Configuration method and system for network-building type energy storage and distributed phase modifier under short-circuit ratio constraint

By establishing a model with linear constraints on the short-circuit ratio of multiple stations, the problem of inconsistent configurations of networked energy storage and distributed condensers in the existing technology is solved, and the optimal configuration of large-scale wind and photovoltaic bases is realized, simplifying the calculation process and reducing the cost. reduce operation and maintenance costs.

CN118739418AActive Publication Date: 2024-10-01ELECTRIC POWER RESEARCH INSTITUTE OF STATE GRID NINGXIA ELECTRIC POWER COMPANY +2

Patent Information

Application Number
CN202410731453.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-06
Publication Date
2024-10-01
Estimated Expiration
2044-06-06

AI Technical Summary

Technical Problem

When configuring distributed condensers and network-type energy storage in large-scale wind and photovoltaic power bases, the existing technology fails to effectively consider the effect of network-type energy storage on improving the short-circuit ratio of multiple sites, resulting in inconsistent planning plans and actual conditions, and requires It requires multiple manual optimizations and the calculation process is cumbersome.

Method used

A method for optimizing the configuration of network-type energy storage and distributed condensers that takes into account the linearization constraints of short-circuit ratios of multiple stations is proposed. By establishing short-circuit capacity and short-circuit ratio models, it is transformed into a linear programming problem to achieve network-type energy storage and Optimized configuration of distributed condensers to avoid iterative calculations.

Benefits of technology

It realizes the optimal configuration of networked energy storage and distributed condensers, simplifies the calculation process, reduces operation and maintenance costs, and meets the conservative requirements of engineering applications.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118739418A_ABST
    Figure CN118739418A_ABST
Patent Text Reader

Abstract

The invention discloses a method and a system for configuring network-constructed energy storage and a distributed phase modifier under the constraint of a short-circuit ratio, and the method comprises the steps: obtaining a short-circuit current at a bus of a new energy station, and building a short-circuit capacity model at a grid-connected bus of the new energy station after the configuration of the distributed phase modifier or the network-constructed energy storage; based on the short-circuit ratio model at the bus of the new energy station, establishing a short-circuit ratio model at the grid-connected bus of the new energy station after configuration of the distributed phase modifier or network-building energy storage and constraint conditions of the short-circuit ratio model; establishing a new energy multi-station short-circuit ratio constraint after configuration of the distributed phase modifier or network construction type energy storage; the optimal comprehensive cost for configuring a distributed phase modifier or constructing network type energy storage is used as a target function; an optimal configuration model of the distributed phase modifier or the network-building type energy storage is formed by the target function, the number constraint and the capacity constraint of configuration of the distributed phase modifier or the network-building type energy storage and the new energy multi-station short-circuit ratio dynamic constraint; and iteratively solving to obtain a configuration result of the network construction type energy storage and the distributed phase modifier under the constraint of the short-circuit ratio, and realizing optimal configuration.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power systems, and in particular to a method and system for optimizing the configuration of grid-connected energy storage and distributed phase regulators taking into account short-circuit ratio linearization constraints of multiple stations. Background Art

[0002] At present, large-scale wind and photovoltaic bases are concentrated in areas with relatively weak grids. The inertia and damping characteristics of local power grids show a downward trend, and the dynamic reactive power support capacity is insufficient. Its new energy carrying strength (new energy multi-station short-circuit ratio) is insufficient, which is easy to cause transient overvoltage, broadband oscillation and other problems. Active support equipment such as distributed phase-shifting or grid-type energy storage is required. Among them, grid-type energy storage can improve the grid regulation and support capabilities, grid short-circuit capacity and new energy multi-station short-circuit ratio. It has good stability under weak grids and can help solve the problem of "hollowing out" of support capacity in new energy-rich areas. Considering the mandatory energy storage configuration policies of various localities, major energy storage manufacturers are currently promoting the application of grid-type energy storage. Ignoring the role of grid-type energy storage and configuring large-scale distributed phase-shifting, the planning and operation and maintenance costs are unbearable. It is urgent to achieve the optimal configuration of grid-type energy storage and distributed phase-shifting.

[0003] In the prior art, the distributed phase-shifting optimization configuration model in the new energy cluster based on the short-circuit ratio of new energy multi-stations is to first determine the equivalent apparent power of each current source in the new energy cluster based on the self-impedance or mutual impedance between each current source in the new energy cluster under the determined distributed phase-shifting configuration scheme; then determine the multi-station short-circuit ratio of each current source in the new energy cluster based on the equivalent apparent power of each current source in the new energy cluster and the short-circuit capacity of the grid-connected point of each current source; finally, determine whether the calculated multi-station short-circuit ratio meets the requirements, if not, continuously adjust the distributed phase-shifting configuration scheme, and calculate the multi-station short-circuit ratio after adjusting the distributed phase-shifting configuration scheme again, until the multi-station short-circuit ratio finally meets a certain limit requirement and then stop the iterative calculation, at which time the distributed phase-shifting configuration scheme is the optimal distributed phase-shifting configuration scheme that meets the multi-station short-circuit ratio. However, the existing technology does not consider the effect of grid-type energy storage on improving the short-circuit ratio of multiple stations, and the planning scheme is inconsistent with the actual planning scheme of transient reactive support equipment in large-scale wind and photovoltaic bases, and cannot achieve the optimal configuration of large-scale grid-type energy storage and distributed phase-shifting devices in large-scale wind and photovoltaic bases; at the same time, when optimizing the configuration of transient reactive support equipment based on the short-circuit ratio constraints of multiple stations, it is often necessary to manually optimize the configuration scheme multiple times. Each time the scheme is adjusted, the short-circuit ratio of multiple stations must be calculated once, and it needs to be continuously iterated until the short-circuit ratio constraints of multiple stations are met. The calculation process is relatively cumbersome. Summary of the invention

[0004] In order to solve the deficiencies in the prior art, the present invention provides a method and system for optimizing the configuration of grid-type energy storage and distributed phase condensers taking into account the linearization constraints of the short-circuit ratios of multiple stations, taking into account the improvement effect of the short-circuit ratios of multiple stations by grid-type energy storage and distributed phase condensers, and linearizing the short-circuit ratio constraints of multiple stations, and converting the optimization configuration model of grid-type energy storage and distributed phase condensers into a linear programming problem, which can achieve the optimal configuration of grid-type energy storage and distributed phase condensers without using an iterative method, and providing a technical basis for the selection of the optimal configuration of grid-type energy storage and distributed phase condensers in large-scale wind and photovoltaic bases.

[0005] The present invention adopts the following technical solution.

[0006] The present invention proposes a method for configuring a grid-type energy storage and a distributed phase regulator under a short-circuit ratio constraint, which is applicable to a new energy station including a grid-type energy storage or a distributed phase regulator, and includes:

[0007] Obtain the short-circuit current at the busbar of the new energy station, and establish a short-circuit capacity model at the grid-connected busbar of the new energy station after configuring distributed phase-converters or grid-type energy storage;

[0008] Based on the short-circuit ratio model at the busbar of the new energy station, the short-circuit ratio model and its constraints at the grid-connected busbar of the new energy station after the configuration of distributed phase-converter or grid-type energy storage are established;

[0009] Based on the short-circuit capacity model at the grid-connected bus of the new energy station after the configuration of distributed phase-converter or grid-type energy storage and the short-circuit ratio model at the grid-connected bus of the new energy station and their constraints, the short-circuit ratio constraint of multiple new energy stations after the configuration of distributed phase-converter or grid-type energy storage is established;

[0010] The objective function is to optimize the comprehensive cost of configuring distributed phase-converters or grid-type energy storage. The objective function, the quantity constraint and capacity constraint of configuring distributed phase-converters or grid-type energy storage, and the dynamic constraint of the short-circuit ratio of multiple new energy stations after configuring distributed phase-converters or grid-type energy storage together constitute an optimal configuration model for distributed phase-converters or grid-type energy storage.

