Information management system and construction method based on digital twin

Through the BIM model segmentation and WBS coding rules of the digital twin information management system, the problem of matching construction quality data and BIM model partitions is solved, achieving efficient management of construction site data and accurate matching of quality information, and improving construction quality management. level.

CN116263836BActive Publication Date: 2024-10-22HUAZHONG UNIV OF SCI & TECH +2
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202310095370.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-01-19
Publication Date
2024-10-22
Estimated Expiration
2043-01-19

AI Technical Summary

Technical Problem

The existing technology cannot accurately match the building construction quality data with the zoning and segmentation parts in the BIM model, resulting in inefficient construction quality management.

Method used

An information management system based on digital twins is adopted, including a BIM model segmentation module, a quality data collection module, and a data association module. The building model is partitioned, layered, and segmented through the BIM segmentation scheme, and WBS coding rules are used to associate quality data information. , to achieve accurate matching of data.

Benefits of technology

It achieves accurate correlation of massive heterogeneous data at the construction site, improves the management efficiency and accuracy of construction quality data, supports visual analysis and control of quality data, and promotes information exchange and sharing.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116263836B_ABST
    Figure CN116263836B_ABST
Patent Text Reader

Abstract

The present invention relates to an information management system based on digital twins, including a BIM model segmentation module, a quality data acquisition module and a data association module; the BIM model segmentation module uses a BIM segmentation scheme to realize the segmentation of partitions, layers and segments on a building BIM model, and the information of the area, layer and segment is filled into the BIM component as an attribute, and the output building, area, layer, segment and component engineering decomposition structure information is output; the quality data acquisition module is used to guide the collection of field data; the data association module organizes the measurement data information based on the WBS coding rule, and realizes the association of the collected quality data information with the corresponding building, area, layer and segment components in the BIM lightweight model. Based on BIM model cutting and WBS coding rules, the present invention effectively solves the problem of fragmentation of construction site data, realizes the association of quality data collected on site with corresponding BIM construction sections, and is expected to be able to efficiently manage field construction quality data and improve the quality management level.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of construction quality management of building projects, and more specifically, to an information management system and construction method based on digital twins. Background Art

[0002] The concept of "digital twin" was first proposed in 2003 as part of product life cycle management, and has been applied to the construction field in recent years. In the aviation field, it is defined as "reverse modeling of structural life prediction and management". From the current research, digital twins mainly include three parts: physical entities, virtual models, and data. It can be described as building virtual models through data information obtained from physical entities, and affecting the operation of physical entities through data information output by virtual models. Data connects physical entities and virtual models to form a closed-loop system. In the field of building construction, the data obtained from physical entities includes both building point cloud data obtained by 3D laser scanners and structural monitoring data obtained by various sensors. The constructed virtual model includes both the virtual model obtained by reverse modeling of point cloud data and the quality monitoring model formed by various quality data. The data information output by the virtual model can be used to guide various activities such as construction and management of building construction projects.

[0003] BIM (Building Information Modeling) was first proposed by Autodesk in 2002. It can integrate various types of information such as quality and progress throughout the life cycle of a building into a three-dimensional model database. Its core is to build a virtual three-dimensional model of a building project. Through a three-dimensional visualization model, BIM can assist in the design, construction, and operation of a building. Based on BIM, participants in construction activities can also work together to improve work efficiency. At present, BIM has been widely promoted in my country and applied to various fields such as rail transit projects, housing construction and municipal engineering.

[0004] The application of BIM is an important manifestation of the application of the "digital twin" concept in the field of construction. For example, by comparing the As-built BIM model (completed BIM model) obtained by 3D laser scanning reverse modeling with the Designed BIM model (design BIM), the quality deviation information of the building can be obtained; by associating the on-site progress information with the BIM platform, managers can obtain a visual expression of the construction progress and make corresponding measures.

