System and method for optimizing utilization rate of production line automation equipment

By setting up sensors and control modules on the refrigerator cabinet production line to monitor and optimize the running time of automated equipment, the problem of equipment utilization monitoring is solved, the comprehensive equipment utilization rate and production efficiency are improved, and corporate profits are enhanced.

CN118747589APending Publication Date: 2024-10-08CHANGHONG MEILING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411003137.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-25
Publication Date
2024-10-08

AI Technical Summary

Technical Problem

Automated equipment in the refrigerator and cabinet manufacturing industry cannot detect the actual operating rhythm and utilization rate of each link, resulting in increased production line time and reduced equipment utilization efficiency and corporate profits.

Method used

Set up sensors and control modules on the production line, obtain the takt time of each station, calculate the maximum takt time, and use the equipment utilization model to adjust the station running time to improve equipment utilization.

Benefits of technology

The actual utilization rate monitoring and optimization of each link of the automation equipment is realized, the comprehensive utilization rate of the equipment is improved, the production line time is reduced, and the corporate profits are increased.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118747589A_ABST
    Figure CN118747589A_ABST
Patent Text Reader

Abstract

The invention provides a production line automation equipment utilization rate optimization system and method, and the system and method are applied to a to-be-measured production line, the to-be-measured production line is provided with a plurality of stations, and the stations are provided with automation equipment. The system comprises sensors which are arranged on all stations of a production line to be measured; the sensor is configured to obtain the beat time of the to-be-detected product at each station; the beat time is the operation time of the automation equipment corresponding to the station; obtaining the maximum beat time according to the beat time; the control module is configured to obtain target operation time and control the station to operate according to the target operation time by utilizing a first equipment utilization rate model based on the maximum beat time; the technical problems that the actual operation rhythm of each link of automatic equipment cannot be detected and the actual utilization rate of each working procedure cannot be directly observed in the current refrigerator cabinet production link, so that the time consumed on a production line is increased, and the equipment utilization efficiency and the enterprise profit are reduced are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of automation equipment, and in particular to a system and method for optimizing the utilization of production line automation equipment. Background Art

[0002] With the development of the economy, the production mode of most manufacturing industries has shifted to automation, which means that the time for production line changeover in most companies will be reduced. The direct benefit is the improvement of the company's production efficiency and profits.

[0003] At present, the use of automated equipment is common in the refrigerator cabinet manufacturing industry. Take the side panel forming line in the refrigerator cabinet production process as an example. It has to go through the links of loading, punching, roll forming, attaching condenser, and U-forming (curling). Basically, automated equipment is involved in each link, which greatly saves production time.

[0004] Faced with the current production environment of the refrigerator cabinet manufacturing industry, the existing automated equipment in the side panel forming line cannot detect the actual operating rhythm of the equipment in each link, cannot directly observe the actual utilization rate of each process, and cannot collect, organize and analyze the data of the equipment. In other words, it cannot find the factors that affect the utilization efficiency of the equipment. As a result, the company cannot analyze the problems and reasons for the comprehensive utilization rate of the equipment based on the actual situation during the operation of the equipment, thereby increasing the time spent on the production line, reducing the utilization efficiency of the equipment and the company's profits. Summary of the invention

[0005] The present application provides a production line automation equipment utilization optimization system and method to solve the current technical problems in the refrigerator cabinet production process, such as the inability to detect the actual operating rhythm of each link of the automation equipment and the inability to directly observe the actual utilization rate of each process, thereby increasing the time spent on the production line, reducing equipment utilization efficiency and corporate profits.

[0006] In a first aspect, the present application provides a production line automation equipment utilization optimization system, which is applied to a production line to be tested, wherein the production line to be tested is provided with a plurality of workstations, and the workstations are provided with automation equipment; comprising: A sensor, wherein the sensor is arranged at each of the workstations of the production line to be tested; the sensor is configured as follows: Obtaining the takt time of the product to be tested at each of the workstations; the takt time is the running time of the automation equipment corresponding to the workstation; According to the beat time, obtaining the maximum beat time; A control module, the control module is in communication with the sensor and is configured to: Based on the maximum takt time, the target operating time is obtained by using a first equipment utilization model and the workstation is controlled to operate according to the target operating time; the first equipment utilization model is: (Time when the equipment is in production state / total time when the equipment is in operation) × 100% = utilization rate of the first equipment; When the workstation operates according to the target operating time, the utilization rate of the first equipment is at a maximum value.

