A method and device for generating satellite trajectory based on power reduction iteration
Through the ground station multi-star trajectory coordination method, the power-reduction iteration method is used to generate a comprehensive trajectory, which solves the problem of low safety in satellite operation and realizes the long-term safe operation of satellites.
Patent Information
- Application Number
- CN202410910140.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-09
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-07-09
AI Technical Summary
Due to the influence of space environmental forces, satellites need to plan reasonable operating trajectories, but their own remote sensing equipment has limited vision and cannot accurately obtain the normal operating trajectory of satellites in the same or adjacent orbit as a planning reference, resulting in low operating safety.
Through the multi-star trajectory coordination method of ground stations, tracking receivers are used to collect the trajectory information of multiple orbital satellites in the same or near-orbit orbit, and the power-reduction iteration method is used to quickly generate comprehensive trajectory, and send it to in-orbit satellites through the transmitter to guide them to perform trajectory planning.
It has achieved long-term safe operation of satellites in orbit, improved operational safety performance, high real-time performance, and effectively avoided the risks of space environmental forces.
Smart Images

Figure CN118457946B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of satellite technology, and in particular to a method and device for generating a satellite trajectory based on power reduction iteration. Background Art
[0002] With the accelerated development of the satellite industry, the number of satellite launches has increased year by year. At the same time, the cost of satellite launches is relatively high. Long-term normal service can effectively obtain profits and hedge costs. Therefore, the safe in-orbit operation of satellites has become an important factor affecting the development of the satellite industry. Risks such as operational safety have been repeatedly mentioned.
[0003] Usually, satellites always fly around the earth at a certain speed under the influence of the earth's gravity. Since there is only one geostationary orbit, the station resources are very tight. Therefore, many functional satellites, such as remote sensing satellites, are deployed in low-orbit space below the geostationary orbit. Low-orbit satellites are easily affected by space environmental forces, such as atmospheric drag perturbations, geomagnetic radiation, solar storms, etc. The actual trajectory of the satellite often changes. In severe cases, long-distance deviations or falls occur. The satellite orbit attitude needs to be adjusted by the energy carried by the satellite. Therefore, reasonable trajectory planning can effectively reduce the impact of space environmental forces and ensure the long-term normal and safe operation of satellites in orbit. At present, due to the limited field of view of satellites' remote sensing equipment and the lack of communication with each other, satellites cannot accurately detect the operation of satellites in the same or adjacent orbits, and it is difficult to directly obtain reasonable trajectory references, and the long-term operation safety is low. Therefore, the present invention adopts the multi-satellite trajectory coordination mode of the ground station, collects the trajectories of multiple satellites that are operating normally in the same orbit or adjacent orbits within a certain time period through the ground station tracking receiver, uses the fast power reduction iteration method to generate the comprehensive trajectory of the normally operating satellite, and then sends it to the in-orbit satellite through the ground station transmitter, so as to guide the in-orbit satellite to plan its operation trajectory, so as to improve its long-term operation safety performance. Summary of the invention
[0004] The purpose of the present invention is to provide a method and device for generating satellite operation trajectories based on power-reduction iteration in view of the deficiencies of the prior art, so as to solve the problem of satellite operation safety caused by the fact that the existing satellites need to plan reasonable operation trajectories due to the influence of space environmental forces, and the limited perception field of their own remote sensing equipment makes it impossible to obtain the normal operation trajectories of satellites in the same orbit or adjacent orbits as a planning reference. The present invention uses a ground station tracking receiver to collect trajectory information of multiple satellites in the same orbit or adjacent orbits that are operating normally within a certain time period, uses a power-reduction iteration method to quickly generate a comprehensive trajectory within the recent certain period, and sends the comprehensive trajectory to the in-orbit satellite through the ground station transmitter. The in-orbit satellite uses the comprehensive trajectory for trajectory planning, thereby performing long-term and safe in-orbit operation.
