Synchronous construction method of external wall panel and main body structure

By constructing the exterior wall panels simultaneously with the main structure and assembling horizontal and vertical through-tubes, the problems of inconvenient transportation and hoisting in traditional construction methods were solved, the overall strength of the exterior wall was improved, and the construction period was shortened.

CN116411710BActive Publication Date: 2026-07-21CITIC CONSTR
View PDF 3 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
CITIC CONSTR
Filing Date
2023-05-09
Publication Date
2026-07-21

AI Technical Summary

Technical Problem

Traditional construction methods for exterior wall panels and main structures in high-rise buildings suffer from problems such as long construction periods, inconvenient transportation and hoisting, and insufficient overall strength of the exterior walls, making it difficult to withstand the effects of self-weight and wind loads over a long period of time.

Method used

The method of simultaneous construction of exterior wall panels and main structure is adopted. By binding column steel bars to the concrete floor slab of the base layer, the exterior wall panels are arranged in a matrix and hoisted and positioned as a whole. Combined with the assembly of horizontal and vertical through pipes, the exterior wall panels are installed layer by layer and concrete is poured to form a stable structural connection.

Benefits of technology

This solved the problem of inconvenient transportation and hoisting of exterior wall panels, improved the overall strength of the exterior wall, enhanced its ability to withstand self-weight and wind loads, and shortened the construction period.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116411710B_ABST
    Figure CN116411710B_ABST
Patent Text Reader

Abstract

The application discloses a kind of outer wall board and main structure synchronous construction method, comprising: S1, the concrete floor of construction reference layer is bound after column reinforcement of reference layer;S2, for the outer wall of non-reserved installation hole of reference layer, multiple outer wall boards are arranged in matrix and stacked between adjacent two column reinforcements, to form the outer wall between corresponding two column reinforcements;For the outer wall of reserved installation hole of reference layer, outer wall board is integrally formed, and installation hole is formed in matched manner, and outer wall board is integrally hoisted and positioned, to form the outer wall between corresponding two column reinforcements;S3, template support is carried out to the main structure of reference layer, outer wall, and concrete is poured, and template is removed after pouring is completed;S4, with reference layer floor as starting point, repeat steps S1-S3 to end by increasing 1 layer each time floor. The present application has the beneficial effects of synchronous construction, convenient installation, while increasing the overall connection strength.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of building construction technology. More specifically, this invention relates to a method for simultaneous construction of exterior wall panels and the main structure. Background Technology

[0002] With the booming development of high-rise buildings, construction units have increasingly higher requirements for construction period. In the construction of high-rise buildings, the traditional construction method is to carry out the construction of the main structure first, and then carry out the construction of the exterior wall panels after the main structure is completed. For some high-rise buildings with tight construction period requirements, the traditional construction method will not be able to meet the requirements of timely completion.

[0003] To shorten the construction period and improve efficiency, existing technologies provide a method for simultaneous construction of exterior wall panels and the main structure. This method defines any floor of a high-rise building as floor N, the upper X floors as floor N+X, and the lower X floors as floor NX. The exterior wall panels of each floor are constructed simultaneously with the main structure. For example, Chinese patent publication number CN115162556A, published on 2022-10-11, entitled "A Method for Prefabricated Exterior Wall Panels Constructed Simultaneously with the Main Structure," discloses a method including prefabricated wall processing and the assembly and installation between the prefabricated walls and the main structure. This method for constructing high-rise prefabricated building structures shortens the overall construction period, but it suffers from the inconvenience of transporting, hoisting, and installing single-sided exterior wall panels as a whole.

[0004] Therefore, there is an urgent need to design a construction method that allows for simultaneous construction and installation of the exterior wall and main structure, while also increasing the overall strength of the exterior wall. This would shorten the construction period, improve convenience, and enable the exterior wall to withstand its own weight and wind loads over a long period, thereby reducing the probability of damage. Summary of the Invention

[0005] One object of the present invention is to solve at least the above-mentioned problems and to provide at least the advantages that will be described later.

[0006] Another objective of this invention is to provide a method for simultaneous construction of exterior wall panels and the main structure, which effectively increases the overall strength of the exterior wall while ensuring simultaneous and convenient installation.

[0007] To achieve these objectives and other advantages according to the present invention, a method for simultaneous construction of exterior wall panels and main structure is provided, comprising the following steps:

[0008] S1. After constructing the concrete floor slab of the benchmark layer, tie the column reinforcement of the benchmark layer;

[0009] S2. For the exterior wall of the base layer without reserved installation holes, multiple exterior wall panels are arranged in a matrix and stacked between the steel bars of two adjacent columns to form the exterior wall between the steel bars of the corresponding two columns.

[0010] For the exterior wall with the reserved installation hole on the base layer, the exterior wall panel is integrally formed and the installation hole is formed accordingly. The exterior wall panel is hoisted and positioned as a whole to form the exterior wall between the corresponding two column steel bars.

[0011] S3. Provide formwork support for the main structure and exterior walls of the base layer, pour concrete, and remove the formwork after pouring.

[0012] S4. Starting from the base floor, add one floor at a time and repeat steps S1-S3 until the end.

