Cost analysis method of building assembly integrated module based on cloud computing

Through the cost analysis method of building prefabricated integrated modules based on cloud computing, the problems of waste of resources, long construction periods and high costs in traditional prefabricated building construction are solved, efficient and convenient cost analysis and optimization are achieved, and hardware costs and construction costs are reduced.

CN118537051BActive Publication Date: 2025-04-11GUOJIAN DIGITAL INTELLIGENCE ENG TECH (SHENZHEN) CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410828386.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-25
Publication Date
2025-04-11
Estimated Expiration
2044-06-25

AI Technical Summary

Technical Problem

There are problems of waste of resources, long construction periods and high costs in traditional prefabricated buildings, and traditional cost analysis relies on expensive computing equipment and is inefficient.

Method used

The cost analysis method of building prefabricated integrated modules is adopted based on cloud computing. By obtaining the requirements information of the initial module, matching the standard modules, optimizing using the life cycle cost model and value engineering analysis method, and finally visually displaying it through the cloud platform.

Benefits of technology

It improves the timeliness and convenience of cost analysis, reduces hardware costs and maintenance costs, realizes cost optimization and resource saving, improves construction efficiency and reduces costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118537051B_ABST
    Figure CN118537051B_ABST
Patent Text Reader

Abstract

The invention discloses a cost analysis method for building prefabricated integrated modules based on cloud computing, and relates to the field of building cost analysis. The cost analysis method for building prefabricated integrated modules based on cloud computing comprises: acquiring building demand data, using a cloud computing platform to match a database or input an integrated module to obtain an initial integrated module, using a life cycle cost calculation model to calculate the cost of the integrated module, using a value engineering method to optimize the integrated module, calculating and optimizing the cost of the integrated module, cyclically optimizing the integrated module, visualizing the integrated module and the cost of the integrated module, and obtaining a visualized cost analysis result and a cost optimization suggestion. The invention calculates the cost of each life cycle stage and the overall cost of the building prefabricated integrated module through a life cycle cost model, uses a value engineering analysis method to optimize the building prefabricated integrated module multiple times, and provides users with a variety of building prefabricated integrated module optimization schemes and cost optimization suggestions.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of building cost analysis, and in particular to a building prefabricated integrated module cost analysis method based on cloud computing. Background Art

[0002] Cast-in-place construction methods have problems such as waste of resources and long construction period. Using prefabricated parts for construction is an important way to shorten the construction period. This type of building is generally called prefabricated building.

[0003] Traditional prefabricated buildings only produce prefabricated parts in factories. During use, operators need to redesign and combine them according to the actual construction situation. During the design process, operators may make mistakes, resulting in insufficient, excessive, and mismatched components, which increases the cost of construction. How to improve construction efficiency and reduce construction costs through innovative methods has become the focus of the construction industry.

[0004] Building assembly integrated module is an advanced construction method, which prefabricates and assembles building components in the factory and then assembles them on site, thus realizing the industrialization, standardization and intelligence of the construction process. Building assembly integrated module greatly reduces the on-site construction time and the additional costs caused during the construction process by prefabricating building integrated modules in the factory.

[0005] Cloud computing is a distributed computing model based on the Internet. It refers to dividing huge data into many small modules through the network, and sending these small modules to a system composed of multiple computing devices for processing and analysis before returning the results. It provides computing resources, storage resources and applications to users through the network, realizing the ability to obtain and use computing resources on demand.

[0006] The cost analysis of traditional construction projects requires expensive computing equipment with powerful computing power, and local computing equipment is prone to being idle for a long time, which undoubtedly greatly increases the initial investment cost of cost analysis. With cloud computing, computing resources can be purchased on demand to reduce the cost of the project. Cost analysis also needs to consider unexpected factors during the construction process, such as insufficient materials extending the construction period, and excessive material reservations causing waste. The use of building prefabricated integrated modules can solve these problems while the integrated modules are still in the factory production process, avoiding problems during the construction process that cause overall project delays and increased costs.

[0007] Therefore, we urgently need to provide a cost analysis method for building prefabricated integrated modules based on cloud computing. Summary of the invention

[0008] The present invention aims to provide a method for analyzing the cost of building prefabricated integrated modules using cloud computing technology, thereby improving the timeliness and convenience of cost analysis.

