Intelligent monitoring method and system for engineering construction progress based on multi-source data collaboration
Through the method of multi-source data collaboration, intelligent monitoring of construction progress of construction projects is realized, which solves the problems of low efficiency and high cost of construction progress monitoring under traditional inspection methods, and improves the real-time and accuracy of construction management.
Patent Information
- Application Number
- CN202411102679.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-13
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2044-08-13
AI Technical Summary
During the construction of construction projects, traditional inspection methods cannot accurately analyze construction monitoring data, resulting in high cost and low efficiency of construction progress monitoring, and the inability to accurately assess construction status and progress.
An intelligent monitoring method for engineering construction progress based on multi-source data collaboration is adopted to achieve visual analysis and exception identification of construction progress by obtaining construction plan information, data collection, abnormality judgment, progress coefficient calculation and output display.
It improves the comprehensiveness, real-timeness and accuracy of construction management, avoids schedule lags and cost increases, and improves resource utilization efficiency and overall construction efficiency.
Smart Images

Figure CN118627761B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of construction project management, and in particular to an intelligent monitoring method and system for project construction progress based on multi-source data collaboration. Background Art
[0002] During the construction of a building project, the progress monitoring of the project is as important to the project results as the quality and cost of the project. The progress monitoring of the project can clearly and clearly display the status of the project. The construction stage is an important stage in the life cycle of a building. If there is a delay in the construction progress, it will affect the cost and quality of the entire construction project.
[0003] At present, there is still a problem in the monitoring of project construction progress: it is impossible to accurately analyze the project construction monitoring data, and the traditional inspection method for project construction progress monitoring is costly and inefficient, and it is impossible to accurately evaluate the project construction status and analyze the project construction progress based on the project construction status. Summary of the invention
[0004] In order to solve the above technical problems, an intelligent monitoring method and system for engineering construction progress based on multi-source data collaboration are provided. This technical solution solves the problems raised in the above background technology that it is impossible to accurately analyze the engineering construction monitoring data, and that the traditional inspection method for engineering construction progress monitoring is costly and inefficient, and it is impossible to accurately evaluate the engineering construction status and analyze the engineering construction progress according to the engineering construction status.
[0005] In order to achieve the above purpose, the technical solution adopted by the present invention is:
[0006] The intelligent monitoring method of engineering construction progress based on multi-source data collaboration includes:
[0007] Acquire engineering construction plan information, wherein the engineering construction plan information includes engineering task information and construction period plan information;
[0008] According to the project construction plan information, the construction plan is divided into stages to obtain the project construction node information;
[0009] Collect data on the construction status of the project to obtain project construction monitoring data, which includes multi-angle oblique image data, depth image data and panoramic image data of the project;
[0010] According to the project construction monitoring data and project construction node information, determine whether there is any abnormality in the project construction. If so, display the abnormality of the project construction. If not, obtain the historical environmental information of the region and the historical allocation information of project construction resources;
[0011] Obtain the project construction progress coefficient based on the regional historical environmental information and the historical deployment information of project construction resources;
[0012] Obtain construction progress difference information based on construction monitoring data, construction plan information and construction progress coefficient;
[0013] Output and display the difference information of project construction progress.
[0014] Preferably, judging whether the engineering construction is abnormal based on the engineering construction monitoring data and the engineering construction node information specifically includes:
[0015] According to the engineering construction monitoring data, based on the 3D point cloud, the engineering 3D model information is obtained;
[0016] According to the three-dimensional model information of the project, based on the model changes during the construction process, the project construction information is obtained;
[0017] Obtain project construction progress information based on project construction node information and project construction information;
[0018] Acquiring engineering construction environment information, wherein the engineering construction environment information includes construction environment temperature information and construction environment meteorological information;
[0019] According to the engineering construction environment information and engineering construction progress information, obtain the engineering construction abnormality coefficient;
[0020] According to the abnormality coefficient of the project construction, it is judged whether there is any abnormality in the project construction.
[0021] Preferably, obtaining the project construction progress information according to the project construction node information and the project construction information specifically includes:
[0022] According to the engineering 3D model information and the engineering construction plan information, the engineering characteristic 3D point information is obtained;
[0023] Acquiring characteristic standard model information, wherein the characteristic standard model information includes engineering construction resource standard model information and engineering standard model information;
[0024] According to the engineering feature 3D point information and feature model information, a feature model matching index is obtained;
[0025] Based on three-dimensional model recognition, a feature model matching index threshold is obtained;
[0026] Acquire an engineering feature model according to a feature model matching index and a feature model matching index threshold;
[0027] According to the engineering construction information and the engineering characteristic model, the engineering 3D model change data is acquired, wherein the engineering 3D model change data includes engineering construction resource model change data and engineering model change data;
[0028] Acquire engineering construction progress information according to the engineering feature model and engineering 3D model change data, wherein the engineering construction progress information includes engineering progress information and engineering construction resource consumption information;
[0029] Among them, the calculation formula of the feature model matching index is:
[0030] ; Where Q is the feature model matching index, is the feature descriptor of the i-th engineering feature 3D point, is the feature descriptor of the i-th engineering feature 3D point of the feature standard model, To control the matching change rate, is the coordinate of the ith engineering feature 3D point, is the coordinate of the i+1th engineering feature 3D point, is the coordinate of the i+2th engineering feature 3D point, is the coordinate of the ith engineering feature 3D point of the feature standard model, is the coordinate of the i+1th engineering feature 3D point of the feature standard model, is the coordinate of the i+2th engineering feature 3D point of the feature standard model, and n is the total number of engineering feature 3D points.