[0005] The object of the present invention is achieved through the following technical solutions: In the first aspect, a method for generating a satellite trajectory based on power reduction iteration comprises the following steps:
[0006] Step 1: Obtain the original trajectories of multiple satellites in the same orbit or adjacent orbits as the target satellite in orbit;
[0007] Step 2: Set a trajectory set, periodically update the trajectories in the trajectory set, convert the original trajectory obtained in the most recent operation cycle into a standard trajectory, and store it in the trajectory set;
[0008] Step 3: When the target satellite in orbit is about to approach the ground station, a power reduction iteration method is used to generate a comprehensive trajectory based on the standard trajectory in the trajectory set. Specifically, any standard trajectory in the trajectory set is paired with each other, and two trajectory points are taken from each standard trajectory to form a convex quadrilateral. A new trajectory is formed according to the angle between the centroid coordinates and the coordinate axis to replace the old trajectory in the trajectory set. After all replacements are completed, a comprehensive trajectory is obtained;
[0009] Step 4: The target satellite in orbit gradually enters the integrated trajectory based on its own altitude and starts the next operation cycle, thus achieving safe in-orbit operation of the satellite.
[0010] Furthermore, the co-orbit or adjacent orbit satellite is a satellite whose distance from the target on-orbit satellite does not exceed a height threshold.
[0011] Furthermore, the step 2 is implemented by the following sub-steps:
[0012] (2.1) Assume a trajectory set Traj, the storage capacity of the set trajectory is , is a positive integer; Set the number of original trajectories that can be collected within the most recent operation cycle T to be less than or equal to the number of original trajectories that can be collected within the most recent operation cycle T.
[0013] (2.2) Randomly select from the original trajectories that can be collected within the most recent operation cycle T Tracks;
[0014] (2.3) Using the equally divided angle interpolation estimation method, the randomly selected The trajectories are transformed into standard trajectories;
[0015] (2.4) Discard the original trajectory in the trajectory set Traj and store the generated standard trajectory in the trajectory set Traj.
[0016] Furthermore, the process of converting to the standard trajectory is as follows:
[0017] 1) In the geocentric inertial coordinate system, the circular angle around the center of the earth is evenly divided into N equal parts, and the angle of each divided angle is equal;
[0018] 2) For any trajectory, draw N angular rays from the center of the earth according to the equally divided angle, which intersect with the corresponding standard trajectory. For any intersection coordinate value , corresponding to The angle between the positive coordinate of the X-axis and the angle between the positive coordinate of the X-axis and the positive coordinate of the X-axis is , using the coordinates of the two trajectory points closest to the i-th equally divided angle in the original satellite trajectory in the counterclockwise and clockwise directions, respectively, , , the angles between the line connecting the center of the earth and the i-th equally divided angle are , using the interpolation estimation method, the coordinates of the standard trajectory at the i-th equally divided angle are obtained :
[0019] ;
[0020] ;
[0021] 3) According to the method in step 2), the N coordinates obtained are the standard trajectory after conversion.
[0022] Furthermore, the step three is implemented by the following sub-steps:
[0023] (3.1) The number of standard trajectories stored in the trajectory set Traj is , pair the standard trajectories in the trajectory set in pairs, for any paired trajectory pair, for any trajectory point in one of the trajectories, its adjacent trajectory points, and the trajectory points and adjacent trajectory points in the corresponding paired trajectory, form a convex quadrilateral and calculate the centroid coordinates, sort the centroid coordinates generated by all trajectory points in ascending order of the angle value with the positive coordinate of the X-axis to form a new trajectory, and complete the calculation of the new trajectory of all paired trajectory pairs;
[0024] (3.2) The new trajectory formed in step (3.1) replaces the old trajectory in the trajectory set Traj. At this time, the number of trajectories in the trajectory set Traj is , that is, a new trajectory is generated once for each pairing iteration, and the power exponent of the number of trajectories decreases by one;
[0025] (3.3) Repeat steps (3.1) and (3.2) until the number of trajectories in the trajectory set Traj is 1. The trajectory obtained at this time is the comprehensive trajectory.