[0007] In some embodiments, the control module is further configured to: Based on the maximum beat time, a beat data set to be tested is generated; the beat data set to be tested includes at least one beat data to be tested, and the difference between the maximum beat time and the beat data to be tested is a multiple of a first preset value; Based on the test beat data set, using the first equipment utilization model, obtaining target test beat data corresponding to the maximum utilization value; Based on the target beat data to be tested, a target running time is obtained.

[0008] In some embodiments, the difference between the maximum beat time and the beat data to be measured is less than or equal to a second preset value.

[0009] In some embodiments, the control module is further configured to: Get the number of powered-on devices; Based on the number of started devices, the second device utilization rate model is used to obtain the second device utilization rate; the second device utilization rate model is: (Number of devices in operation ÷ total number of devices) × 100% = utilization rate of the second device.

[0010] In some embodiments, the system further comprises: A control console is electrically connected to the automation equipment and the control module, and is used to set the operating time of the workstation and obtain the number of equipment started.

[0011] In some embodiments, the console is further configured to: Receiving a maintenance signal sent when the automation equipment is damaged, and a normal working signal sent when the maintenance is completed; Based on the signal to be repaired, storing a starting date when the automation equipment is damaged; Based on the normal working signal, a deadline when the automation device is damaged is stored.

[0012] In some embodiments, the console is further configured to: Obtaining model information of the product to be tested; The model information of the product to be tested and the corresponding target running time are stored.

[0013] A second aspect of the present application provides a method for optimizing utilization of production line automation equipment, which is applied to a system for optimizing utilization of production line automation equipment as described in any one of the first aspects above, comprising: Obtaining the cycle time of the product to be tested at each workstation; the cycle time is the operating time of the automation equipment corresponding to the workstation; According to the beat time, obtaining the maximum beat time; Based on the maximum takt time, the target operating time is obtained by using a first equipment utilization model and the workstation is controlled to operate according to the target operating time; the first equipment utilization model is: (Time when the equipment is in production state / total time when the equipment is in operation) × 100% = equipment utilization rate; Wherein, when the workstation operates according to the target operating time, the equipment utilization rate is at a maximum value.

[0014] In some embodiments, obtaining the target running time based on the maximum takt time and using the first equipment utilization model includes: Based on the maximum beat time, a beat data set to be tested is generated; the beat data set to be tested includes at least one beat data to be tested, and the difference between the maximum beat time and the beat data to be tested is a multiple of a first preset value; Based on the test beat data set, using the first equipment utilization model, obtaining target test beat data corresponding to the maximum utilization value; Based on the target beat data to be tested, a target running time is obtained.

[0015] The present application provides a production line automation equipment utilization optimization system and method, which are applied to a production line to be tested, wherein a plurality of workstations are arranged on the production line to be tested, and automation equipment is arranged on the workstations; the system comprises: a sensor, wherein the sensor is arranged on each of the workstations of the production line to be tested; the sensor is configured to: obtain the tact time of the product to be tested at each of the workstations; the tact time is the running time of the automation equipment corresponding to the workstation; and according to the tact time, obtain the maximum tact time; a control module, wherein the control module is communicatively connected with the sensor and configured to: based on the maximum tact time, obtain the target running time using a first equipment utilization model and control the workstation to run according to the target running time; the first equipment utilization model is: (time when the equipment is in production state ÷ total equipment running time) × 100% = first equipment utilization; wherein, when the workstation runs according to the target running time, the first equipment utilization is at the highest value, so that the actual running tact of each link of the automation equipment can be detected in the production link of the refrigerator cabinet, thereby calculating the actual utilization of each process, and increasing the equipment utilization efficiency by changing the workstation running time. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the technical solution of the present application, the drawings required for use in the embodiments are briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without any creative work.

