Bridge guardrail rapid installation and formwork removal robot system and method
By designing a robot system for rapid installation and removal of bridge guardrails, and utilizing the collaborative cooperation of multiple robot bodies and visual sensors, the problems of cumbersome operations and low efficiency in existing construction methods have been solved, and the rapid erection and removal of bridge guardrails has been achieved, improving Improve construction efficiency and quality, and reduce costs.
Patent Information
- Application Number
- CN202411078413.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-07
- Publication Date
- 2024-10-11
AI Technical Summary
The existing bridge anti-collision guardrail construction methods have problems such as cumbersome operation, waste of manpower and time, poor construction quality, high construction cost, and low construction efficiency.
Design a robot system for rapid installation and removal of formwork for bridge guardrails, including a robot body, a lifting mechanism, a Mecanum wheel, a visual sensor and a manipulator mechanism. Through the cooperation of multiple robot bodies, the guardrail formwork can be quickly erected and removed, reducing manual labor. operation to improve construction efficiency and quality.
It significantly improves the construction efficiency of bridge guardrails, ensures construction quality, reduces construction difficulty and cost, reduces workers' labor intensity, and enables rapid installation and removal of formwork.
Smart Images

Figure CN118756592A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of industrial robots, and in particular to a robot system and method for quickly installing and removing molds of bridge guardrails. Background Art
[0002] At present, the construction of domestic bridge anti-collision guardrails mainly adopts the slipform method, plastic steel formwork method, and steel formwork method. The above methods have many disadvantages, such as the poor construction quality of the slipform method, the insufficient strength and rigidity of the plastic steel formwork construction, and the heavy construction and long installation and removal cycle of the steel formwork method. On this basis, the mold construction and removal of the above construction methods require manual operation and common machinery to complete. For example, the mold is lifted to the top edge of the bridge deck by a lifting equipment to align it with the steel bar head reserved for the bridge deck, and then the mold posture is manually adjusted, and then the tension bolts are installed, and then the top of the inner and outer formworks are locked through the connectors. After the complicated formwork procedure, pouring begins. After the pouring is formed, a cumbersome demolding process is also required. After the mold is removed, it needs to be transported to the next workstation by vehicle to repeat the above process.
[0003] As mentioned above, the existing bridge anti-collision guardrail mold construction and dismantling processes are cumbersome, wasting a lot of manpower and time. The manual operation method is prone to subjective operation errors, and the construction quality is difficult to guarantee. As the construction period is extended, the construction cost of the bridge also increases significantly. Summary of the invention
[0004] The present invention provides a bridge guardrail rapid installation and demolding robot system and method, aiming to solve the problems of cumbersome operation, waste of manpower and time, poor construction quality, high construction cost and low construction efficiency in the prior art of manual operation combined with common equipment.
[0005] To solve the above problems, the technical solution of the present invention is:
[0006] A robot system for rapid installation and demolding of bridge guardrails comprises a robot body, the top of the robot body is connected to a lifting platform through a lifting mechanism, the bottom of the robot body is provided with a Mecanum wheel, cross beams are fixedly provided laterally on the front and rear sides of the top of the lifting platform, one end of the two cross beams are commonly connected to an outer formwork and an inner formwork of the bridge guardrail through a clamping mechanism, and the other end is commonly fixedly connected to a counterweight beam, and a positioning beam is also commonly fixedly connected to the bottom of the two cross beams facing the outer formwork and the inner formwork, a plurality of first visual sensors are evenly distributed on the bottom of the positioning beam, the first visual sensors are connected to a control mechanism provided in the robot body, and are used to identify a construction position for casting the bridge guardrail, a pull ring is provided at the rear of the two side walls of the robot body, a manipulator mechanism is provided at the front of the two side walls, and the manipulator mechanism is electrically connected to the control mechanism.