[0026] Furthermore, in step 3, the process of generating a new trajectory by combining the centroids of the constructed convex quadrilateral using the paired trajectory pairs is as follows: for the i-th trajectory point of one of the trajectories , and compare it with the neighboring trajectory points , Pairing track points , Arrange them counterclockwise to form a convex quadrilateral. Assume that the vertex coordinates of the reordered convex quadrilateral are , t=1,2,3,4, then the centroid coordinates of the convex quadrilateral are They are:
[0027] ;
[0028] Centroid coordinates That is, the trajectory points on the generated new trajectory are generated. For each trajectory point on the paired trajectory, a corresponding new trajectory point is generated, and the new trajectory is formed by sorting the angle values with the positive coordinate of the X-axis from small to large.
[0029] Furthermore, the step 4 is implemented by the following sub-steps:
[0030] (4.1) Assume that the trajectory point of the target satellite in orbit at the current equidistant angle is , the orbit height is , the comprehensive trajectory point planned at the next equally divided angle is , the orbit height is , the angle between it and the positive coordinate of the X-axis is , then the multiple progressive approximation method is used, and the actual trajectory point of the target in-orbit satellite at the next equal division angle is The following formula is used to infer:
[0031] ;
[0032] ;
[0033] in, is a positive integer constant, using empirical values. is the ratio of the included angle between the trajectory point where the target on-orbit satellite starts to enter the integrated trajectory and the integrated trajectory point to be approached to the size of the equally divided angle, which is a positive integer;
[0034] The trajectory point is and the track height is Satisfies the following relationship:
[0035] ;
[0036] The trajectory point is and the track height is Satisfies the following relationship:
[0037] ;
[0038] (4.2) Repeat step (4.1) until the orbital altitude of the target satellite in orbit at the current actual trajectory point and the orbital altitude of the planned integrated trajectory point at the next equal division angle are less than the threshold , the target satellite in orbit adjusts its attitude and directly enters the integrated trajectory point planned at the next equally divided angle.
[0039] In a second aspect, the present invention also provides a satellite trajectory generation device based on power reduction iteration, comprising a memory and one or more processors, wherein the memory stores executable code, and when the processor executes the executable code, the satellite trajectory generation method based on power reduction iteration is implemented.
[0040] In a third aspect, the present invention further provides a computer-readable storage medium having a program stored thereon, and when the program is executed by a processor, the method for generating a satellite trajectory based on power reduction iteration is implemented.
[0041] In a fourth aspect, the present invention further provides a computer program product, including a computer program, which, when executed by a processor, implements the method for generating satellite trajectory based on power reduction iteration.
[0042] The beneficial effect of the present invention is that the present invention proposes a satellite trajectory generation method based on power reduction iteration to provide effective trajectory planning for the target in-orbit satellite. By using the normal operating satellite trajectory collected by the ground station tracking receiver within a certain period of time, a power reduction iteration method is used to quickly generate a comprehensive trajectory, and it is transmitted to the in-orbit satellite through the ground station transmitter to guide the target in-orbit operation to operate safely. This multi-satellite trajectory coordination method realized by the ground station makes full use of the effective operation trajectory reference, and uses the ground station computer to quickly generate trajectory planning. The implementation method has high real-time performance, can effectively avoid the problem of satellite safety operation due to the influence of space environment forces, and provide reliable support for the long-term safe in-orbit operation of satellites. BRIEF DESCRIPTION OF THE DRAWINGS
[0043] Figure 1 The present invention provides a flow chart of a method for generating satellite trajectory based on power reduction iteration.
[0044] Figure 2 It is the trajectory diagram of the target satellite in orbit.
