A smart tunneling construction method based on a tunnel boring machine

By adding sensors and devices to the tunnel boring machine, the geological prediction model is updated in real time and the construction parameters are optimized, which solves the problems of geological prediction errors and human errors in tunnel excavation and achieves safe and efficient tunnel excavation.

CN118065924BActive Publication Date: 2026-11-17CCCC FOURTH HARBOR ENG INST CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410243505.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-03-04
Publication Date
2026-11-17
Estimated Expiration
2044-03-04

AI Technical Summary

Technical Problem

Existing tunnel excavation methods are highly dependent on the accuracy of geological prediction models, which leads to large errors in rock mass strength during construction, resulting in safety accidents such as tunnel deformation or collapse. Furthermore, human error exists in the cutting range, making it difficult to ensure construction safety, quality, and schedule in complex geological environments.

Method used

By adding vibration acceleration sensors, image acquisition devices, and ball launching devices to the tunneling machine, an information database is constructed, the geological prediction model is updated in real time, construction parameters are adaptively optimized, and the cutting planning path is dynamically adjusted by combining ball rebound tests and grouting reinforcement.

Benefits of technology

It improved the safety and efficiency of tunnel excavation, reduced rock mass damage and resource waste, simplified the rock mass strength testing process, ensured the accuracy and reliability of construction, avoided over-excavation, and optimized the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118065924B_ABST
    Figure CN118065924B_ABST
Patent Text Reader

Abstract

This invention provides an intelligent tunneling construction method based on a tunnel boring machine (TBM), applicable to the field of tunnel boring construction technology. The invention includes the following steps: construction preparation, installation of the TBM, acquisition of the rock mass strength R on the TBM cutting surface, establishment of a geological measurement model and updating of the geological prediction model, dynamic adjustment of the cutting planning path, and TBM construction. The step of acquiring the rock mass strength R on the TBM cutting surface also includes noise reduction processing of the vibration acceleration a4 at the end of the tunnel arm, establishing the relationship between the vibration acceleration a4 and the rock mass strength R. By adding components such as vibration acceleration sensors and rebound launchers, the actual rock mass information of the cutting target surface is fed back in real time, and the geological prediction model is updated, optimizing the cutting planning path and realizing digital dynamic adjustment of the tunneling construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of tunnel excavation construction technology, and in particular to an intelligent tunnel excavation construction method based on a tunnel boring machine. Background Technology

[0002] With the development of urban construction, the development and utilization of underground space has become an important trend. Tunneling construction, as a highly efficient, safe, environmentally friendly, and automated construction technique, is widely used in rock excavation construction fields such as traffic tunnels, water conveyance tunnels, and coal mine roadways. Current tunneling construction techniques all establish geological prediction models through pre-construction geological surveys. Based on these models, the configuration parameters of the tunnel boring machine and the properties of the tunnel rock mass are determined, the location of weak areas and their reinforcement methods are assessed, and the cutting plan path is determined based on the predicted rock mass strength. When the actual construction situation does not deviate significantly from the geological prediction model, the entire tunneling process is guided by the geological prediction model. However, this tunneling method is highly dependent on the accuracy of the geological prediction model. The accuracy of the geological prediction model established before construction based on geological surveys is often insufficient, which can easily lead to large errors in predicting rock mass strength during tunneling, resulting in significant tunnel deformation or even collapse and other safety accidents. Secondly, tunnel excavation is carried out manually on-site or remotely via remote control of the tunneling machine, leading to significant human error in the cutting range, low excavation accuracy, and frequent over-excavation. Furthermore, the cutting parameters for each shift are fixed, such as the cutting plan path and cutting rotation torque, and cannot adaptively optimize the original parameter configuration based on the geological stratification characteristics of the cutting target surface. This makes it difficult to guarantee the safety, quality, and schedule goals of tunnel excavation, especially in complex and variable geological environments.

[0003] Therefore, it is necessary to design an intelligent tunneling construction method based on tunnel boring machines to solve the above problems. Summary of the Invention

[0004] The purpose of this invention is to provide an intelligent tunneling construction method based on a tunnel boring machine. By adding vibration acceleration sensors, image acquisition devices, ball launching devices, and other configurations to the traditional tunnel boring machine, a large database of tunneling construction information is constructed. The geological prediction model is dynamically updated based on the actual situation at the construction site, and the original construction parameter configuration scheme is adaptively optimized.

[0005] To achieve the above objectives, the present invention provides the following technical solution:

[0006] A smart tunneling construction method based on a tunnel boring machine, characterized by comprising the following steps:

[0007] S100 Construction Preparation: Establish a geological prediction model, determine the initial construction parameters through the geological prediction model, and obtain the initial cut-off planning path;

[0008] S200 installation of tunneling machine:

[0009] The tunneling machine includes a body and a cutting head. The body has a tunneling arm facing the tunnel, and the cutting head is connected to the front end of the tunneling arm. The body has a built-in engine, and a dust removal fan is installed on the body below the tunneling arm.