[0013] Preferably, the top surface of the concrete floor slab has strip-shaped grooves corresponding to each exterior wall of that floor. For the exterior walls of the base floor that do not have pre-reserved installation holes, they are set to consist of M horizontal rows of exterior wall panels. The installation of the exterior walls specifically includes the following steps:

[0014] Step 1: Install Layer 1, including:

[0015] Install a horizontal through-tube that matches the strip groove of the concrete floor slab, with its top surface protruding from the strip groove;

[0016] The bottom vertical through-pipe and the middle outer wall panel are installed alternately from left to right, followed by the left outer wall panel and the right outer wall panel. The bottom end of the bottom vertical through-pipe is inserted and connected to the horizontal through-pipe. The top and bottom surfaces of the middle outer wall panel, the left outer wall panel, and the right outer wall panel all have a first assembly groove that matches the horizontal through-pipe. The right side of the left outer wall panel, the left side of the right outer wall panel, and the left and right sides of the middle outer wall panel all have a first receiving groove that matches the bottom vertical through-pipe. The top end of the bottom vertical through-pipe protrudes from the middle outer wall panel.

[0017] A left-side pipe is inserted between the reinforcing cage and the left outer wall panel, and a right-side pipe is inserted between the reinforcing cage and the right outer wall panel. The top of both the left-side and right-side pipes is recessed and has a top groove that matches and connects with the first assembly groove on the top of the outer wall panel; the bottom of both the left-side and right-side pipes is recessed and has a first bottom groove that matches and connects with the first assembly groove on the bottom of the outer wall panel; the bottom of the left-side and right-side pipes is inserted and connected to the transverse through-pipe.

[0018] Step 2: Install the intermediate layers from bottom to top, including any intermediate layer:

[0019] A transverse pipe is installed on the groove formed by the matching of the first assembly groove and the top groove on the top surface of the next layer below the intermediate layer;

[0020] The central vertical through-pipe and the central exterior wall panel are installed alternately from left to right, followed by the left and right exterior wall panels.

[0021] When the middle layer is the second layer, the bottom end of the middle vertical through pipe is connected to the through end of the bottom vertical through pipe.

[0022] When the middle layer is the third layer or above, the bottom end of the middle vertical through pipe is connected to the top end of the middle vertical through pipe of the lower layer.

[0023] Install the left and right pipes, and connect the bottoms of the left and right pipes to the lower left and right pipes respectively.

[0024] Step 3: Install the top layer, including:

[0025] Install a horizontal through pipe on the first assembly slot and the top slot matching the top slot on the top surface of the next layer below the top layer;

[0026] Install the top vertical through-pipe and the top middle outer wall panel alternately from left to right, then install the top left outer wall panel and the top right outer wall panel. The bottom end of the top vertical through-pipe is connected to the horizontal through-pipe below. The bottom surface of the top middle outer wall panel, the top left outer wall panel, and the top right outer wall panel all have a second assembly groove that matches the horizontal through-pipe. The right side of the top left outer wall panel, the left side of the top right outer wall panel, and the left and right sides of the top middle outer wall panel all have a second receiving groove that matches the top vertical through-pipe.

[0027] A top left pipe is inserted between the reinforcing cage and the top left outer wall panel, and a top right pipe is inserted between the reinforcing cage and the top right outer wall panel. The bottom of both the top left and top right pipes is recessed and has a second bottom groove that matches and connects with the corresponding second assembly groove. The bottom of the top left and top right pipes are respectively inserted and connected to the lower left and right pipes.

[0028] Preferably, the transverse through-tube is provided with a plurality of mounting holes spaced apart along its length, the mounting holes penetrating the top and bottom surfaces of the transverse through-tube, wherein:

[0029] The bottom vertical through-tube includes a first middle vertical tube and first end tubes located at both ends of the first middle vertical tube and connected to the first middle vertical tube. The first end tubes of the bottom vertical through-tube at the bottom are matched and installed one by one with the mounting holes of the lower horizontal through-tube at the middle. The first bottom grooves of the left and right tubes both protrude downwards and are connected to the first insertion tubes. A pair of first insertion tubes are matched one by one with the mounting holes of the lower horizontal through-tube at both sides.

[0030] The first end of the bottom vertical through-tube is matched and installed one by one with the mounting hole in the middle of the top horizontal through-tube;

[0031] The first end tube has a second through hole on all four sides and the side opposite to the first middle vertical tube. The middle vertical through tube includes a second middle vertical tube, a second end tube located at the top of the second middle vertical tube and connected to the second middle vertical tube, and a second insert tube located at the bottom of the second middle vertical tube and connected to the second middle vertical tube. The second end tube has a fifth through hole on all four sides and the side opposite to the second middle vertical tube. The second insert tube is matched and installed one by one with the second through hole at the top of the first end tube at the bottom of the lower layer or the fifth through hole at the top of the second end tube. The second end tube is matched and installed one by one with the mounting hole of the upper horizontal through tube.

[0032] The top vertical through-tube includes a third middle vertical tube and a third insert tube located at the bottom of the third middle vertical tube and connected to the third middle vertical tube. The third insert tube is matched and installed one by one with the fifth through hole at the top of the second end tube below.

[0033] Preferably, each side wall of the transverse tube has a first through hole communicating with the inner cavity of the transverse tube;

[0034] Each side wall of the first central vertical tube has a third through hole that communicates with the inner cavity of the first central vertical tube;

[0035] Each side wall of the second central vertical tube has a fourth through hole that communicates with the inner cavity of the second central vertical tube;

[0036] The top surface and each side wall of the third central vertical tube are each perforated with a sixth perforation that communicates with the inner cavity of the third central vertical tube.

[0037] Preferably, the first receiving groove on the left side of the right outer wall panel and the first receiving groove on the left side of the middle outer wall panel are both provided with multiple first reinforcing ribs at intervals along the vertical direction, and the first receiving groove on the right side of the left outer wall panel and the first receiving groove on the right side of the middle outer wall panel are both provided with multiple first through grooves at intervals along the vertical direction. The first reinforcing ribs pass through the bottom vertical through pipe located on their left side and are inserted into the first through groove located on their left side one by one.

