Engineering cost auxiliary index management system

By decomposing and sorting the projects to be constructed in the project cost auxiliary index management system, the problem of insufficient sample size and manual subjective influence is solved, and more accurate and objective project cost predictions are achieved.

CN116308569BActive Publication Date: 2024-10-25SHENZHEN DEYASHI ENG CONSULTANTS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211538413.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-12-01
Publication Date
2024-10-25
Estimated Expiration
2042-12-01

AI Technical Summary

Technical Problem

In the existing technology, the problem of insufficient sample number and large subjective influence of workers during project cost prediction results in large errors and inaccurate prediction results.

Method used

A project cost auxiliary index management system is designed. By decomposing the project to be constructed, the auxiliary indexes of the sub-projects to be built are obtained, and based on these indexes, similar or similar sample sub-projects are retrieved in the data storage module for sorting and filtering. , calculate the predicted cost, reduce manual intervention, and improve the objectivity and accuracy of the calculation.

Benefits of technology

It effectively reduces the sample number limit, improves the accuracy and representativeness of the forecast cost, reduces the error in the calculation results, makes the forecast more accurate and objective, and the entire process is automated and has good objectivity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116308569B_ABST
    Figure CN116308569B_ABST
Patent Text Reader

Abstract

The present invention discloses an auxiliary index management system for engineering cost, which belongs to the technical field of project management. The management system decomposes the engineering to be constructed and separately calculates the predicted costs of the sub-projects to be constructed obtained after the decomposition. This method can reduce the restriction on samples and increase the number of samples involved in the calculation reference, thereby effectively reducing the error of the calculation result, making the calculated predicted cost more accurate, objective and representative. The present invention gradually reduces the number of samples involved in the calculation while ensuring the number of samples, and obtains the variation range of the engineering cost when an auxiliary index is used as a variable in different situations within the range of the screened samples. According to the different numbers of auxiliary indexes used as variables, the predicted cost range corresponding to the auxiliary index values ​​in the engineering to be constructed is obtained, and the final predicted cost is determined by calculating the union. This method does not require manual sorting and prediction, and is fully automatic, with good objectivity.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of project management, and specifically relates to an auxiliary index management system for engineering cost. Background Art

[0002] In the early stage of investment investigation of engineering construction, the result of estimating the engineering cost is an important basis for investigation. In addition, accurate estimation of the engineering cost can also assist designers and construction personnel to make reasonable adjustments to achieve reasonable and scientific cost control, thereby maximizing the benefits of engineering investment.

[0003] In the prior art, the commonly used method for predicting project cost is the indicator estimation method, which mainly uses existing similar construction projects as references and relies on the similarity of indicators and the experience of estimation staff. On the one hand, it is often difficult to find two particularly similar construction projects in actual operation, resulting in a limited number of samples, which has a great impact on the accuracy of the prediction results of the project cost; on the other hand, the use of manual estimation work is greatly affected by the subjective influence of the corresponding staff, which has a great impact on the accuracy of the prediction results of the project cost. In order to solve the above problems and achieve accurate and objective prediction of project cost, the present invention provides the following technical solutions. Summary of the invention

[0004] The purpose of the present invention is to provide an auxiliary index management system for engineering cost, so as to solve the problems in the prior art of predicting the engineering cost of construction projects, that is, the number of suitable samples is small, resulting in large errors in the prediction results and being greatly influenced by the subjective influence of the staff.