[0010] The tunneling machine also includes a first acceleration sensor and a second acceleration sensor installed on the machine body, the first acceleration sensor installed on the top surface of the front end of the tunneling arm, and the second acceleration sensor installed at the connection point between the end of the tunneling arm and the machine body.

[0011] The tunneling machine also includes several projectors mounted on its body;

[0012] The tunneling machine also includes a telescopic integrated probe installed inside the cutting head. The telescopic integrated probe includes a ball launching device and a grouting device. The ball launching device is installed at the center of the front end of the telescopic integrated probe. The grouting device includes a ring of several grouting ports on the end face of the telescopic integrated probe, and a grouting conduit is inserted into each grouting port.

[0013] The S300 obtains the rock mass strength R on the tunnel boring machine cutting surface, including the following steps:

[0014] When the tunneling machine is idling (i.e., only the engine is vibrating), the displacement matrix {δ} and velocity matrix of the engine's vibration excitation point are captured by the second acceleration sensor. and acceleration matrix Using finite element analysis software, the mass matrix [M], damping matrix [C], and stiffness matrix [K] of the tunneling machine under different postures were created. Combined with data captured by the second accelerometer, the cutting head vibration response acceleration a2 caused solely by engine vibration in the i-th posture was calculated using the following formula:

[0015]

[0016] In the formula, [M] i [C] i [K] i These are the i-th rows of the mass matrix [M], damping matrix [C], and stiffness matrix [K], respectively;

[0017] When the S302 cutter is not in operation, the dust removal fan is turned on, and the vibration acceleration a3 at the end of the tunneling arm is obtained through the first acceleration sensor. When the tunneling machine is in normal operation, the vibration acceleration a4 at the end of the tunneling arm is captured. The noise of a4 is reduced, and the interference terms a2 and a3 are removed to obtain the true vibration response signal caused by cutting the rock, that is, the vibration acceleration a1 = a4 - [a2 + a3] caused by the collision of the rock mass during tunneling.

[0018] S303 activates the ball launching device of the telescopic integrated probe, obtains the ball rebound height h, establishes the mapping relationship between the vibration acceleration a1 and the ball rebound height h through multiple tests, selects rock masses of different strengths to conduct ball rebound tests, establishes the relationship between the ball rebound height h and the rock strength R, and thus obtains the rock mass strength R on the cutting surface of the tunneling machine, which is the equivalent rock mass strength R.

[0019] S400 establishes a geological measurement model and updates the geological prediction model.

[0020] The equivalent rock mass strength R obtained from step S300 is collected. The tunneling machine is connected to the database and information processing system. The database and information processing system analyzes the distribution law of rock mass strength at the cutting face, establishes a geological measurement model, and compares the equivalent rock mass strength R of the geological measurement model with the predicted rock mass strength R′ of the geological prediction model. If R ≤ 0.85R′, the accuracy of the geological prediction model is not high, and the equivalent rock mass strength R is used to replace it and update the geological prediction model. If R is less than the minimum strength of self-stabilizing surrounding rock, the area is identified as a weak area, and the grouting device of the telescopic integrated probe is activated to grout and reinforce the area. The rebound height h is determined by the ball rebound test, and the rapid detection of the rock mass strength in the reinforced area is completed. The rock mass strength R″ of the reinforced area is then updated to the geological prediction model.

[0021] S500 Cutting Planning Path Dynamic Adjustment

[0022] The initial cutting planning path is dynamically adjusted based on the real-time equivalent rock mass strength R obtained in step S300. When R ≤ 0.85R′, the cutting influence radius r1 is calculated based on the equivalent rock mass strength R of the geological measurement model. When R is less than the minimum strength of the self-stabilizing surrounding rock, the cutting influence radius r2 is calculated based on the rock mass strength R″ of the reinforced area. The trace spacing of the initial cutting planning path is adjusted according to the cutting influence radius r1 or r2 to obtain the optimized cutting planning path. The tunnel design outline and the optimized cutting planning path are projected onto the tunneling cutting target surface using a projector. The tunneling machine performs construction according to the optimized cutting planning path.

[0023] S600 tunneling machine construction

[0024] The tunneling machine carries out construction according to the geological measurement model and the optimized cutting plan path, and the historical data of the entire tunneling process is output to the database and information processing system.

[0025] As a preferred technical solution of the present invention, in step S200, the tunneling machine is also equipped with an image acquisition device and a three-dimensional scanning probe. The image acquisition device is installed on each of the projectors, and a ring of several three-dimensional scanning probes is embedded between the rear end of the telescopic integrated probe and the front end of the cutting head.

[0026] As a preferred technical solution of the present invention, the different postures mentioned in step S301 refer to the states of the cutting head at different horizontal angles α and different vertical angles β. The horizontal angle α is the angle formed by the axis of the cutting head and the center line of the cutting target surface excavation direction, and the rotation range of the horizontal angle α is -25° to 25°. The vertical angle β is the angle formed by the axis of the cutting head and the vertical line of the ground, and the rotation range of the vertical angle β is -35° to 24°.