[0038] Multiple second reinforcing ribs are provided on the second receiving groove on the left side of the top right outer wall panel and on the left side of the top outer wall panel. Multiple third through grooves are provided at intervals along the vertical direction on the second receiving groove on the right side of the top left outer wall panel and on the right side of the top middle outer wall panel. The second reinforcing ribs are inserted into the third through grooves on their left side after passing through the top vertical through pipe located on their left side.

[0039] Preferably, the left side of the left outer wall panel and the right side of the right outer wall panel are provided with multiple second through slots at vertical intervals. A left fixing rib is inserted and fixed to each second through slot of each left outer wall panel, and a right fixing rib is inserted and fixed to each second through slot of each right outer wall panel.

[0040] Preferably, multiple fourth through slots are provided vertically at intervals on the left side of the top left outer wall panel and the right side of the top right outer wall panel, and top left fixing ribs are inserted and fixed to each fourth through slot of each top left outer wall panel; top right fixing ribs are inserted and fixed to each fourth through slot of each top right outer wall panel.

[0041] Preferably, the top of the left top tube, the right top tube, the middle top outer wall panel, the left top outer wall panel, and the right top outer wall panel are all provided with multiple vertical reinforcing ribs, and the vertical reinforcing ribs are arranged vertically.

[0042] Preferably, the top grooves of the left and right tubes have through-holes. For two adjacent left tubes, the first insert of the upper left tube is inserted into the positioning hole of the lower left tube. For two adjacent right tubes, the first insert of the upper right tube is inserted into the positioning hole of the lower right tube.

[0043] Each second bottom groove protrudes downwards and is connected to a fourth insertion tube. A pair of fourth insertion tubes are respectively inserted into the positioning holes of the left and right tubes below.

[0044] The present invention has at least the following beneficial effects:

[0045] By assembling the exterior wall panels and then pouring them together in a unified manner after horizontal and vertical connection, the problems of inconvenience in transportation, hoisting and installation caused by the traditional integral setting of exterior wall panels are solved. At the same time, the overall strength of the exterior wall is increased, and its ability to withstand self-weight and wind loads is enhanced.

[0046] Other advantages, objectives and features of the present invention will become apparent in part from the following description, and in part from those skilled in the art through study and practice of the invention. Attached Figure Description

[0047] Figure 1 This is a schematic diagram of the exterior wall and main structure without a pre-reserved installation hole, according to one of the technical solutions of the present invention;

[0048] Figure 2 This is a schematic diagram of the exterior wall and main structure of the reserved installation hole according to one of the technical solutions of the present invention;

[0049] Figure 3 This is an exploded structural diagram of the exterior wall without a pre-reserved installation hole, according to one of the technical solutions of the present invention;

[0050] Figure 4 This is a schematic diagram of the main structure according to one of the technical solutions of the present invention;

[0051] Figure 5 This is a schematic diagram of the structure of the transverse tube according to one of the technical solutions of the present invention;

[0052] Figure 6 This is a schematic diagram of the bottom vertical through-tube structure according to one of the technical solutions of the present invention;

[0053] Figure 7 This is a schematic diagram of the structure of the vertical through-tube described in one of the technical solutions of the present invention;

[0054] Figure 8 This is a schematic diagram of the top vertical through-tube structure according to one of the technical solutions of the present invention;

[0055] Figure 9 This is a schematic diagram of the structure of the exterior wall panel according to one of the technical solutions of the present invention;

[0056] Figure 10 This is a schematic diagram of the structure of the top-middle outer wall panel according to one of the technical solutions of the present invention;

[0057] Figure 11 This is a schematic diagram of the structure of the left tube according to one of the technical solutions of the present invention.

[0058] The attached diagrams are specifically labeled as follows: 1. Concrete floor slab; 10. Strip groove; 11. Column reinforcement; 2. Horizontal through-pipe; 20. Mounting hole; 21. First through-hole; 3. Bottom vertical through-pipe; 30. First middle vertical pipe; 30. Third through-hole; 31. First end pipe; 31. Second through-hole; 4. Middle outer wall panel; 40. First assembly groove; 41. First receiving groove; 42. First reinforcing rib; 43. First through-groove; 5. Left outer wall panel; 50. Right outer wall panel; 51. Second through-groove; 52. Left side pipe; 53. Right side pipe; 54. Top groove; 55. First bottom groove; 56. First insertion pipe; Positioning. Hole 57; Middle vertical through pipe 6; Second middle vertical pipe 60; Fourth through hole 600; Second end pipe 61; Fifth through hole 610; Second insertion pipe 62; Top vertical through pipe 7; Third middle vertical pipe 70; Sixth through hole 700; Third insertion pipe 71; Top middle outer wall panel 8; Second assembly groove 80; Second receiving groove 81; Second reinforcing rib 82; Third through groove 83; Vertical reinforcing rib 84; Top left outer wall panel 9; Top right outer wall panel 90; Fourth through groove 91; Top left side pipe 92; Top right side pipe 93; Second bottom groove 94; Fourth insertion pipe 95. Detailed Implementation

[0059] The present invention will be further described in detail below with reference to embodiments, so that those skilled in the art can implement it based on the description.

[0060] like Figures 1-11 As shown, the method for simultaneous construction of exterior wall panels and main structure includes the following steps:

[0061] I. Exterior Wall Panel Processing and Manufacturing Stage

[0062] Based on the architectural drawings, the dimensions of the exterior wall panels and supporting components are calculated, and the exterior wall panels and supporting components are prefabricated according to the calculated dimensions.