[0005] In the actual construction process, a large amount of construction quality data will be generated, including tables, pictures and other forms. At present, there are methods to associate these quality data information with the BIM platform, or to associate quality problems with the corresponding CAD design drawings to achieve effective management of the quality of construction projects. However, in actual production activities, construction units will carry out construction according to the pre-set zoning and segmentation projects, which can ensure the effective management of construction activities by construction units. Specifically, in the construction industry, housing construction field, and structural profession, due to the transition from the design stage to the construction stage, it is necessary to deepen the design of the BIM model (Revit format) produced by the design institute or similar roles, and hand it over to the construction unit or similar roles to form the BIM model of the construction party. Specifically, the components (beams, plates, columns, walls) in the BIM model are cut and attributed to the zoning and segmentation according to certain rules according to the zoning and segmentation of construction (zoning and segment are hierarchical horizontal space divisions, zoning is larger than segmenting, and 1-3 generally represents the 3rd segment of the 1st zone). The current quality data information cannot accurately match the subdivided zoning and segmentation parts. Summary of the invention

[0006] The technical problem to be solved by the present invention is to provide an information management system and construction method based on digital twins, which can realize the zoning and segmentation of the building BIM model, conform to the actual engineering practice, and can realize the accurate association between the massive heterogeneous quality data at the construction site and the zoning and segmentation parts in the BIM model.

[0007] The technical solution adopted by the present invention to solve its technical problem is: constructing an information management system based on digital twins, characterized in that it includes a BIM model segmentation module, a quality data acquisition module and a data association module;

[0008] The BIM model segmentation module uses the BIM segmentation scheme to achieve the segmentation of the building BIM model into zones, layers and sections, and the zone, layer and section information is filled into the BIM component as attributes, and the building, zone, layer, section and component engineering decomposition structure information is output, and the measurement work package is supported to be delegated and uploaded to the BIM lightweight platform;

[0009] The quality data acquisition module is used to guide the collection of field data. The quality data acquisition module includes a measurement work package, a measurement operation item, a measurement registration item and a measurement summary package, and outputs quality information data;

[0010] The data association module organizes the measurement data information based on the WBS coding rules, and associates the collected quality data information with the corresponding building, area, floor, and section components in the BIM lightweight model.

[0011] According to the above scheme, the BIM segmentation scheme is a scheme for cutting and / or assigning floors, beams, columns, and walls in the BIM model to partitions and sections. The BIM segmentation scheme is a CAD file that complies with the specifications. The CAD file defines the cutting method of floors, beams, columns, and walls for each partition, section, and floor.

[0012] According to the above scheme, the partitions and segments are to divide the building model in the horizontal direction in the concrete structure project, a horizontal floor is divided into multiple partitions, and a partition is further divided into multiple segments; that is, the first-level division unit is the partition, and the second-level division unit is the segment.

[0013] According to the above scheme, the BIM components are beams, slabs, columns and walls, and the BIM segmentation is the segmentation and division of beams, slabs, columns and walls; the engineering decomposition structure information of buildings, areas, floors, sections and components is a coding scheme for identifying BIM components after segmentation; the decentralized measurement work package is used to support the quality data collection plan, including measurement tasks of different buildings, areas, floors, sections and components; the BIM lightweight platform is to upload the segmented and processed BIM lightweight model to the WEB for lightweight display.

[0014] According to the above scheme, the measurement work package serves as the level of work organization, and multiple dependent or independent measurement tasks constitute a work package; the measurement operation item is to operate a measuring device once, record one or a group of values, and the corresponding level of activity or task and the level of the result obtained; the measurement registration item is the data reported to the system, ignoring the specific measuring equipment and means, independently setting the design value, setting the measurement index of the allowable error range, and the corresponding level of behavior or result; the measurement summary package is the reporting unit, that is, to obtain the evaluation of the quality of the area, layer, section, room, and component.

[0015] According to the above scheme, the WBS coding rules are the coding rules of the work breakdown structure, and the work breakdown structure is decomposed according to buildings, areas, floors, sections, and components, and the components are encoded; the quality data information is the component quality evaluation obtained by the quality data acquisition module, which is organized according to the WBS coding rules, and the information of the quality data collection location is encoded to achieve the association between the quality data information and the corresponding components.