[0045] Figure 3 It is the sub-satellite point trajectory diagram of the target in-orbit satellite, with the horizontal axis being longitude and the vertical axis being latitude.
[0046] Figure 4 It is the original trajectory map of satellites in the same orbit and adjacent orbits collected within the time period T.
[0047] Figure 5 It is a schematic diagram of the operating state of the target on-orbit satellite after entering the comprehensive trajectory generated by the present invention.
[0048] Figure 6 It is a structural diagram of a satellite trajectory generation device based on power reduction iteration provided by the present invention. DETAILED DESCRIPTION
[0049] The present invention will be described in detail below with reference to the accompanying drawings, and the purpose and effect of the present invention will become more apparent. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.
[0050] like Figure 1 As shown, the present invention proposes a method for generating satellite trajectory based on power reduction iteration. The implementation scenario of the present invention is to use a tracking receiver at a ground station to collect satellite trajectory information that operates normally within a certain time period, use a power reduction iteration method to generate a comprehensive trajectory, and then send the comprehensive trajectory to the target in-orbit satellite through the ground station transmitter, so as to help the target in-orbit satellite to operate safely for a long time.
[0051] Since it is difficult to obtain the trajectory data of a real satellite, in this embodiment, STK simulation software is used to simulate the satellite's on-orbit operation status, including satellite orbit altitude, orbit inclination, orbit altitude and orbit inclination of satellites in the same orbit and adjacent orbits, satellite distribution, satellite trajectory, satellite sub-satellite trajectory points, etc., as well as the operation status of the target on-orbit satellite after entering the comprehensive trajectory generated by the method of the present invention. The satellite sub-satellite point is the projection point of the satellite on the ground (or the intersection of the line connecting the satellite and the center of the earth and the ground). Through the sub-satellite trajectory point, a ground station whose installation position coincides with the longitude and latitude of a certain sub-satellite point can be selected to realize the communication between the ground station and the satellite. When the satellite passes through the ground station, the ground station tracking receiver tracks the satellite with the receiving antenna, receives information from the satellite, and sends information to the satellite through the transmitter. Generally, the satellite communicates with the ground station once after one cycle (one orbit around the earth). In this embodiment, the orbit altitude of the target on-orbit satellite S1 simulated by the STK simulation software is 1000km, and the orbit inclination is 45 degrees. The schematic diagram of its on-orbit trajectory is shown as follows: Figure 2 As shown in the figure, the sub-satellite point trajectory diagram is as follows Figure 3 The orbital altitudes of the satellites S2 to S8 in the same orbit and adjacent orbit collected in the time period T simulated by STK simulation software range from 900km to 1100km. The schematic diagram of their orbital trajectories is shown in Figure 4 shown.
[0052] The method of the present invention comprises the following steps:
[0053] Step 1: Collect multiple N satellites in the same orbit or adjacent orbit as the target satellite through the ground station tracking receiver. The trajectory of the satellite in the most recent operation period T, which is normally operated within the time period T, is obtained to obtain the original trajectory;
[0054] In this embodiment, the orbital altitude of the target satellite in orbit is 1000 km, its operation period T (the time it takes to orbit the earth once) is about 105 minutes, and N is set to 4.
[0055] The ground station is located on the surface of the earth and has a fixed position. It receives information sent by the satellite through a tracking receiver installed on it. The satellite in orbit communicates with the ground station once every cycle.
[0056] The co-orbit or adjacent orbit satellite is a satellite that is no more than an astronomical distance from the target in-orbit satellite. In this embodiment .
[0057] The most recent operation cycle T is the time required for the target on-orbit satellite to complete one orbit, and the operation cycle changes caused by the satellite trajectory changes are ignored here.