[0031] Preferably, judging whether the engineering construction is abnormal based on the engineering construction monitoring data and the engineering construction node information specifically includes:
[0032] According to the engineering construction environment information and engineering construction progress information, obtain the engineering construction abnormality coefficient;
[0033] Based on the needs of engineering construction monitoring, obtain the threshold value of engineering construction abnormality coefficient;
[0034] According to the engineering construction abnormality coefficient and the engineering construction abnormality coefficient threshold, it is judged whether the engineering construction is abnormal. If the engineering construction abnormality coefficient is higher than the engineering construction abnormality coefficient threshold, the engineering construction is abnormal. According to the engineering construction abnormality coefficient, the engineering construction abnormality information is obtained;
[0035] Adjust the project construction according to abnormal information of project construction;
[0036] If the engineering construction abnormality coefficient is lower than the engineering construction abnormality coefficient threshold, then there is no abnormality in the engineering construction;
[0037] Among them, the calculation formula of the engineering construction abnormality coefficient is:
[0038] ; In the formula, k is the abnormal coefficient of engineering construction, is the initial value of construction resources, is the value of engineering construction resources, L is the engineering construction resource progress conversion coefficient, T is the construction environment temperature, is the temperature influence coefficient of construction efficiency, is the meteorological intensity of the construction environment, F is the meteorological impact coefficient of construction efficiency, For the progress of the project, is the engineering node coefficient.
[0039] Preferably, obtaining the engineering construction progress difference information according to the engineering construction monitoring information, the engineering construction plan information and the engineering construction progress coefficient specifically includes:
[0040] Acquire historical construction data of the project, wherein the historical construction data of the project includes historical construction progress information of the project and historical construction environment information of the project;
[0041] According to the historical construction data of the project and the historical deployment information of the construction resources, the environmental impact model of the construction project is obtained based on the linear regression model;
[0042] According to the regional historical environment information and the engineering construction environment impact model, obtaining regional historical environment classification information, wherein the regional historical environment classification information includes a first construction environment, a second construction environment, and a third construction environment;
[0043] Acquire engineering construction environment frequency information according to regional historical environment information and regional historical environment classification information, wherein the engineering construction environment frequency information includes a first construction environment frequency, a second construction environment frequency, and a third construction environment frequency;
[0044] Acquire construction environment prediction combination information based on regional historical environmental information and engineering construction plan information, wherein the construction environment prediction combination information includes a plurality of sets of environmental combinations with different temperatures and different weather conditions;
[0045] Obtain the project construction progress coefficient based on the construction environment prediction combination information and the project construction environment frequency information;
[0046] Obtain construction progress difference information based on construction monitoring data, construction plan information and construction progress coefficient;
[0047] Among them, the calculation formula for the project construction progress coefficient is:
[0048] ;W is the construction progress coefficient, is the total engineering quantity of the current engineering node, is the amount of completed construction work, is the remaining time of the current project node, V is the project construction efficiency, Predict the ambient temperature of the jth construction environment combination, is the environmental meteorological intensity of the jth construction environment prediction combination, is the temperature influence coefficient of construction efficiency, F is the meteorological influence coefficient of construction efficiency, is the construction environment frequency of the jth construction environment, and m is the total number of construction environment prediction combinations.
[0049] Preferably, the obtaining of regional historical environment classification information based on regional historical environment information and the project construction environmental impact model specifically includes:
[0050] Obtain the project's historical construction environmental impact index based on the project's historical construction environmental information and the project's construction environmental impact model;
[0051] According to the historical construction progress information of the project, obtain the historical construction progress difference information of the project;
[0052] Match the historical construction progress difference information of the project with the historical construction environmental impact index of the project, remove abnormal data, and obtain the construction environmental impact index set;
[0053] According to the construction environment impact index set, the outlier factor of the construction environment impact index is obtained based on the K nearest neighbor algorithm;
[0054] According to the outlier factor of the construction environment impact index, the first outlier threshold of the construction environment impact index is obtained;
[0055] According to the construction environment impact index set and the first outlier threshold of the construction environment impact index, the outlier data in the construction environment impact index set are aggregated to obtain a second data set of the construction environment impact index;
[0056] According to the second data set of the construction environment impact index, the secondary outlier factor of the construction environment impact index is obtained based on the K nearest neighbor algorithm;
[0057] According to the secondary outlier factor of the construction environment impact index, the second outlier threshold of the construction environment impact index is obtained;
[0058] According to the first outlier threshold of the construction environment impact index and the second outlier threshold of the construction environment impact index, obtaining the construction environment impact index threshold, wherein the construction environment impact index threshold includes the first construction environment impact index threshold and the second construction environment impact index threshold;
[0059] Obtain the construction environmental impact index of the project area based on the regional historical environmental information and the project construction environmental impact model;
[0060] Obtain regional historical environmental classification information based on the construction environmental impact index and the construction environmental impact index threshold;
[0061] Among them, if the construction environment impact index is less than the first threshold of the construction environment impact index, it is the first construction environment; if the construction environment impact index is greater than the first threshold of the construction environment impact index and less than the second threshold of the construction environment impact index, it is the second construction environment; if the construction environment impact index is greater than the second threshold of the construction environment impact index, it is the third construction environment.