[0027] As a preferred embodiment of the present invention, step S302 further includes a step of limiting a1 by a threshold, comprising the following steps:

[0028] (1) Based on the rock samples obtained from the geological survey, the rock samples are divided into n categories according to their rock mass strength from highest to lowest. The strength range of category I rock mass is R1 to R2, and so on, with the strength range of category n rock mass being R n ~R n+1 ;

[0029] (2) Excavate a rock sample with a rock mass strength of R1, and obtain the lower limit value of vibration acceleration a of the type I rock sample according to step S300. 1-1 For rock samples with a rock mass strength of R2, excavation is carried out, and the upper limit value of vibration acceleration a of the type I rock sample is obtained according to step S300. 1-2 The vibration acceleration range of the Class I rock samples is defined as (a 1-1 a 1-2 ), and so on, the vibration acceleration limit range for the nth type of rock sample is (a 1-n a 1-n+1 The vibration acceleration range of the entire rock sample obtained from geological exploration is defined as (a 1-1 a 1-n+1 );

[0030] (3) The measured vibration acceleration a1 during the tunneling process exceeds the range (a 1-1 a 1-n+1 When this happens, the out-of-range data will be removed and not included in the database and information processing system;

[0031] (4) The measured vibration acceleration a1 at each cutting point during the tunneling process is within the range (a 1-1 a 1-2 Within the range (a), when the measured vibration acceleration a1 at a single cut-off point is within the interval (a 1-n a 1-n+1 Within or outside the interval (a) 1-1 a 1-n+1 In addition, this data is removed and not included in the database and information processing system.

[0032] As a preferred technical solution of the present invention, the twice-times of the cutting influence radius in step S500 is equivalent to the trace spacing of the cutting planning path.

[0033] As a preferred technical solution of the present invention, the cutting planning path is equivalent to the movement trajectory of the cutting head, and its movement trajectory includes an S-shape from top to bottom, an S-shape from bottom to top, a W-shape from left to right, or a W-shape from right to left.

[0034] In summary, compared with the prior art, the beneficial effects of the present invention are as follows:

[0035] (1) This invention abandons the traditional tunneling process that uses the same configuration parameters for construction. The cutting configuration parameters for each advance are based on the rock mass distribution perception of the previous advance as a prediction basis. Combined with the vibration acceleration sensor and rebound launch device, the rock mass distribution perception of the current cutting section is obtained in real time and dynamically fed back to the database and information processing system. The geological prediction model is then specifically corrected and optimized, so that the tunneling construction can be flexibly adjusted according to the changes in different geological conditions and construction environment. Based on the real-time collected cutting rock mass information, a more reasonable and scientific cutting planning path is given, which effectively improves the cutting efficiency and safety of the tunneling machine and reduces damage to the rock mass and waste of resources.

[0036] (2) By establishing the relationship between vibration acceleration and rock mass strength, the rock mass strength at the cutting position can be calculated by monitoring the vibration acceleration of the cutting head during tunneling construction. This eliminates the need for cumbersome testing methods such as core drilling or rebound testing. Compared with traditional rock mass strength investigation technology, this invention simplifies the construction process, reduces costs and time investment, and enables the rapid provision of more reliable and real-time rock mass information in complex geological environments.

[0037] (3) The vibration acceleration acquired in real time is noise-reduced to eliminate the interference of engine vibration and dust removal fan vibration, accurately acquire the vibration acceleration caused by the collision of rock mass during tunneling, i.e. the real cutting response, and limit it to a threshold to eliminate abnormal data. This overcomes the lack of awareness and technical limitations of traditional construction methods in eliminating interference items to obtain high-precision rock mass strength, which leads to poor accuracy in rock mass strength identification. This invention ensures that the monitoring results are based on accurate and consistent data, improves the accuracy of monitoring, and helps to conduct more in-depth and accurate data analysis.

[0038] (4) During the tunneling process, the rock mass strength at the cutting point is obtained by real-time monitoring of the vibration acceleration of the cutting head and by rebound tests at local locations. The two methods verify and complement each other, improving the reliability of the monitoring results and effectively solving the problem of poor adaptability of the initial geological prediction model and initial construction parameter configuration. Secondly, the rock mass strength after grouting reinforcement in weak areas is obtained through non-destructive rebound tests. This completes the strength monitoring work while preserving the integrity of the rock mass, reducing risks in terms of safety and quality.