[0058] Step 2: Set the trajectory set Traj, and the update period of the set is T, that is, after every time T, the original trajectory in the trajectory set is discarded, and the equal angle interpolation estimation method is used to convert the original trajectory obtained in the most recent operation cycle T into a standard trajectory and store it in the trajectory set Traj. The specific implementation steps are as follows:
[0059] (2.1) Assume a trajectory set Traj, the storage capacity of the set trajectory is , is a positive integer; Set to be less than or equal to the number of original trajectories that can be collected within the most recent operation cycle T; in this embodiment, set is 3, that is, the storage capacity of the set trajectory is 8.
[0060] (2.2) Randomly select from the original trajectories that can be collected within the most recent operation cycle T Tracks;
[0061] (2.3) Using the equally divided angle interpolation estimation method, the randomly selected The tracks are converted into standard tracks.
[0062] Specifically, the process of converting to the standard trajectory is as follows:
[0063] 1) Assume the geocentric inertial coordinate system is O-XYZ, where O is the center of the earth, XYZ are three mutually perpendicular coordinate axes, ignore the Z-axis coordinate of the original trajectory, and only keep the X-axis coordinate and the Y-axis coordinate. Divide the circular angle around the center of the earth into N equal parts, and the angle of each equal part is equal. In this embodiment, N is set to 36, so that the satellite can enter the predetermined trajectory point more smoothly.
[0064] 2) For any trajectory, draw N angular rays from the center of the earth according to the equally divided angle. Assume that the XY axis coordinates of the rays intersecting with the corresponding standard trajectory are , for any coordinate value , corresponding to The angle between the positive coordinate of the X-axis and the equal angle for , using the coordinates of the two track points closest to the i-th equally divided angle in the original satellite track in the counterclockwise and clockwise directions, assuming that they are , , the angles between the line connecting the center of the earth and the i-th equally divided angle are , using the interpolation estimation method, the coordinates of the standard trajectory at the i-th equally divided angle are obtained .
[0065]
[0066] The N coordinates estimated by interpolation using this method This is the standard trajectory after the trajectory is converted.
[0067] (2.4) Discard the original trajectory in the trajectory set Traj and store the generated standard trajectory in the trajectory set Traj.
[0068] Step 3: When the target satellite in orbit is about to approach the ground station, the ground station computer uses the power reduction iteration method to quickly generate a comprehensive trajectory based on the standard trajectory in the trajectory set Traj; specifically:
[0069] (3.1) Assume that the number of standard trajectories stored in the trajectory set Traj is , pair the standard trajectories in the trajectory set in pairs, for any paired trajectory pair, for any trajectory point in one of the trajectories, its adjacent trajectory point, and the trajectory point and adjacent trajectory point in the corresponding paired trajectory, a total of four trajectory points, are arranged as vertices in a counterclockwise direction to form a convex quadrilateral, and the centroid coordinates of the convex quadrilateral are calculated according to the vertex coordinates of the convex quadrilateral. The centroid coordinates generated by all trajectory points are sorted counterclockwise from small to large according to the angle value with the positive coordinate of the X-axis to form a new trajectory, and the new trajectory calculation of all paired trajectory pairs is completed;
[0070] The process of generating new trajectories by combining the constructed convex quadrilateral centroids is as follows:
[0071] Assume that the last track point of the paired track is repeatedly filled, and the filled tracks are
[0072]
[0073]
[0074] For any point of one of the trajectories , and compare it with the neighboring trajectory points , Pairing track points , Arrange them counterclockwise to form a convex quadrilateral. Assume that the vertex coordinates of the reordered convex quadrilateral are , then the centroid coordinates of the convex quadrilateral are They are:
[0075]
[0076] Centroid coordinates That is, the trajectory point on the generated new trajectory. Repeat the above process for each trajectory point on the paired trajectory until all trajectory points generate corresponding new trajectory points. The generated new trajectory can be expressed as .
