Intelligent mechanical mining method for deep hard rock mine with hydraulic fracturing of rock
Through the combination of rock hydraulic fracturing and big data decision-making platform, the safety hazards and low efficiency of drill and blast method in deep mine mining are solved, and intelligent, automated and mechanized mining of deep hard rock mines are realized, improving efficiency and safety, reduced costs and environmental impact.
Patent Information
- Application Number
- CN202410901423.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-05
- Publication Date
- 2024-10-11
AI Technical Summary
In deep mining, the drill and blast method has safety hazards, environmental pollution, low energy utilization, and poor mining efficiency. In addition, the efficiency of the tunnel boring machine decreases when encountering hard rock, and the equipment wears out, resulting in increased costs and the inability to achieve real-time feedback and accuracy. decision making.
The intelligent mechanical mining method of rock hydraulic fracturing is adopted. The rock drill is used to identify the rock hardness, perform hydraulic fracturing, adjust the rock breaking parameters of the tunnel boring machine, and use the big data decision-making platform to monitor and optimize the mining process in real time to achieve intelligent, Automated and mechanized mining.
It improves mining efficiency, reduces time and energy consumption, enhances safety and environmental protection, reduces equipment wear and cost, and realizes efficient and intelligent mining of deep hard rock mines.
Smart Images

Figure CN118757150A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of mining deep hard rock high ground stress mines, and in particular to an intelligent mechanical mining method for deep hard rock mines by hydraulic fracturing of rocks. Background Art
[0002] Deep underground rock engineering involves multiple fields such as resource and energy mining, water conservancy and hydropower engineering, tunnel transportation engineering, and high-level radioactive waste disposal. In terms of resource and energy mining, with the continuous development of society and economy, human demand for energy continues to increase. With the continuous mining in recent decades, human mining of resources and energy has transitioned from shallow to deep, and the characteristics of high-stress hard rock generated in the deep are becoming more and more prominent, bringing new challenges to the mining of deep mines.
[0003] Deep mining is currently mainly carried out through the drilling and blasting method, but this method has major drawbacks. First, the use of the drilling and blasting method has great safety hazards in the mining process, which can easily cause personal and property safety problems. The dust generated during the mining process is also harmful to the human body and the environment. Secondly, the explosion stress wave generated during the drilling and blasting construction has a large disturbance and damage to the surrounding rock, and is also likely to have an adverse impact on the surrounding environment. This method also causes a large amount of non-human over-excavation and is not easy to accurately construct. In addition, the drilling and blasting method requires a lot of manpower and equipment, and the energy utilization rate generated by the blasting is low. There is a large amount of energy loss, which makes the overall mining efficiency poor.
[0004] The rocks in deep mines are often hard and have high ground stress. When using a tunnel boring machine to break rocks in the mine, when encountering complete and hard rocks, the tunneling efficiency of the tunnel boring machine will be greatly reduced or even completely unable to tunnel, seriously affecting the overall construction progress of the project. In this case, the tool equipment of the tunnel boring machine will wear out greatly, and frequent equipment replacement will lead to increased tunneling costs.
[0005] At present, in mining based on traditional drilling and blasting or tunneling methods, when problems arise in a certain production and construction link, real-time feedback, analysis, decision-making and resolution cannot be achieved, which may affect the construction of the entire line and cause a large waste of manpower, money, materials and machinery. Summary of the invention
[0006] The purpose of the present invention is to provide an intelligent mechanical mining method for deep hard rock mines by hydraulic fracturing of rocks, which can realize the mining of deep hard rock mines through a safe, environmentally friendly and efficient fracturing method, realize the intelligent, automated and mechanized mining of mines, effectively improve the mining efficiency, and save time cost and energy consumption.
