A method for installing a rotary frame of a rotary hearth furnace
By disassembling the rotary hearth furnace's rotating frame into small modules and using an inverted assembly method for pre-assembly and on-site assembly, the installation problem of large rotary hearth furnace rotating frames was solved, improving construction efficiency and safety.
Patent Information
- Application Number
- CN202210616698.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-01
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2042-06-01
AI Technical Summary
The installation of the rotary hearth furnace's rotating frame is difficult, especially due to its large size and heavy weight, which makes installation and positioning difficult and affects the installation quality and safe operation of the equipment.
The slewing frame is disassembled into lower and upper frame components, and further subdivided into smaller modules. These modules are pre-assembled and adjusted before being assembled on-site. An inverted installation method is used to improve installation efficiency and safety.
It simplifies the installation process of complex components, improves construction efficiency and quality, and ensures the safe and reliable operation of the equipment.
Smart Images

Figure CN115164583B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of rotary hearth furnaces, and in particular relates to a method for installing a rotary frame of a rotary hearth furnace. Background Art
[0002] The rotary hearth furnace treatment technology is currently the most advanced metallurgical metal-containing dust and mud treatment technology in the world. By making the metal-containing dust and mud into pellets, drying them and sending them into the rotary hearth furnace, and reducing the pellets into metallized pellets under high temperature (over 1200°C) in the furnace, the effective recycling of metallurgical iron-containing dust and mud can be achieved. The furnace bottom machinery is the core component of the rotary hearth furnace main equipment. It consists of rollers, centering rollers, and a revolving frame. There is no other fixing or supporting method, and it is difficult to install it in place. In addition, the outer ring diameter of the revolving frame exceeds 40m, the size is large, the weight is heavy, and the assembly quality of each unit of the revolving frame is required to be high. Therefore, developing a method for installing the rotary frame of a rotary hearth furnace and solving the technical difficulties in installing the revolving frame of the furnace bottom machinery of a large rotary hearth furnace are of great significance to ensuring the installation quality and safe operation of the rotary hearth furnace main equipment. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a method for installing a rotary frame of a rotary hearth furnace, which is convenient for safely and reliably assembling the rotary frame of the rotary hearth furnace quickly.
[0004] The technical solution adopted by the present invention to solve the technical problem is: to provide a method for installing a rotary frame of a rotary hearth furnace, characterized in that it comprises the following steps:
[0005] S1: Installation and handover of furnace bottom rollers,
[0006] A supporting roller for supporting the rotary frame, a centering roller for maintaining the center position of the rotary frame, and a transmission device arranged on the other side of the centering roller for driving the entire rotary frame to rotate are sequentially installed on the rotary hearth furnace;
[0007] S2: Split the rotary frame,
[0008] According to the structural form of the revolving frame, the revolving frame is sorted and divided into a lower frame assembly and an upper frame assembly, wherein the lower frame assembly includes a plurality of lower sector segments, pin teeth matching the transmission device, a centering guide plate and a track plate matching the centering roller, and the upper frame assembly includes a plurality of upper sector segments, an arc angle plate, a water sealing knife and a scraping plate;
[0009] S3: Pre-assembly of lower frame assembly and upper frame assembly,
[0010] Setting up a pre-assembly frame, and pre-assembling the lower frame assembly and the upper frame assembly respectively. After the pre-assembly is qualified, the fixed positions of the components are marked with numbers in sequence, and then the components are disassembled. After disassembly, the lower sector and the upper sector are sprayed with heat-resistant and rust-proof primer;
[0011] S4: Lower frame module assembly,
[0012] Arrange and evenly divide the lower frame assembly into a number of lower frame modules, each of which includes a number of lower sector segments, and then set up a tire frame at the construction site to assemble the lower sector segments with pin teeth, centering guide rail plates and track plates into a complete lower frame module;
[0013] S5: Lower frame module installation,
[0014] Hoist the lower frame module onto the support roller, adjust the position of the track plate, and ensure that the center line of the track plate coincides with the center line of the roller surface of the support roller;
[0015] S6: Complete lower frame assembly installation.