[0011] The optimal configuration model of distributed phase-converter or grid-type energy storage is solved iteratively to obtain the configuration results of grid-type energy storage and distributed phase-converter under the short-circuit ratio constraint.

[0012] Preferably, the short-circuit current at the busbar of the new energy station is obtained, and a short-circuit capacity model at the grid-connected busbar of the new energy station after the distributed phase-converter or grid-type energy storage is configured is established, including:

[0013] Collect the short-circuit current provided to the bus by grid-type energy storage, distributed phase regulators, and AC systems, and calculate the vector of the short-circuit current at the bus of the new energy station;

[0014] Establish the amplitude constraint and phase angle constraint of the short-circuit current provided by the grid-type energy storage to the bus;

[0015] Based on the amplitude constraint and phase angle constraint of the short-circuit current provided by the grid-type energy storage to the bus, the amplitude of the short-circuit current at the bus of the new energy station is calculated;

[0016] Based on the relationship between the short-circuit capacity at the grid-connected bus of the new energy source after the configuration of distributed phase-converter or grid-type energy storage and the short-circuit current at the bus of the new energy site, a short-circuit capacity model at the grid-connected bus of the new energy site after the configuration of distributed phase-converter or grid-type energy storage is established.

[0017] Preferably, the short-circuit capacity model at the grid-connected busbar of the new energy station after the distributed phase-converter or grid-type energy storage is configured satisfies the following relationship:

[0018]

[0019] In the formula, S aci ′ is the short-circuit capacity at the grid-connected busbar i of the new energy station after the distributed phase-converter or grid-type energy storage is configured; U Ni is the amplitude of the nominal voltage at the grid-connected busbar i of the new energy station; is the amplitude of the short-circuit current at the busbar of the new energy station; S base This is the system baseline capacity.

[0020] Preferably, based on the short-circuit ratio model at the new energy station bus, a short-circuit ratio model at the new energy station grid-connected bus is established, including:

[0021] Establish a short-circuit ratio model at the busbar of a new energy station;

[0022] The short-circuit capacity at the grid-connected bus of the new energy station and the active power injected into the grid-connected bus are collected, and based on the short-circuit ratio model at the grid-connected bus of the new energy station, a short-circuit ratio model at the grid-connected bus of the new energy station is established;

[0023] Based on the constraints of the active power conversion factor between the grid-connected buses i and j caused by the configuration of distributed phase-converters or grid-connected energy storage, a short-circuit ratio model at the grid-connected bus of the new energy station after the configuration of distributed phase-converters or grid-connected energy storage is established;

[0024] The short-circuit ratio of the grid-connected busbar of the new energy station after the distributed phase-converter or grid-type energy storage is configured is not less than the lower limit of the short-circuit ratio of the grid-connected busbar of the new energy station, which is the constraint condition of the short-circuit ratio model of the grid-connected busbar of the new energy station after the distributed phase-converter or grid-type energy storage is configured.

[0025] Preferably, the short-circuit ratio model MRSCR at the grid-connected busbar of the new energy station S,i Satisfies the following relationship:

[0026]

[0027] In the formula, S aci is the short-circuit capacity at the grid-connected busbar i; P REi is the active power injected into the grid-connected bus i, P RE,j is the active power injected into the grid-connected bus j; It is the active power conversion factor of the power between grid-connected buses i and j before configuring distributed phase-converters or grid-connected energy storage.

[0028] Preferably, the short-circuit ratio model MRSCR at the grid-connected busbar of the new energy station after the distributed phase-converter or grid-type energy storage is configured S,i ′ and its constraints satisfy the following relationship:

[0029]

[0030] In the formula, S aci ′ is the short-circuit capacity at the grid-connected busbar i of the new energy station after the distributed phase-converter or grid-type energy storage is configured; MRSCR S,min It is the lower limit of the short-circuit ratio at the grid-connected busbar of the new energy station.

[0031] Preferably, the short-circuit ratio constraint of multiple renewable energy stations after configuring distributed phase-converting devices or grid-type energy storage satisfies the following relationship:

[0032]

[0033] Where U Ni is the amplitude of the nominal voltage at the grid-connected busbar i of the new energy station; is the amplitude of the short-circuit current at the busbar i of the new energy station; S base This is the system baseline capacity.

[0034] Preferably, the short-circuit ratio constraint of multiple renewable energy stations after configuring distributed phase-converting devices or grid-type energy storage satisfies the following relationship:

[0035]

[0036] In the formula, I fb,e,i ,I cn,e,i are the short-circuit currents provided by the grid-type energy storage e and the distributed phase regulator e to the bus i, e∈cn and e∈fb are the voltage source units e of the grid-type energy storage or distributed phase regulator type, respectively; θ cn-sys,e,i The phase angle difference corresponding to the configuration of the grid-type energy storage e or the distributed phase regulator e satisfies θ cn-sys,e,i =θ cn,e,i -θ sys,i θ cn,e,irepresents the phase angle of voltage source generator e at bus i, which is grid-type energy storage, θ sys,i The phase angle of the short-circuit current supplied to an AC system.

[0037] Preferably, the vector of the short-circuit current at the busbar of a new energy station containing a grid-type energy storage or a distributed camera includes: the short-circuit current provided by the grid-type energy storage to the busbar of the new energy station, the short-circuit current provided by the distributed phase regulator to the busbar of the new energy station, and the short-circuit current provided by the AC system to the busbar of the new energy station;

[0038] Calculate the short-circuit current provided by the grid-type energy storage to the busbar of the new energy station or the short-circuit current provided by the distributed phase-shifting machine to the busbar of the new energy station, including: clearing the internal potential of all voltage source units in the system except the distributed phase-shifting machine or grid-type energy storage, and using the internal potential of the distributed phase-shifting machine or grid-type energy storage Calculate with the admittance matrix and satisfy the following relationship:

[0039]

[0040] Where Y n×d is an admittance matrix of n rows × d columns, n is the number of buses in the new energy station, d is the number of distributed phase regulators or grid-type energy storage, I e,1 ,……,I e,i ,……,I e,n They are the short-circuit currents provided by the distributed phase-converter or grid-type energy storage e to the new energy station bus 1, ..., new energy station bus i, ..., new energy station bus n.

[0041] Preferably, the optimal comprehensive cost of configuring distributed phase-converter or grid-type energy storage is used as the objective function; the objective function and the quantity constraint and capacity constraint of configuring distributed phase-converter or grid-type energy storage, as well as the dynamic constraint of the short-circuit ratio of new energy multiple stations after configuring distributed phase-converter or grid-type energy storage, together constitute the optimal configuration model of distributed phase-converter or grid-type energy storage, including:

[0042] Establish quantity constraints and capacity constraints for configuring distributed phase-shifting or grid-type energy storage;

[0043] Based on the quantity constraints and capacity constraints of configuring distributed phase-converters or grid-type energy storage, a comprehensive cost model for configuring distributed phase-converters or grid-type energy storage is established, with the optimal comprehensive cost of configuring distributed phase-converters or grid-type energy storage as the objective function;

[0044] Based on the quantity constraint of distributed phase-converter or grid-type energy storage, the short-circuit ratio constraint of multiple renewable energy stations after the distributed phase-converter or grid-type energy storage is dynamically processed to obtain the dynamic short-circuit ratio constraint of multiple renewable energy stations after the distributed phase-converter or grid-type energy storage is configured;

[0045] The objective function, the quantity constraints and capacity constraints of configuring distributed phase-converter or grid-type energy storage, and the dynamic constraints of the short-circuit ratio of new energy multiple stations after configuring distributed phase-converter or grid-type energy storage, together constitute an optimal configuration model for distributed phase-converter or grid-type energy storage.