[0017] Figure 1 This is a schematic diagram of the structure of the production line automation equipment utilization optimization system in this application.

[0018] Description of reference numerals: 1-Sensor; 2-Control module; 3-Control console. DETAILED DESCRIPTION

[0019] In order to enable those skilled in the art to better understand the technical solutions in this application, the technical solutions in the embodiments of this application will be clearly and completely described below in conjunction with the drawings in the embodiments of this application. Obviously, the described embodiments are only part of the embodiments of this application, not all of them. Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of this application.

[0020] Because in some technologies, the actual operation rhythm of each link of the automation equipment cannot be detected in the refrigerator cabinet production link, and the actual utilization rate of each process cannot be directly observed, so the time spent on the production line will increase, reducing the equipment utilization efficiency and corporate profit technology. In order to solve this technical problem, this application provides a production line automation equipment utilization optimization system and method. The production line automation equipment utilization optimization system and method are described below: For example, automation equipment is an important foundation and guarantee for modern manufacturing production. The data of automation equipment is collected, sorted and analyzed to discover the factors affecting the efficiency of equipment utilization, analyze the problems and causes of equipment utilization, and propose corresponding solutions to continuously improve the comprehensive utilization rate of automation equipment and achieve the goal of increasing production and efficiency.

[0021] Overall Equipment Effectiveness (OEE) is used to express the ratio of actual production capacity to theoretical production capacity. Among the five elements of the production system, production equipment is crucial, and the comprehensive utilization rate of equipment is particularly important for the production efficiency and manufacturing costs of enterprises. OEE is an analytical tool and calculation method. Through the research and analysis of OEE, the comprehensive utilization rate of enterprise equipment can be improved to increase the company's profits, help enterprises reduce unnecessary losses, and promote efficient and sustainable development of enterprises.

[0022] In summary, the present application provides a production line automation equipment utilization optimization system. By installing a microcontroller (MCU) chip with a unified calculation system, i.e., a control module 2, in a single process of the production line, the working time of the automation equipment is intuitively monitored and data is collected. By calculating the OEE data, the operating process, time, and efficiency of the automation equipment can be analyzed and optimized while intuitively monitoring the utilization of each process and link, and the use of the output and equipment can be more effectively detected. The production line automation equipment utilization conversion system can also intuitively monitor and optimize the steps, processes, working time, etc. in the production process, aiming to improve equipment production efficiency and reduce cost expenditures. At the same time, the system has relatively small changes to the existing equipment, precise control, rapid response, simple structural adjustment, and is easy to promote and apply.

[0023] For example, a production line includes multiple workstations, and each workstation performs different processing work. It is understandable that the work of each workstation is different, so the processing time will also be different. Because the workstations on a production line can only maintain the same cycle time, the cycle time of the production line is generally set according to the workstation with the longest cycle time. For example, the processing time of the plate in the forming section is 13 seconds, the time in the condenser section is 16 seconds, and the processing time in the U-section is 15 seconds. It can be seen that the overall cycle time of the production line is 16 seconds, that is, the product stays at each workstation for 16 seconds.

[0024] Depend on Figure 1 It can be seen that the first aspect of the present application provides a production line automation equipment utilization optimization system, which is applied to the production line to be tested, and a number of workstations are arranged on the production line to be tested, and automation equipment is arranged on the workstations; it includes: sensor 1, the sensor 1 is arranged on each of the workstations of the production line to be tested; the sensor 1 is configured to: obtain the tact time of the product to be tested at each of the workstations; the tact time is the running time of the automation equipment corresponding to the workstation; according to the tact time, the maximum tact time is obtained; the tact time can be obtained by obtaining the running time of the automation equipment; control module 2, the control module 2 is communicated with the sensor 1, and is configured to: based on the maximum tact time, use the first equipment utilization model to obtain the target running time and control the workstation to run according to the target running time; the first equipment utilization model is: (time when the equipment is in production state ÷ total equipment running time) × 100% = equipment utilization; wherein, when the workstation runs according to the target running time, the first equipment utilization is at the highest value. The time that the equipment is in production state is the time that the automated equipment is running, and the total equipment running time includes the time that the automated equipment is waiting. For example, if the running time of a certain workstation is 20s, and the cycle time of the automated equipment corresponding to the workstation is 18s, then the time that the equipment is in production state is 18s, and the total equipment running time is 20s.