[0016] Repeat S4 and S5 to install all the lower frame modules in place, adjust the roundness of the pin teeth through the centering guide plate and the pin tooth gasket set, and weld the connecting plate of the pin teeth firmly after installation and adjustment. After all the lower frame modules are installed in place, weld the vertical stopper for axial positioning on the side of the lower sector segment;
[0017] S7: Upper frame module assembly,
[0018] Arrange and divide the upper frame assembly into several upper frame modules, each of which includes several upper sector segments. Then, a tire frame is set up at the construction site, and the upper sector segments are installed on the tire frame. The arc angle plate, water sealing knife and scraper plate are installed on the outer edge of the upper sector segment in sequence.
[0019] According to the position of the vertical stopper on the lower sector segment determined in S6, projecting to the corresponding position of the upper sector segment and installing the adjustment bolt;
[0020] S8: Upper frame module installation,
[0021] Hoist the first upper module onto the lower frame assembly, axially adjust the upper frame module by adjusting bolts, and then hoist all the remaining upper frame modules in sequence, then add upper sector gaskets between the upper sector of adjacent upper frame modules and fix them with connecting bolts. After all the upper frame modules are installed in place, weld horizontal blocks at the bottom of the upper sector, and weld triangular blocks for radial positioning at the corresponding positions of the lower sector.
[0022] Further, in S2, the lower sector is connected and fixed to the track plate by connecting bolts, a connecting plate and pins on both sides, and between two adjacent pins, two pin holes are covered by a pin gasket set and connected and fixed by a plurality of pins;
[0023] Furthermore, the lower frame assembly includes a total of 40 lower sector segments. In S4, the lower frame assembly is split into 10 lower frame modules, each module includes 4 lower sector segments, and lower sector segment gaskets are provided between each lower sector segment and fixed with connecting bolts.
[0024] Furthermore, in S2, the upper surface of the upper sector segment is welded to the cover plate and the inner ring angle steel, the inner ring angle steel is fixed to the arc angle plate by connecting bolts, an asbestos pad is installed between the arc angle plate and the upper sector segment, and asbestos fiber rings are installed at both ends of the upper sector segment with heat-resistant adhesive. The lower outer edge of the upper sector segment is fixedly connected to the water seal knife by connecting bolts, a sealing gasket is installed between the upper sector segment and the water seal knife, and the water seal knife is connected to the scraper plate by connecting bolts.
[0025] Furthermore, the upper frame assembly includes a total of 40 upper sector segments. In S7, the upper frame assembly is split into 6 upper frame modules, each module includes 7, 7, 7, 7, 6, and 6 upper sector segments respectively, and upper sector segment gaskets are provided between each upper sector segment and fixed with connecting bolts.
[0026] Furthermore, in S3, when the lower frame assembly and the upper frame assembly are pre-assembled, adjustments are made by adding lower sector gaskets and upper sector gaskets respectively to ensure that the complete roundness error of the lower sector and the upper sector is no more than 3 mm, and when the components of the lower frame assembly are pre-assembled, an inverted installation scheme opposite to the installation direction is adopted.
[0027] Furthermore, in S4, the lower sector segment is staggered with two hole spacings when assembled with the pin tooth, and after positioning is completed, 2-4 reamed holes are provided on the pin tooth and then fastened.
[0028] Furthermore, in S5, the static contact rate between the track plate and the support roller is not less than 80%.
[0029] Furthermore, in S7, the interface of the stone fiber ring and the interface of the upper sector segment should be staggered by 0.5% to 2%, and the interface gap of the water seal knife is plugged with fiber to ensure that the interface of the water seal knife and the interface of the sealing gasket are staggered by 0.5% to 2%.