[0009] The cost analysis method of building prefabricated integrated modules based on cloud computing includes:

[0010] S1. Obtain an initial building assembly integrated module; obtain the functions, performance and specifications of the building assembly integrated module at the user end, and form the functions, performance and specifications of the building assembly integrated module into the demand information of the building assembly integrated module; send the demand information to the cloud platform, match the demand information of the building assembly integrated module with the demand information corresponding to the standard building assembly integrated module in the building assembly integrated module database, and use the successfully matched standard building assembly integrated module as the initial building assembly integrated module; if there is no successfully matched standard building assembly integrated module, output no matching result, and input the initial building assembly integrated module at the user end;

[0011] S2. Send the project information of the initial building prefabricated integrated module into the life cycle cost model for calculation, and output the initial integrated module cost;

[0012] S3. The cloud platform analyzes and optimizes the demand information and integrated module costs of the initial building assembly integrated modules through the value engineering analysis method, outputs cost optimization suggestions and optimized integrated modules; sends the optimized integrated modules to the life cycle cost model for calculation, and outputs the optimized integrated module costs;

[0013] S4. Calculate the absolute value Ja and the cost reduction rate Jb of the optimized integrated module cost compared to the initial integrated module cost, analyze the values ​​of the absolute value Ja and the cost reduction rate Jb, and obtain a loop instruction; determine whether to loop the S3 process according to the loop instruction;

[0014] S5. The cloud platform collects all the integrated module costs and cost optimization suggestions in the processes of S2, S3 and S4 as result visualization data, visualizes the result visualization data, and outputs the visualization results to the user end;

[0015] As a preferred technical solution of the present invention, the initial building assembly integrated module is obtained, and the specific steps are:

[0016] A1. Obtain the functions, performance and specifications of the building assembly integrated module on the user side, combine the functions, performance and specifications of the building assembly integrated module into the demand information of the building assembly integrated module, and send the demand information to the cloud platform for matching;

[0017] A2. Matching a standard building assembly integrated module with the functional requirements of a building assembly integrated module in the building assembly integrated module database; outputting a first matching result and sending it to A3 matching performance; if there is no matching result, outputting no matching result to the user end;

[0018] A3. Matching a standard building assembly integrated module with building assembly integrated module performance requirements in the first matching result; outputting a second matching result and feeding it into A4 matching specification; if there is no matching result, outputting no matching result and outputting the first matching result to the user terminal;

[0019] A4. Match the standard building prefabricated integrated module with the building prefabricated integrated module specification requirements in the second matching result; output the third matching result and use it as the initial building prefabricated integrated module; if there is no matching result, output no matching result and output the second matching result to the user terminal;

[0020] A5. Input an existing building assembly integrated module as an initial building assembly integrated module at the user end; when receiving an output without a matching result, input the initial building assembly integrated module with reference to the first matching result or the second matching result;

[0021] As a preferred technical solution of the present invention, the life cycle cost model includes a project life cycle decomposition layer, a data processing layer and a cost analysis layer;

[0022] The project life cycle decomposition layer is used to match the life cycle phase of the initial building assembly integration module according to the project information of the initial building assembly integration module;

[0023] The data processing layer is used to match the cost elements corresponding to the initial building prefabricated integrated modules according to the project information of the initial building prefabricated integrated modules, collect the cost data of each life cycle stage according to the cost elements corresponding to the initial building prefabricated integrated modules, pre-process the cost data of each life cycle stage of the building prefabricated integrated modules, and obtain the cost data of the life cycle stage to be calculated;

[0024] The cost analysis layer is used to calculate the initial integrated module cost of the initial building prefabricated integrated module life cycle using the life cycle cost data to be calculated. The initial integrated module cost includes the cost of each stage and the overall cost.

[0025] As a preferred technical solution of the present invention, a life cycle cost model is established, and the specific steps are as follows:

[0026] B1. Determine the life cycle stages of the building assembly integrated module. The complete life cycle stages of the building assembly integrated module include the production material stage, production component stage, production process stage, installation stage, maintenance stage and depreciation stage;

[0027] B2. Determine the cost elements of each life cycle stage. The cost elements of the production material stage include material costs and material transportation costs; the cost elements of the production component stage are component costs; the cost elements of the production process stage include production labor costs and equipment loss costs; the cost elements of the installation stage include installation labor costs and installation transportation costs; the cost elements of the maintenance stage include daily maintenance costs and damage repair costs; the cost elements of the depreciation stage are depreciation costs after use;

[0028] B3. The cost data of the production material stage is recorded as C a , C a =x a +y a , x a is the material cost, y a is the material transportation cost; the cost data of the production component stage is recorded as C b , C b is the component cost; the cost data of the production process stage is recorded as C c , C c =(x c +y c )*d 1 , x c *d 1 is the production labor cost, y c *d 1 is the equipment loss fee; the cost data of the installation phase is recorded as C d , C d =x d +y d , x d For installation labor costs, y d is the installation and transportation fee; the cost data of the maintenance phase is recorded as C e , C e =(d 2 / T)*x d + K , (d 2 / T )*x d is the daily maintenance fee, K is the damage repair fee; the depreciation cost is recorded as C f , C f =α*μ*M,C f Depreciation after use;