[0063] II. On-site installation and construction phase

[0064] 2.1 Construction of N floors (N≥1)

[0065] 2.1.1 Set the lowest floor where the exterior wall panels are installed as the reference floor, defined as floor N. Construct the concrete floor slab 1 of the reference floor, wherein the top surface of the concrete floor slab 1 of the reference floor has strip-shaped grooves 10 corresponding to each exterior wall of the floor.

[0066] 2.1.2 The column reinforcement 11 of the base layer is tied to form a reinforcement cage. There is a reinforcement cage at both ends of any strip groove 10, and a common reinforcement cage at the ends of two adjacent strip grooves 10 along the circumference of the concrete floor slab.

[0067] 2.1.3. Exterior wall assembly

[0068] (1) For exterior walls without pre-reserved installation holes (doors, windows, etc.), the exterior wall assembly includes the following steps:

[0069] I. Assume the exterior wall consists of M layers of exterior wall panels (M≥3), defined from bottom to top as 1, 2, ..., M;

[0070] II. Install the first layer, including the following steps:

[0071] ① Install a horizontal through-tube 2, which matches the strip groove 10 of the concrete floor slab 1. The top surface of the horizontal through-tube 2 protrudes from the strip groove 10. Each side wall of the horizontal through-tube 2 is provided with a first through hole 21 that communicates with the inner cavity of the horizontal through-tube 2. The horizontal through-tube 2 is provided with a plurality of mounting holes 20 at intervals along its length. The mounting holes 20 penetrate the top and bottom surfaces of the horizontal through-tube 2. The principle of the layout of the first through holes 21 is to increase the contact area between each side wall of the horizontal through-tube 2 and each contact surface through the first through holes 21 while ensuring the strength of the horizontal through-tube 2. Preferably, the height of the horizontal through-tube 2 (the height in the vertical direction after matching the strip groove 10) is twice the depth of the strip groove 10.

[0072] ② Install the bottom vertical through-pipe 3 and the middle outer wall panel 4 alternately from left to right, with the bottom vertical through-pipe 3 installed to the right of the rightmost middle outer wall panel 4. That is, if the number of middle outer wall panels 4 in the first layer is K, then the number of bottom vertical through-pipes 3 is K+1. The bottom vertical through-pipes 3 and the middle outer wall panel 4 are installed alternately, wherein:

[0073] The bottom vertical through-tube 3 includes a first middle vertical tube 30 and first end tubes 31 located at both ends of the first middle vertical tube 30 and communicating with the first middle vertical tube 30. The projection of the first middle vertical tube 30 on the horizontal plane falls within the projection range of the first end tubes 31 on the horizontal plane. All the first end tubes 31 of the bottom vertical through-tubes 3 of the first layer are matched and installed one by one with the mounting holes 20 in the middle of the horizontal through-tube 2 (excluding the mounting holes 20 at both ends), and the top surface of the first end tube 31 protrudes out of the corresponding mounting hole 20. Preferably, the protrusion height is 1 / 2 of the height of the first end tube 31; wherein, the four sides of the first end tube 31 and the side opposite to the first middle vertical tube 30 are all provided with second through holes 310, and each side wall of the first middle vertical tube 30 is provided with a third through hole 300 communicating with the inner cavity of the first middle vertical tube 30. The principle of the layout of the third through holes 300 is to ensure the strength of the first middle vertical tube 30 while increasing the contact area between each side wall of the first middle vertical tube 30 and each contact surface through the third through hole 300;

[0074] ③ Install the left exterior wall panel 5 and the right exterior wall panel 50, wherein:

[0075] The top and bottom surfaces of the middle outer wall panel 4, the left outer wall panel 5, and the right outer wall panel 50 are all equipped with first assembly grooves 40 that match the transverse through-pipe 2, so that the middle outer wall panel 4, the left outer wall panel 5, and the right outer wall panel 50 can accommodate the part of the transverse through-pipe 2 protruding from the strip-shaped groove 10 through the first assembly groove 40 at the bottom, thereby making the bottom surfaces of the middle outer wall panel 4, the left outer wall panel 5, and the right outer wall panel 50 contact the top surface of the concrete floor slab 1 located below the corresponding panel.

[0076] The right side of the left outer wall panel 5, the left side of the right outer wall panel 50, and the left and right sides of the middle outer wall panel 4 all have a first receiving groove 41 that matches the bottom vertical through pipe 3, so that adjacent left outer wall panels 5 and middle outer wall panels 4, two adjacent middle outer wall panels 4, and adjacent middle outer wall panels 4 and right outer wall panels 50 are connected to each other to form a space for fitting the corresponding bottom vertical through pipe 3. The first end pipe 31 of the bottom vertical through pipe 3 protrudes out of this space. Preferably, the protrusion height is 1 / 2 of the height of the first end pipe 31.

[0077] Multiple first reinforcing ribs 42 are arranged vertically at intervals in the first receiving groove 41 on the left side of the right outer wall panel 50 and the first receiving groove 41 on the left side of the middle outer wall panel 4. The first reinforcing ribs 42 are arranged horizontally.

[0078] The first receiving groove 41 on the right side of the left outer wall panel 5 and the first receiving groove 41 on the right side of the middle outer wall panel 4 are both provided with multiple first through grooves 43 at intervals along the vertical direction. The first reinforcing rib 42 passes through the bottom vertical through pipe 3 located on its left side and is inserted into the first through groove 43 located on its left side one by one.