[0046] Preferably, the quantity constraint and capacity constraint of distributed phase-converters or grid-type energy storage are configured to satisfy the following relationships respectively:

[0047]

[0048] Where N fd,i 、N cn,i are the upper limits of the number of distributed phase regulators or grid-connected energy storage configured at the grid-connected busbar i; Q fd , Q cn are the upper limits of the capacity of distributed phase regulators or grid-connected energy storage configurations; y fd,e,i ,y cn,e,i Q is whether a distributed phase regulator or a grid-connected energy storage e is configured at the grid-connected bus i. In a non-limiting preferred embodiment, it is a 0-1 state variable; Q fd,e,i , Q cn,e,i It is the capacity of the distributed phase-converter or grid-connected energy storage e configured at the grid-connected bus i.

[0049] Preferably, the dynamic constraint of the short-circuit ratio of multiple renewable energy stations after configuring distributed phase-converting devices or grid-type energy storage satisfies the following relationship:

[0050]

[0051] In the formula, y fd,e,i ,y cn,e,i Whether the grid-connected busbar i is equipped with a distributed phase regulator or grid-connected energy storage e, which is a 0-1 state variable; I fb,e,i ,I cn,e,i are the short-circuit currents provided by the grid-type energy storage e and the distributed phase regulator e to the bus i, e∈cn and e∈fb are the voltage source units e of the grid-type energy storage or distributed phase regulator type, respectively; θ cn-sys,e,i The phase angle difference corresponding to the configuration of the grid-type energy storage e or the distributed phase regulator e satisfies θ cn-sys,e,i =θ cn,e,i -θ sys,i θ cn,e,i represents the phase angle of voltage source generator e at bus i, which is grid-type energy storage, θ sys,i The phase angle of the short-circuit current provided to the AC system; MRSCR S,min is the lower limit of the short-circuit ratio at the grid-connected busbar of the new energy station; S aci is the short-circuit capacity at the grid-connected busbar i; MRSCR S,iis the short-circuit ratio at the grid-connected busbar of the new energy station; It is the short-circuit current provided by the AC system to the new energy station bus i.

[0052] The present invention also proposes a configuration system for grid-type energy storage and distributed phase regulator under short-circuit ratio constraint, which is applicable to a new energy station including grid-type energy storage or distributed phase regulator, and includes:

[0053] Short circuit ratio constraint establishment module, optimization configuration model module, optimization configuration module;

[0054] The short-circuit ratio constraint establishment module is used to obtain the short-circuit current at the bus of the new energy station, and establish the short-circuit capacity model at the grid-connected bus of the new energy station after the distributed phase-converter or grid-type energy storage is configured; based on the short-circuit ratio model at the bus of the new energy station, the short-circuit ratio model and its constraints at the grid-connected bus of the new energy station after the distributed phase-converter or grid-type energy storage is established; based on the short-circuit capacity model at the grid-connected bus of the new energy station after the distributed phase-converter or grid-type energy storage is configured and the short-circuit ratio model at the grid-connected bus of the new energy station and its constraints, the short-circuit ratio constraint of the new energy multi-station after the distributed phase-converter or grid-type energy storage is established;

[0055] The optimization configuration model module is used to take the optimal comprehensive cost of configuring distributed phase-converters or grid-type energy storage as the objective function; the objective function and the quantity constraint and capacity constraint of configuring distributed phase-converters or grid-type energy storage, as well as the dynamic constraint of the short-circuit ratio of multiple new energy stations after configuring distributed phase-converters or grid-type energy storage, together constitute the optimization configuration model of distributed phase-converters or grid-type energy storage;

[0056] The optimization configuration module is used to iteratively solve the optimization configuration model of distributed phase-converter or grid-type energy storage, and obtain the configuration results of grid-type energy storage and distributed phase-converter under the short-circuit ratio constraint.

[0057] The beneficial effects of the present invention are that, compared with the prior art, at least the method proposed in the present invention improves the traditional distributed phase condenser optimization configuration method based on the short-circuit ratio constraint of multiple stations of new energy. The proposed method takes into account the influence of grid-type energy storage and distributed phase condensers on the short-circuit ratio of multiple stations, and linearizes the short-circuit ratio constraint of multiple stations, and transforms the optimization configuration model of grid-type energy storage and distributed phase condensers into a linear programming problem. The optimization configuration of grid-type energy storage and distributed phase condensers can be achieved without an iterative method, and the conservatism of the optimization configuration scheme meets the needs of engineering applications. BRIEF DESCRIPTION OF THE DRAWINGS

[0058] Figure 1 It is a schematic diagram of the short-circuit current on the system side at the grid connection point of a new energy station containing grid-type energy storage and distributed phase regulator in the present invention;

[0059] Figure 2 It is a system-side short-circuit current vector diagram at the grid connection point of a new energy station containing a grid-type energy storage and a distributed phase regulator in the present invention;

[0060] Figure 3 It is a specific flow chart of the distributed phase regulator and grid-type energy storage optimization configuration method established by the present invention;

[0061] Figure 4 is a schematic diagram of a grid structure of an actual example system in an embodiment of the present invention;

[0062] Figure 5 It is a schematic diagram of the network structure in the collection station in the actual calculation example system in the embodiment of the present invention; DETAILED DESCRIPTION

[0063] In order to make the purpose, technical scheme and advantages of the present invention clearer, the technical scheme of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. The embodiments described in this application are only embodiments of a part of the present invention, rather than all embodiments. Based on the spirit of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work belong to the protection scope of the present invention.

[0064] The present invention proposes a method for configuring a grid-type energy storage and a distributed phase regulator under a short-circuit ratio constraint, which is applicable to a new energy station including a grid-type energy storage or a distributed phase regulator, and includes:

[0065] Step 1: Collect the short-circuit current at the busbar of the new energy station, and establish a short-circuit capacity model at the grid-connected busbar of the new energy station after configuring distributed phase-converting condensers or grid-type energy storage.

[0066] Specifically, step 1 includes:

[0067] Step 1.1, collect the short-circuit current provided by the grid-type energy storage, distributed phase regulator, and AC system to the bus i, and calculate the vector of the short-circuit current at the bus of the new energy station;

[0068] In a non-limiting preferred embodiment, Figure 1 As shown in the figure, the vector of short-circuit current at the busbar of a new energy station containing grid-type energy storage or distributed cameras satisfies the following relationship:

[0069]

[0070] In the formula, is the short-circuit current at the busbar i of the new energy station; They are the short-circuit currents provided by the grid-type energy storage, distributed phase regulator and AC system to the bus i of the new energy station.

[0071] θ cn,i,θ sys,i The phase angle of the short-circuit current provided for grid-type energy storage and AC systems.

[0072] In a non-limiting preferred embodiment, if a system is configured with d distributed phase regulators or grid-type energy storage, the Thévenin theorem and the superposition theorem are used to calculate the vector of the three-phase short-circuit current at the bus i of the new energy station: Including: after using the Thevenin theorem to calculate the short-circuit current of each voltage source unit acting on the new energy bus i, the superposition theorem is used to obtain the short-circuit current at the new energy station bus i, which satisfies the following relationship:

[0073]

[0074] In the formula, e∈cn and e∈fb are voltage source units e of grid-type energy storage or distributed phase regulator respectively; It represents the three-phase short-circuit current provided to bus i by voltage source unit e, which is a grid-type energy storage or distributed phase regulator.