[0062] Furthermore, an intelligent monitoring system for construction progress based on multi-source data collaboration is proposed to implement the above-mentioned intelligent monitoring method, including:
[0063] A main control module, the main control module is used to determine whether the construction of the project is abnormal according to the construction monitoring data and the construction node information, obtain the regional historical environment classification information according to the construction environment impact index and the construction environment impact index threshold, obtain the project feature three-dimensional point information according to the project three-dimensional model information and the project construction plan information, obtain the feature model matching index according to the project feature three-dimensional point information and the feature model information, obtain the project construction progress information according to the project feature model and the project three-dimensional model change data, and obtain the project construction progress difference information according to the project construction monitoring data, the project construction plan information and the project construction progress coefficient;
[0064] An information acquisition module, which is used to acquire project construction plan information, project task information and construction period plan information, divide the construction plan into stages according to the project construction plan information, acquire project construction node information, collect data on the project construction status, acquire project construction monitoring data, project multi-angle oblique image data, project depth image data frames and project panoramic image data;
[0065] An evaluation module, the evaluation module is used to obtain regional historical environmental information and historical deployment information of engineering construction resources, obtain the engineering construction progress coefficient based on the regional historical environmental information and the historical deployment information of engineering construction resources, obtain the construction environment prediction combination information based on the regional historical environmental information and engineering construction plan information, and obtain the engineering construction progress coefficient based on the construction environment prediction combination information and engineering construction environment frequency information;
[0066] The display module interacts with the main control module and is used to output abnormal construction signals and construction progress difference information.
[0067] Optionally, the main control module specifically includes:
[0068] A control unit, the control unit is used to obtain the engineering feature three-dimensional point information based on the engineering construction plan information according to the engineering three-dimensional model information, obtain the feature model matching index according to the engineering feature three-dimensional point information and the feature model information, obtain the engineering construction progress information according to the engineering feature model and the engineering three-dimensional model change data, and obtain the engineering construction progress difference information according to the engineering construction monitoring data, the engineering construction plan information and the engineering construction progress coefficient;
[0069] An information receiving unit, which interacts with the information acquisition module and the evaluation module to receive data and transmit it to the judgment unit;
[0070] The judgment unit is used to judge whether there is any abnormality in the construction of the project based on the project construction monitoring data and the project construction node information, and to obtain the regional historical environment classification information based on the construction environment impact index and the construction environment impact index threshold.
[0071] Optionally, the information acquisition module specifically includes:
[0072] A first acquisition unit, the first acquisition unit is used to acquire project construction plan information, project task information and construction period plan information, divide the construction plan into stages according to the project construction plan information, and acquire project construction node information;
[0073] The second acquisition unit is used to collect data on the construction status of the project, and acquire the project construction monitoring data, the project multi-angle oblique image data, the project depth image data and the project panoramic image data.
[0074] Optionally, the evaluation module specifically includes:
[0075] A construction anomaly assessment unit, the construction anomaly assessment unit is used to obtain regional historical environmental information and historical deployment information of project construction resources, and obtain a project construction progress coefficient based on the regional historical environmental information and the historical deployment information of project construction resources;
[0076] The construction progress assessment unit is used to obtain construction environment prediction combination information based on regional historical environment information and engineering construction plan information, and to obtain the engineering construction progress coefficient based on the construction environment prediction combination information and engineering construction environment frequency information.
[0077] Compared with the prior art, the present invention has the following beneficial effects:
[0078] The present invention proposes an intelligent monitoring method and system for engineering construction progress based on multi-source data collaboration. Through the engineering three-dimensional model information, a visual analysis of the engineering construction status is realized. Through the engineering construction abnormality coefficient, abnormal conditions of the engineering construction are timely identified, which avoids delays in engineering progress and cost increases, and improves resource utilization efficiency. Through the engineering construction progress coefficient, early warning of construction delays and engineering progress abnormalities is provided, which improves the comprehensiveness, real-timeness and accuracy of construction management, and improves the overall construction efficiency and quality. BRIEF DESCRIPTION OF THE DRAWINGS
[0079] Figure 1 This is a flow chart of the intelligent monitoring method for engineering construction progress based on multi-source data collaboration proposed by the present invention;
[0080] Figure 2 A flowchart for obtaining an abnormal coefficient of engineering construction of the present invention;
[0081] Figure 3 A flowchart for obtaining construction progress information in the present invention;
[0082] Figure 4 It is a flow chart for obtaining construction progress difference information in the present invention;
[0083] Figure 5 This is a structural block diagram of the intelligent monitoring system for engineering construction progress based on multi-source data collaboration proposed by the present invention. DETAILED DESCRIPTION
[0084] The following description is used to disclose the present invention so that those skilled in the art can implement the present invention. The preferred embodiments described below are only examples, and those skilled in the art may think of other obvious variations.