[0007] Preferably, the robot body includes a cubic shell, a Mecanum wheel is installed at the bottom of the shell, the control mechanism is configured to control the Mecanum wheel, a second visual sensor and a first infrared sensor are respectively provided on the four side walls of the shell, a human-machine interaction device electrically connected to the control mechanism is also provided on the outer surface of the shell, and the second visual sensor and the first infrared sensor are respectively connected to the control mechanism signal through wires.
[0008] Preferably, the lifting mechanism includes four first hydraulic cylinders arranged in a rectangular shape at the top of the shell, the fixed end of the first hydraulic cylinder is embedded in the top of the shell, and the telescopic end is fixedly connected to the bottom end of the lifting platform, and the control mechanism is configured to control the telescopic action of the four first hydraulic cylinders, and the control mechanism is electrically connected to the vehicle-mounted power supply through a wire.
[0009] Preferably, a third visual sensor and a second infrared sensor are respectively provided at both ends of the cross beam, the bottom of one end of the two cross beams are respectively fixedly connected to the top of the counterweight beam arranged along the front-to-back direction, the bottom of the other end of the two cross beams are respectively fixedly connected to the top of the positioning beam arranged along the front-to-back direction, and the third visual sensor and the second infrared sensor are respectively connected to the control mechanism signal through wires.
[0010] Preferably, the clamping mechanism includes a first reaction plate and a second reaction plate which penetrate the cross beam vertically and are arranged opposite to each other, the first reaction plate and the second reaction plate are located between the plate body above the cross beam and are laterally connected with a plurality of stiffening ribs, the first reaction plate and the second reaction plate are located below the cross beam, and the inner surface of the plate body is respectively provided with a group of second hydraulic cylinders, the telescopic ends of the two groups of second hydraulic cylinders are respectively fixedly connected to the upper and lower parts of the outer surface of the outer formwork and the upper and lower parts of the outer surface of the inner formwork, and the fixed ends are respectively fixedly connected to the inner surface of the first reaction plate and the inner surface of the second reaction plate.
[0011] Preferably, the inner template and the outer template are arranged relative to each other, and the front and rear ends of the inner template and the outer template extend out of the front and rear ends of the robot body respectively, and the front and rear adjacent robot bodies are connected to the pull ring through a manipulator mechanism, that is, the rear robot body tightens the pull ring of the front robot body through the manipulator mechanism.
[0012] Preferably, the length of the crossbeam is 2 m, the width of the shell is 1.2 m, and the length of the inner and outer templates is 6 m.
[0013] A construction method for a bridge guardrail rapid installation and demolding robot system comprises the following steps:
[0014] Step 1: transport multiple robot bodies to the bridge deck where the construction location is located, the robot bodies adjust their own positions according to the construction environment drawings pre-input by the human-machine interaction device and the visual information collected by the second and third visual sensors, and move to the edge of the bridge deck, and detect the pouring position of the bridge guardrail through the first visual sensor;
[0015] Step 2: The lifting mechanism of the robot body at the rear is started to place the inner template and the outer template at the preset template support position; then, the robot body adjacent to the front side moves backward, and after adjusting the distance with the robot body adjacent to the rear side, the inner template and the outer template connected to it are placed at the correct template support position, and the robot body adjacent to the rear side tightens the pull ring of the robot body adjacent to the front side through the manipulator mechanism to make the two groups of inner templates and outer templates butt end to end; repeat the above steps to achieve the positioning and docking of multiple robot bodies and multiple groups of inner templates and outer templates;
[0016] Step 3: pouring concrete to form the bridge guardrail;
[0017] Step 4: Each robot body starts the second hydraulic cylinder to retract, removes the inner template and the outer template from the formed bridge, starts the first hydraulic cylinder to suspend the bottom of the inner template and the outer template, and multiple robot bodies move forward synchronously to the next construction position. After arriving at the new workstation, multiple robot bodies simultaneously place the inner template and the outer template at the preset construction position to complete the pouring of the bridge guardrail at the new workstation;
[0018] Step 5: Repeat step 4 until all bridge guardrails are cast and formed.