[0077] (3.2) The new trajectory formed in step (3.1) replaces the old trajectory in the trajectory set Traj. At this time, the number of trajectories in the trajectory set Traj is , that is, a new trajectory is generated once for each pairing iteration, and the power exponent of the number of trajectories decreases by one;
[0078] (3.3) Repeat the above process until the number of trajectories in the trajectory set Traj is 1, and the trajectory at this time is the comprehensive trajectory.
[0079] Step 4: The ground station transmitter sends the generated integrated trajectory to the target satellite in orbit. The satellite in orbit gradually enters the integrated trajectory using multiple progressive approximations based on its own altitude and starts the next operation cycle to achieve safe satellite operation in orbit. The specific implementation process is as follows:
[0080] (4.1) Assume that the trajectory point of the target satellite in orbit at the current equidistant angle is , the orbit height is , the comprehensive trajectory point planned at the next equally divided angle is , the orbit height is , the angle between it and the positive coordinate of the X-axis is , then the multiple progressive approximation method is used, and the actual trajectory point of the satellite on the next equally divided angle is The following formula can be used to infer:
[0081]
[0082]
[0083] in, is a positive integer constant, using empirical values. is the ratio of the angle between the trajectory point where the target satellite enters the integrated trajectory and the integrated trajectory point to be approached to the angle of the bisection angle, which is a positive integer. If it is 5, the target satellite in orbit can be guided to enter the predetermined integrated trajectory slowly and gradually.
[0084] The trajectory point is and the track height is Satisfies the following relationship:
[0085]
[0086] The trajectory point is and the track height is Satisfies the following relationship:
[0087]
[0088] The target in-orbit satellite uses energy thrusters to adjust the satellite trajectory to enter the actual trajectory point.
[0089] (4.2) Repeat step (4.1) until the orbital altitude of the target satellite in orbit at the current actual trajectory point and the orbital altitude of the planned integrated trajectory point at the next equal division angle are less than the threshold , the target satellite in orbit adjusts its attitude and directly enters the planned integrated trajectory point at the next equally divided angle. Figure 5 As shown, set The distance between the satellite S1 and the planned integrated trajectory point is 10 km, and the simulator is used to simulate the process of the satellite S1 directly entering the planned integrated trajectory point at the next equally divided angle. It is found that the satellite S1 can enter the trajectory point smoothly.
[0090] Corresponding to the aforementioned embodiment of a method for generating a satellite trajectory based on power-decreasing iteration, the present invention also provides an embodiment of a device for generating a satellite trajectory based on power-decreasing iteration.
[0091] See also Figure 6An embodiment of the present invention provides a satellite trajectory generation device based on power reduction iteration, including a memory and one or more processors. The memory stores executable code. When the processor executes the executable code, it is used to implement a satellite trajectory generation method based on power reduction iteration in the above embodiment.
[0092] An embodiment of a satellite trajectory generation device based on power reduction iteration provided by the present invention can be applied to any device with data processing capabilities, and the device with data processing capabilities can be a device or apparatus such as a computer. The device embodiment can be implemented through software, or through hardware or a combination of software and hardware. Taking software implementation as an example, as a device in a logical sense, it is formed by the processor of any device with data processing capabilities in which it is located reading the corresponding computer program instructions in the non-volatile memory into the internal memory for execution. From a hardware perspective, if Figure 6 As shown in FIG. 1 , a hardware structure diagram of a satellite trajectory generation device based on power reduction iteration provided by the present invention is provided in any device with data processing capability, except Figure 6 In addition to the processor, memory, network interface, and non-volatile memory shown, any device with data processing capabilities in which the apparatus in the embodiments is located may also include other hardware, generally based on the actual functions of the device with data processing capabilities, which will not be described in detail.
[0093] The implementation process of the functions and effects of each unit in the above-mentioned device is specifically described in the implementation process of the corresponding steps in the above-mentioned method, and will not be repeated here.
[0094] For the device embodiment, since it basically corresponds to the method embodiment, the relevant parts can refer to the partial description of the method embodiment. The device embodiment described above is only schematic, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of the present invention. Ordinary technicians in this field can understand and implement it without paying creative work.