[0030] Further, in S8, the joints of the upper sector are arranged in a staggered manner with the joints of the track plate and the lower sector.
[0031] Beneficial Effects
[0032] The present invention innovates the construction process of the rotary hearth furnace revolving frame, splits the complex components into large components, and then splits the large components into small modules, so that the method of assembling each module separately is simple, and the modules are assembled and installed again under the condition that there is no abnormality in the pre-assembly and hoisted on site, thus solving the installation technical difficulties of the rotary hearth furnace revolving frame with complex structure, being safe and reliable, improving the construction efficiency and ensuring the construction quality. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 This is the general assembly drawing of the rotary frame of the rotary hearth furnace.
[0034] Figure 2 for Figure 1 Cross-section view of the lower-middle frame assembly.
[0035] Figure 3 for Figure 2 Schematic diagram of the structure of the middle and lower fan-shaped sections.
[0036] Figure 4 for Figure 2 Schematic diagram of the middle pin gear assembly.
[0037] Figure 5 for Figure 2 Schematic diagram of the middle and lower frame module structure.
[0038] Figure 6 for Figure 5 Enlarged view of the assembly position of the middle and lower sector segments and pin teeth.
[0039] Figure 7 for Figure 1 Assembly drawing of the middle and upper frame components.
[0040] Figure 8 for Figure 7 Schematic diagram of the middle and upper frame module structure.
[0041] Fig. 9 for Figure 7 Schematic diagram of the installation of the middle horizontal stopper and the triangular stopper.
[0042] Fig.10 for Figure 1 Schematic diagram of the assembly between the upper and lower frame assemblies.
[0043] Among them, 1. Lower frame assembly; 1-1. Lower sector; 1-2. Centering guide plate; 1-3. Lower sector gasket; 1-4. M20×80 connecting bolt; 1-5. M24×90 connecting bolt; 1-6. Connecting plate; 1-7. Pin tooth; 1-8. Pin; 1-9. Reamed hole; 1-10. Pin tooth gasket set; 1-11. Track plate; 2. Upper frame assembly; 2-1. Upper sector; 2-2. Cover plate; 2-3. Upper sector gasket; 2-4. Inner ring angle steel; 2-5. M2 0×100 connecting bolts; 2-6, asbestos pad; 2-7, arc angle plate; 2-8, stone fiber ring; 2-9, sealing gasket; 2-10, M16×60 connecting bolts; 2-11, water seal knife; 2-12, M16×40 connecting bolts; 2-13, scraper plate; 2-14, M20×70 connecting bolts; 2-15, triangular block; 2-16, horizontal block; 2-17, vertical block; 2-18, adjustment bolt; 3-support roller; 4, centering roller; 5, transmission device; 6, rotary hearth furnace foundation.
[0044] The same reference numerals in the various drawings represent the same components. DETAILED DESCRIPTION
[0045] The present invention will be further described below in conjunction with specific embodiments. It should be understood that these embodiments are only used to illustrate the present invention and are not intended to limit the scope of the present invention. In addition, it should be understood that after reading the content taught by the present invention, those skilled in the art can make various changes or modifications to the present invention, and these equivalent forms fall within the scope limited by the appended claims of the application equally.