[0019] The present invention provides a bridge guardrail rapid installation and demolding robot system and method, which has the following beneficial effects:
[0020] The present invention can realize the rapid erection and removal of guardrail templates through the coordinated cooperation of multiple robot bodies. Through the synchronous movement of the robot bodies, the efficiency of mold erection at each station after the first station is further greatly improved. By mutually tightening the robot bodies, multiple robot bodies are combined into a large robot system, which is suitable for large-scale on-site construction of bridge guardrails. Through the above settings, the present invention can significantly improve the construction efficiency of bridge guardrails, ensure construction quality, reduce construction difficulty, improve construction convenience, save construction costs, and reduce the labor intensity of workers. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 , a rear view structural schematic diagram of the present invention during construction;
[0022] Figure 2 , a schematic diagram of a top view of the structure of an embodiment of the present invention (without the positioning beam; without a manipulator mechanism);
[0023] Figure 3 , a schematic diagram of a top view of the structure of an embodiment of the present invention (showing a positioning beam; provided with a manipulator mechanism);
[0024] Figure 4 , a schematic diagram of the present invention combining multiple robot bodies into one robot system to perform bridge deck guardrail construction;
[0025] 1: bridge deck, 2: shell, 3: lifting platform, 4: cross beam, 5: counterweight beam, 6: positioning beam, 7: first reaction plate, 8: second reaction plate, 9: stiffening rib plate, 10: second visual sensor, 11: Mecanum wheel, 12: pull ring, 13: third visual sensor, 14: outer formwork, 15: inner formwork, 16: second hydraulic cylinder, 17: first hydraulic cylinder, 18: manipulator mechanism. DETAILED DESCRIPTION
[0026] The following describes in detail the implementation mode of the present invention in a step-by-step manner. The description is only a preferred embodiment of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
[0027] In the description of the present invention, it should be noted that the directions or positional relationships indicated by terms such as “upper”, “lower”, “left”, “right”, “top”, “bottom”, “inside” and “outside” are based on the directions or positional relationships shown in the accompanying drawings, and are only for the purpose of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, and a specific direction structure and operation, and therefore cannot be understood as a limitation on the present invention.
[0028] Example 1
[0029] A bridge guardrail rapid installation and demoulding robot system, such as Figure 1-4 As shown, the robot body comprises a robot body, the top of the robot body is connected to a lifting platform 3 through a lifting mechanism, a Mecanum wheel 11 is provided at the bottom of the robot body, a crossbeam 4 is fixedly provided on the front and rear sides of the top of the lifting platform 3 in the transverse direction, one end of the two crossbeams 4 is commonly connected to an outer template 14 and an inner template 15 of a bridge guardrail through a clamping mechanism, and the other end is commonly fixedly connected to a counterweight beam 5, and a positioning beam 6 is also commonly fixedly connected to the bottom of the two crossbeams 4 on the side facing the outer template 14 and the inner template 15, and a plurality of first visual sensors (such as Figure 1 As shown in the figure, not marked), the first visual sensor is connected to the control mechanism disposed in the robot body and is used to identify the construction position of pouring bridge guardrails, such as Figure 1 , 3As shown, a pull ring 12 is provided at the rear of the two side walls of the robot body, and a manipulator mechanism 18 is provided at the front of the two side walls. The manipulator mechanism 18 is electrically connected to the control mechanism.
[0030] In this embodiment, the structure and driving technology of the Mecanum wheel are prior art and will not be elaborated here. The manipulator mechanism 18 and the robot body can adopt the automation equipment in the prior art that can realize the relevant functions of the present invention. The positioning beam is used to locate the support position of the template. After positioning, the inner template and the outer template can be placed in the set position, and the cumbersome template support procedure is avoided by the clamping mechanism. It should be noted that the robot body can level itself through the vehicle suspension technology, and then automatically realize the leveling and straightening of the inner template and the outer template. Since there is no need to use the tension screw and the connector connecting the top of the inner and outer templates, the inner template and the outer template can be quickly installed, and the subsequent process of plugging the bolt holes is also omitted.
