An assembled cliff steep slope conveying channel system and construction method

By using a prefabricated steep slope transport channel system, a transport operation platform is formed using standardized components, which solves the problems of high construction difficulty and environmental damage on steep slopes and achieves safe, efficient and environmentally friendly construction results.

CN117163671BActive Publication Date: 2026-02-24GUANGXI ROAD CONSTR ENG GRP CO LTD +1
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202311116037.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-08-31
Publication Date
2026-02-24
Estimated Expiration
2043-08-31

AI Technical Summary

Technical Problem

In steep cliff and slope environments, excavating access roads is difficult, costly, and poses safety hazards. It also causes severe environmental damage that is difficult to restore.

Method used

The prefabricated steep slope transport channel system, including a load-bearing system and a transport system, is adopted. It uses standardized components for installation and disassembly to form a transport operation platform, avoiding the excavation of access roads and adapting to different slope terrains. During installation, it follows the principle of "bottom first, then top" and during disassembly, it follows the principle of "top first, then bottom", achieving green and environmentally friendly construction.

Benefits of technology

It improves construction safety, reduces environmental disturbance, enables timely ecological restoration, lowers construction costs, meets green and environmental protection requirements, and allows components to be recycled multiple times.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117163671B_ABST
    Figure CN117163671B_ABST
Patent Text Reader

Abstract

The application discloses an assembled cliff and steep slope conveying channel system, which comprises a bearing system and a conveying system, and provides a conveying operation platform for construction; the bearing system comprises a foundation, a stand column, a cross beam and a longitudinal beam track; the stand column is arranged on the foundation, two longitudinal beam tracks are arranged on the top of the stand column, the cross beam is arranged on the bottom of the two longitudinal beam tracks, and a pedestrian walkway is further arranged on the cross beam; the conveying system comprises a concrete pump pipe, a conveying trolley and a grab bucket crane which can slide on the longitudinal beam track; the conveying trolley and the grab bucket crane are both installed on the longitudinal beam track, the concrete pump pipe is supported on the cross beam or the longitudinal beam track through a pump pipe supporting structure, and the concrete pump pipe is arranged along the length direction of the longitudinal beam track. The assembled cliff and steep slope conveying channel system can replace the excavated convenient path, has little disturbance to the surrounding environment during installation and construction, can timely restore the surrounding ecology, and meets the green and environment-friendly construction requirement.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the technical field of bridge construction auxiliary equipment, specifically relating to a prefabricated steep slope transport channel system and construction method. Background Technology

[0002] With technological advancements and economic development, the demand for national infrastructure construction is also increasing. Among infrastructure projects, bridges, as important structural elements connecting canyons and spanning rivers, play a vital role in transportation engineering. Bridge construction environments are complex, and it is difficult to avoid construction work on steep cliffs and slopes in mountainous areas. To facilitate the transportation of materials, it is necessary to build temporary access roads in the mountains.

[0003] However, excavating access roads on steep slopes is difficult and costly. Furthermore, vehicles traveling on these excavated access roads are prone to overturning and other accidents, leading to serious consequences and posing significant safety hazards. Additionally, excavating access roads on steep slopes can easily damage the surrounding environment, which is difficult to restore, thus impacting the local ecosystem. Summary of the Invention

[0004] The purpose of this invention is to provide a prefabricated steep slope transport channel system that can replace excavated access roads. Its installation and construction cause little disturbance to the surrounding environment, can restore the surrounding ecology in a timely manner, and meets the requirements of green and environmentally friendly construction.

[0005] To solve the above problems, the present invention adopts the following technical solution:

[0006] A prefabricated steep slope transport channel system includes a load-bearing system and a transport system, providing a transport platform for construction. The load-bearing system includes a foundation, columns, crossbeams, and longitudinal beam tracks. The columns are set on the foundation, two longitudinal beam tracks are erected on top of the columns, and the crossbeams are connected at the bottom of the two longitudinal beam tracks. A pedestrian walkway is also provided on the crossbeams. The transport system includes a concrete pump pipe, a transport trolley that can slide on the longitudinal beam tracks, and a boom crane. The transport trolley and boom crane are both installed on the longitudinal beam tracks. The concrete pump pipe is installed and supported on the crossbeams or longitudinal beam tracks through a pump pipe support structure, and the concrete pump pipe is arranged along the length of the longitudinal beam tracks.

