Construction method of transverse bulkhead with guide frame
By setting reference lines on the port and starboard sections of the spacer compartment to form a stable reference plane, the alignment problem caused by rail deformation is solved, the alignment accuracy is improved and the overall group progress is accelerated.
Patent Information
- Application Number
- CN202211111665.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-09-13
- Publication Date
- 2025-07-11
- Estimated Expiration
- 2042-09-13
AI Technical Summary
The prior art cannot provide a stable reference level, aligning the port and starboard segments of the spacer, resulting in deformation of the rail frame and delays in overall group progress.
At least two reference lines are arranged in the port and starboard sections of the transverse compartment to form a stable reference plane. These planes are used as measurement reference to adjust the installation and alignment of the guide rail frame to ensure the stable positional relationship of the guide rail frame.
The accuracy of port and starboard alignment of the spacer compartment is improved, the steps of rail frame adjustment are reduced, and the overall group progress is shortened.
Smart Images

Figure CN115285312B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of transverse bulkhead manufacturing, in particular to a method for constructing a transverse bulkhead with a guide rail frame. Background Art
[0002] Bulkheads are used to divide the interior of a ship into several cargo holds. In order to position and fix containers, rails are installed on the bulkheads of container ships so that when loading containers, they can be loaded into the cargo holds along the rails on the bulkheads. Therefore, during the construction of container ships, rails need to be installed on the bulkheads. The rails can be installed directly on the bulkhead section after it is built. The rails can also be installed on the bulkhead sections first, and then the bulkhead sections with rails are assembled into bulkhead sections. When the rails are installed in the latter way, the bulkhead sections need to be placed horizontally, and then a rail horizontal plane is selected from the rails on the bulkhead sections as the reference horizontal plane, and then the port side bulkhead section and the starboard side bulkhead section are adjusted to the same horizontal plane with reference to the reference horizontal plane. Since the guide rail frame is long and easily deformed, if the guide rail frame used as the reference horizontal plane is deformed, the port section of the bulkhead and the starboard section of the bulkhead cannot be aligned on the same horizontal plane, and the horizontality of the guide rail frame needs to be adjusted again to align the port section of the bulkhead and the starboard section of the bulkhead, which will delay the assembly progress of the port section of the bulkhead and the starboard section of the bulkhead. In the process of first installing the guide rail frame on the bulkhead section and then assembling the bulkhead sections with the guide rail frame into the bulkhead assembly section, the prior art cannot provide a stable reference horizontal plane to align the port section of the bulkhead and the starboard section of the bulkhead. Summary of the invention
[0003] In view of the shortcomings of the prior art, the present invention provides a method for constructing a bulkhead with a guide rail frame, comprising the following construction processes: constructing a port side section of the bulkhead and a starboard side section of the bulkhead;
[0004] At least two first reference lines are arranged on the port side segment of the bulkhead, wherein the at least two first reference lines form a first reference plane, and the first reference plane is parallel to the wall surface of the port side segment of the bulkhead;
[0005] At least two second reference lines are arranged on the starboard side section of the bulkhead, wherein the at least two second reference lines form a second reference plane, and the second reference plane is parallel to the starboard side section wall of the bulkhead;
[0006] Draw a port side installation auxiliary line on the port side section of the transverse bulkhead;
[0007] Draw a starboard installation auxiliary line on the starboard section of the transverse bulkhead;
[0008] Install the first guide rail bracket on the starboard side segment of the transverse bulkhead according to the starboard installation auxiliary line;
[0009] Install the second guide rail bracket on the port side segment of the transverse bulkhead according to the port installation auxiliary line;
[0010] Adjust the starboard side segment of the transverse bulkhead with the first reference plane as the measurement reference so that the second reference plane and the first reference plane are coplanar; and
[0011] Combine the port side segment of the transverse bulkhead and the starboard side segment of the transverse bulkhead to form the total segment of the transverse bulkhead.
[0012] Preferably, the port installation auxiliary line includes the hull center line, the first longitudinal section line, the first guide rail bracket side line and the first connecting plate side line.
[0013] Preferably, the step of setting at least two first reference lines on the port side segment of the transverse bulkhead, wherein the at least two first reference lines form a first reference plane, and the first reference plane is parallel to the wall surface of the port side segment of the transverse bulkhead includes: setting at least 4 first reference poles on the port side segment of the transverse bulkhead, and setting at least one first reference point on each of the first reference poles, wherein the first reference point is higher than the first guide rail surface, at least one of the first reference lines passes through at least two of the first reference points, and at least another first reference line passes through at least two other first reference points.
[0014] Preferably, the step of installing the first guide rail bracket on the port side segment of the transverse bulkhead according to the port installation auxiliary line includes: installing the first connecting plate with the first connecting plate side line as the reference;
[0015] Lift and install the first guide rail bracket to the first connecting plate with the first guide rail bracket side line as the reference;
[0016] Position the first guide rail bracket;
[0017] Detect the straightness of the first guide rail bracket; and
[0018] Fix the first guide rail bracket to the first connecting plate.