[0025] The present application provides a production line automation equipment utilization optimization system, which obtains the cycle time of each workstation through sensor 1, and obtains the bottleneck workstation, i.e., the maximum cycle time, and achieves balanced production of each workstation by adjusting the cycle time of the bottleneck workstation. The specific adjustment method is shown in the following table:

[0026] For example, taking the BCD-450 model product as an example, the current workstation operates according to the maximum cycle time, that is, the product stays at each workstation for 20 seconds, and its equipment utilization rate is (18+19+20+16+20+17+16+16) ÷ 20×8 = 88.75%; and based on the limitation of the production line, the workstation operation time can be adjusted to 19 seconds, that is, the product stays at each workstation for 19 seconds, and its equipment utilization rate is changed to (18+19+20+16+20+17+16+16) ÷ 19×8 = 93.42%. It is understandable that the equipment utilization rate has increased by 4.67%, that is, the equipment waiting time is shorter, and more equipment is produced in the same time, which improves equipment utilization efficiency and corporate profits.

[0027] In this embodiment, the control module 2 is further configured to: generate a beat data set to be tested based on the maximum beat time; the beat data set to be tested includes at least one beat data to be tested, and the difference between the maximum beat time and the beat data to be tested is a multiple of a first preset value; based on the beat data set to be tested, using the first equipment utilization model, obtain the target beat data to be tested corresponding to the highest utilization value; based on the target beat data to be tested, obtain the target running time. In the present application, the target running time is obtained by generating a beat data set to be tested based on the maximum beat time. For example, the difference between the maximum beat time and the beat data to be tested is set to a multiple of the first preset value of 0.1. Taking the above table as an example, taking the BCD-450 model product as an example, the data in the beat data set to be tested include: 20, 19.9, 19.8, 19.7, 19.6, 19.5, 19.4, 19.3, 19.2, 19.1, 19; wherein the difference between the maximum beat time and the beat data to be tested is less than or equal to the second Preset value. In this embodiment, the second preset value is 1. Due to the limitation of the equipment, the operating time can only be reduced to 19s. It can be understood that if the cycle time of punching station 2 is 20s, if the operating time of its corresponding station is reduced too much, the equipment may be worn, that is, the equipment moves more and faster within the specified time, so the equipment will be worn and the quality of the manufactured products may also decline. Therefore, this application sets the difference between the maximum cycle time and the cycle data to be tested to be less than or equal to the second preset value. The second preset value can be set according to the actual situation. Through the cycle data set to be tested, the equipment utilization corresponding to all data in the cycle data set to be tested is obtained according to the first equipment utilization model, so that the data corresponding to the highest equipment utilization is selected as the target operating time.

[0028] In this embodiment, the control module 2 is further configured to: obtain the number of equipment startups; based on the number of equipment startups, obtain the second equipment utilization rate using the second equipment utilization rate model; the second equipment utilization rate model is: (number of equipment startups ÷ total number of equipment) × 100% = second equipment utilization rate. It can be understood that in addition to the influence of the above-mentioned factors that the automation equipment is in a non-working state during the production process, it also includes the influence of whether the equipment is in a normal working state during the production process. If the equipment is damaged and in a repair state, it will definitely affect the equipment utilization rate and thus cause a decrease in product production; so in this application, the number of equipment startups is obtained through the control module 2, and the number of equipment startups is used to obtain the second equipment utilization rate using the second equipment utilization rate model. For example: there are 100 devices on the production line, and 4 devices are damaged, then the second equipment utilization rate is 96%. The user can understand whether all the equipment on the production line is operating normally through the second equipment utilization rate. If the second equipment utilization rate value is not 100%, the user needs to repair the damaged equipment as soon as possible so that it can be put into production normally, thereby ensuring production volume.