[0016] The inventors also provide a method for constructing an information management system based on digital twins, comprising the following steps:

[0017] S1. Develop a cutting plan for the BIM model according to the zoning, layering and segmentation construction plan;

[0018] S2. Modify the BIM model segmentation scheme;

[0019] S3. Cut the BIM model of the building according to the BIM model cutting plan of the building;

[0020] S4, uploading the segmented BIM model to the WEB end to perform BIM model lightweighting;

[0021] S5. Decentralize measurement work packages according to quality inspection tasks;

[0022] S6. Based on the WBS coding rules, the quality data information is associated with the BIM lightweight model on the WEB side.

[0023] According to the above scheme, step S1 includes the following steps:

[0024] S101. Determine the construction zoning and segmentation plan and formulate the BIM segmentation plan in .dwg format;

[0025] S102. Ensure that the file coordinates are consistent with the Revit model position;

[0026] S103: Name the cutting scheme, including the floor information affected by the cutting scheme.

[0027] According to the above scheme, in step S2, the species defects caused by human factors in the process of formulating the BIM segmentation scheme are corrected; in step S3, the BIM model of the building is cut according to the BIM model cutting scheme of the building, including wall segmentation, beam segmentation, floor segmentation and column segmentation; in step S4, the segmented BIM model is uploaded to the lightweight platform on the WEB side.

[0028] According to the above scheme, in step S5, delegating the measurement work package according to the quality inspection task means issuing the quality inspection task organized by the WBS coding of building, layer, zone, section and component according to the zoning and segmenting construction plan, including the following steps:

[0029] S501. Carry out measurement plan according to the measurement work package and arrange measurement operation items;

[0030] S502, register the measurement results and fill in the measurement registration items;

[0031] S503: Quality determination, obtaining a measurement summary package.

[0032] According to the above solution, in step S6, the measurement summary package obtained in step S5 is associated with the corresponding WBS element based on the WBS coding rule.

[0033] The implementation of the digital twin-based information management system and construction method of the present invention has the following beneficial effects:

[0034] 1. Based on BIM model cutting and WBS coding rules, the present invention effectively solves the problem of data fragmentation at the construction site for the massive multi-source heterogeneous data at the construction site, realizes the association between the quality data collected on site and the corresponding BIM construction section, and is expected to be able to efficiently manage the on-site construction quality data and improve the quality management level;

[0035] 2. The present invention cuts the beams, plates, columns and walls in the building BIM model through the partition and segmentation information presented in the form of .dwg, and uses the WBS coding rules to associate the quality data information collected on site with the corresponding partition and segmentation components in the BIM model, so as to achieve accurate matching of quality information in the BIM model and assist in the quality management of engineering construction;

[0036] 3. The present invention performs fine segmentation of building BIM according to the actual engineering organization plan. The BIM plug-in formed by the BIM cutting method can match the segmented model with the engineering flow operation plan, which is convenient for further development and management according to the BIM model after segmentation in the actual project;

[0037] 4. The present invention can upload the cut BIM model to the BIM lightweight platform, support the visualization of quality data in blocks and regions, help all parties involved in the construction to analyze and control the building quality, and help realize information exchange and sharing among all parties involved, and balance the quality and progress of the project. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] The present invention will be further described below with reference to the accompanying drawings and embodiments, in which:

[0039] Figure 1 It is a structural schematic diagram of an information management system and construction method based on digital twins of the present invention;

[0040] Figure 2 It is a BIM model cutting flow chart of the present invention;

[0041] Figure 3 It is a schematic diagram of an embodiment of the BIM model cutting solution of the present invention;

[0042] Figure 4 This is a defect of the BIM model cutting solution considered by the present invention;

[0043] Figure 5 It is a schematic diagram of loading the cutting scheme of the present invention;

[0044] Figure 6 It is a flow chart of the wall segmentation algorithm of the present invention;

[0045] Figure 7 is a flow chart of the beam segmentation algorithm of the present invention;

[0046] Figure 8 is a flow chart of the floor segmentation algorithm of the present invention;

[0047] Fig. 9 It is a flow chart of the segmentation algorithm of the column of the present invention. DETAILED DESCRIPTION

[0048] In order to have a clearer understanding of the technical features, purposes and effects of the present invention, specific embodiments of the present invention are now described in detail with reference to the accompanying drawings.