[0019] Preferably, the step of positioning the first guide rail bracket includes:
[0020] Position the first guide rail bracket left and right according to the first guide rail bracket side line;
[0021] Position the first guide frame below the first hatch coaming vertically. Among them, the inspection line measured 550 mm downward from the upper edge of the first hatch coaming panel is used as the positioning basis for the guide head edge of the first guide frame. The non - coincidence degree between all the first guide frames and the hull members should be less than or equal to 1 / 3 of the plate thickness; and
[0022] Position the first guide frame horizontally.
[0023] Preferably, the step of positioning the first guide frame below the first hatch coaming vertically includes:
[0024] S11: Respectively set the third benchmarks at the positions beside two adjacent first guide frames on the same first connecting plate, and set the first marks on the third benchmarks;
[0025] S12: Measure 150 mm upward from the upper edge of the first hatch coaming panel as the height of the first guide surface;
[0026] S13: Measure the distance B1 from the upper edge of the first hatch coaming panel upward to the first mark;
[0027] S14: Straighten the first thin line and connect it to the third benchmarks respectively, so that the first thin line is respectively connected to one of the first marks. Among them, the distance from the first thin line to the upper edge of the first hatch coaming panel is the same as the distance B1. Taking the distance from the first thin line to the first guide surface as A1, then A1 = B1 - 150 mm;
[0028] S15: After adjusting the level of the first guide surface, repeat steps S12 to S14 to obtain the distance C1 from the first thin line to the first guide surface. A1 - C1 is the allowance of the first connecting plate; and
[0029] S16: Cut the allowance of the first connecting plate and remove the residue, then the vertical positioning of the first guide frame can be achieved.
[0030] Preferably, the starboard installation auxiliary line includes the second straight profile line, the third straight profile line, the second guide frame side line and the second connecting plate side line.
[0031] Preferably, at least two second reference lines are arranged on the starboard section of the diaphragm tank, wherein the step of forming a second reference plane by the at least two second reference lines and making the second reference plane parallel to the wall surface of the starboard section of the diaphragm tank includes: arranging at least 4 second benchmark poles on the starboard section of the diaphragm tank, and arranging at least one second reference point on each of the second benchmark poles, wherein the second reference point is higher than the second guide rail surface, at least one second reference line passes through at least two of the second reference points, and at least another second reference line passes through at least another two of the second reference points.
[0032] Preferably, the step of installing the second guide rail bracket on the starboard section of the diaphragm tank according to the starboard installation auxiliary line includes: installing the second connecting plate with reference to the edge line of the second connecting plate;
[0033] Lifting and hoisting the second guide rail bracket to the second connecting plate with reference to the edge line of the second guide rail bracket;
[0034] Positioning the second guide rail bracket;
[0035] Detecting the straightness of the second guide rail bracket; and
[0036] Fixing the second guide rail bracket to the second connecting plate.
[0037] Preferably, the step of positioning the second guide rail bracket includes:
[0038] Positioning the second guide rail bracket left and right according to the edge line of the second guide rail bracket;
[0039] Positioning the second guide rail bracket below the second hatch coaming up and down, wherein an inspection line made by measuring 550 mm downward from the upper edge of the second hatch coaming panel is used as the positioning basis for the guide head edge of the second guide rail bracket, and the non - coincidence degree between all the second guide rail brackets and the hull members should be less than or equal to 1 / 3 of the plate thickness; and
[0040] Positioning the second guide rail bracket high and low.
[0041] Preferably, the step of positioning the second guide rail bracket below the second hatch coaming up and down includes:
[0042] S21: respectively arranging fourth benchmark poles at the side positions adjacent to two adjacent second guide rail brackets on the same second connecting plate, and setting second marks on the fourth benchmark poles;
[0043] S22: Measuring 150 mm upward from the upper edge of the second hatch coaming panel as the height of the second guide rail surface;
[0044] S23: Measure upward from the upper edge of the second hatch coaming panel to the second mark to obtain distance B2;
[0045] S24: Straighten the second thin line and connect it to the fourth benchmark respectively, so that the second thin line is connected to one of the second marks. Wherein, the distance from the second thin line to the upper edge of the second hatch coaming panel is consistent with distance B2. Taking the distance from the second thin line to the second guide rail surface as A2, then A2 = B2 - 150 mm;
[0046] S25: After adjusting the level of the second guide rail surface, repeat steps S22 to S24 to obtain the distance C2 from the second thin line to the second guide rail surface. A2 - C2 is the allowance of the second connecting plate; and
[0047] S26: Cut the allowance of the second connecting plate and remove the residue, then the up-and-down positioning of the second guide rail bracket can be realized.
[0048] Preferably, the step of adjusting the starboard transverse bulkhead section with the first reference plane as the measurement reference so that the second reference plane and the first reference plane are coplanar includes:
[0049] Select two points on each of the first guide rail brackets for the horizontal measurement and adjustment of the first guide rail surface, so that the horizontal deviation between the two points is within the range of ±4 mm;
[0050] Re-inspect and adjust the hull center line and the first straight section line until they are correct;
[0051] Re-inspect and adjust the perpendicularity of the second hatch coaming panel, the second straight section line and the third straight section line until they are correct;
[0052] Adjust the half-width position of the starboard transverse bulkhead section by adjusting the spacing between the second guide rail brackets adjacent to the large joint;
[0053] Adjust the centering position of the first hard stop closest to the large joint until it is correct; and
[0054] Weld the positioning weld.