[0007] A further preferred embodiment: a transverse connecting rod connects the two adjacent columns at the bottom of the crossbeam.

[0008] A further preferred embodiment: The foundation includes a foundation base and an anchor bolt assembly, wherein the foundation base is fixed to the ground by the anchor bolt assembly. During construction, a soil drilling rig is used to drill holes, geological conditions are analyzed, the foundation base is poured, anchor piles are then driven in, followed by the installation of columns, and the erection of crossbeams, longitudinal beam tracks, and diagonal braces to form the main load-bearing structure of the first segment.

[0009] A further preferred embodiment: the column is also connected to the adjacent crossbeam via diagonal bracing. The diagonal bracing is adjustable in length to adapt to different slopes and terrain.

[0010] A further preferred embodiment: the top of the column is hinged to the bottom of the longitudinal beam track via a hinge support.

[0011] A further preferred embodiment: the two sections of the longitudinal beam track of each longitudinal beam track are connected by a longitudinal beam track pin hinge, which includes a front hinge lug, a rear hinge lug, and a pin. The front hinge lug is located at the front end of the rear section of the longitudinal beam track, and the rear hinge lug is located at the rear end of the front section of the longitudinal beam track. The front hinge lug and the rear hinge lug are hinged by a pin.

[0012] A further preferred embodiment: the pedestrian walkway includes treads and guardrails, with guardrails installed on both sides of the treads and anti-roll-off baffles installed on the treads.

[0013] A further preferred embodiment features a cover plate on the top of the transport trolley frame, a bottom door at the bottom of the frame, anti-tipping wheels at the bottom of the frame for sliding on the longitudinal beam rails, and side doors on the sides of the frame. The transport trolley can be moved on the longitudinal beam rails by a winch rewinding mechanism, or a remote-controlled motor drive device can be installed on the frame to drive the wheels, allowing it to move on the longitudinal beam rails.

[0014] A further preferred embodiment: the pump pipe support structure includes a pump pipe support base, a pump pipe support hinge seat is provided on the pump pipe support base, a screw sleeve is hinged to the pump pipe support base, a height adjustment screw is internally threaded to the screw sleeve, a pump pipe sleeve clamp is provided at the top of the height adjustment screw, and a turnbuckle is connected between the upper end of the screw sleeve and the pump pipe support base, so that the height and angle of the pump pipe support structure can be adjusted.

[0015] A further preferred embodiment: the derrick crane includes a movable base, the bottom of which is provided with anti-overturning pulleys for sliding on the longitudinal beam track. A fixed rod and a rotating rod are provided on the movable base via supports. The top ends of the fixed rod and the rotating rod are connected to a force-sharing steel wire rope. A steel wire rope for hoisting materials is guided on the rotating rod. The end of the steel wire rope is connected to a hook. The movable base is provided with a limiting ear for fixing and limiting the movable base.

[0016] The anti-overturning wheels and anti-overturning pulleys described above can have the same structure. A roller for sliding on the top of the longitudinal beam track is installed on the wheel frame, and two sets of limiting wheels for sliding on both sides of the bottom of the longitudinal beam track are installed on the wheel frame. The two sets of limiting wheels are arranged in front and behind below the roller to form a triangular limiting sliding structure.

[0017] The installation and construction process of the prefabricated cliff and steep slope transport channel system is as follows:

[0018] The first step is to construct the main load-bearing structure. Holes are drilled using a soil drilling rig, geological conditions are analyzed, the foundation base is poured, anchor piles are then driven in, columns are installed, and horizontal beams, longitudinal beams, and diagonal braces are erected to form the first segment of the main load-bearing structure.

[0019] The second step is to install the boom crane and transport trolley on the longitudinal beam track.

[0020] The third step is the installation of other structures. Materials are transported and unloaded using a derrick crane and transport trolleys, and the pedestrian walkways, guardrails, and concrete pump pipes are installed, completing the installation of the first structural segment.