[0046] The fully assembled rotary hearth furnace rotary frame structure is as follows: Figure 1 As shown, the present invention provides a method for installing a rotary frame of a rotary hearth furnace, and the installation method comprises the following steps:
[0047] S1: Installation and handover of furnace bottom rollers,
[0048] like Figure 1 As shown, a supporting roller 3 for supporting the rotary frame, a centering roller 4 for maintaining the center position of the rotary frame, and a transmission device 5 arranged on the other side of the centering roller 4 for driving the entire rotary frame to rotate are sequentially installed on the rotary hearth furnace foundation 6 that has passed the acceptance test;
[0049] S2: Split the rotary frame,
[0050] According to the structural form of the revolving frame, such as Figure 2 , 7 As shown, the revolving frame is sorted and divided into a lower frame assembly 1 and an upper frame assembly 2. The lower frame assembly 1 includes a plurality of lower sector segments 1-1 (such as Figure 3As shown), the pin teeth 1-7 matched with the transmission device 5, the centering guide plate 1-2 and the track plate 1-11 matched with the centering roller 4, the upper frame assembly 2 includes a plurality of upper fan-shaped segments 2-1, an arc angle plate 2-7, a water sealing knife 2-11 and a scraping plate 2-13,
[0051] The lower sector 1-1 is connected and fixed to the track plate 1-11 by M24×90 connecting bolts 1-5, connecting plates 1-6 and pin teeth 1-7 on both sides. Figure 4 As shown, between two adjacent pin teeth 1-7, two pin tooth holes are covered by a pin tooth gasket set 1-10 respectively and connected and fixed by four 13×100 pins 1-9. In this embodiment, the lower frame assembly 1 includes a total of 40 lower sector segments 1-1;
[0052] The upper surface of the upper sector segment 2-1 is welded to the cover plate 2-22-2 and the inner ring angle steel 2-4, the inner ring angle steel 2-4 is fixed to the arc angle plate 2-7 by M20×100 connecting bolts 2-5, an asbestos pad 2-6 is installed between the arc angle plate 2-7 and the upper sector segment 2-1, and heat-resistant adhesive stone fiber rings 2-8 are installed at both ends of the upper sector segment 2-1. The lower part of the outer edge of the upper sector segment 2-1 is fixedly connected to the water seal knife 2-11 by M16×60 connecting bolts 2-10, a sealing gasket 2-9 is installed between the upper sector segment 2-1 and the water seal knife 2-11, and the water seal knife 2-11 is connected to the scraper plate 2-13 by M16×40 connecting bolts 2-12. In this embodiment, the upper frame assembly 2 includes a total of 40 upper sector segments 2-1;
[0053] S3: Pre-assembly of lower frame assembly and upper frame assembly,
[0054] A pre-assembly frame is set up to pre-assemble the lower frame assembly 1 and the upper frame assembly 2 respectively. After the pre-assembly is inspected and qualified, the fixed positions of the components are marked with numbers in sequence, and then the components are disassembled. After disassembly, the lower sector segment 1-1 and the upper sector segment 2-1 are sprayed with heat-resistant and anti-rust primer, wherein the heat resistance of the primer of the lower sector segment 1-1 and the upper sector segment 2-1 is not less than 200° C. and 100° C. respectively for a long time;
[0055] S4: Lower frame module assembly,
[0056] Arrange and evenly divide the lower frame assembly 1 into several lower frame modules, such as Figure 5 As shown, each lower frame module includes several lower sector segments 1-1. Then, a tire frame is set up at the construction site to assemble the lower sector segments 1-1 with the pin teeth 1-7, the centering guide plate 1-2 and the track plate 1-11 into a complete lower frame module. At the same time, it should be ensured that the flatness deviation of the inner and outer ring joint planes of the track plate 1-11 is not greater than 0.5mm.
[0057] Specifically, the lower frame assembly 1 is split into 10 lower frame modules, each of which includes 4 lower sector segments 1-1, and lower sector segment gaskets 1-3 are provided between each lower sector segment 1-1 and fixed with M20×80 connecting bolts 1-4;
[0058] S5: Lower frame module installation,
[0059] Hoist the lower frame module onto the support roller 3, adjust the position of the track plate 1-11, and ensure that the center line of the track plate 1-11 coincides with the center line of the roller surface of the support roller 3;
[0060] S6: Complete lower frame assembly installation.
[0061] Repeat S4 and S5 to install all the lower frame modules in place, and adjust the roundness of the pin teeth 1-7 through the centering guide plate 1-2 and the pin tooth gasket set 1-10 to ensure that the overall out-of-roundness error of the pin teeth 1-7 is no more than 3mm, and the out-of-roundness error of any four adjacent teeth of the pin teeth 1-7 is no more than 0.2mm.