[0075] Step 1.2, establishing the amplitude constraint and phase angle constraint of the short-circuit current provided by the grid-type energy storage to the bus;

[0076] Short-circuit current provided by grid-type energy storage to bus i The amplitude is affected by the equipment overcurrent capacity I lim Constraint, the phase angle θ of the short-circuit current provided by the grid-type energy storage to the bus i cn,i Constrained by the power outer loop control, the following relationship is satisfied:

[0077]

[0078] In the formula, x cn,i E is the connection impedance between the grid-type energy storage and the system plus the virtual internal impedance of the grid-type energy storage. cn,i It is the terminal voltage of grid-type energy storage.

[0079] Step 1.3, based on the amplitude constraint and phase angle constraint of the short-circuit current provided by the grid-type energy storage to the bus, calculate the amplitude of the short-circuit current at the bus of the new energy station containing the grid-type energy storage or distributed phase-converter

[0080] Specifically, Figure 2 As shown, the three-phase short-circuit fault current amplitude at the busbar i of the new energy station is Satisfies the following relationship:

[0081]

[0082] In the formula, θ cn-sys,e,i is the phase angle difference, satisfying θ cn-sys,e,i =θcn,e,i -θ sys,i θ cn,e,i represents the phase angle of voltage source generator e at bus i, which is grid-type energy storage, θ sys,i The phase angle of the short-circuit current supplied to an AC system.

[0083] Reference Figure 2 The power angle remains unchanged during the sub-transient process of the grid-connected energy storage. Therefore, by changing the reference angle of the power angle, based on the amplitude constraint and phase angle constraint of the short-circuit current provided by the grid-connected energy storage to the bus, the original reference angle of 0 angle is advanced to the phase angle of the short-circuit current provided by the AC system, thereby simplifying the calculation method of the short-circuit current at the grid-connected point and facilitating the establishment of the short-circuit capacity model in step 1.4.

[0084] Step 1.4, based on the relationship between the short-circuit capacity at the new energy grid-connected bus after the distributed phase-converter or grid-type energy storage is configured and the short-circuit current at the new energy station bus, a short-circuit capacity model at the new energy station grid-connected bus after the distributed phase-converter or grid-type energy storage is established;

[0085] The short-circuit capacity model at the grid-connected busbar of a new energy station equipped with distributed phase-converters or grid-connected energy storage satisfies the following relationship:

[0086]

[0087] In the formula, S aci ′ is the short-circuit capacity at the grid-connected busbar i of the new energy station after the distributed phase-converter or grid-type energy storage is configured; U Ni is the amplitude of the nominal voltage at the grid-connected busbar i of the new energy station; is the amplitude of the short-circuit current at the busbar of the new energy station; S base This is the system baseline capacity.

[0088] Step 2: Based on the short-circuit ratio model at the busbar of the new energy station, establish the short-circuit ratio model and its constraints at the grid-connected busbar of the new energy station after configuring distributed phase-converter or grid-type energy storage.

[0089] Specifically, step 2 includes:

[0090] Step 2.1, establish the short-circuit ratio model at the busbar i of the new energy station, satisfying the following relationship:

[0091]

[0092] In the formula, is the nominal voltage of bus i; is the actual operating voltage of bus i; is the actual apparent power of the renewable energy injected into bus i, and the subscript RE represents the renewable energy power generation equipment / station; is the complex power conversion factor between busbars i and j, reflecting the phase and amplitude differences between the electrical quantities at the grid-side access points of each renewable energy power generation equipment / new energy station grid-connected points. are the conjugate complex numbers of the actual operating voltages at busbars i and j respectively; is the equivalent impedance matrix of the AC grid nodes at the busbar The elements in the i-th row and i-th column and the elements in the i-th row and j-th column.

[0093] The present invention adopts a new energy multi-station short-circuit ratio model as shown in formula (5), which is a simplified and linearized model. Compared with the nonlinear short-circuit ratio model, it ensures that the short-circuit ratio calculation has a higher accuracy, so as to facilitate the modeling and solution of the linear programming optimization problem considering the short-circuit ratio constraint, and can realize the optimal planning of grid-type energy storage and distributed phase-shifting machines with short-circuit ratio constraints.

[0094] In a non-limiting preferred embodiment, the new energy station bus includes a new energy station grid-connected bus and a new energy station machine-end bus. The subscript S and subscript G represent the new energy grid-connected bus and the new energy machine-end bus, respectively.

[0095] Step 2.2, collecting the short-circuit capacity at the grid-connected bus of the new energy station and the active power injected into the grid-connected bus, and establishing a multi-station short-circuit ratio model at the grid-connected bus of the new energy station based on the multi-station short-circuit ratio model at the new energy station bus;

[0096] Specifically, if X / R>10 and the voltage phase angles between the renewable energy stations are similar, and the voltage of each node in the system is close to the rated value, and the reactive power output of the renewable energy station at the grid connection point is ignored, then the MRSCR at the grid-connected bus i of the renewable energy station is S,i Satisfies the following relationship:

[0097]

[0098] In the formula, S aci is the short-circuit capacity at the grid-connected busbar i; P REi is the active power injected into the grid-connected bus i, P RE,j is the active power injected into the grid-connected bus j; It is the active power conversion factor between the grid-connected buses i and j before configuring distributed phase-converters or grid-connected energy storage, reflecting the amplitude difference of the equivalent impedance of the grid-side access points of various new energy power generation equipment or the grid-connected points of new energy stations.

[0099] Step 2.3, based on the constraint of the active power conversion factor between the grid-connected buses i and j caused by the configuration of distributed phase-converters or grid-connected energy storage, a multi-station short-circuit ratio model at the grid-connected bus of the new energy station after the configuration of distributed phase-converters or grid-connected energy storage is established;

[0100] If after configuring distributed phase-converters or grid-type energy storage, the grid structure and the active power of the grid connection point of the new energy station are basically unchanged. At this time, considering the impedance parallel characteristics, the active power conversion factor between the grid-connected buses i and j before configuring distributed phase-converters or grid-type energy storage is greater than the active power conversion factor between the grid-connected buses i and j after configuring distributed phase-converters or grid-type energy storage. At this time, the short-circuit capacity S at the grid-connected bus i of the new energy station after configuring distributed phase-converters or grid-type energy storage is aci ' satisfies the following relationship:

[0101]

[0102] In the formula, λ′ ij The active power conversion factor between grid-connected buses i and j after configuring distributed phase regulators or grid-connected energy storage;

[0103] Multi-station short-circuit ratio model MRSCR at the grid-connected bus i of the new energy station after configuring distributed phase-converting or grid-connected energy storage S,i ' satisfies the following relationship:

[0104]

[0105] The multi-station short-circuit ratio model at the grid-connected busbar of the new energy station after the distributed phase-converter or grid-type energy storage is configured is an inequality model with a lower bound. The present invention realizes the conversion from the equation constraints of the short-circuit ratio and the short-circuit capacity, active power, and active power factor after the distributed phase-converter and grid-type energy storage are configured into the inequality constraints of the short-circuit ratio after configuration and the short-circuit capacity after configuration, and the short-circuit ratio before configuration and the short-circuit capacity, simplifies the calculation amount of repeated calculations of active power and active power factor under different configuration conditions, and converts the original equation model of the multi-station short-circuit ratio model into an inequality model with a lower bound, so that it can be added to the optimization configuration model later, and the optimal configuration method can be achieved through optimization, so that it can achieve the minimum and satisfactory multi-station short-circuit ratio.