[0021] The fourth step involves using a transportation and loading / unloading system to transport construction materials such as steel and concrete to the end of the installed segments. This process is repeated from the first to the third step until the entire system is installed.

[0022] The dismantling and construction process is as follows:

[0023] The first step is the dismantling of the remaining structures in the final segment. Using a derrick crane and transport trolleys, the final segment of the pedestrian walkway, guardrails, concrete pump pipes, and other structures are dismantled and transported to the starting point.

[0024] The second step is to move the transport trolley to the penultimate section and fix the boom crane to the end of the penultimate section's load-bearing structure.

[0025] The third step is the dismantling of the main load-bearing structure of the final segment. The main load-bearing structure of the final segment is dismantled from top to bottom. The dismantled longitudinal beams, transverse beams, and column segments are transported to the foot of the mountain using transport trolleys. They are transported as they are dismantled and then neatly stacked and stored in a warehouse at the foot of the mountain for reuse.

[0026] Fourth, after the last section of the load-bearing structure is dismantled, move the cantilever crane to the front end of the previous section of the load-bearing structure and repeat steps one through three until the entire system is dismantled.

[0027] The system's components are all designed to standard dimensions, enabling prefabricated construction. Installation follows the principle of "bottom to top," while disassembly follows the principle of "top to bottom." The load-bearing system must meet overall and local requirements for strength, stiffness, deformation, and stability. Each component of the load-bearing system must be designed to standard dimensions, using socket or bolt connections for easy installation, disassembly, and reuse.

[0028] This prefabricated cliff and steep slope transport channel system can replace excavated access roads, eliminating the need for transport vehicles to navigate steep slopes and preventing vehicle rollover accidents, thus improving safety. Furthermore, its installation and construction cause minimal disturbance to the surrounding environment, enabling timely ecological restoration and meeting green construction requirements. It can also be self-loading and unloading using a crane. All components are designed with standard dimensions, achieving prefabricated construction and allowing for the repeated reuse of materials, saving costs. Attached Figure Description

[0029] Figure 1 This is a schematic diagram of the overall structure of the prefabricated cliff and steep slope transport channel system;

[0030] Figure 2 A schematic diagram of the basic structure;

[0031] Figure 3 A schematic diagram of the connection and installation structure of the longitudinal beam track;

[0032] Figure 4 This is a structural diagram of the transport trolley;

[0033] Figure 5 This is a schematic diagram of the pump pipe support structure;

[0034] Figure 6 This is a structural schematic diagram of a boom crane;

[0035] The names corresponding to the serial numbers in the figure are:

[0036] 1. Foundation; 11. Foundation base; 12. Anchor bolt assembly; 2. Column; 21. Diagonal brace; 22. Lateral connecting rod; 3. Crossbeam; 31. Shaft support; 4. Longitudinal beam track; 41. Longitudinal beam track pin hinge; 411. Front hinge lug; 412. Rear hinge lug; 413. Pin; 5. Pedestrian walkway; 51. Step; 52. Baffle; 6. Guardrail; 7. Transport trolley; 71. Cover plate; 72. Bottom door; 73. Side... 74. Door, anti-overturning wheel, 8. Concrete pump pipe, 81. Pump pipe support structure, 811. Pump pipe sleeve, 812. Pump pipe support base, 813. Pump pipe support hinge, 814. Turnbuckle, 815. Height adjustment screw, 816. Screw sleeve, 9. Drill crane, 91. Anti-overturning pulley, 92. Movable base, 93. Limiting ear, 94. Support, 95. Fixed rod, 96. Rotating rod, 97. Hook. Detailed Implementation

[0037] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0038] Example 1

[0039] A prefabricated steep slope transport channel system includes a load-bearing system and a transport system, providing a transport platform for construction. The load-bearing system includes a foundation 1, columns 2, crossbeams 3, and longitudinal beam tracks 4. The columns 2 are mounted on the foundation 1, and the two longitudinal beam tracks 4 are erected on top of the columns 2. The crossbeams 3 are connected to the bottom of the two longitudinal beam tracks 4, and a pedestrian walkway 5 is also provided on the crossbeams 3. The transport system includes a concrete pump pipe 8, a transport trolley 7 that can slide on the longitudinal beam tracks 4, and a boom crane 9. Both the transport trolley 7 and the boom crane 9 are installed on the longitudinal beam tracks 4. The concrete pump pipe 8 is installed and supported on the crossbeams 3 or the longitudinal beam tracks 4 via a pump pipe support structure 81, and the concrete pump pipe 8 is arranged along the length of the longitudinal beam tracks 4. A transverse connecting rod 22 connects the two adjacent columns 2 at the bottom of the crossbeams 3.