[0055] The main effects of the present invention are as follows: Since the starboard side section and the port side section of the diaphragm tank are not easily deformed themselves, at least two first reference lines and at least two second reference lines are respectively provided on the starboard side section and the port side section of the diaphragm tank. Once the first reference lines and the second reference lines are set, their positions can be kept stable. In this way, the first reference plane formed by at least two first reference lines can maintain a stable positional relationship with respect to the port side section of the diaphragm tank, and the second reference plane formed by at least two second reference lines can also maintain a stable positional relationship with respect to the starboard side section of the diaphragm tank. Since the first reference plane and the second reference plane can maintain a stable positional relationship with respect to the port side section or the starboard side section of the diaphragm tank, when adjusting the starboard side section of the diaphragm tank with the first reference plane as the measurement reference, the coplanarity of the second reference plane and the first reference plane can be made more accurate. Since the first reference plane is parallel to the port side section of the diaphragm tank and the second reference plane is parallel to the starboard side section of the diaphragm tank, after the first reference plane and the second reference plane are more accurately coplanar, the alignment accuracy of the port side section and the starboard side section of the diaphragm tank is also higher. At the same time, since there is no need to adjust the levelness of the guide rail frame to align the port side section and the starboard side section of the diaphragm tank, the overall assembly progress of the port side section and the starboard side section of the diaphragm tank is accelerated.
[0056] The above description is only an overview of the technical solution of the present invention. In order to be able to understand the technical means of the present invention more clearly and implement it according to the content of the specification, the following takes the preferred embodiments of the present invention and combines with the drawings to describe the present invention in detail. Description of the Drawings
[0057] Figure 1 is a flowchart of the construction method of the diaphragm tank with a guide rail frame in the embodiment of the present invention;
[0058] Figure 2 is an exploded view of the diaphragm tank with a guide rail frame in the embodiment of the present invention;
[0059] Figure 3 is a three-dimensional view of the diaphragm tank with a guide rail frame in the embodiment of the present invention;
[0060] Figure 4 is in the embodiment of the present invention, Figure 3 partial enlarged view C;
[0061] Figure 5 is in the embodiment of the present invention, Figure 3 partial enlarged view D;
[0062] Figure 6 is a schematic diagram of marking lines on the diaphragm tank with a guide rail frame in the embodiment of the present invention;
[0063] Figure 7 is a schematic diagram of marking lines on the port side section of the diaphragm tank with a guide rail frame in the embodiment of the present invention;
[0064] Figure 8 It is a schematic diagram of scribing for the starboard section of the diaphragm cabin with a guide rail frame in the embodiment of the present invention;
[0065] Figure 9 It is a sub - flow chart of the construction method of the diaphragm cabin with a guide rail frame in the embodiment of the present invention;
[0066] Figure 10 It is a partial three - dimensional view of the port section of the diaphragm cabin with a guide rail frame in the embodiment of the present invention;
[0067] Figure 11 and Figure 12 It is a sub - flow chart of the construction method of the diaphragm cabin with a guide rail frame in the embodiment of the present invention;
[0068] Figure 13 It is a three - dimensional schematic diagram of scribing for the port section of the diaphragm cabin with a guide rail frame in the embodiment of the present invention;
[0069] Figure 14 It is in the embodiment of the present invention, Figure 13 The sectional view along the E - E line;
[0070] Figure 15 It is in the embodiment of the present invention, Figure 13 The right view;
[0071] Figure 16 、 Figure 17 and Figure 18 It is a sub - flow chart of the construction method of the diaphragm cabin with a guide rail frame in the embodiment of the present invention;
[0072] Figure 19 It is a three - dimensional schematic diagram of scribing for the starboard section of the diaphragm cabin with a guide rail frame in the embodiment of the present invention;
[0073] Figure 20 It is in the embodiment of the present invention, Figure 19 The sectional view along the F - F line;
[0074] Figure 21 It is in the embodiment of the present invention, Figure 19 The right view;
[0075] Figure 22 It is a sub - flow chart of the construction method of the diaphragm cabin with a guide rail frame in the embodiment of the present invention.
[0076] Explanation of reference numerals:
[0077] 10 Port section of the diaphragm cabin
[0078] 10a The first reference point
[0079] 10A The first reference plane
[0080] 10b Center line of the hull
[0081] 10c First longitudinal section line
[0082] 10d First guide rail frame edge line
[0083] 10e First connecting plate edge line
[0084] 100 First hatch coaming panel
[0085] 11 Transverse bulkhead starboard section
[0086] 11a Second reference point
[0087] 11A Second reference plane
[0088] 11b Second longitudinal section line
[0089] 11c Third longitudinal section line
[0090] 11d Second guide rail frame edge line
[0091] 11e Second connecting plate edge line
[0092] 110 Second hatch coaming panel
[0093] 12 First guide rail frame
[0094] 120 First guide rail surface
[0095] 13 Second guide rail frame
[0096] 130 Second guide rail surface
[0097] 14 First benchmark
[0098] 15 Second benchmark
[0099] 16 First connecting plate
[0100] 17 Third benchmark
[0101] 170 First identification
[0102] 18 First thin line
[0103] 19 Second connecting plate
[0104] 20 Fourth benchmark
[0105] 200 Second identification
[0106] 21 Second thin line
[0107] M1 - M5 Construction method steps of the transverse bulkhead with guide rail frame
[0108] Sub-steps of the construction method of the transverse bulkhead with guide frame M61 - M65
[0109] Sub-steps of step M63, M631 - M633
[0110] Sub-steps of the construction method of the transverse bulkhead with guide frame M71 - M75
[0111] Sub-steps of step M73, M731 - M733
[0112] Sub-steps of step M4, M81 - M86 Specific implementation manners
[0113] The following specific embodiments illustrate the implementation manners of the present invention. Those skilled in the art can easily understand other advantages and effects of the present invention from the content disclosed in this specification.