[0062] After installation and adjustment, weld the connecting plate 1-6 of the pin tooth 1-7 firmly. After all the lower frame modules are installed in place, weld the vertical stopper 2-17 for axial positioning on the side of the lower sector 1-1.
[0063] S7: Upper frame module assembly,
[0064] Arrange and divide the upper frame assembly 2 into several upper frame modules, such as Figure 8 As shown, each upper frame module includes a plurality of upper sector segments 2-1. A tire frame is then set up at the construction site, and the upper sector segments 2-1 are installed on the tire frame. An arc angle plate 2-7, a water sealing knife 2-11 and a scraper plate 2-13 are sequentially installed on the outer edge of the upper sector segment 2-1.
[0065] According to the position of the vertical stopper 2-17 on the lower sector 1-1 determined in S6, the corresponding position of the upper sector 2-1 is measured and the adjusting bolt 2-18 is installed.
[0066] Specifically, the upper frame assembly 2 is split into 6 upper frame modules, each of which includes 7, 7, 7, 7, 6, and 6 upper sector segments 2-1, respectively. An upper sector segment gasket 2-3 is provided between each upper sector segment 2-1 and is fixed with M20×70 connecting bolts 2-14;
[0067] S8: Upper frame module installation,
[0068] Hoist the first upper module onto the lower frame assembly 1, axially adjust the upper frame module by adjusting bolts 2-18, and then hoist all the remaining upper frame modules in the same way, add upper segment gaskets 2-3 between the upper segments 2-1 of adjacent upper frame modules, and fix them with connecting bolts, such as Fig. 9 As shown, after all the upper frame modules are installed in place, a horizontal stopper 2-16 is welded at the lower part of the upper sector segment 2-1, and a triangular stopper 2-15 for radial positioning is welded at the corresponding position of the lower sector segment 1-1. The horizontal stopper 2-16 and the triangular stopper 2-15 should be welded first during installation and then welded after the furnace is baked and before load production.
[0069] Among them, in S3, when the lower frame assembly 1 and the upper frame assembly 2 are pre-assembled, they are adjusted by adding the lower sector gasket 1-3 and the upper sector gasket 2-3 respectively to ensure that the complete roundness error of the lower sector 1-1 and the upper sector 2-1 is not greater than 3mm, and an inverted scheme opposite to the installation direction is adopted when the components of the lower frame assembly 1 are pre-assembled. When the inverted scheme is adopted, the upper plane of the lower sector 1-1 can be used to contact the tire frame, and the contact area is large and relatively stable. In contrast, if a conventional upright scheme is adopted, a higher tire frame needs to be set up to lift the lower plane of the lower sector 1-1 before assembling other components, which is costly and unsafe.
[0070] In S4, Figure 6 As shown, the lower sector segment 1-1 and the pin tooth 1-7 are staggered by two hole pitches when assembled, so that the pin tooth 1-7 at one end of each lower sector segment 1-1 protrudes from the edge. Figure 4 As shown, after the positioning is completed, 2-4 reaming holes 1-9 are provided on the pin teeth 1-7 and then fastened.
[0071] In the step S5, the static contact rate between the track plate 1-11 and the support roller 3 is not less than 80%.
[0072] In S7, the interface of the stone fiber ring 2-8 and the interface of the upper fan-shaped segment should be staggered by 0.5% to 2%, and the interface gap of the water seal knife 2-11 is tightly plugged with fiber to ensure that the interface of the water seal knife 2-11 and the interface of the sealing gasket 2-9 are staggered by 0.5% to 2%, thereby ensuring the sealing performance of the rotary hearth furnace.
[0073] In S8, Fig.10 As shown, the joints of the upper sector segment 2-1 are arranged staggered with the joints of the track plate 1-11 and the lower sector segment 1-1.