[0031] Example 2
[0032] like Figure 1-4 As shown, the robot body includes a cubic shell 2, a Mecanum wheel 11 is installed at the bottom of the shell 2, and the control mechanism is configured to control the Mecanum wheel 11. The four side walls of the shell 2 are respectively provided with a second visual sensor 10 and a first infrared sensor (not shown in the figure), and a human-machine interaction device (not shown in the figure) electrically connected to the control mechanism is also provided on the outer surface of the shell 2. The second visual sensor 10 and the first infrared sensor are respectively connected to the control mechanism by wires. The second visual sensor 10 and the first infrared sensor assist the robot body in realizing path recognition and obstacle avoidance.
[0033] like Figure 1 , 3 As shown, the lifting mechanism includes four first hydraulic cylinders 17 arranged in a rectangular shape at the top of the housing 2. The fixed end of the first hydraulic cylinder 17 is embedded in the top of the housing 2, and the telescopic end is fixedly connected to the bottom of the lifting platform 3. The control mechanism is configured to control the telescopic action of the four first hydraulic cylinders 17. The control mechanism is electrically connected to the vehicle power supply through a wire. When the lifting platform rises, the bottom of the inner and outer templates can be separated from the construction position, and then the robot body can move on the bridge deck. When the lifting platform descends, the bottom of the inner and outer templates can be placed at the construction position. After the robot body is locked, pouring construction can be carried out.
[0034] like Figure 1 , 2As shown, a third visual sensor 13 and a second infrared sensor (not shown in the figure) are respectively provided at both ends of the cross beam 4, the bottom of one end of the two cross beams 4 are respectively fixedly connected to the top of the counterweight beam 5 arranged along the front-to-back direction, and the bottom of the other end of the two cross beams 4 are respectively fixedly connected to the top of the positioning beam 6 arranged along the front-to-back direction, and the third visual sensor 13 and the second infrared sensor are respectively connected to the control mechanism signal through wires to assist the robot in identifying the position and avoiding obstacles.
[0035] Example 3
[0036] like Figure 1-4 As shown, the clamping mechanism includes a first reaction plate 7 and a second reaction plate 8 which penetrate the cross beam 4 vertically and are arranged opposite to each other. The first reaction plate 7 and the second reaction plate 8 are located between the plate bodies above the cross beam 4 and are laterally connected with a plurality of stiffening ribs 9. The inner surfaces of the first reaction plate 7 and the second reaction plate 8 which are located below the cross beam are respectively provided with a group of second hydraulic cylinders 16. The telescopic ends of the two groups of second hydraulic cylinders 16 are respectively fixedly connected to the upper and lower parts of the outer surface of the outer formwork 14 and the upper and lower parts of the outer surface of the inner formwork 15, and the fixed ends are respectively fixedly connected to the inner surfaces of the first reaction plate 7 and the inner surfaces of the second reaction plate 8.
[0037] The arrangement of this embodiment can avoid the tedious operation of connecting the inner and outer formworks of conventional bridge guardrails through tension screws and connectors, facilitate the formwork and demolding processes, improve work efficiency, and ensure the accuracy of the alignment of the inner and outer formworks.
[0038] Example 4
[0039] like Figure 1-4 As shown, the inner template 15 and the outer template 14 are arranged relatively to each other, and the front and rear ends of the inner template 15 and the outer template 14 extend out of the front and rear ends of the robot body respectively, and the front and rear adjacent robot bodies are connected to the pull ring 12 through the manipulator mechanism 18, that is, the rear robot body tightens the pull ring 12 of the front robot body through the manipulator mechanism 18.
[0040] In this embodiment, by connecting the robot bodies, multiple robot bodies can operate simultaneously, which can greatly improve construction efficiency.
[0041] Example 5
[0042] like Figure 1-4 As shown, the length of the crossbeam is 2m, the width of the shell is 1.2m, and the length of the inner and outer templates is 6m.
[0043] This embodiment is configured in this way to facilitate the robot body to walk on the bridge deck or road surface, further improving the convenience of construction.
