each team member collected by the team leader, and generates the pre-shift meeting verification check-in information according to the face information collected by the team leader; determines the information of the attendees according to the pre-shift meeting check-in information and the pre-shift meeting verification check-in information; during the pre-shift meeting, obtains the corresponding pre-shift meeting information, where the pre-shift meeting information includes the pre-shift meeting location information, the pre-shift meeting text information, the pre-shift meeting recording information, and the pre-shift meeting picture information.

[0034] As an example, after the team leader completes the allocation of work content, first, a pre-shift meeting is established to establish the connection of all members in the team; after the connection is established, each team member collects their own face information through their own mobile terminal. After the collection is completed, the mobile terminal of the team member sends the collected personal face information to the server to determine whether the personal face information is the face information corresponding to the team member through the server. If so, the pre-shift meeting check-in information corresponding to the team member is generated; however, this only indicates that the team member has established a connection between their mobile terminal and the team leader's mobile terminal at the time of check-in, and does not necessarily mean that the team member has definitely participated in the on-site meeting; therefore, further, the face information of each on-site team member participating in the pre-shift meeting is collected through the team leader's mobile terminal to generate the pre-shift meeting verification check-in information according to the face information collected by the team leader; that is to say, through the above two pieces of face information, it can be determined without doubt whether any team member has participated in the pre-shift meeting on-site; then, during the pre-shift meeting, the corresponding pre-shift meeting information is obtained, and the pre-shift meeting information includes the pre-shift meeting location information, the pre-shift meeting text information, the pre-shift meeting recording information, and the pre-shift meeting picture information; that is to say, during the pre-shift meeting, the team leader can input text, take pictures, take videos through their mobile terminal, or record the whole process.

[0035] In some embodiments, due to the particularity of some working environments, the working locations are without network (for example, the internal environment of a mine); to ensure the stable progress of work tasks at these working locations; the relevant personnel perform the work tasks according to the assignment results, including: before entering the working location without network, the relevant personnel download the corresponding safety inspection template according to the assignment result, so as to download the safety inspection template to the mobile terminal of the relevant personnel; after entering the working location without network, the relevant personnel collect safety inspection data according to the safety inspection template through their own mobile terminal, and after leaving the working location without network, upload the safety inspection data to the server through network connection.

[0036] As an example, before a person enters the mine, first, download the corresponding safety inspection template according to the assignment result, so as to download the safety inspection template to the mobile terminal of the staff member; preferably, the safety inspection template can be divided into a pre-operation safety inspection template, an in-operation safety inspection template and a post-operation safety inspection template; then, after the staff member enters the mine, conduct pre-work safety inspection, in-work safety inspection and post-operation safety inspection respectively according to the safety inspection template; and, at each upload, the mobile terminal will add a corresponding timestamp to each upload data according to the upload time; then, after the staff member leaves the mine and enters a networked environment, the safety inspection data can be uploaded to the server through network connection to ensure the effective progress of work tasks in a networkless environment.

[0037] S102, generate an inspection task according to the work task and assign the inspection task to the corresponding inspector.

[0038] S103, the inspector conducts an inspection according to the inspection task, and when discovering potential hazards during the inspection, generates a corresponding rectification task and sends the rectification task to the corresponding rectifier.

[0039] S104, the rectifier conducts rectification according to the rectification task and sends the rectification result to the acceptor so that the acceptor can review the rectification result.

[0040] Among them, there are various ways to generate an inspection task according to the work task and assign the inspection task to the corresponding inspector.

[0041] As an example, first, obtain a list of inspectors; then, assign the work tasks to the inspectors in sequence according to the list of inspectors.

[0042] In some embodiments, to improve the work efficiency of inspectors, generating inspection tasks according to work tasks and assigning the inspection tasks to corresponding inspectors includes: obtaining the number information of inspectors, and splitting the work tasks according to the number information of inspectors to obtain multiple work task groups; generating an inspection route corresponding to each work task group according to the work location corresponding to each work task in any work task group, generating an inspection time period according to the work tasks in the work task group, and generating an inspection task according to the work task group, inspection route, and inspection time period; and establishing an association between the inspection task and the corresponding inspector ID.