[0074] The present invention innovates the construction process of the rotary hearth furnace revolving frame, splits the complex components into large components, and then splits the large components into small modules, so that the method of assembling each module separately is simple, and the modules are assembled and installed again under the condition that there is no abnormality in the pre-assembly and hoisted on site, thus solving the installation technical difficulties of the rotary hearth furnace revolving frame with complex structure, being safe and reliable, improving the construction efficiency and ensuring the construction quality.
Claims
1. A method for installing a rotary frame of a rotary hearth furnace, It is characterized in that The following steps are involved: S1: Installation and handover of furnace bottom rollers, A support roller (3) for supporting a rotary frame, a centering roller (4) for maintaining the center position of the rotary frame, and a transmission device (5) provided on the other side of the centering roller (4) for driving the entire rotary frame to rotate are sequentially installed on a rotary hearth furnace foundation (6); S2: Split the rotary frame, According to the structural form of the revolving frame, the revolving frame is sorted and divided into a lower frame assembly (1) and an upper frame assembly (2), wherein the lower frame assembly (1) comprises a plurality of lower sector segments (1-1), pin teeth (1-7) matching the transmission device (5), a centering guide plate (1-2) matching the centering roller (4), and a track plate (1-11), and the upper frame assembly (2) comprises a plurality of upper sector segments (2-1), an arc angle plate (2-7), a water sealing knife (2-11), and a scraping plate (2-13); S3: Pre-assembly of lower frame assembly and upper frame assembly, Setting up a pre-assembly frame, and pre-assembling the lower frame assembly (1) and the upper frame assembly (2) respectively; after the pre-assembly passes the inspection, marking the fixed positions of the components in sequence with numbers, and then disassembling the components; after disassembly, spraying the lower sector (1-1) and the upper sector (2-1) with a heat-resistant and rust-proof primer; S4: Lower frame module assembly, Arranging and evenly dividing the lower frame assembly (1) into a plurality of lower frame modules, each lower frame module comprising a plurality of lower sector segments (1-1), then setting up a tire frame at the construction site, and assembling the lower sector segments (1-1) with pin teeth (1-7), a centering guide rail plate (1-2) and a track plate (1-11) into a complete lower frame module; S5: Lower frame module installation, The lower frame module is hoisted onto the support roller (3), and the position of the track plate (1-11) is adjusted to ensure that the center line of the track plate (1-11) coincides with the center line of the roller surface of the support roller (3); S6: Complete lower frame assembly installation, Repeat S4 and S5 to install all the lower frame modules in place, adjust the roundness of the pin teeth (1-7) by means of the centering guide plate (1-2) and the pin teeth gasket set (1-10), and after installation and adjustment, weld the connecting plate (1-6) of the pin teeth (1-7) firmly. After all the lower frame modules are installed in place, weld the vertical stopper (2-17) for axial positioning on the side of the lower sector (1-1); S7: Upper frame module assembly, Arrange and divide the upper frame assembly (2) into a plurality of upper frame modules, each of which comprises a plurality of upper sector segments (2-1); then, erect a tire frame at the construction site, install the upper sector segments (2-1) on the tire frame, install an arc angle plate (2-7), a water seal knife (2-11) and a scraper plate (2-13) on the outer edge of the upper sector segment (2-1) in sequence, and project and measure the corresponding position of the upper sector segment (2-1) according to the position of the vertical stopper (2-17) on the lower sector segment (1-1) determined in S6, and install an adjustment bolt (2-18); S8: Upper frame module installation, The first upper module is hoisted onto the lower frame assembly (1), the upper frame module is axially adjusted by adjusting bolts (2-18), and then all the remaining upper frame modules are hoisted in sequence, and then upper sector gaskets (2-3) are added between the upper sector segments (2-1) of adjacent upper frame modules and fixed with connecting bolts. After all the upper frame modules are installed in place, a horizontal stopper (2-16) is welded to the lower part of the upper sector segment (2-1), and a triangular stopper (2-15) for radial positioning is welded to the corresponding position of the lower sector segment (1-1).