[0095] An embodiment of the present invention further provides a computer-readable storage medium having a program stored thereon. When the program is executed by a processor, a method for generating a satellite trajectory based on power reduction iteration in the above embodiment is implemented.
[0096] The computer-readable storage medium may be an internal storage unit of any device with data processing capability described in any of the aforementioned embodiments, such as a hard disk or a memory. The computer-readable storage medium may also be an external storage device of any device with data processing capability, such as a plug-in hard disk, a smart media card (SMC), an SD card, a flash card, etc. equipped on the device. Furthermore, the computer-readable storage medium may also include both an internal storage unit and an external storage device of any device with data processing capability. The computer-readable storage medium is used to store the computer program and other programs and data required by any device with data processing capability, and may also be used to temporarily store data that has been output or is to be output.
[0097] The present invention also provides a computer program product, including a computer program. When the computer program is executed by a processor, the method for generating a satellite trajectory based on power reduction iteration is implemented.
[0098] The above embodiments are used to illustrate the present invention rather than to limit the present invention. Any modification and change made to the present invention within the spirit of the present invention and the protection scope of the claims shall fall within the protection scope of the present invention.
Claims
1. A method for generating satellite trajectory based on power reduction iteration, characterized in that: The method comprises the following steps: Step 1: Obtain the original trajectories of multiple satellites in the same orbit or adjacent orbits as the target satellite in orbit; Step 2: Set the trajectory set, periodically update the trajectories in the trajectory set, convert the original trajectory obtained in the most recent operation cycle time into a standard trajectory, and store it in the trajectory set; the process of converting to a standard trajectory is as follows: 1) In the geocentric inertial coordinate system, the circular angle around the center of the earth is evenly divided into N equal parts, and the angle of each divided angle is equal; 2) For any trajectory, draw N angular rays from the center of the earth according to the equally divided angle, which intersect with the corresponding standard trajectory. For any intersection coordinate value , corresponding to The angle between the positive coordinate of the X-axis and the angle between the positive coordinate of the X-axis and the positive coordinate of the X-axis is , using the coordinates of the two trajectory points closest to the i-th equally divided angle in the original satellite trajectory in the counterclockwise and clockwise directions, respectively, , , the angles between the line connecting the center of the earth and the i-th equally divided angle are , using the interpolation estimation method, the coordinates of the standard trajectory at the i-th equally divided angle are obtained : ; ; 3) According to the method in step 2), the N coordinates obtained are the converted standard trajectory; Step 3: Generate the comprehensive trajectory of the target satellite in orbit using the power reduction iteration method based on the standard trajectory in the trajectory set. Specifically, pair any two standard trajectories in the trajectory set, take two trajectory points from each standard trajectory to form a convex quadrilateral, and form a new trajectory based on the angle between the centroid coordinates and the coordinate axis to replace the old trajectory in the trajectory set; after all replacements are completed, the comprehensive trajectory is obtained; this step is implemented by the following sub-steps: (3.1) The number of standard trajectories stored in the trajectory set Traj is , pair the standard trajectories in the trajectory set in pairs, for any paired trajectory pair, for any trajectory point in one of the trajectories, its adjacent trajectory points, and the trajectory points and adjacent trajectory points in the corresponding paired trajectory, form a convex quadrilateral and calculate the centroid coordinates, sort the centroid coordinates generated by all trajectory points in ascending order of the angle value with the positive coordinate of the X-axis to form a new trajectory, and complete the calculation of the new trajectory of all paired trajectory pairs; (3.2) The new trajectory formed in step (3.1) replaces the old trajectory in the trajectory set Traj. At this time, the number of trajectories in the trajectory set Traj is , that is, a new trajectory is generated once for each pairing iteration, and the power exponent of the number of trajectories decreases by one; (3.3) Repeat steps (3.1) and (3.2) until the number of trajectories in the trajectory set Traj is 1. The trajectory obtained at this time is the comprehensive trajectory; Step 4: The target satellite in orbit gradually enters the integrated trajectory based on its own altitude and starts the next operation cycle, thus achieving safe in-orbit operation of the satellite.