[0044] Example 6
[0045] Based on the above embodiments, this embodiment discloses a construction method of a bridge guardrail rapid installation and demolding robot system, such as Figure 1-4 As shown, the following steps are included:
[0046] Step 1: transport multiple robot bodies to the bridge deck where the construction location is located, the robot bodies adjust their own positions according to the construction environment drawings pre-input by the human-machine interaction device and the visual information collected by the second and third visual sensors, and move to the edge of the bridge deck, and detect the pouring position of the bridge guardrail through the first visual sensor;
[0047] Step 2: The lifting mechanism of the robot body at the rear is started to place the inner template and the outer template at the preset template support position; then, the robot body adjacent to the front side moves backward, and after adjusting the distance with the robot body adjacent to the rear side, the inner template and the outer template connected to it are placed at the correct template support position, and the robot body adjacent to the rear side tightens the pull ring of the robot body adjacent to the front side through the manipulator mechanism to make the two groups of inner templates and outer templates butt end to end; repeat the above steps to achieve the positioning and docking of multiple robot bodies and multiple groups of inner templates and outer templates;
[0048] Step 3: pouring concrete to form the bridge guardrail;
[0049] Step 4: Each robot body starts the second hydraulic cylinder to retract, removes the inner template and the outer template from the formed bridge, starts the first hydraulic cylinder to suspend the bottom of the inner template and the outer template, and multiple robot bodies move forward synchronously to the next construction position. After arriving at the new workstation, multiple robot bodies simultaneously place the inner template and the outer template at the preset construction position to complete the pouring of the bridge guardrail at the new workstation;
[0050] Step 5: Repeat step 4 until all bridge guardrails are cast and formed.
[0051] This embodiment provides the construction method and construction principle of the present invention (this method omits the conventional steps of installing the end templates at both ends of the mold. The end templates are generally connected to the ends of the inner and outer templates by bolts. After each template is in place, the end templates can be manually encapsulated). Through the coordinated cooperation of multiple robot bodies, the rapid support and rapid removal of the guardrail template can be achieved. Through the synchronous movement of the robot bodies, the mold support efficiency of each station after the first station is further greatly improved. Through the mutual tightening of the robot bodies, multiple robot bodies are combined into a large robot system, which is suitable for large-scale on-site construction of bridge guardrails. Through the above settings, the present invention can significantly improve the construction efficiency of bridge guardrails, ensure construction quality, reduce construction difficulty, improve construction convenience, save construction costs, and reduce the labor intensity of workers.
Claims
1. A bridge guardrail rapid installation and demoulding robot system, characterized by: The invention comprises a robot body, the top of the robot body is connected to a lifting platform through a lifting mechanism, the bottom of the robot body is provided with a Mecanum wheel, cross beams are fixedly provided along the horizontal direction on the front and rear sides of the top of the lifting platform, one end of the two cross beams are commonly connected to the outer formwork and the inner formwork of the bridge guardrail through a clamping mechanism, and the other end is commonly fixedly connected to a counterweight beam, and the bottom of the two cross beams facing the outer formwork and the inner formwork are also commonly fixedly connected to a positioning beam, a plurality of first visual sensors are evenly distributed on the bottom of the positioning beam, the first visual sensors are connected to a control mechanism arranged in the robot body, and are used to identify the construction position of casting the bridge guardrail, a pull ring is provided at the rear of the two side walls of the robot body, a manipulator mechanism is provided at the front of the two side walls, and the manipulator mechanism is electrically connected to the control mechanism.
2. A bridge guardrail rapid installation and demolding robot system as claimed in claim 1, characterized in that: The robot body includes a cubic shell, a Mecanum wheel is installed at the bottom of the shell, the control mechanism is configured to control the Mecanum wheel, a second visual sensor and a first infrared sensor are respectively provided on the four side walls of the shell, and a human-machine interaction device electrically connected to the control mechanism is also provided on the outer surface of the shell, and the second visual sensor and the first infrared sensor are respectively connected to the control mechanism signal through wires.
