A Priority Setting Method for Under-Frequency Load Shedding in Large Power Grids

By determining the power deficit contribution and priority of shelvable loads, and combining the grid regulation effect and steady-state frequency constraints, the under-frequency load shedding scheme of large power grids is optimized, solving the problem of setting dependence on experience in traditional methods, and achieving more efficient frequency recovery and system stability.

CN115642605BActive Publication Date: 2026-11-17YUNNAN POWER GRID CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202210779070.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-06-30
Publication Date
2026-11-17
Estimated Expiration
2042-06-30

AI Technical Summary

Technical Problem

Traditional low-cycle load shedding schemes lack theoretical guidance, and the load shedding targets and their capacity settings rely on experience, resulting in insufficient adaptability and flexibility, and are prone to over-shearing or under-shearing.

Method used

Based on the faulty units and power flow distribution, determine the contribution of shelvable loads to the power deficit of each specific fault. Combine the power deficit size and fault probability to determine the load reduction priority. Calculate the load reduction capacity and target through the grid active power-frequency regulation effect and the delay requirements during the under-frequency load reduction process. Obtain approximate and exact solutions step by step to ensure steady-state frequency constraints.

Benefits of technology

This improves the adaptability and flexibility of the low-cycle load shedding method, effectively avoids over-cutting and under-cutting phenomena, and ensures frequency stability and system safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115642605B_ABST
    Figure CN115642605B_ABST
Patent Text Reader

Abstract

This invention discloses a priority tuning method for under-frequency load shedding in large power grids, comprising the following steps: obtaining the contribution of the load to be shelved to the power deficit under each specific fault; determining the priority of load shelving based on the magnitude of the power deficit and the probability of fault occurrence; obtaining approximate solutions for load shedding capacity and load shedding targets based on the active power-frequency regulation effect of the power grid itself and the delay requirements of each round during under-frequency load shedding; obtaining an exact solution based on the constraint conditions of the steady-state frequency after the under-frequency load shedding action; and continuously repeating the above two steps to complete the tuning for each round until all faults in the fault set have participated in the tuning. The priority tuning method for under-frequency load shedding in large power grids proposed in this invention has good feasibility, effectiveness, dynamic frequency characteristics, and static frequency characteristics.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of underclock load shedding in power grids, and in particular to a method for prioritizing underclock load shedding in large power grids. Background Technology

[0002] Maintaining the frequency within the specified range is a crucial indicator of the safe and stable operation of a power system and a key physical quantity triggering various power system protection measures. It is well known that frequency and active power are strongly coupled; when the active power generated by the system exceeds the active power consumed by the load, the frequency will rise; conversely, when the active power generated by the system is less than the active power consumed by the load, the frequency will fall. Due to the large-scale integration of new energy generating units into the power grid, coupled with the inherent volatility of the load, the active power of the entire power system is in a dynamic equilibrium, and the frequency is also changing in real time. As the system scale continues to expand and various control devices and measures are implemented, the actual power grid's capacity to absorb active power is constantly improving. Therefore, although the frequency fluctuates slightly during normal operation, it remains around 50Hz, within the permissible range of the power grid's safe and stable operation standards.

[0003] The successive commissioning of large power plants has brought strong power generation capacity to the power grid, optimized its operating costs, and adapted to the ever-increasing load. However, the disconnection of a large-capacity unit or even an entire large power plant due to a fault will result in a significant power deficit in the grid, causing a rapid and substantial drop in frequency. This can lead to system oscillations and even further cascading failures, resulting in incalculable economic losses. Under-frequency load shedding, as an important measure of the power system's third line of defense, involves cutting off a certain amount of load to balance the grid's active power after the system frequency drops to a certain threshold and remains there for a certain period, gradually restoring the frequency to around 50Hz.

[0004] Traditional low-cycle load reduction schemes mostly have the following shortcomings:

[0005] (1) The setting of the load reduction object and its capacity relies on experience and lacks theoretical guidance;

[0006] (2) It is only tuned for certain specific faults, which is not adaptable and flexible enough;

[0007] (3) It is easy to overcut or undercut. Summary of the Invention

[0008] The purpose of this section is to outline some aspects of the embodiments of the present invention and to briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section, as well as in the abstract and title of the present application, to avoid obscuring the purpose of this section, the abstract and title of the invention. Such simplifications or omissions shall not be used to limit the scope of the present invention.