[0114] It should be noted that, without conflict, the embodiments in this application and the features in the embodiments can be combined with each other. The present invention will be described in detail below with reference to the drawings and in conjunction with the embodiments. In order to enable those skilled in the art to better understand the solution of the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.
[0115] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and do not necessarily need to describe a specific order or sequence. In addition, the terms "comprising" and "having" and any variations thereof are intended to cover non-exclusive inclusion. For example, a process, method, system, product or device comprising a series of steps or units does not necessarily have to be limited to those steps or units clearly listed, but may include other steps or units not clearly listed or inherent to these processes, methods, products or devices.
[0116] Please refer to Figures 1-8 , in one embodiment, it is a construction method of a transverse bulkhead with a guide frame, including the following steps:
[0117] M1: Fabricate the starboard diaphragm section 10 and the port diaphragm section 11. M2: Set at least two first reference lines on the starboard diaphragm section 10. Among them, at least two first reference lines form a first reference plane 10A, and the first reference plane 10A is parallel to the wall surface of the starboard diaphragm section 10. Set at least two second reference lines on the port diaphragm section 11. Among them, at least two second reference lines form a second reference plane 11A, and the second reference plane 11A is parallel to the wall surface of the port diaphragm section 11. Please refer to Figure 6 and Figure 7 , mark the port installation auxiliary lines on the starboard diaphragm section 10. The port installation auxiliary lines include the hull center line 10b, the first profile line 10c, the first guide rail frame edge line 10d, and the first connecting plate edge line 10e. For example, the first profile line 10c can be a 10m profile line marked by measuring 10.005m from the hull center line 10b to the starboard (m is the unit of meter, the same below). Taking the first profile line 10c as the starting point, draw the first guide rail frame edge lines 10d from left 1 to left 8 on both sides of it. Take the center line of the first guide rail 12 offset by 165mm (mm is the unit of millimeter, the same below) as the first connecting plate edge line 10e. Please refer to Figure 6 and Figure 8 , mark the starboard installation auxiliary lines on the port diaphragm section 11. The starboard installation auxiliary lines include the second profile line 11b, the third profile line 11c, the second guide rail frame edge line 11d, and the second connecting plate edge line 11e. For example, the second profile line 11b can be a 1470mm profile line, and the third profile line 11c can be a 10m profile line made by measuring 8.535m from the 1.47m line from the midship to the starboard. Taking the third profile line 11c as the starting point, draw the second guide rail frame edge lines 11d from right 1 to right 8 on both sides of it. Take the center line of the second guide rail 13 offset by 165mm as the second connecting plate edge line 11e. M3: Install the first guide rail 12 on the starboard diaphragm section 10 according to the port installation auxiliary lines. Install the second guide rail 13 on the port diaphragm section 11 according to the starboard installation auxiliary lines. M4: Adjust the port diaphragm section 11 with the first reference plane 10A as the measurement reference so that the second reference plane 11A and the first reference plane 10A are coplanar. The coplanarity deviation between the first reference plane 10A and the second reference plane 11A can be ≤10mm. M5: Combine the starboard diaphragm section 10 and the port diaphragm section 11 to form the diaphragm subassembly.
[0118] Since the starboard side section 10 and the port side section 11 of the diaphragm tank are not easily deformed by themselves, at least two first reference lines and at least two second reference lines are respectively provided on the starboard side section 10 and the port side section 11 of the diaphragm tank. Once the first reference lines and the second reference lines are set, their positions can be kept stable. In this way, the first reference plane 10A formed by at least two first reference lines can maintain a stable positional relationship with respect to the starboard side section 10 of the diaphragm tank, and the second reference plane 11A formed by at least two second reference lines can also maintain a stable positional relationship with respect to the port side section 11 of the diaphragm tank. Since the first reference plane 10A and the second reference plane 11A can maintain stable positional relationships with respect to the starboard side section 10 or the port side section 11 of the diaphragm tank, when adjusting the port side section 11 of the diaphragm tank with the first reference plane 10A as the measurement reference, the coplanarity of the second reference plane 11A and the first reference plane 10A can be made more accurate. Since the first reference plane 10A is parallel to the starboard side section 10 of the diaphragm tank and the second reference plane 11A is parallel to the port side section 11 of the diaphragm tank, after the first reference plane 10A and the second reference plane 11A are more accurately coplanar, the alignment accuracy between the starboard side section 10 and the port side section 11 of the diaphragm tank is also higher. At the same time, since it is not necessary to adjust the levelness of the guide rail frame to align the starboard side section 10 and the port side section 11 of the diaphragm tank, the overall assembly progress of the starboard side section 10 and the port side section 11 of the diaphragm tank is accelerated.