[0029] B4. Collect verification data of several building prefabricated integrated modules, which include project information and costs of each stage of the building prefabricated integrated modules. Input the project information of the building prefabricated integrated modules into the initial life cycle cost model for verification, and adjust the parameters for calculating the cost data of each life cycle stage based on the cost of each stage;

[0030] As a preferred technical solution of the present invention, the life cycle stages of a complete building prefabricated integrated module include production material stage, production component stage, production process stage, installation stage, maintenance stage and depreciation stage. If the project information of the given building prefabricated integrated module is missing, the stage cost corresponding to the missing project information is set to 0;

[0031] As a preferred technical solution of the present invention, the demand information and integrated module cost of the initial building prefabricated integrated module are analyzed using a value engineering analysis method, and the specific steps are as follows:

[0032] C1. Obtain the demand information, cost of each stage and overall cost of the initial building assembly integrated module;

[0033] C2. Check the standard stage cost ratio corresponding to the preset price level of the total cost of the initial building prefabricated integrated module; calculate the ratio of each stage cost to the total cost, and calculate the difference between the cost ratio of each stage and the standard stage cost ratio; if the difference exceeds the set range, replace the stage plan in the stage plan library for the corresponding stage;

[0034] C3. Check the functional requirements and performance requirements in the initial building prefabricated integrated module demand information, and label the performance of each function according to the preset standard performance level table; calculate the average value of the performance levels of all functions as the average performance level, calculate the difference between the performance level of each function and the average performance level, and if the difference exceeds the set ratio, optimize the performance level of the corresponding function;

[0035] C4. Output the optimized solution as an optimization integrated module; output the operation of changing the phase solution and optimizing the performance level as analysis optimization suggestions;

[0036] As a preferred technical solution of the present invention, whether to loop through the S3 process is determined according to the loop instruction value, and the specific steps are:

[0037] The cost of the building assembly integrated module is recorded as C n The cost of the prefabricated integrated module is recorded as C 0 , the cost of the first optimized integrated module is recorded as C 1 , record the cost of each optimized integrated module in turn;

[0038] The total cost of the initial building assembly integrated module is recorded as C 0 , the total cost of the optimized integrated module obtained by the first optimization is recorded as C 1 , record the total cost C of each optimized integrated module in turn n ;

[0039] Calculate the absolute value of cost reduction J a =|Cn -C n-1 |, calculate the reduction rate J b =(1-C n / C n-1 )*100%;

[0040] Compare the absolute value of cost reduction J a and cost reduction rate J b Is it greater than the set value? If the cost is reduced by an absolute value J a and cost reduction rate J b If there is a value greater than the set value, the loop instruction is output to start the loop, otherwise the loop stop instruction is output;

[0041] As a preferred technical solution of the present invention, the result visualization data is visualized, and the specific steps are:

[0042] The visualization results include a cost line graph and a cost data table. The line graph includes a line graph of the overall cost of the integrated module and a line graph of the cost of each stage of the integrated module.

[0043] Calculate the cost difference and difference ratio of each stage in the upper and lower rows of the cost data table, and output them after the cost of each stage in each row of the table; these two types of data are part of the cost analysis results.

[0044] The present invention has the following advantages:

[0045] 1. The present invention calculates the cost of each life cycle stage and the overall cost of the building prefabricated integrated module through a life cycle cost model, which is convenient for users to quickly conduct cost analysis of the building prefabricated integrated module and obtain detailed costs of each life cycle stage.

[0046] 2. The present invention optimizes the building assembly integrated modules multiple times through the value engineering analysis method, and provides users with a variety of building assembly integrated module optimization solutions and cost optimization suggestions.

[0047] 3. The present invention reduces the cost and maintenance cost of local hardware by using cloud computing technology. Since cloud computing is pay-as-you-go, users can pay according to actual needs, avoiding overinvestment and waste of resources. In addition, using cloud computing platform calculations can enable cost analysis to be performed anytime and anywhere, without being restricted by hardware equipment, which improves the flexibility and effectiveness of cost analysis, so that users can obtain cost analysis in a timely manner and make decisions quickly.

[0048] 4. The present invention uses visualization technology to display cost analysis results and optimization suggestions through line graphs and tables, making it easy for users to quickly obtain cost analysis results and cost optimization suggestions. BRIEF DESCRIPTION OF THE DRAWINGS

[0049] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. The drawings are only used to illustrate the implementation methods and are not to be considered as limitations of the present invention.