[0040] The foundation 1 includes a foundation base 11 and an anchor bolt assembly 12, with the foundation base 11 fixed to the ground via the anchor bolt assembly 12. The column 2 is also connected to the adjacent crossbeam 3 via diagonal bracing 21. The diagonal bracing is adjustable in length to adapt to different slopes. The columns are standardized components, with a single standard column being 2m high. Multiple standard components are connected as needed to form a column; the standard components of the columns are connected by a socket-type pin joint.

[0041] The top of the column 2 is hinged to the bottom of the longitudinal beam track 4 via a hinge support 31.

[0042] The two sections of each longitudinal beam track 4 are connected by a longitudinal beam track pin hinge 41. The longitudinal beam track pin hinge 41 includes a front hinge lug 411, a rear hinge lug 412, and a pin 413. The front hinge lug 411 is located at the front end of the rear longitudinal beam track section, and the rear hinge lug 412 is located at the rear end of the front longitudinal beam track section. The front hinge lug 411 and the rear hinge lug 412 are hinged together by the pin 413. That is, the system is installed in stages, and the length of each section is 4m.

[0043] The pedestrian walkway 5 includes a step 51 and a guardrail 6. The guardrail 6 is installed on both sides of the step 51, and the step 51 is provided with a baffle 52 to prevent it from rolling off.

[0044] The transport trolley 7 has a cover plate 71 on the top of its frame, a bottom door 72 at the bottom of its frame, anti-overturning wheels 74 at the bottom of its frame for sliding on the longitudinal beam track 4, and a side door 73 on the side of its frame.

[0045] The pump pipe support structure 81 includes a pump pipe support base 812, a pump pipe support hinge 813 is provided on the pump pipe support base 812, a screw sleeve 816 is hinged on the pump pipe support base 812, a height adjustment screw 815 is internally threaded to the screw sleeve 816, a pump pipe clamp 811 is provided on the top of the height adjustment screw 815, and a turnbuckle 814 is connected between the upper end of the screw sleeve 816 and the pump pipe support base 812.

[0046] The aforementioned boom crane 9 includes a movable base 92. The bottom of the movable base 92 is provided with an anti-overturning pulley 91 for sliding on the longitudinal beam track 4. A fixed rod 95 and a rotating rod 96 are provided on the movable base 92 via a support 94. The top ends of the fixed rod 95 and the rotating rod 96 are connected to a force-sharing steel wire rope. A steel wire rope for hoisting materials is guided on the rotating rod 96. A hook 97 is connected to the end of the steel wire rope. The movable base 92 is provided with a limiting ear 93 for fixing and limiting the movable base 92.

[0047] During construction, a soil drilling rig was used to drill holes, analyze geological conditions, and pour the foundation base. Anchor bolt assemblies were then installed, followed by the installation of columns, transverse connecting rods, and the erection of crossbeams, longitudinal beams, and diagonal braces, forming the first segment's main load-bearing structure. A derrick crane and transport trolleys were then installed on the longitudinal beams. The derrick crane and transport trolleys were used to transport and unload materials for the installation of the pedestrian walkway, guardrails, and concrete pump pipes, completing the first segment's structural installation. Using the transport and loading system, steel, concrete, and other construction materials were transported to the end of the walkway, and steps one through three were repeated until the entire system was installed. During dismantling, the derrick crane and transport trolleys were used to dismantle the final segment's pedestrian walkway, guardrails, concrete pump pipes, and other structures, and transport them back to the starting point. The transport trolleys were moved to the penultimate segment, and the derrick crane was fixed to the end of the penultimate segment's load-bearing structure. The final segment's main load-bearing structure was then dismantled. The final section of the main load-bearing structure is dismantled from top to bottom. Transport trolleys are used to transport the dismantled longitudinal beams, diagonal braces, cross beams, transverse connecting rods, and columns to the foot of the mountain. The components are transported as they are dismantled and neatly stacked in a warehouse at the foot of the mountain for reuse. After the final section of the load-bearing structure is dismantled, the derrick crane is moved and secured to the end of the previous section. This process is repeated until the entire system is dismantled.