[0085] Reference Figure 1 - Figure 4 As shown, the intelligent monitoring method for engineering construction progress based on multi-source data collaboration in an embodiment of the present invention includes:
[0086] Acquire engineering construction plan information, wherein the engineering construction plan information includes engineering task information and construction period plan information;
[0087] According to the project construction plan information, the construction plan is divided into stages to obtain the project construction node information;
[0088] Collect data on the construction status of the project to obtain project construction monitoring data, which includes multi-angle oblique image data, depth image data and panoramic image data of the project;
[0089] According to the project construction monitoring data and project construction node information, determine whether there is any abnormality in the project construction. If so, display the abnormality of the project construction. If not, obtain the historical environmental information of the region and the historical allocation information of project construction resources;
[0090] Specifically, based on the project construction monitoring data and project construction node information, determine whether there is any abnormality in the project construction, including:
[0091] According to the engineering construction monitoring data, based on the 3D point cloud, the engineering 3D model information is obtained;
[0092] According to the three-dimensional model information of the project, based on the model changes during the construction process, the project construction information is obtained;
[0093] Obtain project construction progress information based on project construction node information and project construction information;
[0094] Acquiring engineering construction environment information, wherein the engineering construction environment information includes construction environment temperature information and construction environment meteorological information;
[0095] According to the engineering construction environment information and engineering construction progress information, obtain the engineering construction abnormality coefficient;
[0096] Based on the needs of engineering construction monitoring, obtain the threshold value of engineering construction abnormality coefficient;
[0097] According to the engineering construction abnormality coefficient and the engineering construction abnormality coefficient threshold, it is judged whether the engineering construction is abnormal. If the engineering construction abnormality coefficient is higher than the engineering construction abnormality coefficient threshold, the engineering construction is abnormal. According to the engineering construction abnormality coefficient, the engineering construction abnormality information is obtained;
[0098] Adjust the project construction according to abnormal information of project construction;
[0099] If the engineering construction abnormality coefficient is lower than the engineering construction abnormality coefficient threshold, then there is no abnormality in the engineering construction;
[0100] Among them, the calculation formula of the engineering construction abnormality coefficient is:
[0101] ; In the formula, k is the abnormal coefficient of engineering construction, is the initial value of construction resources, is the value of engineering construction resources, L is the engineering construction resource progress conversion coefficient, T is the construction environment temperature, is the temperature influence coefficient of construction efficiency, is the meteorological intensity of the construction environment, F is the meteorological impact coefficient of construction efficiency, For the progress of the project, is the engineering node coefficient.
[0102] In this solution, the three-dimensional model information of the project is obtained based on the three-dimensional point cloud through the project construction monitoring data, and the visual analysis of the project construction status is realized. According to the three-dimensional model information of the project and the change status of the construction process model, the project construction information, the project construction node information and the project construction information are obtained, and the project construction progress information is obtained. According to the project construction environment information and the project construction progress information, the project construction abnormality coefficient is obtained. According to the project construction abnormality coefficient and the project construction abnormality coefficient threshold, it is judged whether the project construction is abnormal, and the abnormal situation of the project construction is identified in time, which avoids the delay of the project progress and the increase of cost, improves the resource utilization efficiency, and reduces the construction cost.
[0103] It can be understood that in the actual construction process, the consumption of construction resources such as construction cement, construction steel and other construction materials is proportional to the progress of the construction. If the ratio of the construction progress to the consumption of construction resources does not meet the construction standard, the construction will be abnormal. In this embodiment, the threshold value of the abnormal coefficient of the construction is 1.15;
[0104] It should be noted that the conversion relationship between construction resources and construction progress is often affected by construction efficiency, and construction efficiency has a direct impact on the construction environment. The temperature and weather during the construction process have a great impact on construction efficiency. For example, rainy and snowy weather, cold weather, hot weather, etc. will cause a decrease in construction efficiency.
[0105] Specifically, according to the project construction node information and project construction information, the project construction progress information is obtained, including:
[0106] According to the engineering 3D model information and the engineering construction plan information, the engineering characteristic 3D point information is obtained;
[0107] Acquiring characteristic standard model information, wherein the characteristic standard model information includes engineering construction resource standard model information and engineering standard model information;
[0108] According to the engineering feature 3D point information and feature model information, a feature model matching index is obtained;
[0109] Based on three-dimensional model recognition, a feature model matching index threshold is obtained;
[0110] Acquire an engineering feature model according to a feature model matching index and a feature model matching index threshold;
[0111] According to the engineering construction information and the engineering characteristic model, the engineering 3D model change data is acquired, wherein the engineering 3D model change data includes engineering construction resource model change data and engineering model change data;
[0112] Acquire engineering construction progress information according to the engineering feature model and engineering 3D model change data, wherein the engineering construction progress information includes engineering progress information and engineering construction resource consumption information;
[0113] Among them, the calculation formula of the feature model matching index is:
[0114] ; Where Q is the feature model matching index, is the feature descriptor of the i-th engineering feature 3D point, is the feature descriptor of the i-th engineering feature 3D point of the feature standard model, To control the matching change rate, is the coordinate of the ith engineering feature 3D point, is the coordinate of the i+1th engineering feature 3D point, is the coordinate of the i+2th engineering feature 3D point, is the coordinate of the ith engineering feature 3D point of the feature standard model, is the coordinate of the i+1th engineering feature 3D point of the feature standard model, is the coordinate of the i+2th engineering feature 3D point of the feature standard model, and n is the total number of engineering feature 3D points.
[0115] In this solution, the feature model matching index is obtained through the engineering feature 3D point information and feature model information, the engineering feature model is obtained according to the feature model matching index and the feature model matching index threshold, the engineering 3D model change data is obtained according to the engineering construction information and the engineering feature model, and the engineering construction progress information is obtained according to the engineering feature model and the engineering 3D model change data;
[0116] It is understandable that there is a lot of interference information mixed in the engineering construction monitoring data, and it is impossible to directly analyze the engineering construction monitoring data. Through the engineering construction monitoring data, a three-dimensional model of the engineering construction is established. By identifying the model, the construction project model and engineering construction resource model, etc. are accurately identified. Then, by analyzing the changes in the engineering characteristic model, the progress of the engineering construction and the consumption of engineering construction resources are obtained.