[0039] (5) The combination of multi-view 3D modeling using image acquisition devices and fine modeling using 3D scanning probes satisfies both the requirement for rapid excavation in non-boundary areas and the requirement for obtaining high-precision model data in boundary areas. Efficiency and accuracy are equally important. The high-precision construction in the boundary areas is made up for by the large amount of time saved in the non-boundary areas, which greatly reduces the overall time consumption of the tunnel excavation section. At the same time, it ensures high construction accuracy and quality in the boundary areas and avoids over-excavation. Attached Figure Description

[0040] Figure 1 This is a flowchart of an intelligent tunneling construction method based on a tunnel boring machine according to the present invention;

[0041] Figure 2 This is a schematic diagram of the tunneling machine of the present invention;

[0042] Figure 3 This is a schematic diagram of the cutting head of the present invention;

[0043] Figure 4 This is a schematic diagram of the horizontal angle α and vertical angle β of the cutting head of the present invention;

[0044] Figure 5 This is a schematic diagram of the initial cut-off planning path in a specific embodiment of the present invention;

[0045] Figure 6 This is a schematic diagram of the optimized truncation planning path according to a specific embodiment of the present invention;

[0046] In the figure, 1—body, 11—tunneling arm, 111—first accelerometer, 112—second accelerometer, 12—dust removal fan, 13—projector, 2—cutting head, 21—telescopic integrated probe, 211—ball launching device, 212—grouting device, 22—three-dimensional scanning probe. Detailed Implementation

[0047] The specific embodiments of the present invention will be further described below with reference to the accompanying drawings. It should be noted that these descriptions are for the purpose of aiding understanding the present invention, but do not constitute a limitation thereof. Furthermore, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0048] according to Figure 1 The implementation process of an intelligent tunneling construction method based on a tunnel boring machine includes the following steps:

[0049] S100 Construction Preparation: Establish a geological prediction model, determine the initial construction parameters through the geological prediction model, and obtain the initial cut-off planning path;

[0050] The aforementioned initial construction parameters include the configuration parameters of the tunnel boring machine, the properties of the tunnel rock mass, the location of weak areas and their reinforcement methods, etc. Based on the geological prediction model, the projector 12 is used to transmit projection signals to the cutting target surface to provide initial cutting planning path guidance for the cutting target surface and control the cutting route of the tunnel boring machine.

[0051] S200 installation of tunneling machine:

[0052] like Figure 2 As shown, the tunneling machine includes a body 1 and a cutting head 2. The body 1 has a tunneling arm 11 facing the tunnel. The front end of the tunneling arm 11 is connected to the cutting head 2. The body 1 has a built-in engine (not shown in the figure). A dust removal fan 12 is provided on the body 1 below the tunneling arm 11.

[0053] The tunneling machine also includes a first acceleration sensor 111 and a second acceleration sensor 112 installed on the body 1, the first acceleration sensor 111 installed on the top surface of the front end of the tunneling arm 11, and the second acceleration sensor 112 installed at the end of the tunneling arm 11 where it connects to the body;

[0054] The tunneling machine also includes several projectors 13 mounted on the machine body;

[0055] like Figure 3As shown, the tunneling machine also includes a telescopic integrated probe 21 installed in the cutting head 2. The telescopic integrated probe 21 includes a ball launching device 211 and a grouting device 212. The ball launching device 211 is installed at the center of the front end of the telescopic integrated probe 21. The grouting device 212 includes a plurality of grouting ports that are opened in a ring on the end face of the telescopic integrated probe 21. Each grouting port is provided with a grouting conduit.

[0056] The first accelerometer is installed on the tunneling arm near the cutting head to maximize the capture of the cutting head's vibration acceleration during rock excavation. The second accelerometer is installed on the machine body away from the cutting head to capture the vibration acceleration of the tunneling machine itself during operation. The projector should be positioned to avoid obstruction by the cutting head, ensuring that the projector can project a complete image onto the cutting target surface regardless of the cutting head's position. The image content includes, but is not limited to, geological stratification images, the radius of influence of a single cut, and the planned cutting path. The telescopic integrated probe is retracted and hidden inside the cutting head during routine cutting operations; it is only extended when a ball rebound test is required or when grouting reinforcement is needed for weak surrounding rock.

[0057] The S300 obtains the rock mass strength R on the tunnel boring machine cutting surface, including the following steps:

[0058] When the tunneling machine is idling (i.e., only the engine is vibrating), the displacement matrix {δ} and velocity matrix of the engine's vibration excitation point are captured by the second acceleration sensor. and acceleration matrix Using finite element analysis software, the mass matrix [M], damping matrix [C], and stiffness matrix [K] of the tunneling machine under different postures were created. Combined with data captured by the second accelerometer, the cutting head vibration response acceleration a2 caused solely by engine vibration in the i-th posture was calculated using the following formula:

[0059]

[0060] In the formula, [M] i [C] i [K] i These are the i-th rows of the mass matrix [M], damping matrix [C], and stiffness matrix [K], respectively;

[0061] The aforementioned cutting head vibration response acceleration a2 is the attenuated response generated by the engine's own vibration, which is attenuated and propagates through the main boom and auxiliary boom of the tunneling machine to the end of the tunneling boom.