[0049] like Figure 1-9 As shown, the present invention provides a method for constructing a construction quality information management system based on digital twins, comprising the following steps:

[0050] S1. Develop a cutting plan for the BIM model according to the zoning, layering and segmentation construction plan, as follows:

[0051] S101. Determine the construction zoning and segmentation plan, and formulate a BIM segmentation plan in .dwg format; the cutting plan is a set of files.

[0052] like Figure 3 As shown, each dwg file should have two layers, one named "polygon" or "split" and the other named "name". In the polygon layer, there should be a set of polygons, each polygon is a segment, and the polygon should be a closed polyline. In the name layer, there should be a set of texts, each text is the number of the segment, similar to "M_N", where M is the partition number and N is the segment number, both are integers. Each text must fall within a polygon in the polygon layer. For example, "1_2" means 1 zone, 2 segments. A closed polyline means that the starting point and end point of the drawn line must coincide, and the coordinate attributes of the starting point and end point are consistent. At the same time, the drawn line width must use the default line width, and the drawn line cannot be thickened.

[0053] S102. Ensure that the cutting plan is aligned with the BIM model. When the .dwg format cutting plan is connected in the "origin to origin" mode according to the Revit software, the .dwg format cutting plan should be consistent with the Revit model position.

[0054] S103. Name the cutting scheme, including the floor information affected by the cutting scheme. Naming standard: F .dwg,F -A <j>.dwg. For example, F1-A2.dwg means the first floor of partition 2 is divided into sections.

[0055] S2. Make necessary corrections to the BIM model segmentation scheme, such as Figure 4 As shown, the defects in the BIM model cutting plan are as follows: the polygons in the cutting plan are not sealed; there are a small number of intersections; there are separations; there are repeated polygons; there are few edges. By reading the CAD cutting plan [SO] (technically it can be a cad file or a polygon set), the corrected CAD cutting plan [SN] is output, and the statistical information [ISO] and [ISN] are output, the problems found [Q] and the corrections implemented [C] are also output.

[0056] For polygons without closed edges in the cutting scheme, the sum of the distances between the corresponding points of the polyline before correction and the polygon after correction should be less than a specified value σ; for polygons with a small amount of intersection, when the intersection area of ​​the two polygons is less than the set value, the intersection is corrected to non-intersection; for repeated polygons, only one is kept and the redundant duplicates are deleted; for separated ones, when two or more closed areas in the cutting scheme are separated and the distance between them is within the tolerance value range, they are automatically corrected to the closed areas being inseparable (only the coordinates of some points involved in the intersection are moved); for polygons with few edges, when the distances between the two endpoints of the polyline (2 or more lines) in the cutting scheme and the adjacent polygons are within the tolerance value range, they are automatically corrected to the closed areas being filled.

[0057] The core of the algorithm can be expressed as a function: void correct(schema:multipolylineset):multipolylineset. At the file processing level, it can be expressed as: void correct(oldSchemaFile:String,layerName:String,newSchemaFile:String,logFile:String).

[0058] S3. Cut the BIM model of the building according to the BIM model cutting plan of the building, such as Figure 5 As shown, it includes: wall division, beam division, floor division and column segmentation. The segment information after cutting is filled in the properties of the BIM component, specifically:

[0059] Wall segmentation means that the entire wall across sections is split into multiple walls according to the section division standard. The attachment and association relationships of the newly split walls are consistent with the original walls. At the same time, the section information of the wall is marked. For walls within the section, they are not split, and only the section information of the wall is marked.