[0119] Please also refer to Figures 2-4 Preferably, at least two first reference lines are provided on the starboard side section 10 of the diaphragm tank. Among them, the steps for at least two first reference lines to form a first reference plane 10A parallel to the wall surface of the starboard side section 10 of the diaphragm tank include: setting at least 4 first reference rods 14 on the starboard side section 10 of the diaphragm tank, and setting at least one first reference point 10a on each first reference rod 14. Among them, the first reference point 10a should be higher than the first guide rail surface 120. At least one first reference line passes through at least two first reference points 10a, and at least another first reference line passes through at least another two first reference points 10a. The heights of the first reference points 10a on the first reference rods 14 are all the same, that is, the two first reference lines are parallel or intersect to form the first reference plane 10A. The first guide rail frame 12 can be a guide rail frame with an L-shaped cross section, and the first guide rail surface 120 can be a guide rail surface parallel to the wall surface of the starboard side section of the diaphragm tank. For example, the first reference rod 14 can be a 3# angle iron with a specification of L30×30×4×700mm, and the first reference point 10a can be a center punch set on the first reference rod 14. By setting the first reference point 10a on the first reference rod 14 and making the first reference point 10a higher than the first guide rail surface 120, the first reference point 10a can be prevented from being blocked by the first guide rail surface 120, which is convenient for subsequent wire pulling at different first reference points 10a to form the first reference line.
[0120] Please also refer to Figure 2 、 Figure 3 and Figure 5 , preferably, the steps of setting at least two second reference lines on the starboard section 11 of the transverse bulkhead, wherein at least two second reference lines form a second reference plane 11A parallel to the wall surface of the starboard section 11 of the transverse bulkhead include: setting at least 4 second reference rods 15 on the starboard section 11 of the transverse bulkhead, and setting at least one second reference point 11a on each second reference rod 15, wherein the second reference point 11a is higher than the second guide rail surface 130. At least one second reference line passes through at least two second reference points 11a, and at least another second reference line passes through at least two other second reference points 11a. The heights of the second reference points 11a on the second reference rods 15 are the same, that is, the two second reference lines are parallel or intersect to form the second reference plane 11A. The second guide rail frame 13 can be a guide rail frame with an L-shaped cross section, and the second guide rail surface 130 can be a guide rail surface parallel to the wall surface of the starboard section of the transverse bulkhead. For example, the second reference rod 15 can be a 3# angle iron with a specification of L30×30×4×700mm, and the second reference point 11a can be a center punch set on the second reference rod 15. By setting the second reference point 11a on the second reference rod 15 and making the second reference point 11a higher than the second guide rail surface 130, the second reference point 11a can be prevented from being blocked by the second guide rail surface 130, which is convenient for subsequent wire pulling at different second reference points 11a to form the second reference line.
[0121] Please also refer to Figure 7 、 Figure 9 and Figure 10 , preferably, the steps of installing the first guide rail frame 12 on the port section 10 of the transverse bulkhead according to the port installation auxiliary line include:
[0122] M61: Install the first connecting plate 16 with reference to the first connecting plate edge line 10e. For example, the first connecting plate 16 can be welded to the port section 10 of the transverse bulkhead. M62: Lift and install the first guide rail frame 12 to the first connecting plate 16 with reference to the first guide rail frame edge line 10d. For example, the first guide rail frames 12 numbered 1# - 8# can be lifted and installed to the first connecting plate 16 according to the numbers from left 1 to left 8 of the first guide rail frame edge line 10d. M63: Position the first guide rail frame 12. M64: Detect the straightness of the first guide rail frame 12. M65: Fix the first guide rail frame 12 to the first connecting plate 16. For example, the first guide rail frame 12 can be fixed to the first connecting plate 16 by welding.
[0123] As Figure 11 shown, preferably, step M63 includes:
[0124] M631: Position the first guide rail rack 12 left and right according to the first guide rail rack edge line 10d. For example, the first guide rail rack 12 can be positioned left and right with a distance gauge as the standard. M632: Position the first guide rail rack 12 below the first hatch coaming up and down. Among them, the inspection line made by measuring 550 mm downward from the upper edge of the first hatch coaming panel 100 is used as the positioning basis for the guide head edge of the first guide rail rack 12. The non - coincidence degree between all the first guide rail racks 12 and the hull members should be less than or equal to 1 / 3 of the plate thickness. M633: Position the first guide rail rack 12 high and low.
[0125] Please also refer to Figures 12-15 , preferably, step M632 includes:
[0126] S11: Set the third benchmarks 17 at the side positions of two adjacent first guide rail racks 12 on the same first connecting plate 16 respectively, and set the first marks 170 on the third benchmarks 17. For example, the third benchmark 17 can be a 3# angle iron with a specification of: L30×30×4×2600 mm. The first mark 170 can be a mark formed on the third benchmark 17 by a stone pen or laser. The height of the first mark 170 is between 320 - 700 mm upward from the theoretical wall surface of the transverse bulkhead starboard section 10. The third benchmark 17 can be perpendicular to the wall surface of the transverse bulkhead starboard section 10, and the length of both ends extending out of the first hatch coaming panel 100 is 400 mm. The number of the third benchmarks 17 can be at least 3. At least two third benchmarks 17 are set beside two adjacent first guide rail racks 12, and at least one third benchmark 17 is set beside the other two adjacent first guide rail racks 12.