[0009] In view of the problems existing in the above and / or prior art, the present invention is proposed.

[0010] To solve the above-mentioned technical problems, the present invention provides the following technical solution: a method for prioritizing under-cycle load shedding in a large power grid, comprising the following steps:

[0011] The contribution of the load to be shed to the power deficit under each specific fault is obtained based on the faulted unit and the power flow distribution before the fault.

[0012] The priority of load shedding is determined based on the magnitude of the power deficit and the probability of a fault.

[0013] Approximate solutions for load reduction capacity and load reduction targets are obtained based on the power grid's own active-frequency regulation effect and the delay requirements of each round during the low-frequency load reduction process.

[0014] The exact solution is obtained based on the constraint condition of the steady-state frequency after the low-cycle unloading action;

[0015] Repeat the above two steps to complete the tuning of each round until all faults in the fault set have been tuned.

[0016] As a preferred embodiment of the priority setting method for low-frequency load shedding in large power grids as described in this invention, wherein: the contribution λ of the i-th shearable load to the power deficit of fault k. ki for:

[0017]

[0018] Where μ is an intermediate variable, and δ is the voltage phase angle at the corresponding node. Let be the power factor angle of the corresponding node, and let i and a represent the node numbers of the i-th shearable load and the faulty unit, respectively. L represents the set of all shearable loads.

[0019] As a preferred embodiment of the priority setting method for low-frequency load shedding in large power grids as described in this invention, wherein: the load shedding priority R of the i-th shelvable load... i It can be defined as:

[0020]

[0021] Where F is the fault set including all faults, w represents a simple fault within the complex fault k, and p k Let P be the relative probability of fault k occurring. fk and P fw These represent the power deficits caused by complex fault k and simple fault w, respectively.

[0022] As a preferred embodiment of the priority setting method for low-frequency load shedding in large power grids as described in this invention, wherein: the delay requirement and the load shedding capacity P tr for:

[0023]

[0024] P tr =P fk -P re

[0025] Among them, t r and t r+1 These represent the times when the transient frequency is less than the frequency threshold of the r-th and (r+1)-th cycles during the low-cycle load shedding process, respectively, where Δt is the time delay between the two cycles, and P... fk For power deficit, P re To adjust the power.

[0026] As a preferred embodiment of the priority tuning method for low-frequency load shedding in large power grids described in this invention, the constraint condition for the steady-state frequency is:

[0027] 49.8Hz≤f ∞ ≤50.2Hz

[0028] Among them, f ∞ It is the frequency at which the system reaches steady state after the low-frequency load shedding action.

[0029] As a preferred embodiment of the priority setting method for low-frequency load shedding in a large power grid as described in this invention, the power grid has m branches and n nodes, and the resistance in its line impedance is ignored. Then, its node admittance matrix and branch current vector can be respectively:

[0030] I N =Y N U N

[0031] I B =Y B A T U N

[0032] Among them, I N U N These are the node injection current vector and the node voltage vector, respectively. N Y B These are the nodal admittance matrix and the branch susceptance matrix, respectively. B Let A be the branch current vector and A be the node incidence matrix.

[0033] As a preferred embodiment of the priority setting method for under-frequency load shedding in large power grids according to the present invention, wherein: the priority setting method for under-frequency load shedding in large power grids according to claim 6 is characterized in that: based on the node injection current vector and the node voltage vector, let C = A T Branch current I B Represented as:

[0034]

[0035] Among them, Z N This is the node impedance matrix.

[0036] As a preferred embodiment of the priority setting method for under-frequency load shedding in a large power grid as described in this invention, wherein: the nodes of the faulty unit and its step-up transformer are a and b respectively, and the branch connecting the two nodes is g, then:

[0037]

[0038]

[0039] in, Let y be the current flowing from node a to node b. g The line reactance of branch g is the current flowing out of the generator. It is represented as a linear combination of the currents in the other branches.

[0040] As a preferred embodiment of the priority setting method for under-cycle load shedding in large power grids as described in this invention, wherein: the... Taking the conjugate of both sides of the formula, multiplying them by the voltages at the corresponding nodes, and dividing by the same value, we get:

[0041]

[0042]

[0043] in, and P represents the voltages at nodes a and j, respectively. ab and Q ab P represents the active and reactive power generated by the generator, respectively. j and Q j These represent the active and reactive power absorbed by node j, respectively.