[0043] As an example, first, split the work tasks according to the number of inspectors to obtain multiple work task groups; preferably, during the formation of work task groups, the correlation between work tasks can be analyzed (for example, calculate the distance value between any two work tasks according to the work locations corresponding to the two work tasks, and preset the correlation weights between any two types of work tasks; then, calculate the correlation value between any two work tasks according to the distance value and the weight value), and generate work task groups according to the correlation; then, generate an inspection route according to the work location corresponding to each work task in the work task group; specifically, all possible paths corresponding to the work task group can be generated according to each work location, calculate the route length value corresponding to each possible path, and use the possible path with the minimum route length value as the inspection route; then, generate an inspection time period according to the work tasks in the work task group, generate an inspection task according to the work task group, inspection route, and inspection time period, and establish an association between the inspection task and the corresponding inspector ID to assign the inspection task to the inspector; thus, when the inspector conducts relevant inspections of the corresponding work tasks according to the inspection route, it can effectively prevent the omission of the inspector's inspection work.

[0044] It can be understood that when an inspector discovers a safety hazard (such as a special operation personnel not having a certificate to work) during the inspection process, collect the corresponding information; specifically, the inspector can input corresponding text through their mobile terminal to describe the hazard situation, or collect semantics, videos, and images through their mobile terminal to obtain hazard information; then, generate a corresponding rectification task based on the collected hazard information for subsequent relevant personnel to rectify the hazard.

[0045] As an example, after the inspection personnel generate a rectification task, they can directly assign corresponding rectification personnel and acceptance personnel to the rectification task; after the inspection personnel upload relevant information to the server, the server sends the rectification task to the rectification personnel according to the assignment result; after the rectification personnel receive the rectification task through their mobile terminals, they can rectify according to the hidden danger information in the rectification task, and collect the result file (for example, the result picture after rectification, or the video file during the rectification process, etc.) during the rectification. This result file is the rectification result, and upload the rectification result to the server; after the server receives the rectification result, it sends the rectification result to the designated acceptance personnel; the acceptance personnel judges whether the hidden danger corresponding to the hidden danger information has been eliminated according to the rectification result; if so, it means that the rectification task is completed, and the acceptance personnel can cancel the rectification task; if not, it means that the rectification task is not completed, and the acceptance personnel can reject the review request and return the corresponding rectification opinions. In this way, the closed-loop of the entire safety risk control can be completed, effectively ensuring the safe and stable progress of operation operations and effectively eliminating safety hazards.

[0046] In some embodiments, to improve the convenience of management personnel in performing safety risk control; the work task includes work content and work location, and a corresponding two-dimensional code is set in the work location. Among them, the control method further includes: obtaining the scanning information of the two-dimensional code by the mobile terminal of the management personnel, and sending corresponding spot-check content to the mobile terminal of the management personnel according to the scanning information; obtaining the spot-check items input by the management personnel through their mobile terminals, and generating a spot-check task according to the spot-check items, so that the management personnel can perform corresponding spot-checks according to the spot-check task.

[0047] As an example, the work content, work personnel, etc. corresponding to each work location are stored in the server, and a corresponding two-dimensional code is set at each work location, and the two-dimensional code is associated with the data corresponding to the work location; when the management personnel scan the two-dimensional code through their mobile phones; the server returns the spot-checkable content corresponding to the two-dimensional code (that is, the work content corresponding to the work location) according to the scanning information; the management personnel can select through their mobile terminals to determine the items they need to spot-check (that is, the spot-checkable content selected by the management personnel that will be spot-checked); and send the selection result to the server; the server generates a spot-check task according to the selection result and sends the spot-check task to the mobile terminal of the management personnel, so that the management personnel can perform corresponding spot-checks according to the spot-check task.

[0048] In summary, according to the security risk control method of the embodiments of the present invention, first, production task information is obtained, and corresponding work tasks are generated according to the production task information, and the work tasks are allocated so that relevant personnel can execute the work tasks according to the allocation results; then, inspection tasks are generated according to the work tasks and the inspection tasks are assigned to corresponding inspectors; then, the inspectors conduct inspections according to the inspection tasks, and when potential hazards are found during the inspections, corresponding rectification tasks are generated and the rectification tasks are sent to corresponding rectifiers; then, the rectifiers carry out rectification according to the rectification tasks and send the rectification results to the accepters so that the accepters can review the rectification results; thereby effectively allocating the risk control work during the production operation process, preventing the omission of inspection items, and ensuring the stable progress of the production operation.