[0079] The left side of the left outer wall panel 5 and the right side of the right outer wall panel 50 are both provided with multiple second through slots 51 at vertical intervals.

[0080] ④ Install the left side pipe 52 and the right side pipe 53. Both the left side pipe 52 and the right side pipe 53 are rectangular tubes. The left side pipe 52 is inserted between the corresponding reinforcing cage and the left outer wall panel 5, and the right side pipe 53 is inserted between the corresponding reinforcing cage and the right outer wall panel 50. The placement of the left side pipe 52 and the right side pipe 53 provides sufficient space for the insertion and installation of the left outer wall panel 5 and the right outer wall panel 50. Wherein:

[0081] The top of both the left tube 52 and the right tube 53 is recessed and has a top groove 54 that matches and connects with the first assembly groove 40 on the top of the outer wall panel of the first layer. The top groove 54 on the top of the left tube 52 and the right tube 53 has a positioning hole 57 through it.

[0082] The bottom of both the left tube 52 and the right tube 53 is recessed and has a first bottom groove 55 that matches and engages with the first assembly groove 40 at the bottom of the first layer of the outer wall panel, so that the first assembly groove 40 and the first bottom groove 55 can accommodate the protruding part of the transverse tube 2 of the first layer relative to the strip groove 10.

[0083] Each first bottom groove 55 protrudes downward and is connected to a first insertion tube 56. A pair of first insertion tubes 56 are respectively matched with the mounting holes 20 on both sides of the transverse through tube 2, so as to be inserted into the corresponding mounting holes 20 one by one. At this time, the left and right sides of the left tube 52 are in contact with the steel cage and the left outer wall panel 5 on both sides, respectively, and the bottom is in contact with the top surface of the concrete floor slab 1 below it. The left and right sides of the right tube 53 are in contact with the steel cage and the right outer wall panel 50 on both sides, respectively, and the bottom is in contact with the top surface of the concrete floor slab 1 below it.

[0084] ⑤ The fixing of the left tube 52 and the right tube 53 is as follows:

[0085] The first receiving groove 41 on the left side of the left outer wall panel 5 and the first receiving groove 41 on the right side of the right outer wall panel 50 are both provided with multiple second through grooves 51 at intervals in the vertical direction.

[0086] Left fixing bars are inserted to match each second through slot 51 of each left outer wall panel 5. Each left fixing bar passes through the corresponding steel cage and left side pipe 52 in sequence and is inserted into the corresponding second through slot 51, and is fixed with the corresponding steel cage.

[0087] Right fixing bars are inserted into each second through slot 51 of each right outer wall panel 50. Each right fixing bar passes through the corresponding steel cage and right pipe 53 in sequence and is inserted into the corresponding second through slot 51, and is fixed with the corresponding steel cage.

[0088] III. Install intermediate layers (layer i, M > i ≥ 2) layer by layer. For any intermediate layer (layer i), the following steps are included:

[0089] ① The first assembly groove 40 and the top groove 54 at the top of the i-1th layer are connected to form a strip-shaped groove, and a transverse through pipe 2 is installed in the strip-shaped groove.

[0090] ② From left to right, the central vertical through-pipe 6 and the central outer wall panel 4 are installed alternately, with the central vertical through-pipe 6 installed to the right of the rightmost central outer wall panel 4. That is, if the number of central outer wall panels 4 in the i-th layer is K, then the number of central vertical through-pipes 6 is K+1. The central vertical through-pipes 6 and the central outer wall panels 4 are installed alternately, wherein:

[0091] The central vertical through-tube 6 includes a second central vertical tube 60, a second end tube located at the top of the second central vertical tube 60 and communicating with the second central vertical tube 60, and a second insertion tube located at the bottom of the second central vertical tube 60 and communicating with the second central vertical tube 60, wherein:

[0092] The projection of the second middle vertical tube 60 on the horizontal plane falls within the projection range of the second end tube on the horizontal plane. Each side wall of the second middle vertical tube 60 is respectively penetrated by a fourth perforation that communicates with the inner cavity of the second middle vertical tube 60. The principle of the fourth perforation layout is to ensure the strength of the second middle vertical tube 60 while increasing the contact area between each side wall of the second middle vertical tube 60 and each contact surface through the third perforation 300.

[0093] The second end tube has a fifth through hole on all four sides and on the side opposite to the second middle vertical tube 60.

[0094] When i = 2, and the horizontal through-tube 2 of the i-th layer is installed, all the first end tubes 31 of the i-1th layer located at the top are matched and installed one by one with the mounting holes 20 of the horizontal through-tube 2 (excluding the mounting holes 20 at both ends), and all the second insert tubes of the i-th layer are matched and installed one by one with the second through holes 310 at the top of the first end tube 31 of the i-1th layer located at the top.

[0095] When M>i≥3, and the transverse through-tube 2 of the i-th layer is installed, all the second end tubes of the i-1th layer located at the top (see the description below) are matched and installed one by one with the mounting holes 20 of the transverse through-tube 2 (excluding the mounting holes 20 at both ends), and all the second insertion tubes of the i-th layer are matched and installed one by one with the fifth through hole at the top of the second end tube of the i-1th layer located at the top.

[0096] ③ Install the left exterior wall panel 5 and the right exterior wall panel 50, using the same installation method as the first floor;

[0097] ④ Install the left tube 52 and the right tube 53 in the same way as the first layer. For two adjacent left tubes 52, the first insertion tube 56 of the upper left tube 52 is inserted into the positioning hole 57 of the lower left tube 52. For two adjacent right tubes 53, the first insertion tube 56 of the upper right tube 53 is inserted into the positioning hole 57 of the lower right tube 53.