[0007] To achieve the above object, the present invention provides an intelligent mechanical mining method for deep hard rock mines by hydraulic fracturing of rocks, comprising the following steps:
[0008] S1. Identify and distinguish the hardness of different rocks, obtain the distribution results of rock hardness and cuttability, intelligently identify and distinguish the hardness of different rocks on the face of the ore body through the rock drilling arm of the rock drilling vehicle, and quantify the hardness of the rock. According to the rock hardness evaluation system, the corresponding relationship between rock hardness and rock cuttability is established to form a digital hardness and cuttability evolution law diagram of the rock on the face;
[0009] S2. According to the rock hardness and cuttability distribution results obtained in S1, prefabricated defect treatment is performed for rocks with high hardness that are difficult to cut directly, that is, a rock fracturing construction process based on hydraulic fracturing is performed. For rocks with low hardness and easy to cut, no prefabricated defect treatment is performed;
[0010] S3, based on the construction process and results of hydraulic fracturing in S2, intelligently judge the effect of rock fracturing development on the generation of joints and fissures, and then judge whether to carry out the excavation process of the tunnel boring machine according to the effect. If excavation is not possible, continue the hydraulic fracturing construction and judge the effect;
[0011] S4. According to the judgment result of S3, the rock breaking power and rock breaking parameters of the tunnel boring machine are adjusted in real time and intelligently to carry out the rock excavation process, and the rock mass with prefabricated defects after hydraulic fracturing construction is mined to realize the intelligent mechanized mining of deep hard rock mines;
[0012] During the excavation process, the strength and cuttability characteristics of the rock after fracturing and water softening are fed back to the big data information decision-making platform;
[0013] S5. After the tunnel boring machine excavates a working section, the mining data of the corresponding working section is generated and transmitted to the big data information decision-making platform. Steps S1-S4 are repeated over and over again to finally realize intelligent mechanical mining in deep hard rock mines.
[0014] Preferably, in step S1, the tip of the rock drilling arm is a diamond drill bit for performing an indentation test on the rock at the face.
[0015] Preferably, under the same output power of the rock drilling arm, the hardness of different rocks on the tunnel face is judged according to the indentation difficulty and scratch depth obtained by the indentation test.
[0016] Preferably, the scratch depth is measured by comparing the displacement before and after the indentation test using high-precision DIC or optical scanning equipment, and the data is transmitted to a big data information decision-making platform, and a rock hardness distribution cloud map and a rock cuttability evolution law map are automatically generated through a program.
[0017] Preferably, the hydraulic fracturing in step S2 adopts a conventional fracturing method based on drilling, grooving, sealing, and water injection fracturing, or adopts a high-pressure water abrasive jet technology for fracturing, or places a perforating gun in the borehole and then performs hydraulic fracturing.
[0018] Preferably, the effect of producing joints and fissures in rock fracturing in step S3 includes the length, width, geometric characteristics of the joints and fissures, as well as their number, direction, and inclination characteristics.
[0019] Preferably, the crack development is detected by ultrasonic geophysical exploration, or macroscopically qualitatively determined by drilling observation holes.
[0020] Preferably, the rock breaking power in step S4 refers to the output power during the excavation process.
[0021] Preferably, the rock breaking parameters include the size and rotation speed of the cutter or cutter disc of the tunnel boring machine; the size and spacing of the cutter teeth; the cutting depth, angle and cutting speed.
[0022] Preferably, the big data information decision-making platform in step S5 collects, stores, analyzes, processes and provides feedback on the mining data in the process from S1 to S4, and comprehensively manages the construction process of the four stages S1-S4.
[0023] Therefore, the present invention adopts the above-mentioned deep hard rock mine intelligent mechanical mining method of rock hydraulic fracturing, and the beneficial effects are as follows:
[0024] The rock hardness on the tunnel face surface is used as the rock cuttability judgment index, which has the advantages of simple and fast operation;
[0025] The method of using hydraulic fracturing to fracture rocks and form joints and fissures has the advantages of being safe, economical, efficient, environmentally friendly, and causing little disturbance to the surrounding environment.
[0026] The cracks produced by hydraulic fracturing are usually highly developed, and the length of the cracks can extend to several meters or even longer. The large number of cracks formed can effectively increase the degree of rock fragmentation, thereby improving the cuttability of the rock. In addition, the strength of the rock is reduced under the softening effect of water immersion, which will also increase the cuttability of the rock.
[0027] The cutting power and cutting parameters of the tunnel boring machine can be adjusted intelligently in real time based on the cuttability of the ore body fed back by rock hardness. The intelligent construction plan is conducive to improving its mining efficiency and saving time costs and energy consumption.
[0028] The big data information decision-making platform has the characteristics of autonomous identification and learning, autonomous analysis and processing, autonomous monitoring and feedback, and autonomous decision-making. The construction of this platform is conducive to summarizing the construction experience of each stage and each step of the construction process, and guiding the construction of the next stage accordingly, increasing the accuracy of decision-making at each step in the mining process, thereby achieving the purpose of intelligent, digital, and mechanized mining.