[0029] Depend on Figure 1 It can be seen that the system also includes: a console 3, which is electrically connected to the automation equipment and the control module 2, and is used to set the operating time of the workstation and obtain the number of equipment powered on. In this application, the control module 2 is set in the console 3, and the console 3 is connected to all the automation equipment of the production line for remote control. The user can set the operating time of the workstation through the console 3, and can observe the number of equipment powered on through the console 3.

[0030] In this embodiment, the console 3 is further configured to: receive a signal to be repaired when the automation equipment is damaged, and a normal working signal sent when the repair is completed; based on the signal to be repaired, store the start date when the automation equipment is damaged; based on the normal working signal, store the end date when the automation equipment is damaged. The user can obtain the model of the damaged automation equipment through the console 3 as soon as possible, so as to repair it as soon as possible. The end date and start date of the damaged equipment can be obtained through the console 3, and the user can regularly check the damage records of all equipment, so as to maintain the equipment, thereby avoiding frequent damage, thereby further improving the equipment utilization rate.

[0031] In this embodiment, the console 3 is also configured to: obtain the model information of the product to be tested; store the model information of the product to be tested and the corresponding target running time. If the product entering the production line is processed for the first time, after the target running time is obtained through the above-mentioned production line automation equipment utilization optimization method, it is directly stored in the console 3, as shown in the above table: Taking the BCD-450 model product as an example, the target running time obtained through the above-mentioned production line automation equipment utilization optimization method is 19s, then the product model BCD-450 and the corresponding target running time 19s are directly stored in the console 3. If there are BCD-450 model products in subsequent production, there is no need to re-acquire the target running time, and the workstation can be directly controlled to run at 19s, thereby avoiding the control module 2 from performing repetitive calculations.

[0032] The present application provides a production line automation equipment utilization optimization system, which has the advantages of: installing an MCU chip with a unified calculation system, i.e., a control module 2, in a single process of the production line, so as to intuitively monitor and collect data on the working time of the automation equipment, and by calculating the OEE data, while intuitively monitoring the utilization of each process and link, the operation process, time and efficiency of the automation equipment can be analyzed and optimized, and the use of the output and equipment can be more effectively detected. The production line automation equipment utilization optimization system can intuitively monitor and optimize the steps, processes, working time, etc. in the production process by collecting, sorting and analyzing the data of equipment operation, helping users to find factors that affect the efficiency of equipment utilization. Enterprises can analyze the problems and causes of equipment utilization based on the actual production situation and possible influencing factors, and propose corresponding solutions based on possible causes to continuously improve the comprehensive utilization of equipment, aiming to improve equipment production efficiency and reduce cost expenditures.

[0033] The second aspect of the present application provides a method for optimizing the utilization of production line automation equipment, which is applied to a production line automation equipment utilization optimization system described in any of the above embodiments, including: obtaining the tact time of the product to be tested at each workstation; the tact time is the operating time of the automation equipment corresponding to the workstation; according to the tact time, obtaining the maximum tact time; based on the maximum tact time, using the first equipment utilization model, obtaining the target operating time and controlling the workstation to operate according to the target operating time; the first equipment utilization model is: (time when the equipment is in production state ÷ total equipment operating time) × 100% = equipment utilization; wherein, when the workstation operates according to the target operating time, the equipment utilization is at the highest value. The effects of the above method embodiments can be referred to the effects of the above system embodiments, which will not be repeated here.

[0034] In this embodiment, the method of obtaining the target running time based on the maximum beat time and using the first equipment utilization model includes: generating a beat data set to be tested based on the maximum beat time; the beat data set to be tested includes at least one beat data to be tested, and the difference between the maximum beat time and the beat data to be tested is a multiple of a first preset value; based on the beat data set to be tested, using the first equipment utilization model, obtaining the target beat data to be tested corresponding to the highest utilization value; based on the target beat data to be tested, obtaining the target running time. The effects of the above method embodiments can be found in the effects of the above system embodiments, which will not be described in detail here.

[0035] The above specific implementation methods further explain in detail the purpose, technical solutions and beneficial effects of the embodiments of the present application. It should be understood that the above are only specific implementation methods of the embodiments of the present application and are not used to limit the protection scope of the embodiments of the present application. Any modifications, equivalent substitutions, improvements, etc. made on the basis of the technical solutions of the embodiments of the present application should be included in the protection scope of the embodiments of the present application.