[0098] ⑤ The fixing of the left pipe 52 and the right pipe 53 is the same as the installation method of the first layer;

[0099] IV. Install the Mth layer (top layer), including the following steps:

[0100] ① The first assembly groove 40 and the top groove 54 at the top of the M-1 layer are connected to form a strip-shaped groove, and a transverse through pipe 2 is installed in the strip-shaped groove.

[0101] ② Install the top vertical through-pipe and the top middle outer wall panel 8 alternately from left to right, with the top vertical through-pipe installed to the right of the rightmost top middle outer wall panel 8. That is, if the number of top middle outer wall panels 8 in the Mth layer is K, then the number of top vertical through-pipes is K+1. The top vertical through-pipe and the top middle outer wall panel 8 are installed alternately, wherein:

[0102] The top vertical through-tube includes a third middle vertical tube and a third insertion tube 71 located at the bottom of the third middle vertical tube and connected to the third middle vertical tube. The top surface and each side wall of the third middle vertical tube are respectively penetrated by a sixth through hole 700 that communicates with the inner cavity of the third middle vertical tube. The principle of the layout of the sixth through hole 700 is to ensure the strength of the third middle vertical tube while increasing the contact area between each side wall of the third middle vertical tube and each contact surface through the sixth through hole 700.

[0103] When the transverse tube 2 of the Mth layer is installed, all the second end tubes of the top of the M-1th layer are matched and installed one by one with the mounting holes 20 of the transverse tube 2 (excluding the mounting holes 20 at both ends), and all the third insertion tubes 71 of the Mth layer are matched and installed one by one with the fifth through hole at the top of the second end tube of the top of the M-1th layer.

[0104] ③ Install the top left exterior wall panel 9 and the top right exterior wall panel 90, wherein:

[0105] The bottom surfaces of the top center outer wall panel 8, the top left outer wall panel 9, and the top right outer wall panel 90 all have a second assembly groove 80 that matches the horizontal through pipe 2, so that the top center outer wall panel 8, the top left outer wall panel 9, and the top right outer wall panel 90 can accommodate the protruding part of the horizontal through pipe 2 through the second assembly groove 80 at the bottom, thereby making the bottom surfaces of the top center outer wall panel 8, the top left outer wall panel 9, and the top right outer wall panel 90 contact the top surface of the concrete floor slab 1 located below the corresponding panel.

[0106] The right side of the top left outer wall panel 9, the left side of the top right outer wall panel 90, and the left and right sides of the top middle outer wall panel 8 all have a second receiving groove 81 that matches the top vertical through pipe, so that adjacent top left outer wall panels 9 and top middle outer wall panels 8, two adjacent top middle outer wall panels 8, and adjacent top middle outer wall panels 8 and top right outer wall panels 90 form a space for fitting the corresponding top vertical through pipe after they are connected to each other. The top end of the top vertical through pipe is flush with the top end of the top middle outer wall panel 8, the top left outer wall panel 9, and the top right outer wall panel 90.

[0107] Multiple second reinforcing ribs 82 are provided on the second receiving groove 81 on the left side of the top right outer wall panel 90 and on the left side of the top outer wall panel, and the second reinforcing ribs 82 are horizontally arranged;

[0108] The second receiving groove 81 on the right side of the top left outer wall panel 9 and the second receiving groove 81 on the right side of the top middle outer wall panel 8 are both provided with multiple third through grooves 83 at intervals along the vertical direction. The second reinforcing rib 82 passes through the top vertical through pipe located on its left side and is inserted into the third through groove 83 located on its left side one by one.

[0109] ④ Install the top left side pipe 92 and the top right side pipe 93. Both the top left side pipe 92 and the top right side pipe 93 are rectangular tubes. The top left side pipe 92 is inserted between the corresponding reinforcing cage and the top left outer wall panel 9, and the top right side pipe 93 is inserted between the corresponding reinforcing cage and the top right outer wall panel 90. The placement of the top left side pipe 92 and the top right side pipe 93 provides sufficient space for the insertion and installation of the top left outer wall panel 9 and the top right outer wall panel 90. Wherein:

[0110] The top of the left top tube 92, the right top tube 93, the top middle outer wall panel 8, the left top outer wall panel 9, and the right top outer wall panel 90 are all provided with multiple vertical reinforcing ribs 84, and the vertical reinforcing ribs 84 are set vertically.

[0111] The bottom of both the top left tube 92 and the top right tube 93 are recessed and have a second bottom groove 94 that matches and engages with the second assembly groove 80 at the bottom of the outer wall panel of the M-1 layer, so that the second assembly groove 80 and the second bottom groove 94 can accommodate the protruding part of the transverse tube 2 of the M-1 layer relative to the strip groove 10.

[0112] Each second bottom groove 94 protrudes downward and is connected to a fourth insertion tube 95. A pair of fourth insertion tubes 95 are respectively inserted into the positioning holes 57 of the lower left tube 52 and right tube 53, so that the top left tube 92 is inserted and positioned on the lower left tube 52, and the top right tube 93 is inserted and positioned on the lower right tube 53. At this time, the left and right sides of the top left tube 92 are in contact with the steel cage and the top left outer wall panel 9 on both sides, respectively, and the bottom is in contact with the top surface of the top left tube 92 below it. The left and right sides of the top right tube 93 are in contact with the steel cage and the top right outer wall panel 90 on both sides, respectively, and the bottom is in contact with the top surface of the top right tube 93 below it.