[0050] Figure 1 A schematic diagram of a cost analysis method for building prefabricated integrated modules based on cloud computing in an embodiment of the present invention;

[0051] Figure 2 The present invention is a flowchart of another method for cost analysis of building prefabricated integrated modules based on cloud computing in an embodiment of the present invention. DETAILED DESCRIPTION

[0052] In order to enable persons skilled in the art to better understand the technical solutions in the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Example

[0053] The embodiment of the present invention provides a cost analysis method for building prefabricated integrated modules based on cloud computing, such as Figure 1 As shown, including:

[0054] S1. Obtain an initial building assembly integrated module; obtain the functions, performance and specifications of the building assembly integrated module at the user end, and form the functions, performance and specifications of the building assembly integrated module into the demand information of the building assembly integrated module; send the demand information to the cloud platform, match the demand information of the building assembly integrated module with the demand information corresponding to the standard building assembly integrated module in the building assembly integrated module database, and use the successfully matched standard building assembly integrated module as the initial building assembly integrated module; if there is no successfully matched standard building assembly integrated module, output no matching result, and input the initial building assembly integrated module at the user end;

[0055] The demand information of the building assembly integrated module includes the functional requirements of the building assembly integrated module, the performance requirements corresponding to the functions of the building assembly integrated module, and the specification requirements of the building assembly integrated module; the functional requirements are stored in the form of identification, the performance requirements are stored in the form of performance levels, and the specification requirements are stored in the form of length, width, and height data of the integrated module;

[0056] Get the initial building assembly integrated module, specific steps:

[0057] A1. Obtain the functions, performance and specifications of the building assembly integrated module on the user side, combine the functions, performance and specifications of the building assembly integrated module into the demand information of the building assembly integrated module, and send the demand information to the cloud platform for matching;

[0058] A2. Matching a standard building assembly integrated module with the functional requirements of a building assembly integrated module in the building assembly integrated module database; outputting a first matching result and sending it to A3 matching performance; if there is no matching result, outputting no matching result to the user end;

[0059] A3. Matching a standard building assembly integrated module with building assembly integrated module performance requirements in the first matching result; outputting a second matching result and feeding it into A4 matching specification; if there is no matching result, outputting no matching result and outputting the first matching result to the user terminal;

[0060] A4. Match the standard building prefabricated integrated module with the building prefabricated integrated module specification requirements in the second matching result; output the third matching result and use it as the initial building prefabricated integrated module; if there is no matching result, output no matching result and output the second matching result to the user terminal;

[0061] A5. Input an existing building assembly integrated module as an initial building assembly integrated module at the user end; when receiving an output without a matching result, input the initial building assembly integrated module with reference to the first matching result or the second matching result;

[0062] S2. Send the project information of the initial building prefabricated integrated module into the life cycle cost model for calculation, and output the initial integrated module cost;

[0063] The project information of the initial building prefabricated integrated module includes the demand information, production quantity, installation location, preset production time, preset maintenance cycle and preset service life of the initial building prefabricated integrated module;

[0064] The life cycle cost model of building prefabricated integrated modules is a comprehensive calculation framework that covers the costs of each life cycle stage;

[0065] The life cycle cost model includes the project life cycle decomposition layer, data processing layer and cost analysis layer;

[0066] The project life cycle decomposition layer is used to match the life cycle phase of the initial building assembly integration module according to the project information of the initial building assembly integration module;

[0067] The data processing layer is used to match the cost elements corresponding to the initial building prefabricated integrated modules according to the project information of the initial building prefabricated integrated modules, collect the cost data of each life cycle stage according to the cost elements corresponding to the initial building prefabricated integrated modules, pre-process the cost data of each life cycle stage of the building prefabricated integrated modules, and obtain the cost data of the life cycle stage to be calculated;

[0068] Cost elements are derived from a combination of historical data, market research, and expert judgment;

[0069] The cost analysis layer is used to calculate the initial integrated module cost of the initial building prefabricated integrated module life cycle using the life cycle cost data to be calculated. The initial integrated module cost includes the cost of each stage and the overall cost.

[0070] Establish a life cycle cost model, specific steps:

[0071] B1. Determine the life cycle stages of the building assembly integrated module. The complete life cycle stages of the building assembly integrated module include the production material stage, production component stage, production process stage, installation stage, maintenance stage and depreciation stage;

[0072] B2. Determine the cost elements of each life cycle stage. The cost elements of the production material stage include material costs and material transportation costs; the cost elements of the production component stage are component costs; the cost elements of the production process stage include production labor costs and equipment loss costs; the cost elements of the installation stage include installation labor costs and installation transportation costs; the cost elements of the maintenance stage include daily maintenance costs and damage repair costs; the cost elements of the depreciation stage are depreciation costs after use;

[0073] B3. The cost data of the production material stage is recorded as C a , C a =x a +y a , x a is the material cost of the integrated module frame, which is obtained by calculating the frame area of ​​the integrated module and the material cost per unit area. a Cost of transporting materials to the production site; do not choose only low-cost materials, but also consider the strength performance indicators of different types of materials; and plan the stage of replacing different materials according to the stage cost of production materials and the strength performance indicators of materials;

[0074] Cost data for the production component stage is recorded in C b , C b The total cost of purchasing or producing components is calculated by summing up the cost of each component. Components can be purchased or produced. The purchase cost is lower when the demand is small, and the production cost is lower when the demand is large. The purchase or production of different components is adjusted according to the demand for the components.