[0029] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a schematic diagram of the distribution of rock lithology hardness at the face of an embodiment of an intelligent mechanical mining method for deep hard rock mines using hydraulic rock fracturing according to the present invention;
[0031] Figure 2 It is a schematic diagram of an indentation test line and hydraulic fracturing drilling of an embodiment of a deep hard rock mine intelligent mechanical mining method for rock hydraulic fracturing of the present invention;
[0032] Figure 3 It is a schematic diagram of a rock drilling trolley in an embodiment of a method for intelligent mechanical mining of deep hard rock mines by hydraulic rock fracturing of the present invention;
[0033] Figure 4 It is a schematic diagram of a tunneling machine of an embodiment of an intelligent mechanical mining method for deep hard rock mines using hydraulic rock fracturing according to the present invention;
[0034] Figure 5 It is a schematic diagram of the cutting or perforating positions of an embodiment of an intelligent mechanical mining method for deep hard rock mines by hydraulic fracturing of rocks according to the present invention;
[0035] Figure 6 This is a hypothetical schematic diagram of hydraulic fracturing of an embodiment of an intelligent mechanical mining method for deep hard rock mines using hydraulic fracturing of rocks according to the present invention;
[0036] Figure 7 It is a schematic diagram of an intelligent mining mode of a deep hard rock mine according to an embodiment of an intelligent mechanical mining method for a deep hard rock mine using hydraulic rock fracturing of the present invention.
[0037] Reference numerals
[0038] 1. Clay rock; 2. Limestone; 3. Mudstone; 4. Filling material; 5. Natural joints; 6. Indentation layout line; 7. Hydraulic drilling; 8. Drilling rig; 9. Control room; 10. First drill arm; 11. Hanging basket; 12. Second drill arm; 13. Third drill arm; 14. DIC equipment; 15. Ultrasonic equipment; 16. Diamond drill bit; 17. Longitudinal axis pick-tooth type tunnel boring machine; 18. Horizontal axis roller cutter type tunnel boring machine; 19. Pick; 20. Roller; 21. Face; 22. Drilling; 23. Perforation; 24. Hydraulic fracturing crack; 25. Big data information decision-making platform. DETAILED DESCRIPTION
[0039] The technical solution of the present invention is further described below through the accompanying drawings and embodiments.
[0040] Unless otherwise defined, technical or scientific terms used in the present invention shall have the common meanings understood by one having ordinary skills in the field to which the present invention belongs.
[0041] Embodiment 1
[0042] The present invention provides an intelligent mechanical mining method for deep hard rock mines by hydraulic fracturing of rocks, comprising the following steps:
[0043] S1. A worker controls the first drill arm 10 of the drilling rig 8 in the control room 9 to perform an indentation test on different rocks of the tunnel face 21 at the same output power. The schematic diagram of the drilling rig is shown in FIG. Figure 3 As shown in the figure, the rock hardness distribution diagram of the tunnel face 21 is as follows Figure 1 As shown, it is the distribution of some rock layers of the face 21, including clay rock 1, limestone 2, mudstone 3, filling material 4, and natural joints 5.
[0044] During the test, the spacing between the measuring lines is 10-15cm, and the spacing between the measuring lines is 10-15cm. The drill bit used in the first drill arm 10 is a diamond drill bit 16, which has the highest hardness and can perform an indentation test on rocks of any hardness. After the indentation test, rocks with different hardness will form scratches of different depths on their surfaces. The scratch depth can be obtained by comparing the displacement difference before and after the indentation test by the DIC or optical scanning device 14 installed on the hanging basket 11. Under the same output power of the first drill arm 10, the greater the scratch depth, the smaller the rock hardness, thereby establishing a corresponding relationship between rock hardness and scratch depth, and realizing intelligent identification, differentiation and quantitative processing of rock hardness. The data is then transmitted to the big data information decision-making platform 25, and a rock hardness distribution map and a rock cuttability evolution law map are automatically generated through a program.
[0045] S2. For the hard and difficult-to-mine rocks identified in step S1, firstly drill a hole through the first drill arm 10. The depth of the hole 22 is 5-10m, and should not exceed 10m. Then, the second drill arm 12 performs high-pressure water abrasive jet cutting or inserts a perforating gun into the formed hole for perforating operation to form initial cracks, which is beneficial to the induction of cracks in the later hydraulic fracturing process. The spacing between two grooves or perforations 23 of the same hydraulic drill hole 22 is 0.3-0.5m. The schematic diagram of the position of the groove or perforation 23 is as shown in FIG. Figure 5 shown.
[0046] Then, hydraulic fracturing operation is performed through the third drill arm 13. The spacing of hydraulic drill holes is 3-4m and the row spacing is 3m. The hydraulic fracturing method is used to produce defects such as prefabricated joints and cracks inside the rock, thereby destroying the integrity of the rock and improving the crushability and cuttability of the rock.