[0049] To implement the above embodiments, an embodiment of the present invention provides a computer-readable storage medium, on which a security risk control program is stored. When the security risk control program is executed by a processor, the security risk control method as described above is implemented.

[0050] According to the computer-readable storage medium of the embodiments of the present invention, by storing the security risk control program, when the processor executes the security risk control program, the security risk control method as described above is implemented, thereby effectively allocating the risk control work during the production operation process, preventing the omission of inspection items, and ensuring the stable progress of the production operation.

[0051] Those skilled in the art should understand that the embodiments of the present invention can be provided as a method, a system, or a computer program product. Therefore, the present invention can take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware aspects. Moreover, the present invention can take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0052] The present invention is described with reference to the flowcharts and / or block diagrams of methods, apparatuses (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, and the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to the processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing devices to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing devices generate for implementing in the process Figure 1 one process or multiple processes and / or blocks Figure 1means for the functions specified in one or more boxes.

[0053] These computer program instructions may also be stored in a computer-readable memory that can direct a computer or other programmable data processing apparatus to operate in a particular manner, such that the instructions stored in the computer-readable memory produce a manufacture including an instruction means that implements the functions specified in one Figure 1 one or more processes and / or boxes Figure 1 means for the functions specified in one or more boxes.

[0054] These computer program instructions may also be loaded onto a computer or other programmable data processing apparatus, such that a series of operational steps are performed on the computer or other programmable apparatus to produce a computer-implemented process, whereby the instructions executed on the computer or other programmable apparatus provide steps for implementing the functions specified in one Figure 1 one or more processes and / or boxes Figure 1 means for the functions specified in one or more boxes.

[0055] It should be noted that, in the claims, any reference signs placed between parentheses shall not be construed as limiting the claim. The word "comprising" does not exclude the presence of elements or steps not listed in a claim. The word "a" or "an" preceding an element does not exclude the presence of a plurality of such elements. The invention may be implemented by means of hardware comprising several distinct elements and by means of a suitably programmed computer. In a unit claim listing several means, several of these means may be embodied by the same item of hardware. The use of the words first, second, and third, etc. does not denote any order. These words may be interpreted as names.

[0056] Although the preferred embodiments of the present invention have been described, additional changes and modifications can be made by those skilled in the art once they learn of the basic inventive concept. Therefore, the appended claims are intended to be construed to include the preferred embodiments as well as all changes and modifications falling within the scope of the present invention.

[0057] It is obvious that those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalent technologies, the present invention is also intended to include these modifications and variations.

[0058] In the description of the present invention, it should be understood that the terms "first" and "second" are used for descriptive purposes only and cannot be construed as indicating or implying relative importance or implicitly specifying the quantity of the indicated technical features. Thus, features defined with "first" and "second" may explicitly or implicitly include one or more of such features. In the description of the present invention, "a plurality of" means two or more unless otherwise specifically defined.

[0059] In the present invention, unless otherwise clearly defined and limited, the terms such as "mounted", "connected", "connected to", "fixed" and the like shall be construed in a broad sense. For example, it may be a fixed connection, a detachable connection, or integrated; it may be a mechanical connection or an electrical connection; it may be directly connected or indirectly connected through an intermediate medium, and it may be the communication inside two elements or the interaction relationship between two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention may be understood according to specific circumstances.

[0060] In the present invention, unless otherwise clearly defined and limited, the first feature being "on" or "under" the second feature may be that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, the first feature being "above", "over" and "on top of" the second feature may be that the first feature is directly above or obliquely above the second feature, or merely indicates that the horizontal height of the first feature is higher than that of the second feature. The first feature being "under", "below" and "beneath" the second feature may be that the first feature is directly below or obliquely below the second feature, or merely indicates that the horizontal height of the first feature is lower than that of the second feature.

[0061] In the description of this specification, the descriptions with reference to terms such as "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. mean that the specific features, structures, materials or characteristics described in connection with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic descriptions of the above terms should not be understood as necessarily referring to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in a suitable manner in any one or more embodiments or examples. In addition, without contradiction, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of different embodiments or examples.