[0075] The cost data of the production process stage is recorded as C c , C c =(x c +y c )*d 1 , d 1 Default production time, x c is the average daily production labor cost, y cThe daily average equipment loss fee is different. The production time under different equipment is different, and the corresponding daily average equipment loss fee is also different. The effect of lowering production costs within the expected construction period can be achieved by adjusting the use of different equipment.

[0076] The cost data of the installation phase is recorded as C d , C d =x d +y d , x d For installation labor costs, y d For installation and transportation costs, during the installation phase, you can choose whether to outsource the installation or send someone to the installation site for installation based on the installation and transportation costs and installation labor costs at different distances from the installation site. If the installation site is far away, the installation labor costs of sending someone to install will be very high, so it is better to choose to outsource the installation at the installation site.

[0077] The cost data of the maintenance phase is recorded as C e , C e =(d 2 / T)*x d +K,d 2 is the preset service life, T is the preset maintenance period, x d is the maintenance cost of each maintenance, K is the expected damage repair cost; if the maintenance cycle is adjusted, the corresponding expected damage repair cost will increase as the maintenance cycle becomes longer, and adjusting the appropriate maintenance cycle can reduce the maintenance cost;

[0078] The cost of the depreciation stage is recorded as C f , C f =α*μ*M, α is the value loss ratio when the integrated module is no longer used, μ is the ratio of the currency when the integrated module is no longer used to the currency when the integrated module was built, and M is the total initial cost of depreciable materials; the main impact of the depreciation stage cost is the preset service life, the type of production integrated module frame and the type of components; the higher the depreciation stage cost, the lower the overall cost of the project, and changes in the production material stage will affect the depreciation stage cost;

[0079] B4. Collect verification data of several building prefabricated integrated modules, which include project information and costs of each stage of the building prefabricated integrated modules. Input the project information of the building prefabricated integrated modules into the initial life cycle cost model for verification, and adjust the parameters for calculating the cost data of each life cycle stage based on the cost of each stage;

[0080] S3. Use the value engineering (VE) analysis method in the cloud platform to analyze the function, performance and cost of the building prefabricated integrated module, cut unnecessary costs, improve efficiency and quality, achieve the purpose of cost control, and obtain the first optimized integrated module; send the first optimized integrated module to the life cycle cost model again to calculate the cost of the building prefabricated integrated module, and obtain the cost of the first optimized integrated module;

[0081] The life cycle stages of a complete building assembly integrated module include the production material stage, the production component stage, the production process stage, the installation stage, the maintenance stage, and the depreciation stage. If the project information of the given building assembly integrated module is missing, the stage cost corresponding to the missing project information is set to 0;

[0082] Value engineering is a systematic approach that aims to achieve the required quality, performance and reliability at the lowest overall cost by improving the functionality of products, services or processes. In the construction field, value engineering is widely used in the design, construction and operation phases of projects to ensure the highest value is provided within the budget.

[0083] Use the value engineering analysis method to analyze the demand information and integrated module cost of the initial building assembly integrated module. The specific steps are:

[0084] C1. Obtain the demand information, cost of each stage and overall cost of the initial building assembly integrated module;

[0085] C2. Check the standard stage cost ratio corresponding to the preset price level of the total cost of the initial building prefabricated integrated module; calculate the ratio of each stage cost to the total cost, and calculate the difference between the cost ratio of each stage and the standard stage cost ratio; if the difference exceeds the set range, replace the stage plan in the stage plan library for the corresponding stage;

[0086] The stage solution library stores different stage solutions for different stages. When the cost of production materials is too high, you can search for different stage solutions for production materials in the stage solution library. The cost of production materials is generally determined by the type of materials. Under the condition that the material grade is not lower than the set material grade, choose cheaper materials to reduce the problem of too high cost of production materials.