Claims

1. A production line automation equipment utilization optimization system, applied to a production line to be tested, wherein the production line to be tested is provided with a plurality of workstations, and the workstations are provided with automation equipment; characterized in that: include: A sensor (1), wherein the sensor (1) is arranged at each of the workstations of the production line to be tested; the sensor (1) is configured as follows: Obtaining the takt time of the product to be tested at each of the workstations; the takt time is the running time of the automation equipment corresponding to the workstation; According to the beat time, obtaining the maximum beat time; A control module (2), the control module (2) being communicatively connected to the sensor (1) and configured to: Based on the maximum takt time, the target operating time is obtained by using a first equipment utilization model and the workstation is controlled to operate according to the target operating time; the first equipment utilization model is: (Time when the equipment is in production state / total time when the equipment is in operation) × 100% = utilization rate of the first equipment; When the workstation operates according to the target operating time, the utilization rate of the first equipment is at a maximum value.

2. A production line automation equipment utilization optimization system according to claim 1, characterized in that: The control module (2) is further configured to: Based on the maximum beat time, a beat data set to be tested is generated; the beat data set to be tested includes at least one beat data to be tested, and the difference between the maximum beat time and the beat data to be tested is a multiple of a first preset value; Based on the test beat data set, using the first equipment utilization model, obtaining target test beat data corresponding to the maximum utilization value; Based on the target beat data to be tested, a target running time is obtained.

3. A production line automation equipment utilization optimization system according to claim 2, characterized in that: The difference between the maximum beat time and the beat data to be measured is less than or equal to a second preset value.

4. The production line automation equipment utilization optimization system according to claim 1, characterized in that: The control module (2) is also configured to: Get the number of powered-on devices; Based on the number of started devices, the second device utilization rate model is used to obtain the second device utilization rate; the second device utilization rate model is: (Number of devices in operation ÷ total number of devices) × 100% = utilization rate of the second device.

5. The production line automation equipment utilization optimization system according to claim 1, characterized in that: The system further comprises: A control console (3), the control console (3) being electrically connected to the automation equipment and the control module (2), the control console (3) being used to set the operating time of the workstation and obtain the number of equipment started.

6. A production line automation equipment utilization optimization system according to claim 5, characterized in that: The console (3) is also configured to: Receiving a maintenance signal sent when the automation equipment is damaged, and a normal working signal sent when the maintenance is completed; Based on the signal to be repaired, storing a starting date when the automation equipment is damaged; Based on the normal working signal, a deadline when the automation device is damaged is stored.

7. A production line automation equipment utilization optimization system according to claim 5, characterized in that: The console (3) is also configured to: Obtaining model information of the product to be tested; The model information of the product to be tested and the corresponding target running time are stored.

8. A method for optimizing the utilization of production line automation equipment, applied to a system for optimizing the utilization of production line automation equipment as described in any one of claims 1 to 7, characterized in that: include: Obtain the cycle time of the product to be tested at each workstation; The takt time is the operating time of the automation equipment corresponding to the workstation; According to the beat time, obtaining the maximum beat time; Based on the maximum takt time, the target operating time is obtained by using a first equipment utilization model and the workstation is controlled to operate according to the target operating time; the first equipment utilization model is: (Time when the equipment is in production state / total time when the equipment is in operation) × 100% = equipment utilization rate; Wherein, when the workstation operates according to the target operating time, the equipment utilization rate is at a maximum value.

9. A method for optimizing utilization of production line automation equipment according to claim 8, characterized in that: The obtaining of the target operating time based on the maximum takt time and using the first equipment utilization model comprises: Based on the maximum beat time, a beat data set to be tested is generated; the beat data set to be tested includes at least one beat data to be tested, and the difference between the maximum beat time and the beat data to be tested is a multiple of a first preset value; Based on the test beat data set, using the first equipment utilization model, obtaining target test beat data corresponding to the maximum utilization value; Based on the target beat data to be tested, a target running time is obtained.