[0117] Obtain the project construction progress coefficient based on the regional historical environmental information and the historical deployment information of project construction resources;
[0118] Obtain construction progress difference information based on construction monitoring data, construction plan information and construction progress coefficient;
[0119] Specifically, according to the engineering construction monitoring information, engineering construction plan information and engineering construction progress coefficient, the engineering construction progress difference information is obtained, including:
[0120] Acquire historical construction data of the project, wherein the historical construction data of the project includes historical construction progress information of the project and historical construction environment information of the project;
[0121] According to the historical construction data of the project and the historical deployment information of the construction resources, the environmental impact model of the project construction is obtained based on the linear regression model;
[0122] According to the regional historical environment information and the engineering construction environment impact model, obtaining regional historical environment classification information, wherein the regional historical environment classification information includes a first construction environment, a second construction environment, and a third construction environment;
[0123] Acquire engineering construction environment frequency information according to regional historical environment information and regional historical environment classification information, wherein the engineering construction environment frequency information includes a first construction environment frequency, a second construction environment frequency, and a third construction environment frequency;
[0124] Acquire construction environment prediction combination information based on regional historical environmental information and engineering construction plan information, wherein the construction environment prediction combination information includes a plurality of sets of environmental combinations with different temperatures and different weather conditions;
[0125] Obtain the project construction progress coefficient based on the construction environment prediction combination information and the project construction environment frequency information;
[0126] Obtain construction progress difference information based on construction monitoring data, construction plan information and construction progress coefficient;
[0127] Among them, the calculation formula for the project construction progress coefficient is:
[0128] ;W is the construction progress coefficient, is the total engineering quantity of the current engineering node, is the amount of completed construction work, is the remaining time of the current project node, V is the project construction efficiency, Predict the ambient temperature of the jth construction environment combination, is the environmental meteorological intensity of the jth construction environment prediction combination, is the temperature influence coefficient of construction efficiency, F is the meteorological influence coefficient of construction efficiency, is the construction environment frequency of the jth construction environment, and m is the total number of construction environment prediction combinations.
[0129] In this scheme, the project construction environment impact model is obtained based on the linear regression model through the historical construction data of the project and the historical deployment information of the project construction resources. The linear regression model is trained to accurately analyze the impact of different temperatures and weather on construction efficiency. The historical environment of the project construction area is analyzed to divide the regional historical environment information into the first construction environment, the second construction environment and the third construction environment. According to the regional historical environment information and the regional historical environment classification information, the project construction environment frequency information is obtained, that is, the project construction environment frequency information includes the first construction environment frequency, the second construction environment frequency and the third construction environment frequency. According to the regional historical environment information, the regional environmental temperature range and the regional environmental meteorological type are obtained. At intervals of 5°C, the regional environmental temperature and the regional environmental meteorological are combined to obtain the construction environment prediction combination information. According to the construction environment prediction combination information and the project construction environment frequency information, the project construction progress coefficient is obtained. According to the project construction progress coefficient, construction delays and abnormal project progress are warned in advance, which improves the comprehensiveness, real-timeness and accuracy of construction management, and improves the overall construction efficiency and quality.
[0130] Among them, according to the engineering construction monitoring data, engineering construction plan information and engineering construction progress coefficient, the engineering construction progress difference information is obtained, specifically:
[0131] like , the construction progress of the project is normal. , then the construction progress of the project is warned, and the construction progress is adjusted according to the construction progress coefficient. , then the construction progress of the project is abnormal.
[0132] It can be understood that the daily environmental data of the construction area of the project is used as the basic data, and the environmental data of one month is used as the cycle. The environmental data in one month is divided into the first construction environment, the second construction environment and the third construction environment, and the number of days each construction environment appears is used as the frequency of the first construction environment, the frequency of the second construction environment and the frequency of the third construction environment;
[0133] It should be noted that, in the construction environment prediction combination information, if the construction environment impact index is greater than twice the second threshold of the construction environment impact index, then this set of construction environment prediction combinations cannot be used and is removed.
[0134] Specifically, according to the regional historical environment information and the project construction environmental impact model, the regional historical environment classification information is obtained, including:
[0135] Obtain the project's historical construction environmental impact index based on the project's historical construction environmental information and the project's construction environmental impact model;
[0136] According to the historical construction progress information of the project, obtain the historical construction progress difference information of the project;
[0137] Match the historical construction progress difference information of the project with the historical construction environmental impact index of the project, remove abnormal data, and obtain the construction environmental impact index set;
[0138] According to the construction environment impact index set, the outlier factor of the construction environment impact index is obtained based on the K nearest neighbor algorithm;
[0139] According to the outlier factor of the construction environment impact index, the first outlier threshold of the construction environment impact index is obtained;
[0140] According to the construction environment impact index set and the first outlier threshold of the construction environment impact index, the outlier data in the construction environment impact index set are aggregated to obtain a second data set of the construction environment impact index;
[0141] According to the second data set of the construction environment impact index, the secondary outlier factor of the construction environment impact index is obtained based on the K nearest neighbor algorithm;
[0142] According to the secondary outlier factor of the construction environment impact index, the second outlier threshold of the construction environment impact index is obtained;
[0143] According to the first outlier threshold of the construction environment impact index and the second outlier threshold of the construction environment impact index, obtaining the construction environment impact index threshold, wherein the construction environment impact index threshold includes the first construction environment impact index threshold and the second construction environment impact index threshold;
[0144] Obtain the construction environmental impact index of the project area based on the regional historical environmental information and the project construction environmental impact model;
[0145] Obtain regional historical environmental classification information based on the construction environmental impact index and the construction environmental impact index threshold;
[0146] Among them, if the construction environment impact index is less than the first threshold of the construction environment impact index, it is the first construction environment; if the construction environment impact index is greater than the first threshold of the construction environment impact index and less than the second threshold of the construction environment impact index, it is the second construction environment; if the construction environment impact index is greater than the second threshold of the construction environment impact index, it is the third construction environment.