2. The method for installing a rotary frame of a rotary hearth furnace according to claim 1, It is characterized in that In S2, the lower sector (1-1) is connected and fixed to the track plate (1-11) via connecting bolts, a connecting plate (1-6) and pin teeth (1-7) on both sides, and between two adjacent pin teeth (1-7), two pin tooth holes are covered by a pin tooth gasket group (1-10) and connected and fixed by a plurality of pins (1-8).
3. The method for installing a rotary frame of a rotary hearth furnace according to claim 2, It is characterized in that The lower frame assembly (1) comprises a total of 40 lower sector segments (1-1). In S4, the lower frame assembly (1) is split into 10 lower frame modules, each module comprising 4 lower sector segments (1-1), and lower sector segment gaskets (1-3) are provided between each lower sector segment (1-1) and fixed by connecting bolts.
4. The method for installing a rotary frame of a rotary hearth furnace according to claim 1, It is characterized in that In S2, the upper surface of the upper sector (2-1) is welded to the cover plate (2-2) and the inner angle steel (2-4); the inner angle steel (2-4) is fixed to the arc angle plate (2-7) by connecting bolts; an asbestos pad (2-6) is installed between the arc angle plate (2-7) and the upper sector (2-1); asbestos fiber rings (2-8) are installed at both ends of the upper sector (2-1) with heat-resistant adhesive; the lower part of the outer edge of the upper sector (2-1) is fixedly connected to the water seal knife (2-11) by connecting bolts; a sealing pad (2-9) is installed between the upper sector (2-1) and the water seal knife (2-11); and the water seal knife (2-11) is connected to the scraper plate (2-13) by connecting bolts.
5. The method for installing a rotary frame of a rotary hearth furnace according to claim 4, It is characterized in that The upper frame assembly (2) comprises a total of 40 upper sector segments (2-1). In S7, the upper frame assembly (2) is split into 6 upper frame modules, each module comprising 7, 7, 7, 7, 6, and 6 upper sector segments (2-1), respectively. An upper sector segment gasket (2-3) is provided between each upper sector segment (2-1) and is fixed by connecting bolts.
6. The method for installing a rotary frame of a rotary hearth furnace according to claim 1, It is characterized in that In S3, when the lower frame assembly (1) and the upper frame assembly (2) are pre-assembled, adjustments are made by adding lower sector gaskets (1-3) and upper sector gaskets (2-3) respectively, so as to ensure that the complete roundness error of the lower sector (1-1) and the upper sector (2-1) is not greater than 3 mm, and when the components of the lower frame assembly (1) are pre-assembled, a flip-down scheme opposite to the installation direction is adopted.
7. The method for installing a rotary frame of a rotary hearth furnace according to claim 1, It is characterized in that In S4, the lower sector (1-1) and the pin tooth (1-7) are staggered by two hole distances when assembled, and after positioning is completed, 2 to 4 reamed holes (1-9) are provided on the pin tooth (1-7) and then fastened.
8. The method for installing a rotary frame of a rotary hearth furnace according to claim 1, It is characterized in that In S5, the static contact rate between the track plate (1-11) and the support roller (3) is not less than 80%.
9. The method for installing a rotary frame of a rotary hearth furnace according to claim 4, It is characterized in that In S7, the interface of the stone fiber ring (2-8) and the interface of the upper sector (2-1) should be staggered by 0.5% to 2%, and the interface gap of the water seal knife (2-11) is tightly plugged with fiber to ensure that the interface of the water seal knife (2-11) and the interface of the sealing gasket (2-9) are staggered by 0.5% to 2%.
10. The method for installing a rotary frame of a rotary hearth furnace according to claim 1, It is characterized in that In S8, the joints of the upper sector (2-1) are arranged in a staggered manner with the joints of the track plate (1-11) and the lower sector (1-1).