[0044] As a preferred embodiment of the priority setting method for under-frequency load shedding in large power grids as described in this invention, the active power generated by the faulty unit during normal operation is expressed as:

[0045]

[0046] Where, δ aδ is the phase angle of the voltage at node a; j Let be the phase angle of the voltage at node j; Let be the power factor angle of node j.

[0047] The beneficial effects of this invention are as follows: This invention proposes the contribution of shelvable load power to the unit's output power, and identifies the load "most relevant" to the power deficit; thereby improving the control effect in the approaching state of sliding mode; it proposes the priority of shelvable load reduction based on the size of the power deficit and the probability of fault occurrence, improving the adaptability and flexibility of the tuning scheme; it considers adjusting the power to reduce the load reduction capacity; it divides the tuning process into two steps, "obtaining an approximate solution" and "obtaining an exact solution", improving computational efficiency while ensuring steady-state frequency constraints; compared with the prior art, the priority tuning method for low-frequency load reduction in large power grids proposed in this invention has good feasibility, effectiveness, dynamic frequency characteristics, and static frequency characteristics. Attached Figure Description

[0048] To more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort. Wherein:

[0049] Figure 1 This is a conceptual framework diagram of the present invention.

[0050] Figure 2 This is the overall flowchart of the present invention.

[0051] Figure 3 This is a simplified schematic diagram of the actual power grid in a certain province of China.

[0052] Figure 4 It is the system frequency curve when three of the largest power plants in terms of installed capacity fail and disconnect from the grid simultaneously without any measures being taken.

[0053] Figure 5 The system frequency curves are obtained after the three largest power plants in terms of installed capacity simultaneously fail and disconnect from the grid, and the low-frequency load reduction scheme obtained in this invention is adopted.

[0054] Figure 6 This is a comparison chart of the lowest frequency during the transient process between the optimized scheme and the first set of random schemes.

[0055] Figure 7 This is a comparison chart of the highest frequencies during the transient process between the optimized scheme and the first set of random schemes.

[0056] Figure 8 This is a comparison chart of the lowest frequency during the transient process of the optimized scheme and the second set of random schemes.

[0057] Figure 9 This is a comparison chart of the highest frequencies during the transient process of the optimized scheme and the second set of random schemes.

[0058] Figure 10 This is a comparison chart of the lowest frequency during the transient process of the optimized scheme and the third random scheme.

[0059] Figure 11 This is a comparison chart of the highest frequency during the transient process between the optimized scheme and the third random scheme. Detailed Implementation

[0060] To make the above-mentioned objects, features and advantages of the present invention more apparent and understandable, the specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings.

[0061] Many specific details are set forth in the following description in order to provide a full understanding of the invention. However, the invention may also be practiced in other ways different from those described herein, and those skilled in the art can make similar extensions without departing from the spirit of the invention. Therefore, the invention is not limited to the specific embodiments disclosed below.

[0062] Secondly, the present invention will be described in detail with reference to the schematic diagrams. When detailing the embodiments of the present invention, for ease of explanation, the cross-sectional views illustrating the device structure will be partially enlarged, not according to the usual scale. Furthermore, the schematic diagrams are merely examples and should not limit the scope of protection of the present invention. In addition, actual fabrication should include three-dimensional spatial dimensions of length, width, and depth.

[0063] Furthermore, the term "an embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The phrase "in one embodiment" appearing in different places throughout this specification does not necessarily refer to the same embodiment, nor is it a single or selective embodiment that mutually excludes other embodiments.

[0064] Example 1

[0065] Reference Figures 1-2 This embodiment provides a priority setting method for under-cycle load shedding in a large power grid, including the following steps:

[0066] S1: Based on the faulty unit and the power flow distribution before the fault, obtain the contribution of the load to be cut off to the power deficit under each specific fault.

[0067] S2: Determine the priority of load shedding based on the magnitude of the power deficit and the probability of fault occurrence;

[0068] S3: Based on the active power-frequency regulation effect of the power grid itself and the delay requirements of each round during the under-frequency load shedding process, obtain approximate solutions for the load shedding capacity and load shedding objects;

[0069] S4: Obtain the exact solution based on the constraint condition of the steady-state frequency after the low-cycle load shedding action;

[0070] S5: Repeat steps S3 and S4 continuously to complete the tuning of each round until all faults in the fault set have been tuned.