[0147] In this scheme, by matching the historical construction progress difference information of the project with the historical construction environmental impact index of the project, the abnormal data is removed, and the construction environmental impact index set is obtained. According to the construction environmental impact index set, based on the K nearest neighbor algorithm, the outlier factor of the construction environmental impact index is obtained. According to the outlier factor of the construction environmental impact index, the first outlier threshold of the construction environmental impact index is obtained, and the first outlier threshold of the construction environmental impact index is used as the first threshold of the construction environmental impact index. According to the first outlier threshold of the construction environmental impact index, the construction environmental impact index set is cleaned, the outlier data in the construction environmental impact index set is selected, and the data is used as a data set again for outlier data identification, and the second outlier threshold of the construction environmental impact index is obtained. The second outlier threshold of the construction environmental impact index is used as the second threshold of the construction environmental impact index. The regional historical environmental information is classified according to the construction environmental impact index threshold.
[0148] Output and display the difference information of project construction progress.
[0149] Reference Figure 5 As shown, further, combined with the above-mentioned intelligent monitoring method for engineering construction progress based on multi-source data collaboration, an intelligent monitoring system for engineering construction progress based on multi-source data collaboration is proposed, including:
[0150] A main control module, the main control module is used to determine whether the construction of the project is abnormal according to the construction monitoring data and the construction node information, obtain the regional historical environment classification information according to the construction environment impact index and the construction environment impact index threshold, obtain the project feature three-dimensional point information according to the project three-dimensional model information and the project construction plan information, obtain the feature model matching index according to the project feature three-dimensional point information and the feature model information, obtain the project construction progress information according to the project feature model and the project three-dimensional model change data, and obtain the project construction progress difference information according to the project construction monitoring data, the project construction plan information and the project construction progress coefficient;
[0151] An information acquisition module, which is used to acquire project construction plan information, project task information and construction period plan information, divide the construction plan into stages according to the project construction plan information, acquire project construction node information, collect data on the project construction status, acquire project construction monitoring data, project multi-angle oblique image data, project depth image data frames and project panoramic image data;
[0152] An evaluation module, the evaluation module is used to obtain regional historical environmental information and historical deployment information of engineering construction resources, obtain the engineering construction progress coefficient based on the regional historical environmental information and the historical deployment information of engineering construction resources, obtain the construction environment prediction combination information based on the regional historical environmental information and engineering construction plan information, and obtain the engineering construction progress coefficient based on the construction environment prediction combination information and engineering construction environment frequency information;
[0153] The display module interacts with the main control module and is used to output abnormal construction signals and construction progress difference information.
[0154] Main control module, specifically including:
[0155] A control unit, the control unit is used to obtain the engineering feature three-dimensional point information based on the engineering construction plan information according to the engineering three-dimensional model information, obtain the feature model matching index according to the engineering feature three-dimensional point information and the feature model information, obtain the engineering construction progress information according to the engineering feature model and the engineering three-dimensional model change data, and obtain the engineering construction progress difference information according to the engineering construction monitoring data, the engineering construction plan information and the engineering construction progress coefficient;
[0156] An information receiving unit, which interacts with the information acquisition module and the evaluation module to receive data and transmit it to the judgment unit;
[0157] The judgment unit is used to judge whether there is any abnormality in the construction of the project based on the project construction monitoring data and the project construction node information, and to obtain the regional historical environment classification information based on the construction environment impact index and the construction environment impact index threshold.
[0158] Information acquisition module, specifically including:
[0159] A first acquisition unit, the first acquisition unit is used to acquire project construction plan information, project task information and construction period plan information, divide the construction plan into stages according to the project construction plan information, and acquire project construction node information;
[0160] The second acquisition unit is used to collect data on the construction status of the project, and acquire the project construction monitoring data, the project multi-angle oblique image data, the project depth image data and the project panoramic image data.
[0161] Assessment modules include:
[0162] A construction anomaly assessment unit, the construction anomaly assessment unit is used to obtain regional historical environmental information and historical deployment information of project construction resources, and obtain a project construction progress coefficient based on the regional historical environmental information and the historical deployment information of project construction resources;
[0163] The construction progress assessment unit is used to obtain construction environment prediction combination information based on regional historical environment information and engineering construction plan information, and to obtain the engineering construction progress coefficient based on the construction environment prediction combination information and engineering construction environment frequency information.
[0164] To sum up, the advantages of the present invention are: through the engineering construction monitoring data, based on the three-dimensional point cloud, the engineering three-dimensional model information is obtained, and the visual analysis of the engineering construction status is realized; through the engineering construction environment information and the engineering construction progress information, the engineering construction abnormality coefficient is obtained, and the engineering construction abnormality is timely identified through the engineering construction abnormality coefficient, thereby avoiding delays in the progress of the project and increased costs, improving the efficiency of resource utilization, and reducing construction costs; through the construction environment prediction combination information and the engineering construction environment frequency information, the engineering construction progress coefficient is obtained, and the construction delay and engineering progress abnormality are warned in advance through the engineering construction progress coefficient, thereby improving the comprehensiveness, real-timeness and accuracy of construction management, and improving the overall construction efficiency and quality.
[0165] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions only describe the principles of the present invention. The present invention may be subject to various changes and improvements without departing from the spirit and scope of the present invention. These changes and improvements fall within the scope of the present invention. The scope of protection claimed by the present invention is defined by the attached claims and their equivalents.