[0087] The preset price levels are given by professionals, and the corresponding standard stage costs can be obtained from historical data or set by professionals;

[0088] If the project information of the initial building prefabricated integrated module is missing, the missing items need to be cut and the remaining life cycle stages need to be re-divided into stage cost ratios;

[0089] C3. Check the functional requirements and performance requirements in the initial building prefabricated integrated module demand information, and label the performance of each function according to the preset standard performance level table; calculate the average value of the performance levels of all functions as the average performance level, calculate the difference between the performance level of each function and the average performance level, and if the difference exceeds the set ratio, optimize the performance level of the corresponding function;

[0090] The performance level label is obtained by dividing the performance level corresponding to the function according to a certain ratio. When optimizing the performance level, the lowest performance level must be considered, which cannot be lower than the performance requirements in the building assembly integrated module demand information;

[0091] C4. Output the optimized solution as an optimization integrated module; output the operation of changing the phase solution and optimizing the performance level as analysis optimization suggestions;

[0092] S4. Calculate the absolute value Ja and the cost reduction rate Jb of the optimized integrated module cost compared to the initial integrated module cost, analyze the values ​​of the absolute value Ja and the cost reduction rate Jb, and obtain a loop instruction; determine whether to loop the S3 process according to the loop instruction;

[0093] The cost of the building assembly integrated module is recorded as C n The cost of the prefabricated integrated module is recorded as C 0 , the cost of the first optimized integrated module is recorded as C 1 , record the cost of each optimized integrated module in turn;

[0094] The total cost of the initial building assembly integrated module is recorded as C 0 , the total cost of the optimized integrated module obtained by the first optimization is recorded as C 1 , record the total cost C of each optimized integrated module in turn n ;

[0095] Calculate the absolute value of cost reduction J a =|C n -C n-1 |, calculate the reduction rate J b =(1-C n / C n-1 )*100%;

[0096] Compare the absolute value of cost reduction J a and cost reduction rate J b Is it greater than the set value? If the cost is reduced by an absolute value J a and cost reduction rate J b If there is a value greater than the set value, the loop instruction is output to start the loop, otherwise the loop stop instruction is output;

[0097] The set value needs to be set according to the actual situation. A smaller set value can analyze more optimized integrated modules, but if the set value is too small, the calculation cost will increase and error optimization will easily occur; the absolute value of cost reduction J a When the total cost is large, it is more useful than the cost reduction rate. If the total cost is not large, the set value can be set to infinity.

[0098] S5. The cloud platform collects all the integrated module costs and cost optimization suggestions in the processes of S2, S3 and S4 as result visualization data, visualizes the result visualization data, and outputs the visualization results to the user end;

[0099] Visualize the result data. Specific steps:

[0100] The visualization results include a cost line graph and a cost data table. The line graph includes a line graph of the overall cost of the integrated module and a line graph of the cost of each stage of the integrated module.

[0101] Calculate the cost difference and difference ratio of each stage in the upper and lower rows of the cost data table, and output them after the cost of each stage in each row of the table; these two data are part of the cost analysis results;

[0102] The cost analysis results include the life cycle costs and overall costs of the building assembly integrated modules, the absolute value and cost reduction rate of the optimized integrated modules compared with the original integrated modules;

[0103] By associating the line graph with the table, users can observe the areas with large cost changes through the line graph and click to jump to the cost analysis results and cost optimization suggestions corresponding to the associated table; through the visualization results, the cost analysis results and cost optimization suggestions of the building prefabricated integrated modules can be quickly obtained, which is convenient for selecting the optimal integrated module among multiple optimized integrated modules. Example

[0104] The embodiment of the present invention provides a cost analysis method for building prefabricated integrated modules based on cloud computing, such as Figure 2 As shown, including:

[0105] The user end is used to input the acquired demand data, input the initial building assembly integration module, and receive the cost analysis results and optimization suggestions;

[0106] The cloud platform is used to match standard integration modules, obtain initial integration modules, calculate initial integration module costs, optimize integration module costs, and visualize results. Using the cloud platform for cloud computing does not require powerful computing equipment on the user side, so that cost analysis can be performed without equipment restrictions, thereby improving the efficiency of cost analysis.

[0107] Specific steps for cost analysis of building assembly integrated modules based on cloud computing:

[0108] 1. Get the initial integration module, specific steps:

[0109] The user end inputs the demand data, which includes the functions, performance and specifications of the building assembly integrated module;

[0110] After receiving the input demand data, the cloud platform matches the standard integrated module in the building assembly integrated module database and determines the next step according to the matching result; if there is a result that matches the function, performance and specification, the output is the initial building assembly integrated module; otherwise, the output is no matching result to the user end;

[0111] On the user side, when the initial building assembly integration module is not output, the initial building assembly integration module needs to be input. When inputting, the building assembly integration module with matching functions can be referred to;

[0112] 2. Module cost analysis and optimization, specific steps:

[0113] The cloud platform feeds the project information of the initial building assembly integrated module into the life cycle cost model for calculation and outputs the initial integrated module cost;

[0114] The cloud platform uses the value engineering analysis method to analyze and optimize the demand information and integrated module costs of the initial building assembly integrated modules, outputs cost optimization suggestions and optimized integrated modules; sends the optimized integrated modules to the life cycle cost model for calculation, and outputs the optimized integrated module costs; decides whether to perform cyclic optimization based on the difference between the optimized integrated module costs and the initial integrated module costs;

[0115] 3. Visualization of cost results and optimization suggestions, specific steps:

[0116] The cloud platform organizes the integrated module functions, performance, costs at each stage, overall costs, analysis suggestions, absolute cost reduction and cost reduction rate into result visualization data; uses visualization tools to visualize the result visualization data and outputs visualization results;

[0117] On the user side, the costs of the initial integrated module and each optimized integrated module are obtained through the visualization results; the final optimized integrated module is selected through the cost optimization data and the visualization results.