3. A bridge guardrail rapid installation and demolding robot system as claimed in claim 2, characterized in that: The lifting mechanism includes four first hydraulic cylinders arranged in a rectangular shape at the top of the shell, the fixed end of the first hydraulic cylinder is embedded in the top of the shell, and the telescopic end is fixedly connected to the bottom end of the lifting platform. The control mechanism is configured to control the telescopic action of the four first hydraulic cylinders, and the control mechanism is electrically connected to the vehicle-mounted power supply through a wire.
4. A bridge guardrail rapid installation and demolding robot system as claimed in claim 3, characterized in that: A third visual sensor and a second infrared sensor are respectively provided at both ends of the cross beam, the bottom of one end of the two cross beams are respectively fixedly connected to the top of the counterweight beam arranged along the front and rear direction, and the bottom of the other end of the two cross beams are respectively fixedly connected to the top of the positioning beam arranged along the front and rear direction, and the third visual sensor and the second infrared sensor are respectively connected to the control mechanism signal through wires.
5. A bridge guardrail rapid installation and demolding robot system as claimed in claim 4, characterized in that: The clamping mechanism includes a first reaction plate and a second reaction plate that penetrate the cross beam vertically and are arranged opposite to each other. The first reaction plate and the second reaction plate are located between the plate body above the cross beam and are connected with a plurality of stiffening ribs in the transverse direction. The first reaction plate and the second reaction plate are located below the cross beam, and the inner surface of the plate body is respectively provided with a group of second hydraulic cylinders. The telescopic ends of the two groups of second hydraulic cylinders are respectively fixedly connected to the upper and lower parts of the outer surface of the outer formwork and the upper and lower parts of the outer surface of the inner formwork, and the fixed ends are respectively fixedly connected to the inner surface of the first reaction plate and the inner surface of the second reaction plate.
6. A bridge guardrail rapid installation and demolding robot system as claimed in claim 5, characterized in that: The inner template and the outer template are arranged relatively to each other, and the front and rear ends of the inner template and the outer template extend out of the front and rear ends of the robot body respectively. The front and rear adjacent robot bodies are connected to the pull ring through a manipulator mechanism, that is, the rear robot body tightens the pull ring of the front robot body through the manipulator mechanism.
7. A bridge guardrail rapid installation and demolding robot system as claimed in claim 6, characterized in that: The length of the crossbeam is 2m, the width of the shell is 1.2m, and the length of the inner template and the outer template is 6m.
8. The construction method of a bridge guardrail rapid installation and demolding robot system as claimed in claim 7, characterized in that: The steps include: Step 1: transport multiple robot bodies to the bridge deck where the construction location is located, the robot bodies adjust their own positions according to the construction environment drawings pre-input by the human-machine interaction device and the visual information collected by the second and third visual sensors, and move to the edge of the bridge deck, and detect the pouring position of the bridge guardrail through the first visual sensor; Step 2: The lifting mechanism of the robot body at the rear is started to place the inner template and the outer template at the preset template support position; then, the robot body adjacent to the front side moves backward, and after adjusting the distance with the robot body adjacent to the rear side, the inner template and the outer template connected to it are placed at the correct template support position, and the robot body adjacent to the rear side tightens the pull ring of the robot body adjacent to the front side through the manipulator mechanism to make the two groups of inner templates and outer templates butt end to end; repeat the above steps to achieve the positioning and docking of multiple robot bodies and multiple groups of inner templates and outer templates; Step 3: pouring concrete to form the bridge guardrail; Step 4: Each robot body starts the second hydraulic cylinder to retract, removes the inner template and the outer template from the formed bridge, starts the first hydraulic cylinder to suspend the bottom of the inner template and the outer template, and multiple robot bodies move forward synchronously to the next construction position. After arriving at the new workstation, multiple robot bodies simultaneously place the inner template and the outer template at the preset construction position to complete the pouring of the bridge guardrail at the new workstation; Step 5: Repeat step 4 until all bridge guardrails are cast and formed.