Claims
1. An intelligent monitoring method for construction progress based on multi-source data collaboration, characterized in that: include: Acquire engineering construction plan information, wherein the engineering construction plan information includes engineering task information and construction period plan information; According to the project construction plan information, the construction plan is divided into stages to obtain the project construction node information; Collect data on the construction status of the project to obtain project construction monitoring data, which includes multi-angle oblique image data, depth image data and panoramic image data of the project; According to the project construction monitoring data and project construction node information, determine whether there is any abnormality in the project construction. If so, display the abnormality of the project construction. If not, obtain the historical environmental information of the region and the historical allocation information of project construction resources; Obtain the project construction progress coefficient based on the regional historical environmental information and the historical deployment information of project construction resources; Obtain construction progress difference information based on construction monitoring data, construction plan information and construction progress coefficient; Output and display the difference information of project construction progress; The determining whether the engineering construction is abnormal based on the engineering construction monitoring data and the engineering construction node information specifically includes: According to the engineering construction monitoring data, based on the 3D point cloud, the engineering 3D model information is obtained; According to the three-dimensional model information of the project, based on the model changes during the construction process, the project construction information is obtained; Obtain project construction progress information based on project construction node information and project construction information; Acquiring engineering construction environment information, wherein the engineering construction environment information includes construction environment temperature information and construction environment meteorological information; According to the engineering construction environment information and engineering construction progress information, obtain the engineering construction abnormality coefficient; According to the abnormal coefficient of engineering construction, determine whether there is any abnormality in the engineering construction; The obtaining of the project construction progress information according to the project construction node information and the project construction information specifically includes: According to the engineering 3D model information and the engineering construction plan information, the engineering characteristic 3D point information is obtained; Acquiring characteristic standard model information, wherein the characteristic standard model information includes engineering construction resource standard model information and engineering standard model information; According to the engineering feature 3D point information and feature model information, a feature model matching index is obtained; Based on three-dimensional model recognition, a feature model matching index threshold is obtained; Acquire an engineering feature model according to a feature model matching index and a feature model matching index threshold; According to the engineering construction information and the engineering characteristic model, the engineering 3D model change data is acquired, wherein the engineering 3D model change data includes engineering construction resource model change data and engineering model change data; Acquire engineering construction progress information according to the engineering feature model and engineering 3D model change data, wherein the engineering construction progress information includes engineering progress information and engineering construction resource consumption information; Among them, the calculation formula of the feature model matching index is: ; Where Q is the feature model matching index, is the feature descriptor of the i-th engineering feature 3D point, is the feature descriptor of the i-th engineering feature 3D point of the feature standard model, To control the matching change rate, is the coordinate of the ith engineering feature 3D point, is the coordinate of the i+1th engineering feature 3D point, is the coordinate of the i+2th engineering feature 3D point, is the coordinate of the ith engineering feature 3D point of the feature standard model, is the coordinate of the i+1th engineering feature 3D point of the feature standard model, is the coordinate of the i+2th engineering feature 3D point of the feature standard model, and n is the total number of engineering feature 3D points; The determining whether the engineering construction is abnormal based on the engineering construction monitoring data and the engineering construction node information specifically includes: According to the engineering construction environment information and engineering construction progress information, obtain the engineering construction abnormality coefficient; Based on the needs of engineering construction monitoring, obtain the threshold value of engineering construction abnormality coefficient; According to the engineering construction abnormality coefficient and the engineering construction abnormality coefficient threshold, it is judged whether the engineering construction is abnormal. If the engineering construction abnormality coefficient is higher than the engineering construction abnormality coefficient threshold, the engineering construction is abnormal. According to the engineering construction abnormality coefficient, the engineering construction abnormality information is obtained; Adjust the project construction according to the abnormal information of project construction; If the engineering construction abnormality coefficient is lower than the engineering construction abnormality coefficient threshold, then there is no abnormality in the engineering construction; Among them, the calculation formula of the engineering construction abnormality coefficient is: ; In the formula, k is the abnormal coefficient of engineering construction, is the initial value of construction resources, is the construction resource value, is the construction resource progress conversion coefficient, is the construction environment temperature, is the temperature influence coefficient of construction efficiency, is the meteorological intensity of the construction environment, F is the meteorological impact coefficient of construction efficiency, For the progress of the project, is the engineering node coefficient; The obtaining of construction progress difference information according to the construction monitoring information, construction plan information and construction progress coefficient specifically includes: Acquire historical construction data of the project, wherein the historical construction data of the project includes historical construction progress information of the project and historical construction environment information of the project; According to the historical construction data of the project and the historical deployment information of the construction resources, the environmental impact model of the construction project is obtained based on the linear regression model; According to the regional historical environment information and the engineering construction environment impact model, obtaining regional historical environment classification information, wherein the regional historical environment classification information includes a first construction environment, a second construction environment, and a third construction environment; Acquire engineering construction environment frequency information according to regional historical environment information and regional historical environment classification information, wherein the engineering construction environment frequency information includes a first construction environment frequency, a second construction environment frequency, and a third construction environment frequency; Acquire construction environment prediction combination information based on regional historical environmental information and engineering construction plan information, wherein the construction environment prediction combination information includes a plurality of sets of environmental combinations with different temperatures and different weather conditions; Obtain the project construction progress coefficient based on the construction environment prediction combination information and the project construction environment frequency information; Obtain construction progress difference information based on construction monitoring data, construction plan information and construction progress coefficient; Among them, the calculation formula for the project construction progress coefficient is: ;W is the construction progress coefficient, is the total engineering quantity of the current engineering node, is the amount of construction completed, is the remaining time of the current project node, V is the project construction efficiency, Predict the ambient temperature of the jth construction environment combination, is the environmental meteorological intensity of the jth construction environment prediction combination, is the temperature influence coefficient of construction efficiency, F is the meteorological influence coefficient of construction efficiency, is the construction environment frequency of the jth construction environment, and m is the total number of construction environment prediction combinations.