[0071] Specifically, based on S1, the power deficit contribution λ of the i-th shearable load to fault k is... ki for:

[0072]

[0073] Where μ is an intermediate variable, and δ is the voltage phase angle at the corresponding node. Let be the power factor angle of the corresponding node, and let i and a represent the node numbers of the i-th shearable load and the faulty unit, respectively. L represents the set of all shearable loads.

[0074] The load shedding priority R of the i-th load that can be sheared is obtained from S2. i It can be defined as:

[0075]

[0076] Where F is the fault set including all faults, w represents a simple fault within the complex fault k, and p k Let P be the relative probability of fault k occurring. fk and P fw These represent the power deficits caused by complex fault k and simple fault w, respectively.

[0077] Based on the delay requirements and load reduction capacity P of the S3 design tr for:

[0078]

[0079] P tr =P fk -P re

[0080] Among them, t r and t r+1 These represent the times when the transient frequency is less than the frequency threshold of the r-th and (r+1)-th cycles during the low-cycle load shedding process, respectively, where Δt is the time delay between the two cycles, and P... fk For power deficit, P re To adjust the power.

[0081] The constraint condition for the steady-state frequency designed according to S4 is as follows:

[0082] 49.8Hz≤f ∞≤50.2Hz

[0083] Among them, f ∞ It is the frequency at which the system reaches steady state after the low-frequency load shedding action.

[0084] Specifically, inspired by the power flow tracking concept in the electricity market, the distribution of active power generated by each generator unit among various loads is different. After a large power source loss, if the loads that bear a large proportion of the active power generated during normal operation can be disconnected, it will play a more effective role in balancing active power, thus achieving a better frequency recovery effect. On the other hand, since the disconnected loads are the loads "most relevant" to the power deficit, the load reduction capacity will be effectively reduced. Assuming that the power grid under study has m branches and n nodes, and ignoring the resistance in its line impedance, its node admittance matrix and branch current vector can be written as formula (1) and formula (2) respectively:

[0085] I N =Y N U N (1)

[0086] I B =Y B A T U N (2)

[0087] Among them, I N U N These are the node injection current vector and the node voltage vector, respectively. N Y B These are the nodal admittance matrix and the branch susceptance matrix, respectively. B Let A be the branch current vector and A be the node incidence matrix.

[0088] Solve equations (1) and (2) simultaneously, and let C = A. T The branch current I can be B Represented as:

[0089]

[0090] Among them, Z N This is the node impedance matrix.

[0091] If we let the nodes of the faulty unit and its step-up transformer be a and b respectively, and the branch connecting the two nodes be g, then we have:

[0092]

[0093]

[0094] in, Let y be the current flowing from node a to node b.g Let g be the line reactance of branch g. In formula (4), the current flowing out of the generator is... This is expressed as a linear combination of the currents in other branches. However, in this invention, active power is the more fundamental physical quantity affecting the system frequency. Therefore, this invention takes the conjugate of both sides of equation (4), multiplies them together, and divides them by the voltage of the corresponding node to obtain equations (6) and (7):

[0095]

[0096]

[0097] in, and P represents the voltages at nodes a and j, respectively. ab and Q ab P represents the active and reactive power generated by the generator, respectively. j and Q j These represent the active and reactive power absorbed by node j, respectively.

[0098] Taking the real part of formula (7), the active power generated by the faulty unit during normal operation can be expressed as:

[0099]

[0100] Where, δ a δ is the phase angle of the voltage at node a; j Let be the phase angle of the voltage at node j; Let be the power factor angle of node j.

[0101] Formula (8) expresses the active power generated by the faulty unit during normal operation as a linear combination of the active power of each load. If we further assume that the unit fails and disconnects from the grid, its corresponding fault number is k, and the power factor angle of the i-th load that can be shelved is... Based on equation (8), the power deficit contribution λ of the i-th shearable load to fault k can be defined. ki for:

[0102]

[0103] From formula (9), we can see that the contribution λ ki The larger the value, the greater the proportion of the i-th shelvable load in the power deficit caused by fault k, and the more likely that load should be shelved first when fault k occurs.