[0113] ⑤ The fixing of the top left tube 92 and the top right tube 93 is as follows:

[0114] Multiple fourth through slots 91 are provided at intervals along the vertical direction on the left side of the top left outer wall panel 9 and the right side of the top right outer wall panel 90.

[0115] A top left fixing bar is inserted into each fourth through slot 91 of each top left outer wall panel 9. Each top left fixing bar passes through the corresponding steel cage and top left pipe 92 in sequence and is inserted into the corresponding fourth through slot 91, and is fixed with the corresponding steel cage.

[0116] Top right fixing bars are inserted into each fourth through slot 91 of each top right outer wall panel 90. Each top right fixing bar passes through the corresponding steel cage and top right pipe 93 in sequence and is inserted into the corresponding fourth through slot 91, and is fixed with the corresponding steel cage.

[0117] (2) such as Figure 2 As shown, for exterior walls with pre-drilled installation holes, the exterior wall assembly includes the following steps:

[0118] The exterior wall panels are installed as a whole in the conventional way, forming a single piece and with matching installation holes. The exterior wall panels are hoisted and positioned as a whole. The exterior wall panels can be equipped with positioning embedded steel bars to increase the connection and fixing effect when pouring the concrete slab above the exterior wall together with other exterior walls.

[0119] 2.1.4 Repeat steps 2.1.3 until the entire exterior wall panel is installed along the circumference.

[0120] 2.1.5. For the column reinforcement (which constitutes part of the main structure) and exterior wall panels of this floor, formwork support is provided, concrete is poured, and the formwork is removed after the pouring is completed. The concrete floor slab and the poured column reinforcement constitute the main structure of this floor.

[0121] 2.2 Starting from the Nth floor, each floor is increased by 1 floor, and steps 2.1.1-2.1.6 are repeated until the end. The top floor is capped, and the main structure also includes a concrete floor slab at the top of the top floor.

[0122] Although embodiments of the present invention have been disclosed above, they are not limited to the applications listed in the specification and embodiments. They can be applied to various fields suitable for the present invention. For those skilled in the art, other modifications can be easily made. Therefore, without departing from the general concept defined by the claims and their equivalents, the present invention is not limited to the specific details and illustrations shown and described herein.

Claims

1. A method for simultaneous construction of exterior wall panels and main structure, characterized in that, Includes the following steps: S1. After constructing the concrete floor slab of the benchmark layer, tie the column reinforcement of the benchmark layer; S2. For the exterior wall of the base layer without reserved installation holes, multiple exterior wall panels are arranged in a matrix and stacked between the steel bars of two adjacent columns to form the exterior wall between the steel bars of the corresponding two columns. For the exterior wall with the reserved installation hole on the base layer, the exterior wall panel is integrally formed and the installation hole is formed accordingly. The exterior wall panel is hoisted and positioned as a whole to form the exterior wall between the corresponding two column steel bars. S3. Provide formwork support for the main structure and exterior walls of the base layer, pour concrete, and remove the formwork after pouring. S4. Starting from the base floor, add 1 floor for each subsequent floor and repeat steps S1-S3 until the end. The concrete floor slab has strip-shaped grooves on its top surface corresponding to each exterior wall of that floor. For the exterior walls of the base floor that do not have pre-reserved installation holes, they are designed to be composed of M horizontal rows of exterior wall panels. The installation of the exterior walls specifically includes the following steps: Step 1: Install Layer 1, including: Install a horizontal through-tube that matches the strip groove of the concrete floor slab, with its top surface protruding from the strip groove; The bottom vertical through-pipe and the middle outer wall panel are installed alternately from left to right, followed by the left outer wall panel and the right outer wall panel. The bottom end of the bottom vertical through-pipe is inserted and connected to the horizontal through-pipe. The top and bottom surfaces of the middle outer wall panel, the left outer wall panel, and the right outer wall panel all have a first assembly groove that matches the horizontal through-pipe. The right side of the left outer wall panel, the left side of the right outer wall panel, and the left and right sides of the middle outer wall panel all have a first receiving groove that matches the bottom vertical through-pipe. The top end of the bottom vertical through-pipe protrudes from the middle outer wall panel. A left-side pipe is inserted between the reinforcing cage and the left outer wall panel, and a right-side pipe is inserted between the reinforcing cage and the right outer wall panel. The top of both the left-side and right-side pipes is recessed and has a top groove that matches and connects with the first assembly groove on the top of the outer wall panel; the bottom of both the left-side and right-side pipes is recessed and has a first bottom groove that matches and connects with the first assembly groove on the bottom of the outer wall panel; the bottom of the left-side and right-side pipes is inserted and connected to the transverse through-pipe. Step 2: Install the intermediate layers from bottom to top, including any intermediate layer: A transverse pipe is installed on the groove formed by the matching of the first assembly groove and the top groove on the top surface of the next layer below the intermediate layer; The central vertical through-pipe and the central exterior wall panel are installed alternately from left to right, followed by the left and right exterior wall panels. When the middle layer is the second layer, the bottom end of the middle vertical through pipe is connected to the through end of the bottom vertical through pipe. When the middle layer is the third layer or above, the bottom end of the middle vertical through pipe is connected to the top end of the middle vertical through pipe of the lower layer. Install the left and right pipes, and connect the bottoms of the left and right pipes to the lower left and right pipes respectively. Step 3: Install the top layer, including: Install a horizontal through pipe on the first assembly slot and the top slot matching the top slot on the top surface of the next layer below the top layer; Install the top vertical through-pipe and the top middle outer wall panel alternately from left to right, then install the top left outer wall panel and the top right outer wall panel. The bottom end of the top vertical through-pipe is connected to the horizontal through-pipe below. The bottom surface of the top middle outer wall panel, the top left outer wall panel, and the top right outer wall panel all have a second assembly groove that matches the horizontal through-pipe. The right side of the top left outer wall panel, the left side of the top right outer wall panel, and the left and right sides of the top middle outer wall panel all have a second receiving groove that matches the top vertical through-pipe. A top left pipe is inserted between the reinforcing cage and the top left outer wall panel, and a top right pipe is inserted between the reinforcing cage and the top right outer wall panel. The bottom of both the top left and top right pipes is recessed and has a second bottom groove that matches and connects with the corresponding second assembly groove. The bottom of the top left and top right pipes are respectively inserted and connected to the lower left and right pipes.