2. The method for intelligent monitoring of construction progress based on multi-source data collaboration according to claim 1 is characterized in that: The obtaining of regional historical environment classification information based on regional historical environment information and the project construction environmental impact model specifically includes: Obtain the project's historical construction environmental impact index based on the project's historical construction environmental information and the project's construction environmental impact model; According to the historical construction progress information of the project, obtain the historical construction progress difference information of the project; Match the historical construction progress difference information of the project with the historical construction environmental impact index of the project, remove abnormal data, and obtain the construction environmental impact index set; According to the construction environment impact index set, the outlier factor of the construction environment impact index is obtained based on the K nearest neighbor algorithm; According to the outlier factor of the construction environment impact index, the first outlier threshold of the construction environment impact index is obtained; According to the construction environment impact index set and the first outlier threshold of the construction environment impact index, the outlier data in the construction environment impact index set are aggregated to obtain a second data set of the construction environment impact index; According to the second data set of the construction environment impact index, the secondary outlier factor of the construction environment impact index is obtained based on the K nearest neighbor algorithm; According to the secondary outlier factor of the construction environment impact index, the second outlier threshold of the construction environment impact index is obtained; According to the first outlier threshold of the construction environment impact index and the second outlier threshold of the construction environment impact index, obtaining the construction environment impact index threshold, wherein the construction environment impact index threshold includes the first construction environment impact index threshold and the second construction environment impact index threshold; Obtain the construction environmental impact index of the project area based on the regional historical environmental information and the project construction environmental impact model; Obtain regional historical environmental classification information based on the construction environmental impact index and the construction environmental impact index threshold; Among them, if the construction environment impact index is less than the first threshold of the construction environment impact index, it is the first construction environment; if the construction environment impact index is greater than the first threshold of the construction environment impact index and less than the second threshold of the construction environment impact index, it is the second construction environment; if the construction environment impact index is greater than the second threshold of the construction environment impact index, it is the third construction environment.
3. An intelligent monitoring system for construction progress based on multi-source data collaboration, used to implement the intelligent monitoring method according to any one of claims 1 to 2, characterized in that: include: A main control module, the main control module is used to determine whether the construction of the project is abnormal according to the construction monitoring data and the construction node information, obtain the regional historical environment classification information according to the construction environment impact index and the construction environment impact index threshold, obtain the project feature three-dimensional point information according to the project three-dimensional model information and the project construction plan information, obtain the feature model matching index according to the project feature three-dimensional point information and the feature model information, obtain the project construction progress information according to the project feature model and the project three-dimensional model change data, and obtain the project construction progress difference information according to the project construction monitoring data, the project construction plan information and the project construction progress coefficient; An information acquisition module, which is used to acquire project construction plan information, project task information and construction period plan information, divide the construction plan into stages according to the project construction plan information, acquire project construction node information, collect data on the project construction status, acquire project construction monitoring data, project multi-angle oblique image data, project depth image data frames and project panoramic image data; An evaluation module, the evaluation module is used to obtain regional historical environmental information and historical deployment information of engineering construction resources, obtain the engineering construction progress coefficient based on the regional historical environmental information and the historical deployment information of engineering construction resources, obtain the construction environment prediction combination information based on the regional historical environmental information and engineering construction plan information, and obtain the engineering construction progress coefficient based on the construction environment prediction combination information and engineering construction environment frequency information; The display module interacts with the main control module and is used to output abnormal construction signals and construction progress difference information.
4. The intelligent monitoring system for construction progress based on multi-source data collaboration according to claim 3 is characterized in that: The main control module specifically includes: A control unit, the control unit is used to obtain the engineering feature three-dimensional point information based on the engineering construction plan information according to the engineering three-dimensional model information, obtain the feature model matching index according to the engineering feature three-dimensional point information and the feature model information, obtain the engineering construction progress information according to the engineering feature model and the engineering three-dimensional model change data, and obtain the engineering construction progress difference information according to the engineering construction monitoring data, the engineering construction plan information and the engineering construction progress coefficient; An information receiving unit, which interacts with the information acquisition module and the evaluation module to receive data and transmit it to the judgment unit; The judgment unit is used to judge whether there is any abnormality in the construction of the project based on the project construction monitoring data and the project construction node information, and to obtain the regional historical environment classification information based on the construction environment impact index and the construction environment impact index threshold.
5. The intelligent monitoring system for construction progress based on multi-source data collaboration according to claim 3 is characterized in that: The information acquisition module specifically includes: A first acquisition unit, the first acquisition unit is used to acquire project construction plan information, project task information and construction period plan information, divide the construction plan into stages according to the project construction plan information, and acquire project construction node information; The second acquisition unit is used to collect data on the construction status of the project, and acquire the project construction monitoring data, the project multi-angle oblique image data, the project depth image data and the project panoramic image data.
6. The intelligent monitoring system for construction progress based on multi-source data collaboration according to claim 3 is characterized in that: The evaluation module specifically includes: A construction anomaly assessment unit, the construction anomaly assessment unit is used to obtain regional historical environmental information and historical deployment information of project construction resources, and obtain a project construction progress coefficient based on the regional historical environmental information and the historical deployment information of project construction resources; The construction progress assessment unit is used to obtain construction environment prediction combination information based on regional historical environment information and engineering construction plan information, and to obtain the engineering construction progress coefficient based on the construction environment prediction combination information and engineering construction environment frequency information.