[0127] S12: Measure 150 mm upward from the upper edge of the first hatch coaming panel 100 as the height of the first guide rail surface 120.
[0128] S13: Measure the distance B1 from the upper edge of the first hatch coaming panel 100 upward to the first mark 170.
[0129] S14: Straighten the first thin line 18 and connect it to the third benchmarks 17 respectively, so that the first thin line 18 is connected to a first mark 170 respectively. Among them, the distance from the first thin line 18 to the upper edge of the first hatch coaming panel 100 is the same as the distance B1. Taking the distance from the first thin line 18 to the first guide rail surface 120 as A1, then A1 = B1 - 150 mm. When there are multiple third benchmarks 17, such as 3, two first thin lines 18 can be prepared, and each first thin line 18 is connected to a first mark 170. Measure the distance A1 from the two first thin lines 18 to the first guide rail surface 120 respectively in two times, and then take the average value.
[0130] S15: After adjusting the level of the first guide surface 120, repeat steps S12 to S14 to obtain the distance C1 from the first thin line 18 to the first guide surface 120. A1 - C1 is the allowance of the first connecting plate 16. For example, the level of the first guide surface 120 can be adjusted by a clamp. The difference in the level between two adjacent first guide surfaces 120 can be 2 mm.
[0131] S16: Cut the allowance of the first connecting plate 16 and remove the residue, then the up - and - down positioning of the first guide frame 12 can be achieved.
[0132] Please also refer to Figure 1 、 Figure 8 and Figure 16 Preferably, the steps of installing the second guide frame 13 on the starboard side segment 11 of the transverse bulkhead according to the starboard installation auxiliary line include:
[0133] M71: Install the second connecting plate 19 with reference to the second connecting plate edge line 11e. For example, the second connecting plate 19 can be welded to the starboard side segment 11 of the transverse bulkhead. M72: Lift and install the second guide frame 13 to the second connecting plate 19 with reference to the second guide frame edge line 11d. For example, the second guide frames 13 numbered 1# - 8# can be lifted and installed to the second connecting plate 19 according to the numbers from right 1 to right 8 of the second guide frame edge line 11d. M73: Position the second guide frame 13. M74: Detect the straightness of the second guide frame 13. M75: Fix the second guide frame 13 to the second connecting plate 19. For example, the second guide frame 13 can be fixed to the second connecting plate 19 by welding.
[0134] As Figure 17 shown, preferably, step M73 includes:
[0135] M731: Position the second guide frame 13 left - and - right with reference to the second guide frame edge line 11d. For example, the second guide frame 13 can be positioned left - and - right with a distance - maintaining gauge as the standard.
[0136] M732: Position the second guide frame 13 above and below the second hatch coaming. Among them, the inspection line made by measuring 550 mm downward from the upper edge of the second hatch coaming panel 110 is used as the positioning basis for the leading edge of the second guide frame 13. The non - coincidence degree between all second guide frames 13 and the hull members should be less than or equal to 1 / 3 of the plate thickness.
[0137] M733: Position the second guide frame 13 high - and - low.
[0138] Please also refer to Figures 18-21 Preferably, step M732 includes:
[0139] S21: At the positions beside two adjacent second guide frames 13 on the same second connecting plate 19, fourth benchmarks 20 are respectively arranged, and second markings 200 are arranged on the fourth benchmarks 20. For example, the fourth benchmark 20 can be an angle iron No. 3 with a specification of L30×30×4×2600mm, and the second marking 200 can be a mark formed on the fourth benchmark 20 by a stone pen or laser. The height of the second marking 200 is between 320 - 700mm upward from the theoretical surface of the wall of the starboard transverse bulkhead section 11. The total number of the first benchmark 14, the second benchmark 15, the third benchmark 17 and the fourth benchmark 20 is N + 6, where N is the total number of the first connecting plate 16 and the second connecting plate 19. The fourth benchmark 20 can be perpendicular to the wall of the starboard transverse bulkhead section 11, and the length that both ends extend out of the second hatch coaming panel 110 is 400mm. The number of the fourth benchmarks 20 can be at least 3. At least two fourth benchmarks 20 are arranged beside two adjacent second guide frames 13, and at least one fourth benchmark 20 is arranged beside the other two adjacent second guide frames 13.
[0140] S22: Taking the upper edge of the second hatch coaming panel 110 as a reference, measure 150mm upward as the height of the second guide surface 130.
[0141] S23: Measure upward from the upper edge of the second hatch coaming panel 110 to the second marking 200 to obtain the distance B2.
[0142] S24: Straighten the second thin line 21 and connect it to the fourth benchmark 20 respectively, so that the second thin line 21 is respectively connected to a second marking 200. Among them, the distance from the second thin line 21 to the upper edge of the second hatch coaming panel 110 is consistent with the distance B2. Taking the distance from the second thin line 21 to the second guide surface 130 as A2, then A2 = B2 - 150mm. When there are multiple fourth benchmarks 20, such as 3, two second thin lines 21 can be prepared, and each second thin line 21 is connected to a second marking 200. Measure the distance A2 from the two second thin lines 21 to the second guide surface 130 respectively in two times, and then take the average value.