[0047] When the joints and fissures generated inside the rock develop to a certain scale, a local mining loose zone will be formed, which will achieve the purpose of releasing the original rock stress, creating free surface and compensating space. At the same time, the strength of the rock will be reduced due to the softening effect of water after being soaked in water, which will significantly improve the cuttability of the rock.
[0048] For rocks with low hardness and good cuttability that can be directly broken and cut, no prefabrication defect treatment is performed. The relationship between injection parameters such as injection pressure and flow rate and time during hydraulic fracturing will be recorded in real time in the big data information decision-making platform25.
[0049] S3. During the hydraulic fracturing construction process of step S2, the development of hydraulic cracks caused by rock fracturing is monitored in real time by ultrasonic equipment 15, and the ultrasonic equipment 15 is arranged 1-1.5 m above and below the hydraulic drilling hole of the tunnel face 21.
[0050] The monitoring of crack development includes geometric characteristics such as crack length and width, as well as geometric characteristics such as number, direction, and inclination. Figure 6 As shown in the figure, according to a large number of indoor and field tests of hydraulic fracturing, it is known that the main cracks produced by hydraulic fracturing are along the direction of maximum principal stress and perpendicular to the direction of minimum principal stress. The crack extension length can reach several meters. Figure 2 The indentation layout lines 6 and the hydraulic drill holes 7 arranged in the middle are used for fracturing, which can greatly reduce the number of drill holes 22 while fully fracturing the rock, thereby reducing costs and accelerating construction progress.
[0051] The crack length can be obtained based on the KGD model of two-dimensional hydraulic crack:
[0052]
[0053] Where, L is the crack length; Q is the construction displacement; H is the crack height; C is the fracturing fluid loss coefficient; w max represents the maximum crack width; t is the fracturing time; S p Indicates the initial filtration loss of fracturing fluid; erfc(α L ) is α L Error compensation parameter; α L It indicates the distance of the crack from the start of fracturing along the x direction when considering the initial filtration loss time t.
[0054] During the fracturing process, the crack development conditions monitored by ultrasonic wave will be transmitted to the big data information decision-making platform 25 in real time for storage, and analyzed based on this to see whether the conditions for tunnel boring machine excavation are met. When it is detected that the main hydraulic cracks have extended to the boundary of hard rock, it can be considered that the conditions for excavation are met.
[0055] S4. When the development conditions of hydraulic cracks in step S3 meet the conditions for excavation, excavation operation begins. Currently, commonly used mechanical excavators are longitudinal axis pick-tooth excavators 17 and transverse axis roller cutter excavators 18, such as Figure 4 As shown, the excavation operation is completed by the pick 19 and the roller cutter 20 respectively. During the excavation process, the rock breaking power and rock breaking parameters of the roadheader can be adjusted in real time, wherein the rock breaking power refers to the output power of the roadheader during the excavation process, and the rock breaking parameters include the size of the roller cutter (cutter disc) of the roadheader and its rotation speed; the size and spacing of the cutter teeth; the cutting depth, angle and cutting speed, etc. In addition, during the excavation process, the hardness and cuttability of the rock can be fed back in real time according to the cutting conditions of the roller cutter or the cutter disc, and its information data is stored in the big data information decision-making platform 25, which will provide a basis for analysis for the mining of the next working section.
[0056] S5. After the tunnel boring machine completes each work section, the mining data of the corresponding work section will be generated and transmitted to the big data information decision-making platform 25. The mining data includes rock hardness distribution cloud map, hydraulic fracturing data, crack development, and rock breaking parameters. Then, steps S1-S4 are repeated for each work section. By collecting, storing, analyzing, processing and feedback of the above mining data, the construction process of the four stages of S1-S4 is comprehensively managed and controlled, and finally the whole process of intelligent mechanical mining in deep hard rock mines is realized. The schematic diagram of its mining mode is shown as follows Figure 7 shown.
[0057] Therefore, the present invention adopts the above-mentioned intelligent mechanical mining method for deep hard rock mines using rock hydraulic fracturing, and realizes the mining of deep hard rock mines through a safe, environmentally friendly and efficient fracturing method, which can realize the intelligent, automated and mechanized mining of mines, effectively improve mining efficiency, and save time cost and energy consumption.
[0058] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that they can still modify or replace the technical solution of the present invention with equivalents, and these modifications or equivalent replacements cannot cause the modified technical solution to deviate from the spirit and scope of the technical solution of the present invention.