[0106] Step 2.4, the multi-station short-circuit ratio at the grid-connected bus of the new energy station after the distributed phase-converter or grid-type energy storage is configured is not less than the lower limit of the multi-station short-circuit ratio at the grid-connected bus of the new energy station, which is the constraint condition of the multi-station short-circuit ratio model at the grid-connected bus of the new energy station after the distributed phase-converter or grid-type energy storage is configured.

[0107] The multi-station short-circuit ratio MRSCR at the grid-connected busbar of the new energy station after configuring distributed phase-converting or grid-type energy storage S,i ′Not less than the lower limit of the multi-station short-circuit ratio MRSCR at the grid-connected busbar of the new energy station S,min , is the short-circuit ratio model of multiple stations at the grid-connected busbar of the new energy station after the distributed phase-converter or grid-type energy storage is configured and its constraints, which satisfies the following relationship:

[0108]

[0109] Step 3: Based on the short-circuit capacity model at the grid-connected bus of the new energy station after the distributed phase-converter or grid-type energy storage is configured and the multi-station short-circuit ratio model at the grid-connected bus of the new energy station and their constraints, establish the short-circuit ratio constraint of the new energy multi-station after the distributed phase-converter or grid-type energy storage is configured.

[0110] The constraint condition of the short-circuit ratio of multiple renewable energy stations after configuring distributed phase-converting or grid-type energy storage satisfies the following relationship:

[0111]

[0112] The amplitude of the short-circuit current at the busbar of the new energy station after the configuration of distributed phase-converter or grid-type energy storage satisfies the following relationship:

[0113]

[0114] Furthermore, the short-circuit ratio constraint of new energy multi-stations after configuring distributed phase-converters or grid-type energy storage satisfies the following relationship:

[0115]

[0116] Where, Ifb ,e,i ,I cn,e,i are the short-circuit currents provided by the grid-type energy storage e and the distributed phase regulator e to the bus i, e∈cn and e∈fb are the voltage source type units e of the grid-type energy storage or distributed phase regulator type, respectively; θ cn-sys,e,i It is the phase angle difference corresponding to the configuration of grid-type energy storage e or distributed phase regulator e.

[0117] Before configuring distributed phase regulators or grid-connected energy storage, the short-circuit capacity at the grid-connected bus i of the new energy station and the short-circuit current I provided by the system sys,i Under the premise that the short-circuit ratios of multiple stations are known, the short-circuit ratio constraints of multiple new energy stations after the optimization of distributed phase-converters or grid-type energy storage are configured. When a three-phase short-circuit fault occurs on the grid-connected busbar of the new energy station, the short-circuit current I provided by the distributed phase-converters or grid-type energy storage is fb,e,i ,I cn,e,i ,θ cn-sys,e,i related.

[0118] In a non-limiting preferred embodiment, the short-circuit current I provided by the grid-type energy storage e and the distributed phase regulator e to the bus i is calculated. fb,e,i or I cn,e,i When the internal potential of all voltage source units in the system except the distributed phase regulator or grid-type energy storage e is cleared to zero, the internal potential of the distributed phase regulator or grid-type energy storage e is Use the short-circuit current calculation program to find the fault current provided by unit e to bus j As shown below:

[0119]

[0120] Where Y n×d is an n-row × d-column admittance matrix.

[0121] Step 4, taking the optimal comprehensive cost of configuring distributed phase-modulators or grid-type energy storage as the objective function; the objective function and the quantity constraint and capacity constraint of configuring distributed phase-modulators or grid-type energy storage, as well as the dynamic constraint of the short-circuit ratio of new energy multiple stations after configuring distributed phase-modulators or grid-type energy storage, together constitute the optimal configuration model of distributed phase-modulators or grid-type energy storage.

[0122] Specifically, step 4 includes:

[0123] Step 4.1, establish the quantity constraints and capacity constraints of distributed phase-converters or grid-type energy storage;

[0124] The number constraints and capacity constraints of distributed phase-converters or grid-type energy storage are configured to satisfy equations (14) and (15) respectively:

[0125]

[0126] Where N fd,i 、N cn,i are the upper limits of the number of distributed phase regulators or grid-connected energy storage configured at the grid-connected busbar i; Q fd , Q cn are the upper limits of the capacity of distributed phase regulators or grid-connected energy storage configurations; y fd,e,i ,y cn,e,i Q is whether a distributed phase regulator or a grid-connected energy storage e is configured at the grid-connected bus i. In a non-limiting preferred embodiment, it is a 0-1 state variable; Q fd,e,i , Q cn,e,i It is the capacity of the distributed phase-converter or grid-connected energy storage e configured at the grid-connected bus i.

[0127] Step 4.2, based on the quantity constraint and capacity constraint of configuring distributed phase-converters or grid-type energy storage, a comprehensive cost model for configuring distributed phase-converters or grid-type energy storage is established, with the optimal comprehensive cost of configuring distributed phase-converters or grid-type energy storage as the objective function;

[0128] Specifically, the comprehensive cost model C includes the purchase cost and operation cost of distributed phase-converter or grid-connected energy storage, which satisfies equations (16) to (20):

[0129] C=C 0,fd +C m,fd +C 0,cn +C m,cn (16)

[0130]

[0131] In the formula, C 0,fd , C m,fd are the configuration cost and operation and maintenance cost of distributed phase condenser respectively; C 0,cn , C m,cn are the grid-connected energy storage configuration costs and operation and maintenance costs respectively; c 0,fd 、c 1,fd 、c 2,fd are the configuration cost, loss cost, and manual operation and maintenance cost of a single distributed phase regulator; c 0,cn 、c 1,cn 、c 2,cn They are the configuration cost, loss cost, and manual operation and maintenance cost of a single grid-connected energy storage unit;

[0132] Step 4.3, based on the quantity constraint of the distributed phase-converter or grid-type energy storage, dynamically process the short-circuit ratio constraint of the new energy multi-station after the distributed phase-converter or grid-type energy storage is configured, and obtain the dynamic constraint of the short-circuit ratio of the new energy multi-station after the distributed phase-converter or grid-type energy storage is configured;

[0133] The dynamic constraint of short-circuit ratio of multiple renewable energy stations after configuring distributed phase-converting or grid-type energy storage satisfies the following relationship:

[0134]

[0135] The obtained short-circuit ratio constraint of multiple new energy stations after configuring distributed phase-converters or grid-type energy storage is an inequality constraint, which represents a goal of minimizing the short-circuit ratio constraint from the perspective of system topology and system parameters. The quantity constraint of configuring distributed phase-converters or grid-type energy storage represents a goal of satisfying the short-circuit ratio constraint of multiple new energy stations from the least number and most economical configuration of distributed phase-converters or grid-type energy storage; based on the quantity constraint of configuring distributed phase-converters or grid-type energy storage, the short-circuit ratio constraint of multiple new energy stations after configuring distributed phase-converters or grid-type energy storage is dynamically processed to obtain the dynamic short-circuit ratio constraint of multiple new energy stations after configuring distributed phase-converters or grid-type energy storage, which realizes the goal of minimizing the number and capacity of distributed phase-converters and grid-type energy storage that meet the short-circuit ratio constraint of multiple new energy stations by integrating two different approaches. The method proposed in the present invention does not achieve the goal of minimizing the short-circuit ratio constraint of multiple stations of new energy through a complex nonlinear short-circuit ratio constraint model of multiple stations, but achieves the goal based on a simplified, linearized short-circuit ratio model of multiple stations. While ensuring that the short-circuit ratio calculation of multiple stations has high accuracy, the nonlinear planning problem of the optimal planning model of grid-type energy storage and distributed phase regulator under the short-circuit ratio constraint of multiple stations is converted into a linear planning problem for efficient linear solution, thereby achieving the optimal planning of grid-type energy storage and distributed phase regulator under the short-circuit ratio constraint of multiple stations.