[0060] Beam division: refers to the division of a long beam across sections into multiple beams according to the section division standard. The association relationship of the newly divided beams is consistent with the original beam. At the same time, the section information of the beam is marked. For beams within a section, they are not divided, and only the section information of the beam is marked.

[0061] Column segmentation: refers to the marking of segment information on the column's annotation attributes according to the segmentation standards.

[0062] Floor segmentation: refers to the splitting of the floor across sections into multiple floors according to the section division standard. The dependency and association relationship of the newly split floor remain consistent with the original floor. At the same time, the section information of the floor is marked. For the floor within the section, it is not split, and only the section information of the floor is marked.

[0063] At the algorithm level:

[0064] [1] First, identify the cutting object.

[0065] Including beams, slabs, columns, and walls, BIM provides API selection codes. In the Revit document, the columns are of the FamilyInstance class and are classified as the built-in OST_StructuralColumns and OST_Columns elements, and their selection codes are as follows:

[0066] Structural column filtering conditions:

[0067] (new FilteredElementCollector(Autodesk.Revit.DB.Document.doc))

[0068] .OfClass(typeof(Autodesk.Revit.DB.Document.FamilyInstance))

[0069] .OfCategory(BuiltInCategory.OST_StructuralColumns);

[0070] Architectural columns filter conditions:

[0071] (new FilteredElementCollector(Autodesk.Revit.DB.Document.doc))

[0072] .OfClass(typeof(Autodesk.Revit.DB.Document.FamilyInstance))

[0073] .OfCategory(BuiltInCategory.OST_Columns);

[0074] Walls are elements with the class Wall and the category built-in OST_Walls. The selection code based on the Revit API is as follows:

[0075] (new FilteredElementCollector(Autodesk.Revit.DB.Document.doc))

[0076] .OfClass(typeof(Autodesk.Revit.DB.Document.Wall))

[0077] .OfCategory(BuiltInCategory.OST_Walls);

[0078] A floor is an element of class Floor and classified as built-in OST_Floors. The selection code of the floor based on the Revit API is as follows:

[0079] (new FilteredElementCollector(Autodesk.Revit.DB.Document.doc)

[0080] .OfClass(typeof(Autodesk.Revit.DB.Document.Floor))

[0081] .OfCategory(BuiltInCategory.OST_Floors);

[0082] Elements of the beam class FamilyInstance and the category built-in OST_StructuralFraming. Beam selection codes based on the Revit API:

[0083] (new FilteredElementCollector(Autodesk.Revit.DB.Document.doc))

[0084] .OfClass(typeof(Autodesk.Revit.DB.Document.FamilyInstance)

[0085] .OfCategory(BuiltInCategory.OST_StructuralFraming);

[0086] [2] Cutting components and dividing walls:

[0087]

[0088]

[0089] Beam:

[0090]

[0091] plate:

[0092]

[0093]

[0094] column:

[0095]

[0096] S4. Upload the segmented BIM model to the WEB end to perform BIM model lightweighting. Specifically, the WEB end includes three first-level menus: project management, model management, and quality management. Project management is used to create projects, manage projects, and view project information; model management is used to manage model files, upload segmented BIM models, manage model directories, model review, and view models; quality management includes issuing measurement work packages organized according to "building-area-layer-section-component" to achieve the association between measurement information data and BIM components.

[0097] S5. Decentralize measurement work packages according to quality inspection tasks, specifically:

[0098] The measurement work package list including the measurement summary package results are shown as follows:

[0099]

[0100] A single measurement package includes the measurement registration item results and the measurement operation box results, and contains the following contents:

[0101]

[0102] Quality inspection personnel collect on-site data based on the delegated measurement work packages. The measurement work tasks are organized according to the WBS organization rules - building-floor-partition-segment-component, so as to realize the association between the measurement data (WBS elements) and the corresponding BIM components.