[0005] The purpose of the present invention can be achieved by the following technical solutions:

[0006] Engineering cost auxiliary index management system, including:

[0007] A data storage module is used to store completed engineering projects, sample sub-projects obtained by decomposing completed engineering projects, auxiliary indicator sets of each sample sub-project and the cost U of each sample sub-project;

[0008] Auxiliary index retrieval module, used to retrieve the content in the data storage module according to the sub-projects to be built obtained by decomposing the engineering project to be built;

[0009] The data processing module is used to analyze and process the information uploaded by the auxiliary index retrieval module, so as to obtain the predicted cost of the project to be constructed;

[0010] The working method of the above-mentioned project cost auxiliary index management system includes the following steps:

[0011] S1. Obtain the corresponding sample sub-projects in the data storage module, and obtain the auxiliary indicator set of each sample sub-project and the cost U of each sample sub-project;

[0012] S2. Decompose the construction project to be built, obtain several sub-projects to be built, compare one sub-project to be built with the sample sub-projects in the data storage module, and mark the auxiliary indicator in the sub-project to be built as Z;

[0013] Obtain the number R of sample sub-projects corresponding to auxiliary indicators that are the same as or similar to the auxiliary indicator Z in the data storage module, and sort the v auxiliary indicators corresponding to the sub-project to be built into Z1, Z2, ..., Zv in descending order according to the corresponding R values, where v is the number of auxiliary indicators corresponding to the sub-project to be built;

[0014] Obtain the sample sub-items corresponding to the auxiliary indicators that are the same as or similar to the auxiliary indicator Zi in the data storage module and the number Ri of the corresponding sample sub-items, where 1≤i≤v-1;

[0015] Obtain sample sub-items corresponding to auxiliary indicators that are the same as or close to the auxiliary indicator Z(i+1) and the number R(i+1) of corresponding sample sub-items from the corresponding Ri sample sub-items;

[0016] When R(i+1)>Ry always holds true, the R(i+1) sample sub-items finally obtained are used as control sub-items;

[0017] When R(i+1)≤Ry and Ri>Ry is established, the corresponding Z(i+1) to Zv are marked as floating indicators, and the final Ri sample sub-items are used as control sub-items, and Ry is the preset value;

[0018] S3. When there is no floating indicator, the project cost U corresponding to each comparison sub-project is obtained, and after filtering out the values ​​with large deviations, the predicted cost Uy of the sub-project to be built is calculated based on the remaining sub-project costs U;

[0019] When there are floating indicators: mark the floating indicators as Zz1, Zz2, ..., Zzj, where j is the number of floating indicators, j ≥ 1;

[0020] Within the scope of the control sub-item, one of the j floating indicators is first determined as the standard indicator, and the other auxiliary indicators are used as benchmark indicators. The control sub-items with the same or similar corresponding benchmark indicators are used as a sample group, thereby obtaining c sample groups, c ≥ 1;

[0021] In a sample group, obtain the sub-project cost U corresponding to different standard indicators, and the corresponding cost range in the sample group according to the parameter value or category of the corresponding standard indicator in the sub-project to be built;

[0022] After setting the standard indicators in sequence, obtain j cost ranges, obtain the median of the intersection of these j cost ranges, and use the median as the predicted cost Uy;

[0023] S4. Calculate and sum the predicted costs Uy of the sub-projects to be constructed of the construction project in sequence to obtain the predicted cost of the construction project to be constructed.

[0024] As a further solution of the present invention, the auxiliary indicator set is composed of a number of corresponding auxiliary indicators, and the auxiliary indicators include building area, floor area, building height, number of building floors, decoration level, engineering structure type and foundation type.

[0025] As a further solution of the present invention, the closeness means that the difference rate between the two benchmark indicators is less than a preset threshold.

[0026] As a further solution of the present invention, the method for calculating the predicted cost Uy according to the remaining sub-project cost U in step S3 is:

[0027] The project cost U corresponding to each comparison sub-project is marked as U1, U2, ..., Ug in sequence, where g = R (i + 1);

[0028] According to the formula Calculate the dispersion value F of the data set from U1 to Ug;

[0029] When F≤Fy holds true, Up is used as the predicted cost Uy of the sub-project to be built;

[0030] When F>Fy, the corresponding Uk values ​​are deleted in the order of |Uk-Up| from large to small until F≤Fy is established. The number of Uk deleted at this time is counted. If a / g is less than or equal to the preset ratio, the average value of the remaining Uk values ​​that have not been deleted is used as the predicted cost Uy of the sub-project to be built;

[0031] If a / g is greater than the preset ratio, the median between U1 and Ug is used as the predicted cost Uy of the subproject to be built;

[0032] Fy is a preset value, Up = (U1 + U2 +, ..., + Ug) / g, 1≤k≤g.