[0136] Step 4.4, the objective function and the quantity constraints and capacity constraints of the distributed phase-converter or grid-type energy storage, as well as the dynamic constraints of the short-circuit ratio of the new energy multi-station after the distributed phase-converter or grid-type energy storage are configured, together constitute the optimal configuration model of the distributed phase-converter or grid-type energy storage.

[0137] Step 5, iteratively solve the optimal configuration model of the distributed phase-converter or grid-type energy storage, and obtain the configuration results of the grid-type energy storage and the distributed phase-converter under the short-circuit ratio constraint.

[0138] Specifically, Figure 3 As shown in the figure, firstly, the basic parameters of the power grid are pre-entered into the PSD-BPA software, and the configuration optimization problem of the distributed phase-converting and grid-type energy storage is converted into the optimization problem of the startup mode of the distributed phase-converting and grid-type energy storage; secondly, the short-circuit current calculation program and the short-circuit ratio calculation program without grid-type energy storage in the PSD-BPA software are called to calculate the short-circuit current and short-circuit ratio under different unit startup modes, based on the S calculated in advance under the full shutdown mode of the distributed phase-converting and grid-type energy storage. aci 、MRSCR S,i Data, as well as the I calculated in advance in full boot mode sys,i ,I fb,e,i ,I cn,e,i ,θ cn-sys,e,iData, reduce the variables to be found to y cn,e,i ,y fb,e,i Finally, the main program of the optimization configuration model is built based on the YALMIP toolkit of Matlab software, and the IPOPT solver is called to solve the problem, thus realizing the optimal configuration of distributed phase-shifting machines and grid-type energy storage.

[0139] This embodiment uses Figure 4 Taking the actual simulation system shown in the figure as an example, the implementation steps of a method for optimizing the configuration of grid-type energy storage and distributed phase regulators taking into account the linearization constraints of short-circuit ratios of multiple stations are explained:

[0140] 1. Establish basic grid parameters

[0141] For a certain actual "Shagohuang" photovoltaic base, the UHV DC transmission system is shown in the following diagram: Figure 4 As shown, the Z converter station at the sending end is connected to the main grid at the sending end through three 750 kV lines. The rated power of the UHV DC is 8000MW and the rated voltage is ±800kV. The nearby supporting thermal power is 2640MW, and the supporting "Shagohuang" photovoltaic is 6000MW, which is collected to the G substation (35kV / 330kV / 750kV three-level boost), and a supporting 600MW energy storage is built (including 100MW grid-type energy storage). It is planned to build 500MW grid-type energy storage and a maximum of 24 50MVar distributed phase-shifting devices; the maximum output of supporting new energy is 95%; the grid-type energy storage is connected to the 35kV bus through a 0.4kV / 35kV booster transformer; the distributed phase-shifting device is connected to the 35kV bus through a 10kV / 35kV booster transformer; the grid structure in the collection station is as follows Figure 5 As shown in Table 1, the planning, loss, and operation and maintenance costs of a single device are shown in Table 1, and the main parameters of the power grid structure are shown in Table 2.

[0142] Table 1 Planning, loss, and operation and maintenance costs of a single device

[0143]

[0144] Table 2 Main parameters of power grid structure

[0145]

[0146] At the same time, when the critical short-circuit ratio RSCRG,min of the new energy station terminal is 1.5 under unit voltage, the corresponding critical short-circuit ratio RSCR at the grid connection point is S,min The calculation method is as follows:

[0147]

[0148] Combined with the relevant requirements of the national standard GB / T 40594 on the critical short-circuit ratio of the new energy station, the critical short-circuit ratio RSCR of the new energy station G,minWhen the value is 1.5, after retaining a certain engineering margin, the critical multi-station short-circuit ratio MRSCR of the new energy station grid connection point is recommended. S,min Take 1.70.

[0149] 2. Generate basic planning parameters through PSD-BPA.

[0150] The electromechanical transient simulation model of the system is established on the PSD-BPA power system analysis software platform. The short-circuit ratio and short-circuit capacity of multiple stations at each grid connection point are evaluated before all distributed phase regulators and grid-connected energy storage are connected. The results are shown in Table 3.

[0151] Table 3 Minimum short-circuit ratio of multiple stations and minimum short-circuit capacity at the grid connection point

[0152]

[0153] In the case of large-scale new energy generation, full operation of grid-type energy storage and distributed phase-shifting devices, and charging state of grid-type energy storage (low system short-circuit capacity, low short-circuit capacity increased by grid-type energy storage), consider the number of distributed phase-shifting devices or grid-type energy storage at each grid connection point i, and distribute their capacity as evenly as possible (N fd,i 、N cn,i =1, Q fd,e,i For 50 MVar, Q cn,e,i The short-circuit current complex matrix of each voltage source unit and the main grid side at each grid-connected point is (24+30+36)×36, and the short-circuit ratio and short-circuit capacity of each grid-connected point are shown in the following table.

[0154] Table 4 Short-circuit ratio and short-circuit capacity of grid connection points under different configuration conditions

[0155]

[0156] It can be seen that with the increase in the configuration capacity of distributed phase-converters and grid-type energy storage and the improvement of the overcurrent capacity of grid-type energy storage, the minimum short-circuit ratio and minimum short-circuit capacity of each grid-connected point gradually increase. When the grid-type energy storage capacity is 500MW and the distributed phase-converter capacity is 1200MVar, the short-circuit ratio of multiple stations at each grid-connected point is far greater than the requirement. In order to ensure the economy of the plan, it is necessary to achieve the optimal configuration of distributed phase-converters and grid-type energy storage. Considering the high construction and operation and maintenance costs of distributed phase-converters, it is advisable to use grid-type energy storage equipment with higher overcurrent capacity, and only consider grid-type energy storage with 3 times the overcurrent capacity in the future.

[0157] 3. Through the constructed optimization configuration model, the optimal configuration of grid-type energy storage and distributed phase-shifting machines can be achieved.

[0158] The upper limit N of the number of distributed phase regulators configured at each grid connection point i fd,i For 1 unit, Qfd,e,i The energy storage scenario is configured as follows:

[0159] Scenario 1: Maximum number of grid-connected energy storage units N cn,i For 1 unit, Q cn,e,i 16.66MW;

[0160] Scenario 2: Maximum number of grid-connected energy storage units N cn,i For 1 unit, Q cn,e,i 20MW;

[0161] Scenario 3: Maximum number of grid-connected energy storage units N cn,i For 2 units, Q cn,e,i 16.66MW;

[0162] Scenario 4: Maximum number of grid-connected energy storage units N cn,i For 2 units, Q cn,e,i 20MW;

[0163] Scenario 5: Maximum number of grid-connected energy storage units N cn,i For 2 units, Q cn,e,i 27.76MW;

[0164] Scenario 6: Maximum number of grid-connected energy storage units N cn,i For 3 units, Q cn,e,i It is 16.66MW.

[0165] At this point, the planning results for each scenario are shown in the following table:

[0166] Table 5 Planning results under each scenario

[0167]

[0168] It can be seen from Table 5 that with the increase of the capacity of the voltage source type unit, the minimum short-circuit ratio and the minimum short-circuit capacity of each grid-connected point gradually increase; the more distributed phase-converters are configured, the higher the comprehensive cost; simply increasing the configured grid-type energy storage capacity, the comprehensive cost shows a trend of first decreasing and then increasing. When the grid-type energy storage capacity is 420MW, 17 distributed phase-converters, and the capacity is 850MVar, the short-circuit ratio of multiple stations at each grid-connected point meets the requirements, and the optimal configuration of distributed phase-converters and grid-type energy storage is achieved.