[0103] The specific steps include:

[0104] S501. Carry out measurement plan according to the measurement work package and arrange measurement operation items;

[0105] S502, register the measurement results and fill in the measurement registration items;

[0106] S503: Quality determination, obtaining a measurement summary package.

[0107] S6. Based on the WBS coding rules, the quality data information is associated with the BIM lightweight model on the WEB side, specifically:

[0108] WBS rules refer to:

[0109] 1. A building consists of at least one rvt file. After uploading, a model number will be generated for the rvt file to identify the building information;

[0110] 2. WBS organizational structure rules: building-floor-division-section-component;

[0111] 3. WBS elements include work names and work codes. The names can be customized and have business attributes. Work codes should be generated according to the spatial division method. The spatial division is divided into vertical space and horizontal space. The definition rules under the vertical space are:

[0112] For example:

[0113] R1: The building code is expressed by code, which is obtained from the image model management module, eg. M856001;

[0114] R2: The floor code is expressed in the form of F[0-9]*, eg. F1;

[0115] R3: The partition code is A[0-9]*, where the number should conform to the segment identification data in the CAD drawing, e.g. the partition code corresponding to segment 1-2 in CAD is A1;

[0116] R4: The segment code is S[0-9]*, where the number should conform to the segment identification data in the CAD drawing, e.g. the segment code corresponding to segment 1-2 in CAD is S2;

[0117] R5: The component code is composed of C and BIM construction number, eg.C8654001.

[0118] Further:

[0119] 1. An element in WBS belongs to M, and the number of M can be extracted from the name. There should be a component or BIM element identified as a building in BIM. The coding attribute of this component or BIM element is the number extracted from the WBS. If the two are considered to match, the BIM association attribute of WBS is automatically set to the BIM component or element;

[0120] 2. An element in WBS belongs to F, and the floor information F[0-9]* can be extracted from the name. There should be a component or BIM element in BIM that is identified as a floor. The elevation attribute of the component or BIM element is the floor information extracted from the WBS. The two are considered to match, and the BIM association attribute of the WBS is automatically set to the BIM component or element;

[0121] 3. An element in WBS belongs to A, and the number of A can be extracted from the name. There should be a component or BIM element identified as a partition in BIM. The coding attribute of this component or BIM element is the number extracted from the WBS. The two are considered to match, and the BIM association attribute of WBS is automatically set to the BIM component or element;

[0122] 4. An element in WBS belongs to S, and the number of S can be extracted from the name. There should be a component or BIM element identified as a segment in BIM, and the coding attribute of the component or BIM element is the number extracted from the WBS. The two are considered to match, and the BIM association attribute of WBS is automatically set to the BIM component or element;

[0123] 5. An element in WBS belongs to C, and the number of C can be extracted from the name. There should be a component identified as this in BIM, and the coding attribute of this component is the number extracted from the WBS. The two are considered to match, and the BIM association attribute of WBS is automatically set to this BIM component.

[0124] A construction quality management system based on digital twins constructed according to the above method includes a BIM model segmentation module, a quality data acquisition module, and a data association module.

[0125] The BIM model segmentation module uses the BIM segmentation scheme to achieve the segmentation of the building BIM model into zones, layers, and sections. The zone, layer, and section information are filled into the BIM components as attributes, and the decomposition structure information of the building, zone, layer, section, and component engineering is output. At the same time, it supports the decentralization of measurement work packages and uploading to the BIM lightweight platform. The BIM segmentation scheme is a scheme for cutting and / or assigning floors, beams, columns, and walls in the BIM model to zones and sections. The BIM segmentation scheme is a CAD file that complies with the specifications. The CAD file defines the cutting method of floors, beams, columns, and walls for each zone, section, and floor. In concrete structure engineering, the building model is divided horizontally. A horizontal floor is divided into multiple zones, and a zone is further divided into multiple sections; that is, the first-level division unit is the zone, and the second-level division unit is the section. BIM components are beams, slabs, columns, and walls. BIM segmentation is the segmentation and division of beams, slabs, columns, and walls. The engineering decomposition structure information of buildings, areas, floors, sections, and components is a coding scheme for identifying BIM components after segmentation. The decentralized measurement work package is used to support the quality data collection plan, including measurement tasks of different buildings, areas, floors, sections, and components. The BIM lightweight platform is a lightweight BIM model that has been segmented and processed and uploaded to the WEB for lightweight display. The BIM model segmentation module is used to (1) import a segmentation scheme document of the .dwg type, (2) import a building BIM model, (3) segment the BIM model according to the segmentation document, (4) fill in the segmentation information of the segmented BIM model components according to the segmentation scheme, and finally obtain the segmented BIM lightweight model and delegate the engineering decomposition structure.