[0033] As a further solution of the present invention, when the standard index is in the form of parameter values, n coordinate points are obtained with the parameter values ​​of the standard index as the horizontal coordinates and the sub-project cost U corresponding to the parameter values ​​as the vertical coordinates, and curve fitting is performed on the n coordinate points to obtain a control curve, wherein n is the number of sub-projects in the sample group;

[0034] Obtain c control curves based on each sample group;

[0035] Obtain the parameter values ​​of the corresponding standard indicators in the sub-project to be built, obtain the corresponding c sub-project costs in the comparison curve, and thus obtain a cost range;

[0036] When the standard indicator is in the form of categories, obtain the m sub-item costs U corresponding to a category in the standard indicator in a sample group, and use the distribution range of the m sub-item costs U as the cost range of the corresponding category in the corresponding standard indicator;

[0037] m is the number of standard indicators of a category in a sample group.

[0038] As a further solution of the present invention, the standard indicators in the form of parameter values ​​include building area, floor area, building height, and number of building floors, and the standard indicators in the form of types include decoration level, engineering structure type, and foundation type.

[0039] Beneficial effects of the present invention:

[0040] (1) The present invention decomposes the construction project to be built and separately calculates the predicted costs of the sub-projects to be built obtained after the decomposition. This method can reduce the restrictions on samples and increase the number of samples involved in the calculation reference, thereby effectively reducing the error of the calculation result and making the calculated predicted cost more accurate, objective and representative;

[0041] (2) The present invention gradually reduces the number of samples involved in the calculation while ensuring the number of samples, and obtains the variation range of the project cost when an auxiliary indicator is used as a variable under different circumstances within the range of the screened samples. According to the number of auxiliary indicators used as variables, one or more predicted cost ranges corresponding to the auxiliary indicator values ​​in the project to be constructed can be obtained, and the final predicted cost is determined by calculating the union. This method does not require manual sorting and prediction, and is fully automatic, with good objectivity;

[0042] (3) The present invention decomposes the auxiliary indicators in the sub-project to be built, and statistically obtains the number of auxiliary indicators in the data storage module that are the same or similar to the auxiliary indicators in the sub-project to be built. In the subsequent processing process, the range of samples is narrowed down in order of corresponding R values ​​from large to small, which can effectively increase the number of sample sub-projects that ultimately participate in the calculation, thereby facilitating improving the accuracy of the final calculation results. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] The present invention will be further described below in conjunction with the accompanying drawings.

[0044] Figure 1 It is a schematic diagram of the framework structure of the engineering cost auxiliary index management system of the present invention. DETAILED DESCRIPTION

[0045] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0046] Engineering cost auxiliary indicator management system, such as Figure 1 As shown, including:

[0047] The data storage module is used to store completed engineering projects, decompose the stored completed engineering projects, and store the corresponding sample sub-projects obtained by decomposition, the auxiliary indicator set of each sample sub-project, and the cost U of each sample sub-project;

[0048] The auxiliary indicator set is composed of a number of corresponding auxiliary indicators, including building area, floor area, building height, number of building floors, decoration level, engineering structure type, foundation type, etc.;

[0049] An auxiliary indicator retrieval module is used to retrieve the sample sub-projects, the auxiliary indicator sets of each sample sub-project and the cost U of each sample sub-project in the data storage module according to the sub-projects to be built obtained by decomposing the engineering project to be built;

[0050] The data processing module is used to analyze and process the information uploaded by the auxiliary index retrieval module, so as to obtain the predicted cost of the project to be constructed;

[0051] The working method of the above-mentioned engineering cost auxiliary index management system includes the following steps:

[0052] S1. Obtain completed engineering projects as samples in the data storage module, decompose the samples, obtain several corresponding sample sub-projects, and obtain the auxiliary indicator set of each sample sub-project and the cost U of each sample sub-project;

[0053] S2. Decompose the construction project to be built, obtain several sub-projects to be built, compare one sub-project to be built with the sample sub-projects in the data storage module, and mark the auxiliary indicator in the sub-project to be built as Z;

[0054] Obtain the number R of sample sub-projects corresponding to auxiliary indicators that are the same as or similar to the auxiliary indicator Z in the data storage module, and sort the v auxiliary indicators corresponding to the sub-project to be built into Z1, Z2, ..., Zv in descending order according to the corresponding R values, where v is the number of auxiliary indicators corresponding to the sub-project to be built;

[0055] Obtain the sample sub-items corresponding to the auxiliary indicators that are the same as or similar to the auxiliary indicator Zi in the data storage module and the number Ri of the corresponding sample sub-items, where 1≤i≤v-1;

[0056] Obtain sample sub-items corresponding to auxiliary indicators that are the same as or close to the auxiliary indicator Z(i+1) and the number R(i+1) of corresponding sample sub-items from the corresponding Ri sample sub-items;

[0057] When R(i+1)>Ry always holds true, the R(i+1) sample sub-items finally obtained are used as control sub-items;

[0058] When R(i+1)≤Ry and Ri>Ry holds, the corresponding Z(i+1) to Zv are marked as floating indicators, and the Ri sample sub-items finally obtained are used as control sub-items;

[0059] Ry is a preset value; the term "similar" means that the difference rate between the two benchmark indicators is less than a preset threshold;

[0060] In this step, the auxiliary indicators in the sub-project to be built are decomposed, and the number of auxiliary indicators in the data storage module that are the same or similar to the auxiliary indicators in the sub-project to be built is counted. In the subsequent processing process, the range of samples is narrowed down in the order of corresponding R values ​​from large to small, which can effectively increase the number of sample sub-projects that are finally involved in the calculation, thereby facilitating the improvement of the accuracy of the final calculation results;

[0061] S3. When there is no floating indicator, the project cost U corresponding to each comparison sub-project is obtained, and after filtering out the values ​​with large deviations, the predicted cost Uy of the sub-project to be built is calculated based on the remaining sub-project costs U;

[0062] When there is a floating indicator:

[0063] The floating indicators are marked as Zz1, Zz2, ..., Zzj, where j is the number of floating indicators, j ≥ 1;

[0064] Within the scope of the control sub-item, one of the j floating indicators is first determined as the standard indicator, and the other auxiliary indicators are used as benchmark indicators. The control sub-items with the same or similar corresponding benchmark indicators are used as a sample group, thereby obtaining c sample groups, c ≥ 1;

[0065] The close correspondence between the two benchmark indicators means that the difference between the two benchmark indicators is less than a preset threshold;

[0066] In a sample group, obtain the sub-project cost U corresponding to different standard indicators;

[0067] When the standard index is in the form of parameter values, obtain n coordinate points with the parameter values ​​of the standard index as the horizontal coordinate and the sub-project cost U corresponding to the parameter values ​​as the vertical coordinate, perform curve fitting on these n coordinate points to obtain a control curve, where n is the number of sub-projects in the sample group;

[0068] Obtain c control curves based on each sample group;

[0069] Obtain the parameter values ​​of the corresponding standard indicators in the sub-project to be built, obtain the corresponding c sub-project costs in the comparison curve, and thus obtain a cost range;

[0070] When the standard indicator is in the form of categories, obtain the m sub-item costs U corresponding to a category in the standard indicator in a sample group, and use the distribution range of the m sub-item costs U as the cost range of the corresponding category in the corresponding standard indicator;

[0071] m is the number of standard indicators of a category in a sample group;

[0072] Standard indicators in the form of parameter values ​​include building area, floor area, building height, number of building floors, etc. Standard indicators in the form of types include decoration level, engineering structure type, foundation type, etc.