[0169] Table 6 Short-circuit ratio and short-circuit capacity of each scenario under different short-circuit ratio calculation methods

[0170]

[0171] Based on the method proposed in this paper and the short-circuit ratio calculation method of multiple stations of new energy, the short-circuit ratio and short-circuit capacity of multiple stations in each planning scenario are shown in Table 6. It can be seen from Table 6 that the minimum short-circuit ratio and minimum short-circuit capacity of each grid connection point calculated by the method proposed in this paper and the short-circuit ratio calculation method of multiple stations of new energy are less deviated. The calculation results of the short-circuit ratio of multiple stations by the method proposed in this paper are only 0.53% to 1.88% larger, and the calculation results of the short-circuit capacity are only 0.86% to 3.53% larger. The conservativeness of the results meets the needs of engineering applications, which verifies the effectiveness and accuracy of the method proposed in this paper.

Claims

1. A method for configuring a grid-type energy storage and a distributed phase regulator under a short-circuit ratio constraint, which is applicable to a new energy station including a grid-type energy storage or a distributed phase regulator, and is characterized in that: include: Obtain the short-circuit current at the busbar of the new energy station, and establish a short-circuit capacity model at the grid-connected busbar of the new energy station after configuring distributed phase-converters or grid-type energy storage; Based on the short-circuit ratio model at the busbar of the new energy station, the short-circuit ratio model and its constraints at the grid-connected busbar of the new energy station after the configuration of distributed phase-converter or grid-type energy storage are established; Based on the short-circuit capacity model at the grid-connected bus of the new energy station after the configuration of distributed phase-converter or grid-type energy storage and the short-circuit ratio model at the grid-connected bus of the new energy station and their constraints, the short-circuit ratio constraint of multiple new energy stations after the configuration of distributed phase-converter or grid-type energy storage is established; The objective function is to optimize the comprehensive cost of configuring distributed phase-converters or grid-type energy storage. The objective function, the quantity constraint and capacity constraint of configuring distributed phase-converters or grid-type energy storage, and the dynamic constraint of the short-circuit ratio of multiple new energy stations after configuring distributed phase-converters or grid-type energy storage together constitute an optimal configuration model for distributed phase-converters or grid-type energy storage. The optimal configuration model of distributed phase-converter or grid-type energy storage is solved iteratively to obtain the configuration results of grid-type energy storage and distributed phase-converter under the short-circuit ratio constraint.

2. The method for configuring grid-type energy storage and distributed phase regulator under short-circuit ratio constraint according to claim 1, characterized in that: Obtain the short-circuit current at the busbar of the new energy station, and establish a short-circuit capacity model at the grid-connected busbar of the new energy station after configuring distributed phase-converters or grid-type energy storage, including: Collect the short-circuit current provided to the bus by grid-type energy storage, distributed phase regulators, and AC systems, and calculate the vector of the short-circuit current at the bus of the new energy station; Establish the amplitude constraint and phase angle constraint of the short-circuit current provided by the grid-type energy storage to the bus; Based on the amplitude constraint and phase angle constraint of the short-circuit current provided by the grid-type energy storage to the bus, the amplitude of the short-circuit current at the bus of the new energy station is calculated; Based on the relationship between the short-circuit capacity at the grid-connected bus of the new energy source after the configuration of distributed phase-converter or grid-type energy storage and the short-circuit current at the bus of the new energy site, a short-circuit capacity model at the grid-connected bus of the new energy site after the configuration of distributed phase-converter or grid-type energy storage is established.

3. The method for configuring grid-type energy storage and distributed phase regulator under short-circuit ratio constraint according to claim 2, characterized in that: The short-circuit capacity model at the grid-connected busbar of a new energy station equipped with distributed phase-converters or grid-connected energy storage satisfies the following relationship: In the formula, S aci ′ is the short-circuit capacity at the grid-connected busbar i of the new energy station after the distributed phase-converter or grid-type energy storage is configured; U Ni is the amplitude of the nominal voltage at the grid-connected busbar i of the new energy station; is the amplitude of the short-circuit current at the busbar of the new energy station; S base This is the system baseline capacity.

4. The method for configuring grid-type energy storage and distributed phase regulator under short-circuit ratio constraint according to claim 1, characterized in that: Based on the short-circuit ratio model at the busbar of the new energy station, a short-circuit ratio model at the grid-connected busbar of the new energy station is established, including: Establish a short-circuit ratio model at the busbar of a new energy station; The short-circuit capacity at the grid-connected bus of the new energy station and the active power injected into the grid-connected bus are collected, and based on the short-circuit ratio model at the grid-connected bus of the new energy station, a short-circuit ratio model at the grid-connected bus of the new energy station is established; Based on the constraints of the active power conversion factor between the grid-connected buses i and j caused by the configuration of distributed phase-converters or grid-connected energy storage, a short-circuit ratio model at the grid-connected bus of the new energy station after the configuration of distributed phase-converters or grid-connected energy storage is established; The short-circuit ratio of the grid-connected busbar of the new energy station after the distributed phase-converter or grid-type energy storage is configured is not less than the lower limit of the short-circuit ratio of the grid-connected busbar of the new energy station, which is the constraint condition of the short-circuit ratio model of the grid-connected busbar of the new energy station after the distributed phase-converter or grid-type energy storage is configured.

5. The method for configuring grid-type energy storage and distributed phase regulator under short-circuit ratio constraint according to claim 4, characterized in that: MRSCR short-circuit ratio model at the grid-connected busbar of new energy stations S,i Satisfies the following relationship: In the formula, S aci is the short-circuit capacity at the grid-connected busbar i; P REi is the active power injected into the grid-connected bus i, P RE,j is the active power injected into the grid-connected bus j; It is the active power conversion factor of the power between grid-connected buses i and j before configuring distributed phase-converters or grid-connected energy storage.

6. The method for configuring grid-type energy storage and distributed phase regulator under short-circuit ratio constraint according to claim 5, characterized in that: MRSCR short-circuit ratio model at the grid-connected busbar of a new energy station after configuring distributed phase-converting or grid-connected energy storage S,i ′ and its constraints satisfy the following relationship: In the formula, S aci ′ is the short-circuit capacity at the grid-connected busbar i of the new energy station after the distributed phase-converter or grid-type energy storage is configured; MRSCR S,min It is the lower limit of the short-circuit ratio at the grid-connected busbar of the new energy station.

7. The method for configuring grid-type energy storage and distributed phase regulator under short-circuit ratio constraint according to claim 6, characterized in that: The short-circuit ratio constraint of multiple renewable energy stations after configuring distributed phase-converting or grid-type energy storage satisfies the following relationship: Where U Ni is the amplitude of the nominal voltage at the grid-connected busbar i of the new energy station; is the amplitude of the short-circuit current at the busbar i of the new energy station; S base This is the system baseline capacity.

8. The method for configuring grid-type energy storage and distributed phase regulator under short-circuit ratio constraint according to claim 7, characterized in that: The short-circuit ratio constraint of multiple renewable energy stations after configuring distributed phase-converting or grid-type energy storage satisfies the following relationship: In the formula, I fb,e,i ,I cn,e,i are the short-circuit currents provided by the grid-type energy storage e and the distributed phase regulator e to the bus i, e∈cn and e∈fb are the voltage source type units e of the grid-type energy storage or distributed phase regulator type, respectively; θ cn-sys,e,i The phase angle difference corresponding to the configuration of the grid-type energy storage e or the distributed phase regulator e satisfies θ cn-sys,e,i =θ cn,e,i -θ sys,i θ cn,e,i represents the phase angle of voltage source generator e at bus i, which is grid-type energy storage, θ sys,i The phase angle of the short-circuit current supplied to an AC system.