[0048] The specific installation and construction process is as follows: First, construct the main load-bearing structure. Drill holes using a soil drilling rig, analyze geological conditions, pour the foundation base 11, then drive in anchor piles of anchor bolt assembly 12, then install columns 2 and transverse connections 22, and erect crossbeams 3, longitudinal beams 4 and diagonal braces 21 to form the first segment of the main load-bearing structure.

[0049] The second step is to install the boom crane 9 and the transport trolley 7 on the longitudinal beam 4.

[0050] The third step is the installation of other structures. Using a derrick crane 9 and a transport trolley 7, materials are transported and unloaded to install the pedestrian walkway 5, guardrails 6, and concrete pump pipes 8, completing the installation of the first segment of the structure.

[0051] The fourth step involves using a transportation and loading / unloading system to transport construction materials such as steel and concrete to the end of the installed segments. This process is repeated from the first to the third step until the entire system is installed.

[0052] The specific dismantling process is as follows: First, dismantle the remaining structures of the final segment. Use the derrick crane 9 and transport trolley 7 to dismantle and transport the pedestrian walkway 5, guardrail 6, concrete pump pipe 8, and other structures of the final segment to the starting point.

[0053] The second step is to move the transport trolley 7 to the penultimate section and fix the boom crane 9 to the end of the penultimate section's load-bearing structure.

[0054] The third step is the dismantling of the main load-bearing structure of the last segment. The main load-bearing structure of the last segment is dismantled from top to bottom. The dismantled longitudinal beams 4, diagonal braces 21, cross beams 3, transverse connections 22, and column 2 segments are transported to the foot of the mountain using transport trolleys 7. The dismantled segments are transported as they are dismantled and then neatly stacked and stored in the warehouse at the foot of the mountain for reuse.

[0055] Fourth, after the last segment of the load-bearing structure is dismantled, move and fix the cantilever crane 8 to the end of the previous segment of the load-bearing structure, and repeat steps one through three until the entire system is dismantled; after the entire system is dismantled, clean up the site in time and restore the greenery.

[0056] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A prefabricated cliff and steep slope transport channel system, comprising a load-bearing system and a transport system, characterized in that: The load-bearing system includes a foundation (1), columns (2), crossbeams (3), and longitudinal beam tracks (4). The columns (2) are set on the foundation (1), and the two longitudinal beam tracks (4) are erected on the top of the columns (2). The crossbeams (3) are connected and set at the bottom of the two longitudinal beam tracks (4). A pedestrian walkway (5) is also provided on the crossbeams (3). The transportation system includes a concrete pump pipe (8), a transport trolley (7) that can slide on the longitudinal beam tracks (4), and a boom crane (9). The transport trolley (7) and the boom crane (9) are both installed on the longitudinal beam tracks (4). The concrete pump pipe (8) is installed and supported on the crossbeams (3) or longitudinal beam tracks (4) through a pump pipe support structure (81). The concrete pump pipe (8) is arranged along the length of the longitudinal beam track (4); the column (2) is also connected to the adjacent crossbeam (3) by the diagonal brace (21); the top of the column (2) is hinged to the bottom of the longitudinal beam track (4) by the pivot support (31); the two sections of the longitudinal beam track of each longitudinal beam track (4) are connected by the longitudinal beam track pin hinge (41), the longitudinal beam track pin hinge (41) includes a front hinge lug (411), a rear hinge lug (412) and a pin (413), the front hinge lug (411) is set at the front end of the rear section of the longitudinal beam track, the rear hinge lug (412) is set at the rear end of the front section of the longitudinal beam track, and the front hinge lug (411) and the rear hinge lug (412) are connected by the pin (413). The transport trolley (7) is hinged; the top of the frame is provided with a cover plate (71), the bottom of the frame is provided with a bottom door (72), the bottom of the frame is also provided with anti-overturning wheels (74) for sliding on the longitudinal beam track (4), and the side of the frame is provided with a side door (73); the pump pipe support structure (81) includes a pump pipe support base (812), a pump pipe support hinge seat (813) is provided on the pump pipe support base (812), a screw sleeve (816) is hinged on the pump pipe support base (812), a height adjustment screw (815) is internally threaded on the screw sleeve (816), a pump pipe sleeve clamp (811) is provided on the top of the height adjustment screw (815), and the screw sleeve (816) is internally threaded with a height adjustment screw (815). The upper end of the ) is connected to the pump pipe support base (812) by a turnbuckle (814); the derrick crane (9) includes a movable base (92), the bottom of the movable base (92) is provided with an anti-overturning pulley (91) for sliding on the longitudinal beam track (4), the movable base (92) is provided with a fixed rod (95) and a rotating rod (96) through a support (94), the top of the fixed rod (95) and the rotating rod (96) are connected with a force-sharing wire rope, the rotating rod (96) is guided with a wire rope for hoisting materials, the end of the wire rope is connected with a hook (97), and the movable base (92) is provided with a limiting ear (93) for fixing and limiting the movable base (92);The anti-overturning wheel (74) and anti-overturning pulley (91) described above have the same structure. A roller for sliding on the top of the longitudinal beam track (4) is installed on the wheel frame, and two sets of limiting wheels for sliding on both sides of the bottom of the longitudinal beam track (4) are installed on the wheel frame. The two sets of limiting wheels are arranged front and back below the roller to form a triangular limiting sliding structure.