2. The method for generating satellite trajectory based on power reduction iteration according to claim 1, characterized in that: The co-orbit or adjacent orbit satellite is a satellite whose distance from the target on-orbit satellite does not exceed a height threshold.
3. The method for generating satellite trajectory based on power reduction iteration according to claim 1, characterized in that: The step 2 is implemented by the following sub-steps: (2.1) Assume a trajectory set Traj, the storage capacity of the set trajectory is , is a positive integer; Set the number of original trajectories that can be collected within the most recent operation cycle T to be less than or equal to the number of original trajectories that can be collected within the most recent operation cycle T. (2.2) Randomly select from the original trajectories that can be collected within the most recent operation cycle T Tracks; (2.3) Using the equally divided angle interpolation estimation method, the randomly selected The trajectories are transformed into standard trajectories; (2.4) Discard the original trajectory in the trajectory set Traj and store the generated standard trajectory in the trajectory set Traj.
4. The method for generating satellite trajectory based on power reduction iteration according to claim 1, characterized in that: In step 3, the process of generating a new trajectory by combining the centroids of the constructed convex quadrilateral using paired trajectory pairs is as follows: for the i-th trajectory point of one of the trajectories , and compare it with the neighboring trajectory points , Pairing track points , Arrange them counterclockwise to form a convex quadrilateral. Assume that the vertex coordinates of the reordered convex quadrilateral are , t=1,2,3,4, then the centroid coordinates of the convex quadrilateral are They are: ; Centroid coordinates That is, the trajectory points on the generated new trajectory are generated. For each trajectory point on the paired trajectory, a corresponding new trajectory point is generated, and the new trajectory is formed by sorting the angle values with the positive coordinate of the X-axis from small to large.
5. The method for generating satellite trajectory based on power reduction iteration according to claim 1, characterized in that: The step 4 is implemented by the following sub-steps: (4.1) Assume that the trajectory point of the target satellite in orbit at the current equidistant angle is , the orbit height is , the comprehensive trajectory point planned at the next equally divided angle is , the orbit height is , the angle between it and the positive coordinate of the X-axis is , then the multiple progressive approximation method is used, and the actual trajectory point of the target in-orbit satellite at the next equal division angle is The following formula is used to infer: ; ; in, is a positive integer constant, using empirical values. is the ratio of the included angle between the trajectory point where the target on-orbit satellite starts to enter the integrated trajectory and the integrated trajectory point to be approached to the size of the equally divided angle, which is a positive integer; The trajectory point is and the track height is Satisfies the following relationship: ; The trajectory point is and the track height is Satisfies the following relationship: ; (4.2) Repeat step (4.1) until the orbital altitude of the target satellite in orbit at the current actual trajectory point and the orbital altitude of the planned integrated trajectory point at the next equal division angle are less than the threshold , the target satellite in orbit adjusts its attitude and directly enters the integrated trajectory point planned at the next equally divided angle.
6. A satellite trajectory generation device based on power reduction iteration, comprising a memory and one or more processors, wherein the memory stores executable code, characterized in that: When the processor executes the executable code, a method for generating a satellite trajectory based on power reduction iteration as described in any one of claims 1 to 5 is implemented.
7. A computer-readable storage medium having a program stored thereon, characterized in that: When the program is executed by a processor, a method for generating a satellite trajectory based on power reduction iteration as described in any one of claims 1 to 5 is implemented.
8. A computer program product, comprising a computer program, characterized in that When the computer program is executed by a processor, a method for generating a satellite trajectory based on power reduction iteration as described in any one of claims 1 to 5 is implemented.