[0143] S25: After adjusting the level of the second guide surface 130, repeat steps S22 to S24 to obtain the distance C2 from the second thin line 21 to the second guide surface 130. A2 - C2 is the allowance of the second connecting plate 19. For example, the level of the second guide surface 130 can be adjusted by a cleat. The difference in the levelness between two adjacent second guide surfaces 130 can be 2mm.
[0144] S26: Cut the allowance of the second connecting plate 19 and remove the residue, then the up - and - down positioning of the second guide frame 13 can be achieved.
[0145] As Figure 22 shown, preferably, step M4 includes:
[0146] M81: Select two points on each of the first guide frames 12 for horizontal measurement and adjustment of the first guide surface 120 so that the horizontal deviation between the two points is within the range of ±4 mm. M82: Re-inspect and adjust the hull center line 10b and the first profile line 10c until they are correct. After the installation of the first guide frames 12 is completed, the hull center line 10b and the first profile line 10c may be deformed. Therefore, they can be restored to the correct state (such as the design state) through re-inspection and adjustment. For example, the hull center line 10b and the first profile line 10c can be re-inspected until they are correct by using a theodolite and an angle gauge. M83: Re-inspect and adjust the perpendicularity of the second hatch coaming panel 110, the second profile line 11b, and the third profile line 11c until they are correct. After the installation of the second guide frames 13 is completed, the perpendicularity of the second hatch coaming panel 110, the second profile line 11b, and the third profile line 11c may be deformed. Therefore, they can be restored to the correct state (such as the design state) through re-inspection and adjustment. For example, the perpendicularity of the second hatch coaming panel 110, the second profile line 11b, and the third profile line 11c can be re-inspected until they are correct by using a theodolite and an angle gauge. M84: Adjust the half-width position of the starboard transverse bulkhead section 11 by adjusting the spacing between the second guide frames 13 adjacent to the large joint. M85: Adjust the centering position of the first stiffener closest to the large joint until it is correct. For example, the large joint can be a weld seam. M86: Weld the tack welds.
[0147] The above has introduced in detail a method for constructing a transverse bulkhead with guide frames provided by an embodiment of the present invention. For those of ordinary skill in the art, there will be changes in the specific implementation manners and application scopes according to the idea of the embodiment of the present invention. In summary, the content of this specification should not be construed as a limitation of the present invention. All equivalent modifications or changes made according to the spirit and technical idea of the present invention should still be covered by the claims of the present invention.
Claims
1. A construction method for a transverse bulkhead with a guide rail frame, comprising the following construction processes: Construct the left-side section and the right-side section of the transverse bulkhead, characterized in that: Set at least two first reference lines on the left-side section of the transverse bulkhead, wherein the at least two first reference lines form a first reference plane, and the first reference plane is parallel to the wall surface of the left-side section of the transverse bulkhead; Set at least two second reference lines on the right-side section of the transverse bulkhead, wherein the at least two second reference lines form a second reference plane, and the second reference plane is parallel to the wall surface of the right-side section of the transverse bulkhead; Mark the left-side installation auxiliary line on the left-side section of the transverse bulkhead; Mark the right-side installation auxiliary line on the right-side section of the transverse bulkhead; Install the first guide rail frame on the left-side section of the transverse bulkhead according to the left-side installation auxiliary line; Install the second guide rail frame on the right-side section of the transverse bulkhead according to the right-side installation auxiliary line; Adjust the right-side section of the transverse bulkhead with the first reference plane as the measurement reference so that the second reference plane and the first reference plane are coplanar; and Combine the left-side section and the right-side section of the transverse bulkhead into a transverse bulkhead sub-assembly.
2. The method for constructing a transverse bulkhead with a guide frame according to claim 1, characterized in that, The left-side installation auxiliary line includes the hull center line, the first buttock line, the first guide rail frame edge line, and the first connecting plate edge line.
3. The construction method of the transverse bulkhead with a guide rail frame according to claim 2, characterized in that, The step of setting at least two first reference lines on the left-side section of the transverse bulkhead, wherein the at least two first reference lines form a first reference plane, and the first reference plane is parallel to the wall surface of the left-side section of the transverse bulkhead includes: Set at least 4 first benchmarks on the left-side section of the transverse bulkhead, and set at least one first reference point on each of the first benchmarks, wherein the first reference point is higher than the first guide rail surface, at least one of the first reference lines passes through at least two of the first reference points, and at least another one of the first reference lines passes through at least another two of the first reference points.
4. The method for constructing a transverse bulkhead with a guide rail frame according to claim 3, characterized in that, The step of installing the first guide rail frame on the left-side section of the transverse bulkhead according to the left-side installation auxiliary line includes: Install the first connecting plate with the first connecting plate edge line as the reference; Lift and install the first guide rail frame to the first connecting plate with the first guide rail frame edge line as the reference; Position the first guide rail frame; Detect the straightness of the first guide rail frame; and Fix the first guide rail frame to the first connecting plate.
5. The construction method of the transverse bulkhead with a guide frame according to claim 4, characterized in that, The step of positioning the first guide rail frame includes: Position the first guide rail frame left and right according to the first guide rail frame edge line; Position the first guide rail frame below the first hatch coaming up and down, wherein a inspection line made by measuring 550mm downward from the upper edge of the first hatch coaming panel is used as the positioning basis for the guide head edge of the first guide rail frame, and the non-coincidence degree between all the first guide rail frames and the hull members should be less than or equal to 1 / 3 of the plate thickness; and Position the first guide rail frame high and low.