2. The prefabricated steep slope transport channel system according to claim 1, characterized in that: The bottom of the beam (3) is connected by a transverse connecting rod (22) between two adjacent columns (2).

3. The prefabricated steep slope transport channel system according to claim 1, characterized in that: The foundation (1) includes a foundation base (11) and an anchor bolt assembly (12), wherein the foundation base (11) is fixed to the ground by the anchor bolt assembly (12).

4. The prefabricated steep slope transport channel system according to claim 1, characterized in that: The pedestrian walkway (5) includes a step (51) and a guardrail (6). The guardrail (6) is set on both sides of the step (51), and the step (51) is provided with a baffle (52) to prevent it from rolling off.

5. The prefabricated steep slope transport channel system according to claim 1, characterized in that: The construction process is as follows: The installation and construction process is as follows: First, the load-bearing system is constructed. Holes are drilled using a soil drilling rig, geological conditions are analyzed, the foundation base is poured, anchor piles are driven in, columns are installed, and crossbeams, longitudinal beam tracks, and diagonal braces are erected to form the first section of the load-bearing system. The second step is to install the boom crane and transport trolley on the longitudinal beam track; The third step involves using a boom crane and transport trolleys to transport and unload materials, install pedestrian walkways, guardrails, and concrete pump pipes, and complete the installation of the first structural segment. The fourth step involves using a boom crane and transport trolleys to transport and load / unload construction materials to the end of the segment. This process is repeated from the first to the third step until the entire system is installed. The dismantling and construction process is as follows: The first step is to use a derrick crane and transport trolleys to dismantle and transport the last section of the pedestrian walkway, guardrails, and concrete pump pipe structure to the starting point. The second step is to move the transport trolley to the penultimate section and fix the boom crane to the end of the penultimate section's load-bearing system. The third step is to disassemble the last section of the load-bearing system from top to bottom. The disassembled longitudinal beams, crossbeams, and column sections are transported to the foot of the mountain using transport trolleys. They are transported as they are disassembled and then neatly stacked and stored in a warehouse at the foot of the mountain for reuse. Fourth, after the last section of the load-bearing system is dismantled, move the boom crane to the front end of the previous section of the load-bearing system and repeat steps one through three until the entire system is dismantled.

Citation Information

Patent Citations

  • Concrete transportation method for bridge body of high-pier bridge in gully region

    CN102535344A

  • Mountain forest space curve steel structure trestle road installation method

    CN113026528A

  • Inclined bridge for automobile transportation

    CN201842518U

  • Travelling cable crane

    CN202429923U

  • Pipeline supporting device

    CN218913969U