[0062] When the S302 cutter is not in operation, the dust removal fan is turned on, and the vibration acceleration a3 at the end of the tunneling arm is obtained through the first acceleration sensor. When the tunneling machine is in normal operation, the vibration acceleration a4 at the end of the tunneling arm is captured. The noise of a4 is reduced, and the interference terms a2 and a3 are removed to obtain the true vibration response signal caused by cutting the rock, that is, the vibration acceleration a1 = a4 - [a2 + a3] caused by the collision of the rock mass during tunneling.

[0063] The vibration acceleration a4 captured under normal operating conditions of the tunneling machine is noise-reduced to eliminate the interference of the cutting head vibration response acceleration a2 and the vibration acceleration a3 caused by the dust removal fan. This improves the accuracy of the measurement and the quality of the data, and helps to more accurately assess the rock mass condition and strength.

[0064] S303 opens the ball launching device of the telescopic integrated probe to obtain the ball rebound height h. Through multiple tests, the mapping relationship between vibration acceleration a1 and ball rebound height h is established. Different rock masses are selected for ball rebound tests to establish the relationship between ball rebound height h and rock strength R, thereby obtaining the rock strength R on the cutting surface of the tunneling machine, which is the equivalent rock strength R.

[0065] The rock mass strength R is determined in the following way:

[0066] As shown in Table 1, when α = -24° and β = 23°, the mass matrix [M] is calculated in the finite element model. 22 Damping matrix [C] 22 and stiffness matrix [K] 22 The vibration response acceleration a of the cutting head at node (2,2) in the matrix is ​​obtained. 2(2,2) When α = -25° and β = 23°, the mass matrix [M] is calculated. 12 Damping matrix [C] 12 and stiffness matrix [K] 12 The vibration response acceleration a of the cutting head at node (1,2) in the matrix is ​​obtained. 2(1,2) Similarly, the vibration response acceleration a2 of the cutting head under different postures can be obtained according to Table 1. Using this acceleration as the noise reduction function of the vibration acceleration a1 of the cutting head, an accurate noise reduction function can be provided under different postures, thereby effectively identifying the true signal of the vibration response caused by cutting rocks.

[0067] To obtain a more accurate noise reduction function, more detailed angle interpolation is used to calculate the attitude conditions, such as using 0.5° or 0.1° as the variation value between adjacent conditions. Since the α and β angles of the tunneling machine change continuously during operation, for attitudes not listed in Table 1, the nearest adjacent condition is used for interpolation. For example, when cutting is performed with α = -24.8° and β = 23°, the noise reduction function can be calculated using the following interpolation formula:

[0068] a 2(2,2) +0.8×a 2(1,2) (a 2(1,2) -a 2(2,2) )

[0069] Table 1: [M] values ​​of α and β for different postures i [C] i [K] i

[0070]

[0071]

[0072] S400 establishes a geological measurement model and updates the geological prediction model.

[0073] The equivalent rock mass strength R obtained from step S300 is collected. The tunneling machine is connected to the database and information processing system. The database and information processing system analyzes the distribution law of rock mass strength at the cutting face, establishes a geological measurement model, and compares the equivalent rock mass strength R of the geological measurement model with the predicted rock mass strength R′ of the geological prediction model. If R≤0.85R′, the accuracy of the geological prediction model is not high, and the equivalent rock mass strength R is used to replace it and update it in the geological prediction model. If R is less than the minimum strength of the self-stabilizing surrounding rock, the area is identified as a weak area, and the grouting device of the telescopic integrated probe is activated to grout and reinforce the area. The rebound height h is determined by the ball rebound test, and the rapid detection of the rock mass strength in the reinforced area is completed. The rock mass strength R″ of the reinforced area is then updated in the geological prediction model.

[0074] The aforementioned database and information processing system store information during the tunneling process and integrate big data mapping relationships, including response vibration acceleration, equivalent rock mass strength R, rock mass strength R″ measured by rebound test, three-dimensional model, geological model, and cutting planning path, etc.

[0075] The rock mass strength R″ of the aforementioned weak areas after grouting reinforcement was tested using a non-destructive rebound test, which is superior to the method of obtaining the equivalent rock mass strength R by using the vibration acceleration of the cutting head. This method quickly obtains more accurate rock mass data while preserving the integrity of the rock mass, reducing risks in terms of safety and quality.

[0076] S500 Cutting Planning Path Dynamic Adjustment

[0077] The initial cutting planning path is dynamically adjusted based on the real-time equivalent rock mass strength R obtained in step S300. When R ≤ 0.85R′, the cutting influence radius r1 is calculated based on the equivalent rock mass strength R of the geological measurement model. When R is less than the minimum strength of the self-stabilizing surrounding rock, the cutting influence radius r2 is calculated based on the rock mass strength R″ of the reinforced area. The trace spacing of the initial cutting planning path is adjusted according to the cutting influence radius r1 or r2 to obtain the optimized cutting planning path. The tunnel design outline and the optimized cutting planning path are projected onto the tunneling cutting target surface using a projector. The tunneling machine carries out construction according to the optimized cutting planning path.