[0118] It should be understood that those skilled in the art can make improvements or changes based on the above description, and all such improvements and changes should fall within the scope of protection of the appended claims of the present invention. Parts not described in detail in this specification belong to the prior art known to those skilled in the art.

Claims

1. A cost analysis method for building prefabricated integrated modules based on cloud computing, characterized in that: include: S1. Obtaining the initial building assembly integrated module; Obtaining the functions, performances and specifications of the building assembly integrated module at the user end, and composing the functions, performances and specifications of the building assembly integrated module into the demand information of the building assembly integrated module; sending the demand information to the cloud platform, matching the demand information of the building assembly integrated module with the demand information corresponding to the standard building assembly integrated module in the building assembly integrated module database, and using the successfully matched standard building assembly integrated module as the initial building assembly integrated module; if there is no successfully matched standard building assembly integrated module, outputting no matching result, and inputting the initial building assembly integrated module at the user end; S2. Send the project information of the initial building prefabricated integrated module into the life cycle cost model for calculation, and output the initial integrated module cost; S3. The cloud platform analyzes and optimizes the demand information and integrated module costs of the initial building assembly integrated modules through the value engineering analysis method, outputs cost optimization suggestions and optimized integrated modules; sends the optimized integrated modules to the life cycle cost model for calculation, and outputs the optimized integrated module costs; S4. Calculate the absolute value of cost reduction of the optimized integrated module cost compared to the initial integrated module cost J a and cost reduction rate J b , the absolute value of cost reduction J a and cost reduction rate J b Analyze the value of to obtain the loop instruction; decide whether to loop the S3 process according to the loop instruction; S5. The cloud platform collects all integrated module costs and cost optimization suggestions in the processes of S2, S3 and S4 as result visualization data, visualizes the result visualization data, and outputs the visualization results to the user end.

2. The method for cost analysis of building prefabricated integrated modules based on cloud computing according to claim 1 is characterized in that: Get the initial building assembly integrated module, specific steps: A1. Obtain the functions, performance and specifications of the building assembly integrated module on the user side, combine the functions, performance and specifications of the building assembly integrated module into the demand information of the building assembly integrated module, and send the demand information to the cloud platform for matching; A2. Matching a standard building assembly integrated module with the functional requirements of a building assembly integrated module in the building assembly integrated module database; outputting a first matching result and sending it to A3 matching performance; if there is no matching result, outputting no matching result to the user end; A3. Matching a standard building assembly integrated module with building assembly integrated module performance requirements in the first matching result; outputting a second matching result and feeding it into A4 matching specification; if there is no matching result, outputting no matching result and outputting the first matching result to the user terminal; A4. Match the standard building prefabricated integrated module with the building prefabricated integrated module specification requirements in the second matching result; output the third matching result and use it as the initial building prefabricated integrated module; if there is no matching result, output no matching result and output the second matching result to the user terminal; A5. Input an existing building assembly integrated module as an initial building assembly integrated module at the user end; when receiving an output with no matching result, input the initial building assembly integrated module with reference to the first matching result or the second matching result.

3. The method for cost analysis of building prefabricated integrated modules based on cloud computing according to claim 1 is characterized in that: The life cycle cost model includes the project life cycle decomposition layer, data processing layer and cost analysis layer; The project life cycle decomposition layer is used to match the life cycle phase of the initial building assembly integration module according to the project information of the initial building assembly integration module; The data processing layer is used to match the cost elements corresponding to the initial building prefabricated integrated modules according to the project information of the initial building prefabricated integrated modules, collect the cost data of each life cycle stage according to the cost elements corresponding to the initial building prefabricated integrated modules, pre-process the cost data of each life cycle stage of the building prefabricated integrated modules, and obtain the cost data of the life cycle stage to be calculated; The cost analysis layer is used to calculate the initial integrated module cost of the initial building prefabricated integrated module life cycle using the life cycle cost data to be calculated. The initial integrated module cost includes the cost of each stage and the overall cost.