[0104] The contribution λ proposed by formula (9) kiThis refers to a specific fault, while underclocking applies to all possible faults. Therefore, the probability and severity of the fault should also be considered. In this invention, the probability of a fault is expressed as a "relative probability," that is, the probability of a fault occurring in a large power plant is 1 / 2, and the probability of two large power plants failing simultaneously is (1 / 2). 2 =1 / 4, and so on; the severity of the fault is measured by the active power generated by the large power plant during normal operation. Alternatively, the complex fault of multiple large power plants simultaneously disconnecting from the grid can be viewed as the superposition of simple faults of individual power plants disconnecting from the grid within each plant; then the load shedding priority R of the i-th load that can be shelved is... i It can be defined as:

[0105] R i =∑ k∈F p k ×P fk ×λ ki =∑ k∈F ∑ w∈k p k ×P fw ×λ wi (10)

[0106] Where F is the fault set including all faults, w represents a simple fault within the complex fault k, and p k Let P be the relative probability of fault k occurring. fk and P fw These represent the power deficits caused by complex fault k and simple fault w, respectively.

[0107] As can be seen from formula (10), the higher the probability of a fault occurring, the greater the power deficit, and the greater the contribution of the load to the power deficit, the higher the priority R of that load. i The larger the load, the more it should be removed first.

[0108] Because the power grid itself has an active power-frequency regulation effect, it possesses a certain degree of regulation capability for the system after a power deficit occurs, and this capability cannot be ignored. Therefore, it is used as the basis for finding an approximate solution. First, we define the system's regulation power P. re When a power deficit occurs in the system, it does not trigger under-frequency load shedding and can restore the system frequency to above 49.8Hz, representing the maximum fault power, through its own active-frequency regulation effect. In this invention, the defined regulation power P... re The fault power is continuously added through simulation to determine the fault.

[0109] Then, the faults that meet the delay requirements given by formula (11) are tuned:

[0110]

[0111] Among them, t r and t r+1 Δt represents the time when the transient frequency is less than the frequency threshold of the r-th and r+1-th cycles during the low-cycle load shedding process, respectively, and Δt is the time delay between the two cycles.

[0112] Approximate solution P for the reduced load capacity tr for:

[0113] P tr =P fk -P re (12)

[0114] The method for determining the load to be reduced is to add loads in descending order of load reduction priority R until the total capacity of all loads to be reduced exceeds the load reduction capacity P for the first time. tr until.

[0115] The approximate solution obtained above can only satisfy the wheel stage selection constraint, and may not be able to satisfy the steady-state frequency constraint given by formula (13). Therefore, based on the approximate solution, further fine-tuning should be done to obtain the accurate solution.

[0116] 49.8Hz≤f ∞ ≤50.2Hz (13)

[0117] If the steady-state frequency is below 49.8Hz, it indicates under-cutting, meaning the amount of load cut is insufficient, and higher-priority loads should be added from the loads available for cutting. If the steady-state frequency is above 50.3Hz, it indicates over-cutting, meaning the capacity cut is too large, and lower-priority loads should be removed from the loads to be cut.

[0118] The process of obtaining approximate and exact solutions is repeated continuously to complete the tuning for each round until all faults in the fault set have been tuned.

[0119] In this embodiment, the contribution of the load to be cut off to the power deficit is first obtained based on the faulty unit and the power flow distribution before the fault. The coupling strength between each load that can be cut off and the faulty unit is ranked to solve the problem of lack of theoretical guidance for the setting of the load reduction target.

[0120] Then, for all faults in the fault set, the priority of load shedding is determined according to the size of the power deficit and the probability of the fault occurrence, thereby improving the adaptability and flexibility of the setting scheme.

[0121] Finally, considering the power system's self-regulation capability and the steady-state frequency constraint after under-frequency load shedding, the setting process is divided into two steps: "obtaining an approximate solution" and "obtaining an exact solution" according to the priority order and the principle of minimum load shedding. This improves the efficiency of simulation calculations while avoiding over-shearing and under-shearing phenomena.

[0122] Compared with existing technologies, the low-cycle load shedding method proposed in this invention theoretically explores the priority ranking of shearable loads, has good adaptability and flexibility, and can effectively avoid over-shearing and under-shearing phenomena.