[0073] After setting the standard indicators in sequence, obtain j cost ranges, obtain the median of the intersection of these j cost ranges, and use the median as the predicted cost Uy;

[0074] This step gradually reduces the number of samples involved in the calculation while ensuring the number of samples, and obtains the range of changes in the project cost when an auxiliary indicator is used as a variable under different circumstances within the range of the screened samples. According to the number of auxiliary indicators used as variables, one or more predicted cost ranges corresponding to the auxiliary indicator values ​​in the project to be constructed can be obtained, and the final predicted cost is determined by calculating the union. This method does not require manual sorting and prediction, and is fully automatic, with good objectivity;

[0075] The method for filtering out the values ​​with larger deviation values ​​in step S3 is:

[0076] The project cost U corresponding to each comparison sub-project is marked as U1, U2, ..., Ug in sequence, where g = R (i + 1);

[0077] According to the formula Calculate the dispersion value F of the data set from U1 to Ug;

[0078] When F≤Fy holds true, Up is used as the predicted cost Uy of the sub-project to be built;

[0079] When F>Fy, the corresponding Uk values ​​are deleted in the order of |Uk-Up| from large to small until F≤Fy is established. The number of Uk deleted at this time is counted. If a / g is less than or equal to the preset ratio, the average value of the remaining Uk values ​​that have not been deleted is used as the predicted cost Uy of the sub-project to be built;

[0080] If a / g is greater than the preset ratio, the median between U1 and Ug is used as the predicted cost Uy of the subproject to be built;

[0081] Fy is a preset value, Up = (U1 + U2 +, ..., + Ug) / g, 1 ≤ k ≤ g;

[0082] S4. Calculate and sum the predicted costs Uy of the sub-projects to be constructed of the construction project in sequence to obtain the predicted cost of the construction project to be constructed.

[0083] The present invention decomposes the construction project and separately calculates the predicted costs of the sub-projects to be built after the decomposition. This method can reduce the restrictions on samples and increase the number of samples involved in the calculation reference, thereby effectively reducing the error of the calculation result and making the calculated predicted cost more accurate, objective and representative.

[0084] In the description of the specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0085] The above contents are merely examples and explanations of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the invention or exceed the scope defined by the claims, they shall all fall within the protection scope of the present invention.