4. The method for cost analysis of building prefabricated integrated modules based on cloud computing according to claim 3 is characterized in that: Establish a life cycle cost model, specific steps: B1. Determine the life cycle stages of the building assembly integrated module. The complete life cycle stages of the building assembly integrated module include the production material stage, production component stage, production process stage, installation stage, maintenance stage and depreciation stage; B2. Determine the cost elements of each life cycle stage. The cost elements of the production material stage include material costs and material transportation costs; the cost elements of the production component stage are component costs; The cost elements of the production process stage include production labor costs and equipment loss costs; the cost elements of the installation stage include installation labor costs and installation transportation costs; the cost elements of the maintenance stage include daily maintenance costs and damage repair costs; the cost elements of the depreciation stage include depreciation costs after use; B3. The cost data of the production material stage is recorded as C a , C a =x a +y a , x a is the material cost, y a is the material transportation cost; the cost data of the production component stage is recorded as C b , C b is the component cost; the cost data of the production process stage is recorded as C c , C c =(x c +y c )*d1,x c *d1 is the production labor cost, y c *d1 is the equipment loss fee; the cost data of the installation stage is recorded as C d , C d =x d +y d , x d For installation labor costs, y d is the installation and transportation fee; the cost data of the maintenance phase is recorded as C e , C e =(d2 / T)*x d +K, (d2 / T)*x d is the daily maintenance fee, K is the damage repair fee; the depreciation cost is recorded as C f , C f =α*μ*M,C f is the depreciation fee after use, where α is the value loss ratio of the integrated module when it is no longer used, μ is the ratio of the currency when the integrated module is no longer used to the currency when the integrated module was built, and M is the total initial cost of depreciable materials; B4. Collect verification data of several building prefabricated integrated modules. The verification data of building prefabricated integrated modules include the project information and cost of each stage of the building prefabricated integrated modules. Input the project information of the building prefabricated integrated modules into the initial life cycle cost model for verification, and adjust the parameters for calculating the cost data of each life cycle stage based on the cost of each stage.

5. The method for cost analysis of building prefabricated integrated modules based on cloud computing according to claim 3 is characterized in that: The life cycle stages of a complete building prefabricated integrated module include the production material stage, production component stage, production process stage, installation stage, maintenance stage and depreciation stage. If the project information of a given building prefabricated integrated module is missing, the stage cost corresponding to the missing project information is set to 0.

6. The method for cost analysis of building prefabricated integrated modules based on cloud computing according to claim 1, characterized in that: Use the value engineering analysis method to analyze the demand information and integrated module cost of the initial building assembly integrated module. The specific steps are: C1. Obtain the demand information, cost of each stage and overall cost of the initial building assembly integrated module; C2. Check the standard phase cost ratio corresponding to the preset price level of the total cost of the initial building prefabricated integrated module; Calculate the proportion of each stage cost to the overall cost, and calculate the difference between the proportion of each stage cost and the standard stage cost proportion; if the difference exceeds the set range, replace the stage plan in the stage plan library for the corresponding stage; C3. Check the functional requirements and performance requirements in the initial building prefabricated integrated module demand information, and label the performance of each function according to the preset standard performance level table; calculate the average value of the performance levels of all functions as the average performance level, calculate the difference between the performance level of each function and the average performance level, and if the difference exceeds the set ratio, optimize the performance level of the corresponding function; C4. Output the optimized solution as an optimized integrated module; The output of the operation of changing the phase plan and optimizing the performance level is the analysis optimization suggestion.

7. The method for cost analysis of building prefabricated integrated modules based on cloud computing according to claim 1, characterized in that: Determine whether to loop the S3 process based on the loop instruction value. The specific steps are: The total cost of the initial building assembly integrated module is recorded as C0, the total cost of the optimized integrated module obtained by the first optimization is recorded as C1, and the total cost of each optimized integrated module is recorded in turn as C n ; Calculate the absolute value of cost reduction J a =|C n -C n-1 |, calculate the reduction rate J b =(1-C n / C n-1 )*100%; Compare the absolute value of cost reduction J a and cost reduction rate J b Is it greater than the set value? If the cost is reduced by an absolute value J a and cost reduction rate J b If there is a value greater than the set value, the loop instruction is output to start the loop, otherwise the loop stop instruction is output.

8. The method for cost analysis of building prefabricated integrated modules based on cloud computing according to claim 1, characterized in that: Visualize the result data. Specific steps: The visualization results include a cost line graph and a cost data table. The line graph includes a line graph of the overall cost of the integrated module and a line graph of the cost of each stage of the integrated module. Calculate the cost difference and difference ratio of each stage in the upper and lower rows of the cost data table, and output them after the cost of each stage in each row of the table; these two types of data are part of the cost analysis results.

Citation Information

Patent Citations

  • Infrastructure asset management system and / or method

    AU2020100769A4

  • Full chain budget data processing system and method for production infrastructure standard cost system

    CN103679373A