[0123] Example 2

[0124] Reference Figures 3-11 This is the second embodiment of the present invention, which is based on the previous embodiment and differs from the previous embodiment in that:

[0125] To verify the feasibility and effectiveness of the proposed method, this invention conducted a simulation analysis using a real power grid in a southern province of my country as an example, conducted in the PSD-BPA software environment. This power grid has nine large power plants with an installed capacity of over 2000MW and 21 load shedding points. A simplified schematic diagram is shown below. Figure 3 As shown.

[0126] The key parameter settings for the low-cycle load reduction scheme are as follows:

[0127] The initial frequency, frequency difference, and delay are set according to the actual power grid operation guidelines, and are respectively set to 49.0Hz, 0.2Hz, and 0.2s.

[0128] Assuming the simultaneous disconnection of three large power plants is considered the most severe fault concentration, if no measures are taken after the three largest power plants (totaling 12450MW) disconnect simultaneously, the system will directly become unstable, leading to even more serious faults, such as... Figure 4 As shown.

[0129] If the three power plants with the largest installed capacity simultaneously fail and disconnect from the grid, and the load reduction scheme obtained according to the method of this invention is implemented, the frequency change of the system will be as follows: Figure 5 As shown, during the fault, the lowest frequency of the system was around 48.20Hz, and the steady-state frequency recovered to around 49.83Hz. This shows that the low-frequency problem of the system was effectively solved, and the system frequency will not continue to deteriorate, thus demonstrating the feasibility of the present invention.

[0130] On the other hand, 21 shelvable loads were tuned without prioritizing load reduction to obtain three sets of random low-frequency load reduction schemes with similar load reduction capacity in each round. These schemes were compared with the optimized low-frequency load reduction scheme tuned according to the method of this invention. To reduce the workload of verification, all faults in the fault set were clustered according to their fault power to generate six typical faults. The comparison results of the three random schemes and the optimized scheme are shown in Tables 1-3, where Table 1 shows the comparison data of the operation of the optimized scheme and the first random scheme:

[0131] Table 1

[0132]

[0133]

[0134] Table 2 shows the comparison data of the optimized scheme and the second random scheme:

[0135] Table 2

[0136]

[0137] Table 3 shows the comparison data of the optimized scheme and the third random scheme:

[0138] Table 3

[0139]

[0140]

[0141] Plot the results of Tables 1-3 on Figures 6-11 As can be seen from the results, the optimized low-frequency load shedding scheme can restore the system frequency to above 49.8Hz under various fault conditions. Compared with the random low-frequency load shedding scheme that is not tuned according to its load shedding priority, it not only increases the lowest frequency in the transient process to avoid the possible over-shear risk, but also reduces the highest frequency in the transient process to reduce the system fluctuation, and increases the steady-state frequency, further demonstrating the effectiveness of the present invention.

[0142] It is important to note that the constructions and arrangements of this application shown in several different exemplary embodiments are merely illustrative. Although only a few embodiments are described in detail in this disclosure, those who consult this disclosure will readily understand that many modifications are possible (e.g., changes in the size, dimensions, structure, shape, and proportions of various elements, as well as parameter values ​​(e.g., temperature, pressure, etc.), mounting arrangements, use of materials, color, orientation, etc.) without substantially departing from the novel teachings and advantages of the subject matter described in this application). For example, an element shown as integrally formed may be composed of multiple parts or elements, the position of elements may be inverted or otherwise altered, and the nature or number or position of discrete elements may be changed or altered. Therefore, all such modifications are intended to be included within the scope of the invention. The order or sequence of any process or method steps may be changed or rearranged according to alternative embodiments. In the claims, any "device plus function" clause is intended to cover the structure described herein that performs the function, and not only structurally equivalent but also equivalent in structure. Other substitutions, modifications, alterations, and omissions may be made in the design, operation, and arrangement of the exemplary embodiments without departing from the scope of the invention. Therefore, the present invention is not limited to the specific embodiments, but extends to various modifications that still fall within the scope of the appended claims.

[0143] Furthermore, in order to provide a concise description of exemplary embodiments, not all features of actual embodiments (i.e., those features that are not relevant to the currently considered best mode for carrying out the invention, or those features that are not relevant to implementing the invention) may be omitted.