[0078] The optimization implementation process of the above-mentioned cut-off planning path is as follows:

[0079] like Figure 5 and Figure 6 As shown, based on the geological prediction model, the cutting influence radius r of the rock mass at the target face is determined to be 0.5m, and the predicted rock mass strength R′ is 72MPa. The initial cutting path is designed as an S-shaped trajectory from top to bottom. Construction is carried out according to the initial cutting path determined by the geological prediction model, and the geological prediction model is updated based on the converted rock mass strength R obtained in real time by the vibration acceleration sensor. The converted rock mass strength R at point A is monitored and obtained. a 70MPa, R a =70MPa>0.85R'=0.85×72MPa=61.2MPa. According to the calculation results, the geological prediction model has a high accuracy in predicting the rock mass condition at point A, and there is no need to update the geological prediction model. The cutting work is carried out according to the original cutting influence radius r. When cutting to point B, the equivalent rock mass strength R at point B is monitored. b 59 MPa, R b =59MPa < 0.85R' = 0.85 × 72MPa = 61.2MPa. At this point, the geological prediction model has poor accuracy in predicting the rock mass condition at point B. Therefore, the geological prediction model needs to be updated based on the calculated rock mass strength R. b The calculated cutting influence radius r' is 0.7m. For the remaining uncut area, the four initial cutting planning paths are optimized into three, which effectively improves the cutting efficiency and safety of the tunneling machine and reduces damage to the rock mass and waste of resources.

[0080] S600 tunneling machine construction

[0081] The tunneling machine operates according to the geological measurement model and the optimized cutting plan path, and the historical data of the entire tunneling process is output to the database and information processing system.

[0082] like Figure 2 As shown, in step S200, the tunneling machine is also equipped with an image acquisition device (not shown in the figure) and a three-dimensional scanning probe 22. The image acquisition device is installed on each projector, and a ring of several three-dimensional scanning probes is embedded between the rear end of the telescopic integrated probe and the front end of the cutting head.

[0083] Image acquisition devices are used to obtain 3D contour information of the cut-off target surface from different angles, and to build a 3D model of the excavation of the non-boundary area of ​​the tunnel in real time throughout the entire process. This intuitively expresses the geological structure and characteristics of the cut-off target surface, and better simulates and analyzes the actual situation of the tunnel construction process. 3D scanning probes are used to obtain high-precision 3D contour models of the tunnel boundary area, accurately calculate the excavation volume of the tunnel boundary area, and avoid over-excavation. The combination of multi-view 3D modeling using image acquisition devices and precise modeling using 3D scanning probes satisfies both the requirements for rapid excavation in non-boundary areas and the requirement for obtaining high-precision model data in boundary areas, achieving a balance between efficiency and accuracy.

[0084] like Figure 4 As shown, in step S301, different postures refer to the state of the cutting head at different horizontal angles α and different vertical angles β. The horizontal angle α is the angle formed by the axis of the cutting head and the center line of the cutting target surface excavation direction. The rotation range of the horizontal angle α is -25° to 25°. The vertical angle β is the angle formed by the axis of the cutting head and the vertical line of the ground. The rotation range of the vertical angle β is -35° to 24°.

[0085] The horizontal angle is mainly used to control the deflection angle of the tunneling machine in the horizontal direction. By controlling the size of the horizontal angle α, the direction and trajectory of the tunneling machine can be controlled. The vertical angle is used to control the tilt angle of the tunneling machine in the vertical direction. By controlling the size of the vertical angle β, the height and tunneling depth of the tunneling machine can be controlled.

[0086] Step S302 also includes a step of limiting a1 by a threshold, which includes the following steps:

[0087] (1) Based on the rock samples obtained from the geological survey, the rock samples are divided into n categories according to their rock mass strength from highest to lowest. The strength range of category I rock mass is R1 to R2, and so on, with the strength range of category n rock mass being R n ~R n+1 ;

[0088] (2) Excavate a rock sample with a rock mass strength of R1, and obtain the lower limit value of vibration acceleration a for the Class I rock sample according to step S300. 1-1 For rock samples with a rock mass strength of R2, excavation is carried out, and the upper limit value of vibration acceleration a for Class I rock samples is obtained according to step S300. 1-2 The vibration acceleration range for Class I rock samples is defined as (a 1-1a 1-2 ), and so on, the vibration acceleration limit range for the nth type of rock sample is (a 1-n a 1-n+1 The vibration acceleration range of the entire rock sample obtained from geological exploration is defined as (a 1-1 a 1-n+1 );

[0089] (3) The measured vibration acceleration a1 during the tunneling process exceeds the range (a 1-1 a 1-n+1 When this happens, the out-of-range data will be removed and not included in the database and information processing system;

[0090] (4) The measured vibration acceleration a1 at each cutting point during the tunneling process is within the range (a 1-1 a 1-2 Within the range (a), when the measured vibration acceleration a1 at a single cut-off point is within the interval (a 1-n a 1-n+1 Within or outside the interval (a) 1-1 a 1-n+1 In addition, this data will be removed and not included in the database and information processing system.