[0126] The quality data acquisition module is used to guide the collection of field data. The quality data acquisition module includes measurement work packages, measurement operation items, measurement registration items and measurement summary packages, and outputs quality information data; the measurement work package is the level of work organization, and multiple dependent or independent measurement tasks constitute a work package; the measurement operation item is to operate a measuring device once, record one or a group of values, and the corresponding level of activity or task, and the level of the result obtained; the measurement registration item is the data reported to the system, ignoring the specific measurement equipment and means, independently setting the design value, setting the measurement indicator of the allowable error range, and the corresponding level of behavior or result; the measurement summary package is the reporting unit, that is, to obtain the evaluation of the quality of the area, layer, section, room, and component. The quality data collection association module is used to collect on-site quality data information, such as concrete strength, concrete cover thickness, steel bar spacing, component flatness, verticality, etc. It specifically includes (1) measurement work packages, including measurement tasks, (2) measurement operation items, specifically referring to the various activities in the quality data collection process, (3) measurement registration items, specifically referring to the uploaded quality data and standards, (4) measurement summary packages, that is, the evaluation of quality, and finally outputs the quality data information organized by WBS coding.

[0127] The data association module organizes the measurement data information based on the WBS coding rules to associate the collected quality data information with the corresponding building, area, floor, and section components in the BIM lightweight model. The WBS coding rules are the coding rules of the work breakdown structure. The work breakdown structure is decomposed according to buildings, areas, floors, sections, and components, and the components are coded; the quality data information is the component quality evaluation obtained by the quality data collection module, which is organized according to the WBS coding rules, and the information of the quality data collection location is coded to achieve the association of the quality data information with the corresponding components.

[0128] The embodiments of the present invention are described above in conjunction with the accompanying drawings, but the present invention is not limited to the above-mentioned specific implementation methods. The above-mentioned specific implementation methods are merely illustrative and not restrictive. Under the enlightenment of the present invention, ordinary technicians in this field can also make many forms without departing from the scope of protection of the purpose of the present invention and the claims, which all fall within the protection of the present invention.< / j>

Claims

1. An information management system based on digital twins, characterized in that: It includes BIM model segmentation module, quality data collection module and data association module; The BIM model segmentation module uses the BIM segmentation scheme to achieve the segmentation of the building BIM model into zones, layers and sections, and the zone, layer and section information is filled into the BIM component as attributes, and the building, zone, layer, section and component engineering decomposition structure information is output, and the measurement work package is supported to be delegated and uploaded to the BIM lightweight platform; The BIM segmentation scheme is a scheme for cutting and / or assigning floors, beams, columns, and walls in the BIM model to partitions and sections. The BIM segmentation scheme is a CAD file that complies with the specifications. The CAD file defines the cutting method of floors, beams, columns, and walls for each partition, section, and floor. The quality data acquisition module is used to guide the collection of field data. The quality data acquisition module includes a measurement work package, a measurement operation item, a measurement registration item and a measurement summary package, and outputs quality information data; The measurement work package is a level of work organization, and multiple dependent or independent measurement tasks constitute a work package; the measurement operation item is to operate a measurement device once, record one or a group of values, and the corresponding level of activity or task and the level of the result obtained; the measurement registration item is the data reported to the system, ignoring the specific measurement equipment and means, independently setting the design value, setting the measurement index of the allowable error range, and the corresponding level of behavior or result; the measurement summary package is the reporting unit, that is, obtaining the evaluation of the quality of the area, layer, section, room, and component; The data association module organizes the measurement data information based on the WBS coding rules, and associates the collected quality data information with the corresponding building, area, floor, and section components in the BIM lightweight model.