6. The method for constructing a transverse bulkhead with a guide rail frame according to claim 5, characterized in that, The step of positioning the first guide rail frame below the first hatch coaming up and down includes: S11: Respectively set third benchmarks at the side positions adjacent to two adjacent first guide rail frames on the same first connecting plate, and set first marks on the third benchmarks; S12: Measure 150 mm upward from the upper edge of the first hatch coaming panel as the height of the first guide rail surface; S13: Measure the distance B1 from the upper edge of the first hatch coaming panel upward to the first mark; S14: Straighten the first thin line and connect it to the third benchmark respectively, so that the first thin line is connected to one of the first marks respectively. Among them, the distance from the first thin line to the upper edge of the first hatch coaming panel is consistent with the distance B1. Take the distance from the first thin line to the first guide rail surface as A1, then A1 = B1 - 150 mm; S15: After adjusting the level of the first guide rail surface, repeat steps S12 to S14 to obtain the distance C1 from the first thin line to the first guide rail surface. A1 - C1 is the surplus of the first connecting plate; and S16: Cut the surplus of the first connecting plate and remove the residue, then the up and down positioning of the first guide rail bracket can be realized.
7. The construction method of the diaphragm cabin with a guide rail frame according to claim 2, characterized in that, The starboard installation auxiliary line includes a second straight section line, a third straight section line, a second guide rail bracket side line and a second connecting plate side line.
8. The construction method of the diaphragm cabin with a guide rail frame according to claim 7, characterized in that, The step of arranging at least two second reference lines on the starboard section of the diaphragm Among them, the step that the at least two second reference lines form a second reference plane parallel to the wall surface of the starboard section of the diaphragm includes: Arrange at least 4 second benchmarks on the starboard section of the diaphragm, and set at least one second reference point on each second benchmark. Among them, the second reference point should be higher than the second guide rail surface. At least one second reference line passes through at least two of the second reference points, and at least another second reference line passes through at least two other second reference points.
9. The method for constructing a transverse bulkhead with a guide rail frame according to claim 8, characterized in that The step of installing the second guide rail bracket on the starboard section of the diaphragm according to the starboard installation auxiliary line includes: Install the second connecting plate with reference to the second connecting plate side line; Lift and install the second guide rail bracket to the second connecting plate with reference to the second guide rail bracket side line; Position the second guide rail bracket; Detect the straightness of the second guide rail bracket; and Fix the second guide rail bracket to the second connecting plate.
10. The method for constructing a transverse bulkhead with a guide rail frame according to claim 9, characterized in that, The step of positioning the second guide rail bracket includes: Position the second guide rail bracket left and right according to the second guide rail bracket side line; Position the second guide rail bracket below the second hatch coaming up and down. Among them, use the inspection line made by measuring 550 mm downward from the upper edge of the second hatch coaming panel as the positioning basis for the guide head edge of the second guide rail bracket. The non - coincidence degree between all the second guide rail brackets and the hull members should be less than or equal to 1 / 3 of the plate thickness; and Position the second guide rail bracket high and low.
11. The construction method of the transverse bulkhead with a guide rail frame according to claim 10, characterized in that, The step of positioning the second guide rail bracket below the second hatch coaming up and down includes: S21: Set fourth benchmarks at the side positions adjacent to two second guide rail brackets on the same second connecting plate respectively, and set second marks on the fourth benchmarks; S22: Measure 150 mm upward from the upper edge of the second hatch coaming panel as the height of the second guide rail surface; S23: Measure the distance B2 from the upper edge of the second hatch coaming panel upward to the second mark; S24: Straighten the second thin line and connect it to the fourth benchmark respectively, so that the second thin line is connected to one of the second markings. Wherein, the distance from the second thin line to the upper edge of the second hatch coaming panel is the same as distance B2. Taking the distance from the second thin line to the second guide rail surface as A2, then A2 = B2 - 150 mm; S25: After adjusting the level of the second guide rail surface, repeat steps S22 to S24 to obtain the distance C2 from the second thin line to the second guide rail surface. A2 - C2 is the allowance of the second connecting plate; and S26: Cut the allowance of the second connecting plate and remove the residue, then the up and down positioning of the second guide rail bracket can be achieved.
12. The method for constructing a transverse bulkhead with a guide rail frame according to claim 11, characterized in that, The step of adjusting the starboard transverse bulkhead section with the first reference plane as the measurement benchmark to make the second reference plane and the first reference plane coplanar includes: Select two points on each of the first guide rail brackets for horizontal measurement and adjustment of the first guide rail surface, so that the horizontal deviation between the two points is within the range of ±4 mm; Re-inspect and adjust the hull center line and the first straight profile line until they are correct; Re-inspect and adjust the perpendicularity of the second hatch coaming panel, the second straight profile line and the third straight profile line until they are correct; Adjust the half-width position of the starboard transverse bulkhead section by adjusting the distance between the second guide rail brackets adjacent to the large joint; Adjust the centering position of the first hard stop closest to the large joint until it is correct; and Weld the positioning weld.
Citation Information
Patent Citations
Horizontal general assembly method of curved surface sections of fore body
CN102019999A
Installation method of container feet
CN104029793A