[0091] The above steps limit the threshold of a1, eliminate abnormal data, ensure that only data within the normal range is used for subsequent analysis, improve the reliability and accuracy of the data, reduce the impact of abnormal data on the fluctuation of results, make the analysis results more stable, and provide reference value for the tunneling construction of the next node.

[0092] like Figure 6 As shown, in step S500, twice the radius of influence of the cut is equivalent to the trace spacing of the cut planning path.

[0093] The cutting planning path is equivalent to the movement trajectory of the cutting head, which includes an S-shape from top to bottom, an S-shape from bottom to top, a W-shape from left to right, or a W-shape from right to left.

[0094] This invention, by adding components such as vibration acceleration sensors and rebound launchers, acquires the actual rock mass strength of the cutting target surface in real time. It then performs noise reduction processing and threshold setting on this rock mass strength, eliminating vibration interference and abnormal data to provide more accurate and precise strength data. This provides more reliable support for updating the geological prediction model and optimizing the cutting planning path. The cutting configuration parameters for each advance are based on the rock mass distribution perception of the previous advance's cutting section as a prediction basis. Combined with the real-time acquisition of the rock mass distribution perception of the cutting section using vibration acceleration sensors and rebound launchers, the geological prediction model and cutting planning path are corrected and optimized. Based on the actual construction situation, more reasonable and scientific construction configuration suggestions are given, realizing digital dynamic adjustment of tunneling construction.

[0095] It should be understood that the above embodiments are one or more embodiments of the present invention, and there are many other embodiments and variations based on the present invention; any variations and modifications made by those skilled in the art through the present invention without making pioneering innovations are all within the protection scope of the present invention.

Claims

1. A smart tunneling construction method based on a tunnel boring machine, characterized in that: Includes the following steps: S100 Construction Preparation: Establish a geological prediction model, determine the initial construction parameters through the geological prediction model, and obtain the initial cut-off planning path; S200 installation of tunneling machine: The tunneling machine includes a body and a cutting head. The body has a tunneling arm facing the tunnel, and the cutting head is connected to the front end of the tunneling arm. The body has a built-in engine, and a dust removal fan is installed on the body below the tunneling arm. The tunneling machine also includes a first acceleration sensor and a second acceleration sensor installed on the machine body, the first acceleration sensor installed on the top surface of the front end of the tunneling arm, and the second acceleration sensor installed at the connection point between the end of the tunneling arm and the machine body. The tunneling machine also includes several projectors mounted on its body; The tunneling machine also includes a telescopic integrated probe installed inside the cutting head. The telescopic integrated probe includes a ball launching device and a grouting device. The ball launching device is installed at the center of the front end of the telescopic integrated probe. The grouting device includes a ring of several grouting ports on the end face of the telescopic integrated probe, and a grouting conduit is inserted into each grouting port. The S300 obtains the rock mass strength R on the tunnel boring machine cutting surface, including the following steps: When the tunneling machine is idling (i.e., only the engine is vibrating), the displacement matrix {δ} and velocity matrix of the engine's vibration excitation point are captured by the second accelerometer. and acceleration matrix Using finite element analysis software, the mass matrix [M], damping matrix [C], and stiffness matrix [K] of the tunneling machine under different postures were created. Combined with data captured by the second accelerometer, the cutting head vibration response acceleration a2 caused solely by engine vibration in the i-th posture was calculated using the following formula: where [M], [C], and [K] are the mass, damping, and stiffness matrices, respectively. i i i are the i-th row of the mass, damping, and stiffness matrices, respectively.​​ When the S302 cutter is not in operation, the dust removal fan is turned on, and the vibration acceleration a3 at the end of the tunneling arm is obtained through the first acceleration sensor. When the tunneling machine is in normal operation, the vibration acceleration a4 at the end of the tunneling arm is captured. The noise of a4 is reduced, and the interference terms a2 and a3 are removed to obtain the true vibration response signal caused by cutting the rock, that is, the vibration acceleration a1 = a4 - [a2 + a3] caused by the collision of the rock mass during tunneling. S303 activates the ball launching device of the telescopic integrated probe, obtains the ball rebound height h, establishes the mapping relationship between the vibration acceleration a1 and the ball rebound height h through multiple tests, selects rock masses of different strengths to conduct ball rebound tests, establishes the relationship between the ball rebound height h and the rock strength R, and thus obtains the rock mass strength R on the cutting surface of the tunneling machine, which is the equivalent rock mass strength R. S400 establishes a geological measurement model and updates the geological prediction model: The equivalent rock mass strength R obtained from step S300 is collected. The tunneling machine is connected to the database and information processing system. The database and information processing system analyzes the distribution law of rock mass strength at the cutting face, establishes a geological measurement model, and compares the equivalent rock mass strength R of the geological measurement model with the predicted rock mass strength R′ of the geological prediction model. If R ≤ 0.85R′, the accuracy of the geological prediction model is not high, and the equivalent rock mass strength R is used to replace it and update the geological prediction model. If R is less than the minimum strength of self-stabilizing surrounding rock, the area is identified as a weak area, and the grouting device of the telescopic integrated probe is activated to grout and reinforce the area. The rebound height h is determined by the ball rebound test, and the rapid detection of the rock mass strength in the reinforced area is completed. The rock mass strength R″ of the reinforced area is then updated to the geological prediction model. S500 cut-off planning path dynamic adjustment: The initial cutting planning path is dynamically adjusted based on the real-time equivalent rock mass strength R obtained in step S300. When R ≤ 0.85R′, the cutting influence radius r1 is calculated based on the equivalent rock mass strength R of the geological measurement model. When R is less than the minimum strength of the self-stabilizing surrounding rock, the cutting influence radius r2 is calculated based on the rock mass strength R″ of the reinforced area. The trace spacing of the initial cutting planning path is adjusted according to the cutting influence radius r1 or r2 to obtain the optimized cutting planning path. The tunnel design outline and the optimized cutting planning path are projected onto the tunneling cutting target surface using a projector. The tunneling machine performs construction according to the optimized cutting planning path. S600 tunneling machine construction: The tunneling machine carries out construction according to the geological measurement model and the optimized cutting plan path, and the historical data of the entire tunneling process is output to the database and information processing system.