Claims

1. The project cost auxiliary index management system is characterized by: include: A data storage module is used to store completed engineering projects, sample sub-projects obtained by decomposing completed engineering projects, auxiliary indicator sets of each sample sub-project and the cost U of each sample sub-project; Auxiliary index retrieval module, used to retrieve the content in the data storage module according to the sub-projects to be built obtained by decomposing the engineering project to be built; The data processing module is used to analyze and process the information uploaded by the auxiliary index retrieval module, so as to obtain the predicted cost of the project to be constructed; The working method of the above-mentioned engineering cost auxiliary index management system includes the following steps: S1. Obtain the corresponding sample sub-projects in the data storage module, and obtain the auxiliary indicator set of each sample sub-project and the cost U of each sample sub-project; S2. Decompose the construction project to be built, obtain several sub-projects to be built, compare one sub-project to be built with the sample sub-projects in the data storage module, and mark the auxiliary indicator in the sub-project to be built as Z; Obtain the number R of sample sub-projects corresponding to auxiliary indicators that are the same as or similar to the auxiliary indicator Z in the data storage module, and sort the v auxiliary indicators corresponding to the sub-project to be built into Z1, Z2, ..., Zv in descending order according to the corresponding R values, where v is the number of auxiliary indicators corresponding to the sub-project to be built; Obtain the sample sub-items corresponding to the auxiliary indicators that are the same as or similar to the auxiliary indicator Zi in the data storage module and the number Ri of the corresponding sample sub-items, where 1≤i≤v-1; Obtain sample sub-items corresponding to auxiliary indicators that are the same as or close to the auxiliary indicator Z(i+1) and the number R(i+1) of corresponding sample sub-items from the corresponding Ri sample sub-items; When R(i+1)>Ry always holds true, the R(i+1) sample sub-items finally obtained are used as control sub-items; When R(i+1)≤Ry and Ri>Ry is established, the corresponding Z(i+1) to Zv are marked as floating indicators, and the final Ri sample sub-items are used as control sub-items, and Ry is the preset value; S3. When there is no floating indicator, the project cost U corresponding to each comparison sub-project is obtained, and after filtering out the values ​​with large deviations, the predicted cost Uy of the sub-project to be built is calculated based on the remaining sub-project costs U; When there are floating indicators: mark the floating indicators as Zz1, Zz2, ..., Zzj, where j is the number of floating indicators, j ≥ 1; Within the scope of the control sub-item, one of the j floating indicators is first determined as the standard indicator, and the other auxiliary indicators are used as benchmark indicators. The control sub-items with the same or similar corresponding benchmark indicators are used as a sample group, thereby obtaining c sample groups, c ≥ 1; In a sample group, obtain the sub-project cost U corresponding to different standard indicators, and the corresponding cost range in the sample group according to the parameter value or category of the corresponding standard indicator in the sub-project to be built; After setting the standard indicators in sequence, obtain j cost ranges, obtain the median of the intersection of these j cost ranges, and use the median as the predicted cost Uy; S4, sequentially calculating and summing the predicted cost Uy of the sub-projects to be constructed of the construction project to be constructed, to obtain the predicted cost of the construction project to be constructed; The auxiliary indicator set is composed of a number of corresponding auxiliary indicators, including building area, floor area, building height, number of building floors, decoration level, engineering structure type and foundation type.

2. The engineering cost auxiliary index management system according to claim 1 is characterized in that: The closeness means that the difference rate between the two benchmark indicators is less than a preset threshold.

3. The engineering cost auxiliary index management system according to claim 1 is characterized in that: The method for calculating the predicted cost Uy according to the remaining sub-project cost U in step S3 is: The project cost U corresponding to each comparison sub-project is marked as U1, U2, ..., Ug in sequence, where g = R (i + 1); According to the formula Calculate the dispersion value F of the data set from U1 to Ug; When F≤Fy holds true, Up is used as the predicted cost Uy of the sub-project to be built; When F>Fy, the corresponding Uk values ​​are deleted in the order of |Uk-Up| from large to small until F≤Fy is established. The number of Uk deleted at this time is counted. If a / g is less than or equal to the preset ratio, the average value of the remaining Uk values ​​that have not been deleted is used as the predicted cost Uy of the sub-project to be built; If a / g is greater than the preset ratio, the median between U1 and Ug is used as the predicted cost Uy of the subproject to be built; Fy is a preset value, Up = (U1 + U2 +, ..., + Ug) / g, 1≤k≤g.

4. The engineering cost auxiliary index management system according to claim 1 is characterized in that: When the standard index is in the form of parameter values, obtain n coordinate points with the parameter values ​​of the standard index as the horizontal coordinate and the sub-project cost U corresponding to the parameter values ​​as the vertical coordinate, perform curve fitting on these n coordinate points to obtain a control curve, where n is the number of sub-projects in the sample group; Obtain c control curves based on each sample group; Obtain the parameter values ​​of the corresponding standard indicators in the sub-project to be built, obtain the corresponding c sub-project costs in the comparison curve, and thus obtain a cost range; When the standard indicator is in the form of categories, obtain the m sub-item costs U corresponding to a category in the standard indicator in a sample group, and use the distribution range of the m sub-item costs U as the cost range of the corresponding category in the corresponding standard indicator; m is the number of standard indicators of a category in a sample group.

5. The engineering cost auxiliary index management system according to claim 4 is characterized in that: The standard indicators in the form of numerical parameters include building area, floor area, building height, and number of building floors. The standard indicators in the form of types include decoration level, engineering structure type, and foundation type.