2. The information management system based on digital twin according to claim 1, characterized in that: The partitions and sections are to divide the building model in the horizontal direction in the concrete structure engineering. A horizontal floor is divided into multiple partitions, and a partition is further divided into multiple sections; that is, the first-level division unit is the partition, and the second-level division unit is the section.

3. The information management system based on digital twin according to claim 1, characterized in that: The BIM components are beams, slabs, columns and walls, and the BIM segmentation is the segmentation and division of beams, slabs, columns and walls; the engineering decomposition structure information of buildings, areas, floors, sections and components is a coding scheme for identifying BIM components after segmentation; the decentralized measurement work package is used to support the quality data collection plan, including measurement tasks for different buildings, areas, floors, sections and components; the BIM lightweight platform is to upload the segmented and processed BIM lightweight model to the WEB for lightweight display.

4. The information management system based on digital twin according to claim 1, characterized in that: The WBS coding rule is the coding rule of the work breakdown structure. The work breakdown structure is decomposed according to buildings, areas, floors, sections, and components, and the components are coded; The quality data information is the component quality evaluation obtained by the quality data acquisition module, which is organized according to the WBS coding rules, and the information of the quality data acquisition position is encoded to achieve the association between the quality data information and the corresponding component.

5. A method for constructing an information management system based on digital twins according to claim 1, characterized in that: The following steps are involved: S1. Develop a cutting plan for the BIM model according to the zoning, layering and segmentation construction plan; S2. Modify the BIM model segmentation scheme; S3. Cut the BIM model of the building according to the BIM model cutting plan of the building; S4, uploading the segmented BIM model to the WEB end to perform BIM model lightweighting; S5. Decentralize measurement work packages according to quality inspection tasks; S6. Based on the WBS coding rules, the quality data information is associated with the BIM lightweight model on the WEB side.

6. The method for constructing an information management system based on digital twins according to claim 5, characterized in that: The step S1 comprises the following steps: S101. Determine the construction zoning and segmentation plan and formulate the BIM segmentation plan in .dwg format; S102. Ensure that the file coordinates are consistent with the Revit model position; S103: Name the cutting scheme, including the floor information affected by the cutting scheme.

7. The method for constructing an information management system based on digital twins according to claim 5, characterized in that: In the step S2, the species defects caused by human factors in the process of formulating the BIM segmentation plan are corrected; in the step S3, the BIM model of the building is segmented according to the BIM model segmentation plan of the building, including wall segmentation, beam segmentation, floor segmentation and column segmentation; in the step S4, the segmented BIM model is uploaded to the lightweight platform on the WEB side.

8. The method for constructing an information management system based on digital twins according to claim 5, characterized in that: In step S5, delegating the measurement work package according to the quality inspection task means issuing the quality inspection task organized by WBS coding of building, floor, zone, section and component according to the zoning and segmenting construction plan, including the following steps: S501. Carry out measurement plan according to the measurement work package and arrange measurement operation items; S502, register the measurement results and fill in the measurement registration items; S503: Quality determination, obtaining a measurement summary package.

9. The method for constructing an information management system based on digital twins according to claim 5, characterized in that: In step S6, the measurement summary package obtained in step S5 is associated with the corresponding WBS element based on the WBS coding rule.

Citation Information

Patent Citations

  • Tunnel excavation three-step seven-step method based on BIM technology

    CN108170988A

  • BIM-model-based quality management standardization method of building engineering

    CN108376376A

  • A BIM-based engineering construction process management system and method

    CN109388910A

  • Digitalized bridge construction system based on BIM model

    CN110096814A

  • Quality evaluation method and system based on BIM model

    CN114519498A