[0144] It should be understood that numerous specific implementation decisions can be made during the development of any practical implementation, such as in any engineering or design project. Such development efforts may be complex and time-consuming, but for those skilled in the art who benefit from this disclosure, the development effort will be a routine work of design, manufacturing, and production without requiring much experimentation.

[0145] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and are not intended to limit it. Although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions can be made to the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention, and all such modifications or substitutions should be covered within the scope of the claims of the present invention.

Claims

1. A method for prioritizing under-cycle load shedding in a large power grid, characterized in that: Includes the following steps: The contribution of the load to be shed to the power deficit under each specific fault is obtained based on the faulted unit and the power flow distribution before the fault. The priority of load shedding is determined based on the magnitude of the power deficit and the probability of a fault. Approximate solutions for load reduction capacity and load reduction targets are obtained based on the power grid's own active-frequency regulation effect and the delay requirements of each round during the low-frequency load reduction process. The exact solution is obtained based on the constraint condition of the steady-state frequency after the low-cycle unloading action; Repeat the above two steps to complete the tuning of each round until all faults in the fault set have been tuned. The contribution of the i-th shearable load to the power deficit of fault k for: ; Where μ is an intermediate variable, and δ is the voltage phase angle at the corresponding node. Let be the power factor angle of the corresponding node, and let i and a represent the node numbers of the i-th shearable load and the faulty unit, respectively. L represents the set of all shearable loads.

2. The priority setting method for under-cycle load shedding in a large power grid according to claim 1, characterized in that: The load shedding priority of the i-th available load. It can be defined as: ; Where F is the fault set including all faults, and w represents a simple fault within the complex fault k. Let k be the relative probability of failure k occurring. and These represent the power deficits caused by complex fault k and simple fault w, respectively.

3. The priority setting method for under-cycle load shedding in a large power grid according to claim 1 or 2, characterized in that: The delay requirements and load reduction capacity for: ; ; in, and These represent the times when the transient frequency is less than the frequency threshold of the r-th round and the frequency threshold of the (r+1)-th round, respectively, during the low-cycle load shedding process. This refers to the time delay between two consecutive rounds. This is due to a power deficit. To adjust the power.

4. The priority setting method for under-cycle load shedding in a large power grid according to claim 3, characterized in that: The constraint condition for the steady-state frequency is: ; in, It is the frequency at which the system reaches steady state after the low-frequency load shedding action.

5. The priority setting method for under-cycle load shedding in a large power grid according to claim 4, characterized in that: A power grid has m branches and n nodes. Ignoring the resistance in the line impedance, the node admittance matrix and branch current vectors can be defined as follows: ; ; in, , These are the node injection current vector and the node voltage vector, respectively. , These are the nodal admittance matrix and the branch susceptance matrix, respectively. The branch current vector, This is the node association matrix.

6. The priority setting method for under-cycle load shedding in a large power grid according to claim 5, characterized in that: Based on the node injected current vector and the node voltage vector, let Branch current Represented as: ; in, This is the node impedance matrix.

7. The priority setting method for under-cycle load shedding in a large power grid according to claim 6, characterized in that: The faulty generator unit and its step-up transformer are connected at nodes a and b, respectively, and the branch connecting the two nodes is g. Then: ; ; in, Let be the current flowing from node a to node b. The line reactance of branch g is the current flowing out of the generator. It is represented as a linear combination of the currents in the other branches.

8. The priority setting method for under-cycle load shedding in a large power grid according to claim 7, characterized in that: The Taking the conjugate of both sides of the formula, multiplying them by the voltages at the corresponding nodes, and dividing by the same value, we get: ; ; in, and Let be the voltages at nodes a and j, respectively. and These represent the active and reactive power generated by the generator, respectively. and These represent the active and reactive power absorbed by node j, respectively.

9. The priority setting method for under-cycle load shedding in a large power grid according to claim 8, characterized in that: The active power generated by the faulty unit during normal operation is expressed as: ; in, Let be the phase angle of the voltage at node a; Let be the phase angle of the voltage at node j; Let be the power factor angle of node j.

Citation Information

Patent Citations

  • Computing method for subarea power grid after high-power vacancy

    CN102819618A

  • Low-frequency load shedding scheme tuning method adapted to different power shortages

    CN108964068A