[0062] Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and should not be construed as limiting the present invention. Those of ordinary skill in the art can make changes, modifications, substitutions and variations to the above embodiments within the scope of the present invention.

Claims

1. A security risk control method, characterized in that, Including the following steps: Obtain production task information, generate corresponding work tasks according to the production task information, and allocate the work tasks so that relevant personnel can execute the work tasks according to the allocation results; Generate inspection tasks according to the work tasks and allocate the inspection tasks to corresponding inspectors; The inspector conducts inspections according to the inspection tasks, and when potential hazards are found during the inspections, generate corresponding rectification tasks and send the rectification tasks to corresponding rectifiers; The rectifier conducts rectification according to the rectification tasks and sends the rectification results to the accepter so that the accepter can review the rectification results; Among them, generating inspection tasks according to the work tasks and allocating the inspection tasks to corresponding inspectors includes: Obtain the number information of inspectors, and split the work tasks according to the number information of inspectors to obtain multiple work task groups; Generate an inspection route corresponding to the work task group according to the work location corresponding to each work task in any work task group, generate an inspection time period according to the work tasks in the work task group, and generate an inspection task according to the work task group, the inspection route and the inspection time period; Establish the association between the inspection task and the corresponding inspector ID; Among them, splitting the work tasks according to the number information of inspectors to obtain multiple work task groups includes: During the formation of work task groups, analyze the correlation between work tasks; Calculate the distance value between any two work tasks according to the work locations corresponding to the two work tasks, and calculate the correlation value between any two work tasks according to the distance value and the preset correlation weight value between any two work tasks; Generate work task groups according to the results of the correlation analysis.

2. The safety risk control method according to claim 1, characterized in that The work tasks include work content and work location, and a corresponding two-dimensional code is set in the work location. Among them, the control method further includes: Obtain the scanning information of the two-dimensional code by the mobile terminal of the management personnel, and send corresponding random inspection content to the mobile terminal of the management personnel according to the scanning information; Obtain the random inspection items input by the management personnel through their mobile terminals, and generate random inspection tasks according to the random inspection items so that the management personnel can conduct corresponding random inspections according to the random inspection tasks.

3. The security risk control method according to claim 1, characterized in that, The allocation of the work tasks includes: Send the work tasks to the corresponding team leader, and obtain the team member IDs input by the team leader and the work content corresponding to each team member ID; Allocate corresponding work content to the team member IDs according to the input of the team leader.

4. The safety risk control method according to claim 3, wherein The relevant personnel execute the work tasks according to the allocation results, including: After the work content is allocated, the team leader establishes a pre-shift meeting; Obtain the self-face information collected by each team member, and generate pre-shift meeting attendance information corresponding to the team member according to the self-face information; Obtain the face information corresponding to each team member collected by the team leader, and generate pre-shift meeting verification attendance information according to the face information collected by the team leader; Determine the information of the attendees based on the sign-in information of the pre-shift meeting and the verified sign-in information of the pre-shift meeting; During the process of the pre-shift meeting, obtain the corresponding pre-shift meeting information, where the pre-shift meeting information includes pre-shift meeting location information, pre-shift meeting text information, pre-shift meeting recording information, and pre-shift meeting picture information.

5. The security risk control method according to claim 1, wherein, The execution of the work tasks by the relevant personnel according to the assignment results includes: Before the relevant personnel enter the work location without network environment, download the corresponding safety inspection template according to the assignment result to download the safety inspection template to the mobile terminal of the relevant personnel; After the relevant personnel enter the work location without network environment, collect safety inspection data according to the safety inspection template through their own mobile terminals, and after leaving the work location without network environment, upload the safety inspection data to the server through network connection.

6. A computer-readable storage medium, characterized in that, It stores a safety risk control program, and when the safety risk control program is executed by a processor, it implements the safety risk control method according to any one of claims 1-5.

Citation Information

Patent Citations

  • Public security inspection task achieving method and system

    CN104200304A

  • Device and method for performing data transmission in mine network-free state

    CN105119613A

  • Pre-class speaking management system and management method

    CN112365235A

  • Intelligent construction site hazard source management method and system

    CN114283038A