2. The method for simultaneous construction of exterior wall panels and main structure as described in claim 1, characterized in that, The transverse tube is provided with a plurality of mounting holes spaced apart along its length, the mounting holes penetrating the top and bottom surfaces of the transverse tube, wherein: The bottom vertical through-tube includes a first middle vertical tube and first end tubes located at both ends of the first middle vertical tube and connected to the first middle vertical tube. The first end tubes of the bottom vertical through-tube at the bottom are matched and installed one by one with the mounting holes of the lower horizontal through-tube at the middle. The first bottom grooves of the left and right tubes both protrude downwards and are connected to the first insertion tubes. A pair of first insertion tubes are matched one by one with the mounting holes of the lower horizontal through-tube at both sides. The first end of the bottom vertical through-tube is matched and installed one by one with the mounting hole in the middle of the top horizontal through-tube; The first end tube has a second through hole on all four sides and the side opposite to the first middle vertical tube. The middle vertical through tube includes a second middle vertical tube, a second end tube located at the top of the second middle vertical tube and connected to the second middle vertical tube, and a second insert tube located at the bottom of the second middle vertical tube and connected to the second middle vertical tube. The second end tube has a fifth through hole on all four sides and the side opposite to the second middle vertical tube. The second insert tube is matched and installed one by one with the second through hole at the top of the first end tube at the bottom of the lower layer or the fifth through hole at the top of the second end tube. The second end tube is matched and installed one by one with the mounting hole of the upper horizontal through tube. The top vertical through-tube includes a third middle vertical tube and a third insert tube located at the bottom of the third middle vertical tube and connected to the third middle vertical tube. The third insert tube is matched and installed one by one with the fifth through hole at the top of the second end tube below.

3. The method for simultaneous construction of exterior wall panels and main structure as described in claim 2, characterized in that, Each side wall of the transverse tube is respectively perforated with a first through hole that communicates with the inner cavity of the transverse tube. Each side wall of the first central vertical tube has a third through hole that communicates with the inner cavity of the first central vertical tube; Each side wall of the second central vertical tube has a fourth through hole that communicates with the inner cavity of the second central vertical tube; The top surface and each side wall of the third central vertical tube are each perforated with a sixth perforation that communicates with the inner cavity of the third central vertical tube.

4. The method for simultaneous construction of exterior wall panels and main structure as described in claim 3, characterized in that, The first receiving groove on the left side of the right outer wall panel and the first receiving groove on the left side of the middle outer wall panel are both provided with multiple first reinforcing ribs at intervals along the vertical direction. The first receiving groove on the right side of the left outer wall panel and the first receiving groove on the right side of the middle outer wall panel are both provided with multiple first through grooves at intervals along the vertical direction. The first reinforcing ribs pass through the bottom vertical through pipe located on their left side and are inserted into the first through groove located on their left side one by one. Multiple second reinforcing ribs are provided on the second receiving groove on the left side of the top right outer wall panel and on the left side of the top outer wall panel. Multiple third through grooves are provided at intervals along the vertical direction on the second receiving groove on the right side of the top left outer wall panel and on the right side of the top middle outer wall panel. The second reinforcing ribs are inserted into the third through grooves on their left side after passing through the top vertical through pipe located on their left side.

5. The method for simultaneous construction of exterior wall panels and main structure as described in claim 4, characterized in that, The left side of the left outer wall panel and the right side of the right outer wall panel are provided with multiple second through slots at vertical intervals. A left fixing rib is inserted and fixed to each second through slot of each left outer wall panel, and a right fixing rib is inserted and fixed to each second through slot of each right outer wall panel.

6. The method for simultaneous construction of exterior wall panels and main structure as described in claim 4, characterized in that, Multiple fourth through slots are vertically spaced on the left side of the top left outer wall panel and the right side of the top right outer wall panel. Top left fixing ribs are inserted and fixed to each fourth through slot of each top left outer wall panel; top right fixing ribs are inserted and fixed to each fourth through slot of each top right outer wall panel.

7. The method for simultaneous construction of exterior wall panels and main structure as described in claim 1, characterized in that, The top left pipe, the top right pipe, the top middle outer wall panel, the top left outer wall panel, and the top right outer wall panel are all provided with multiple vertical reinforcing ribs, which are set vertically.

8. The method for simultaneous construction of exterior wall panels and main structure as described in claim 2, characterized in that, The top grooves of the left and right tubes have positioning holes. For two adjacent left tubes, the first insertion tube of the upper left tube is inserted into the positioning hole of the lower left tube. For two adjacent right tubes, the first insertion tube of the upper right tube is inserted into the positioning hole of the lower right tube. Each second bottom groove protrudes downwards and is connected to a fourth insertion tube. A pair of fourth insertion tubes are respectively inserted into the positioning holes of the left and right tubes below.