Claims
1. An intelligent mechanical mining method for deep hard rock mines using rock hydraulic fracturing, characterized in that: The following steps are involved: S1. Identify and distinguish the hardness of different rocks, obtain the distribution results of rock hardness and cuttability, intelligently identify and distinguish the hardness of different rocks on the face of the ore body through the rock drilling arm of the rock drilling vehicle, and quantify the hardness of the rock. According to the rock hardness evaluation system, the corresponding relationship between rock hardness and rock cuttability is established to form a digital hardness and cuttability evolution law diagram of the rock on the face; S2. According to the rock hardness and cuttability distribution results obtained in S1, prefabricated defect treatment is performed for rocks with high hardness that are difficult to cut directly, that is, a rock fracturing construction process based on hydraulic fracturing is performed. For rocks with low hardness and easy to cut, no prefabricated defect treatment is performed; S3, based on the construction process and results of hydraulic fracturing in S2, intelligently judge the effect of rock fracturing development on the generation of joints and fissures, and then judge whether to carry out the excavation process of the tunnel boring machine according to the effect. If excavation is not possible, continue the hydraulic fracturing construction and judge the effect; S4. According to the judgment result of S3, the rock breaking power and rock breaking parameters of the tunnel boring machine are adjusted in real time and intelligently to carry out the rock excavation process, and the rock mass with prefabricated defects after hydraulic fracturing construction is mined to realize the intelligent mechanized mining of deep hard rock mines; During the excavation process, the strength and cuttability characteristics of the rock after fracturing and water softening are fed back to the big data information decision-making platform; S5. After the tunnel boring machine excavates a working section, the mining data of the corresponding working section is generated and transmitted to the big data information decision-making platform. Steps S1-S4 are repeated over and over again to finally realize intelligent mechanical mining in deep hard rock mines.
2. The method of deep hard rock mining by hydraulic fracturing according to claim 1 is characterized by: In step S1, the tip of the rock drilling arm is a diamond drill bit, which is used to perform an indentation test on the rock at the tunnel face.
3. The intelligent mechanical mining method for deep hard rock mines by hydraulic rock fracturing according to claim 2 is characterized by: Under the same output power of the rock drill arm, the hardness of different rocks on the tunnel face is judged according to the indentation difficulty and scratch depth obtained by the indentation test.
4. The intelligent mechanical mining method for deep hard rock mines by hydraulic fracturing of rocks according to claim 3 is characterized by: The scratch depth is measured by comparing the displacement before and after the indentation test using high-precision DIC or optical scanning equipment, and the data is transmitted to a big data information decision-making platform, and a rock hardness distribution cloud map and a rock cuttability evolution law map are automatically generated through a program.
5. The method of deep hard rock mining by hydraulic fracturing according to claim 1 is characterized by: The hydraulic fracturing in step S2 adopts a conventional fracturing method based on drilling, grooving, sealing, and water injection fracturing, or adopts a high-pressure water abrasive jet technology for fracturing, or places a perforating gun in the borehole and then performs a hydraulic fracturing method.
6. The intelligent mechanical mining method for deep hard rock mines by hydraulic rock fracturing according to claim 1 is characterized by: The effect of rock fracturing to produce joints and fissures in step S3 includes the length, width, geometric characteristics of the joints and fissures, as well as the number, direction, and inclination characteristics thereof.
7. The method of deep hard rock mining by hydraulic fracturing according to claim 6 is characterized by: In step S3, the crack development is detected by ultrasonic geophysical exploration or macroscopically qualitatively determined by drilling observation holes.
8. The intelligent mechanical mining method for deep hard rock mines using rock hydraulic fracturing according to claim 1 is characterized by: The rock breaking power in step S4 refers to the output power during the excavation process.
9. The method of deep hard rock mining by hydraulic fracturing according to claim 8 is characterized by: The rock breaking parameters in step S4 include the size and rotation speed of the cutter or cutter head of the tunnel boring machine; the size and spacing of the cutter teeth; the cutting depth, angle and cutting speed.
10. The method of deep hard rock mining by hydraulic fracturing according to claim 1 is characterized by: The big data information decision-making platform in step S5 collects, stores, analyzes, processes and provides feedback on the mining data from S1 to S4, and comprehensively manages the construction process of the four stages S1-S4.
Citation Information
Patent Citations
Non-blasting mechanized intelligent mining method for deep hard rock ore body
CN113431581A
Mechanical mining equipment and process based on hard rock hole array mutagenesis fracture modification
CN114893182A
Drilling, pressing and digging integrated hard rock roadway rapid driving method
CN115961970A
Cited By
Method for improving lump coal rate of coal by using abrasive jet slotting and hydrophilic softener
CN120007247A
Deep well mine carbon sequestration method based on sCO2 fracturing method
CN121345626A