9. The method for configuring grid-type energy storage and distributed phase regulator under short-circuit ratio constraint according to claim 8, characterized in that: The vector of short-circuit current at the busbar of a new energy station with grid-type energy storage or distributed cameras includes: the short-circuit current provided by the grid-type energy storage to the busbar of the new energy station, the short-circuit current provided by the distributed phase regulator to the busbar of the new energy station, and the short-circuit current provided by the AC system to the busbar of the new energy station; Calculate the short-circuit current provided by the grid-type energy storage to the busbar of the new energy station or the short-circuit current provided by the distributed phase-shifting machine to the busbar of the new energy station, including: clearing the internal potential of all voltage source units in the system except the distributed phase-shifting machine or grid-type energy storage, and using the internal potential of the distributed phase-shifting machine or grid-type energy storage Calculate with the admittance matrix and satisfy the following relationship: Where Y n×d is an admittance matrix of n rows × d columns, n is the number of buses in the new energy station, d is the number of distributed phase regulators or grid-type energy storage, I e,1 ,……,I e,i ,……,I e,n They are the short-circuit currents provided by the distributed phase-converter or grid-type energy storage e to the new energy station bus 1, ..., new energy station bus i, ..., new energy station bus n.

10. The method for configuring grid-type energy storage and distributed phase regulator under short-circuit ratio constraint according to claim 1, characterized in that: The objective function is to optimize the comprehensive cost of configuring distributed phase-converter or grid-type energy storage. The objective function, the quantity constraint and capacity constraint of configuring distributed phase-converter or grid-type energy storage, and the dynamic constraint of short-circuit ratio of new energy multi-stations after configuring distributed phase-converter or grid-type energy storage together constitute the optimal configuration model of distributed phase-converter or grid-type energy storage, including: Establish quantity constraints and capacity constraints for configuring distributed phase-shifting or grid-type energy storage; Based on the quantity constraints and capacity constraints of configuring distributed phase-converters or grid-type energy storage, a comprehensive cost model for configuring distributed phase-converters or grid-type energy storage is established, with the optimal comprehensive cost of configuring distributed phase-converters or grid-type energy storage as the objective function; Based on the quantity constraint of distributed phase-converter or grid-type energy storage, the short-circuit ratio constraint of multiple renewable energy stations after the distributed phase-converter or grid-type energy storage is dynamically processed to obtain the dynamic short-circuit ratio constraint of multiple renewable energy stations after the distributed phase-converter or grid-type energy storage is configured; The objective function, the quantity constraints and capacity constraints of configuring distributed phase-converter or grid-type energy storage, and the dynamic constraints of the short-circuit ratio of new energy multiple stations after configuring distributed phase-converter or grid-type energy storage, together constitute an optimal configuration model for distributed phase-converter or grid-type energy storage.

11. The method for configuring grid-type energy storage and distributed phase regulator under short-circuit ratio constraint according to claim 10, characterized in that: The quantity constraints and capacity constraints of distributed phase-converters or grid-type energy storage are configured to satisfy the following relationships: Where N fd,i 、N cn,i are the upper limits of the number of distributed phase regulators or grid-connected energy storage configured at the grid-connected busbar i; Q fd , Q cn are the upper limits of the capacity of distributed phase regulators or grid-connected energy storage configurations; y fd,e,i ,y cn,e,i Q is whether a distributed phase regulator or a grid-connected energy storage e is configured at the grid-connected bus i. In a non-limiting preferred embodiment, it is a 0-1 state variable; Q fd,e,i , Q cn,e,i It is the capacity of the distributed phase-converter or grid-connected energy storage e configured at the grid-connected bus i.

12. The method for configuring grid-type energy storage and distributed phase regulator under short-circuit ratio constraint according to claim 10, characterized in that: The dynamic constraint of short-circuit ratio of multiple renewable energy stations after configuring distributed phase-converting or grid-type energy storage satisfies the following relationship: In the formula, y fd,e,i ,y cn,e,i Whether the grid-connected busbar i is equipped with a distributed phase regulator or grid-connected energy storage e, which is a 0-1 state variable; I fb,e,i ,I cn,e,i are the short-circuit currents provided by the grid-type energy storage e and the distributed phase regulator e to the bus i, e∈cn and e∈fb are the voltage source type units e of the grid-type energy storage or distributed phase regulator type, respectively; θ cn-sys,e,i The phase angle difference corresponding to the configuration of the grid-type energy storage e or the distributed phase regulator e satisfies θ cn-sys,e,i =θ cn,e,i -θ sys,i θ cn,e,i represents the phase angle of voltage source generator e at bus i, which is grid-type energy storage, θ sys,i The phase angle of the short-circuit current provided to the AC system; MRSCR S,min is the lower limit of the short-circuit ratio at the grid-connected busbar of the new energy station; S aci is the short-circuit capacity at the grid-connected busbar i; MRSCR S,i is the short-circuit ratio at the grid-connected busbar of the new energy station; It is the short-circuit current provided by the AC system to the new energy station bus i.

13. A short-circuit ratio constrained grid-type energy storage and distributed phase-shifting configuration system, suitable for new energy stations including grid-type energy storage or distributed phase-shifting, characterized in that: include: Short circuit ratio constraint establishment module, optimization configuration model module, optimization configuration module; The short-circuit ratio constraint establishment module is used to obtain the short-circuit current at the bus of the new energy station, and establish the short-circuit capacity model at the grid-connected bus of the new energy station after the distributed phase-converter or grid-type energy storage is configured; based on the short-circuit ratio model at the bus of the new energy station, the short-circuit ratio model and its constraints at the grid-connected bus of the new energy station after the distributed phase-converter or grid-type energy storage is established; based on the short-circuit capacity model at the grid-connected bus of the new energy station after the distributed phase-converter or grid-type energy storage is configured and the short-circuit ratio model at the grid-connected bus of the new energy station and its constraints, the short-circuit ratio constraint of the new energy multi-station after the distributed phase-converter or grid-type energy storage is established; The optimization configuration model module is used to take the optimal comprehensive cost of configuring distributed phase-converters or grid-type energy storage as the objective function; the objective function and the quantity constraint and capacity constraint of configuring distributed phase-converters or grid-type energy storage, as well as the dynamic constraint of the short-circuit ratio of multiple new energy stations after configuring distributed phase-converters or grid-type energy storage, together constitute the optimization configuration model of distributed phase-converters or grid-type energy storage; The optimization configuration module is used to iteratively solve the optimization configuration model of distributed phase-converter or grid-type energy storage, and obtain the configuration results of grid-type energy storage and distributed phase-converter under the short-circuit ratio constraint.

Citation Information

Patent Citations

  • Phase modifier optimal configuration method and system for improving power grid voltage intensity

    CN114844130A

  • Distributed phase modifier configuration method and device for improving new energy multi-station short circuit ratio

    CN117638966A

  • Network source collaborative planning method and system considering new energy multi-station short circuit ratio

    CN117713245A

  • Phase modifier configuration method and device, equipment, storage medium and program product

    CN117878955A

Cited By

  • Network construction power supply capacity configuration optimization method and system

    CN119401573A

  • Capacity configuration method and device for internal phase modifier of wind power plant

    CN119448406A

  • Short-circuit ratio margin-based capacity configuration method and system for network construction type converter

    CN119561154A

  • Networking type energy storage locating and sizing optimization method considering new energy multi-station short circuit ratio improvement

    CN119921365A

  • Reactive equipment multi-target collaborative optimization configuration method and device based on short-circuit ratio

    CN120377284A