2. The intelligent tunneling construction method based on a tunnel boring machine according to claim 1, characterized in that: In step S200, the tunneling machine is also equipped with an image acquisition device and a three-dimensional scanning probe. The image acquisition device is installed on each of the projectors. A ring of three-dimensional scanning probes is embedded between the rear end of the telescopic integrated probe and the front end of the cutting head.

3. The intelligent tunneling construction method based on a tunnel boring machine according to claim 1, characterized in that: The different postures mentioned in step S301 refer to the states of the cutting head at different horizontal angles α and different vertical angles β. The horizontal angle α is the angle formed by the axis of the cutting head and the center line of the cutting target surface excavation direction, and the rotation range of the horizontal angle α is -25° to 25°. The vertical angle β is the angle formed by the axis of the cutting head and the vertical line of the ground, and the rotation range of the vertical angle β is -35° to 24°.

4. The intelligent tunneling construction method based on a tunnel boring machine according to claim 1, characterized in that: Step S302 also includes a step of limiting a1 by a threshold, which includes the following steps: (1) Based on the rock samples obtained from the geological survey, the rock samples are divided into n categories according to their rock mass strength from highest to lowest. The strength range of category I rock mass is R1 to R2, and so on, with the strength range of category n rock mass being R n ~R n+1 ; (2) Excavate a rock sample with a rock mass strength of R1, and obtain the lower limit value of vibration acceleration a for the Class I rock sample according to step S300. 1-1 For rock samples with a rock mass strength of R2, excavation is carried out, and the upper limit value of vibration acceleration a of the type I rock sample is obtained according to step S300. 1-2 The vibration acceleration range of the Class I rock samples is defined as (a 1-1 a 1-2 ), and so on, the vibration acceleration limit range for the nth type of rock sample is (a 1-n a 1-n+1 The vibration acceleration range of the entire rock sample obtained from geological exploration is defined as (a 1-1 a 1-n+1 ); (3) The measured vibration acceleration a1 during the tunneling process exceeds the range (a 1-1 a 1-n+1 When this happens, the out-of-range data will be removed and not included in the database and information processing system; (4) The measured vibration acceleration a1 at each cutting point during the tunneling process is within the range (a 1-1 a 1-2 Within the range (a), when the measured vibration acceleration a1 at a single cut-off point is within the interval (a 1-n a 1-n+1 Within or outside the interval (a) 1-1 a 1-n+1 In addition, this data is removed and not included in the database and information processing system.

5. The intelligent tunneling construction method based on a tunnel boring machine according to claim 1, characterized in that: The twice-th radius of influence of the cut mentioned in step S500 is equivalent to the trace spacing of the cut planning path.

6. The intelligent tunneling construction method based on a tunnel boring machine according to claim 1, characterized in that: The cutting planning path is equivalent to the movement trajectory of the cutting head, which includes an S-shape from top to bottom, an S-shape from bottom to top, a W-shape from left to right, or a W-shape from right to left.

Citation Information

Patent Citations

  • Earth surface parameter identification method suitable for TBM rapid tunneling

    CN111679319A

  • Coal mine boom roadheader cutting control method and system based on visual navigation

    CN111946340A