Ship production site resource allocation method, allocation system, medium and equipment
By constructing an information database and resource scheduling calculation model, the problem of arbitrariness and uncertainty in traditional resource allocation is solved, and efficient and accurate resource allocation of intermediate products in the ship production site is achieved, which improves production efficiency and resource utilization, and reduces costs and delays.
Patent Information
- Application Number
- CN202410922736.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-10
- Publication Date
- 2024-10-15
AI Technical Summary
Traditional ship production site resource allocation relies on empirical judgment and lacks scientific data support, resulting in randomness and uncertainty in resource allocation, which limits production efficiency and on-time product delivery.
By building a comprehensive information database and refined resource scheduling calculation model, including production site resource information database, crane resource information database and intermediate product construction standard information database, the possible site resource allocation plan for each intermediate product is determined to ensure crane capacity. and site size to meet the needs, and combine feasible solutions through the resource scheduling calculation model.
It achieves efficient and accurate site resource allocation for multiple intermediate products within a predetermined time period, improves resource utilization, the rationality of production scheduling and production efficiency, reduces production delays and costs, and enhances the flexibility and reliability of production plans. Retrospective.
Smart Images

Figure CN118780550A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of intelligent ship construction, and in particular to a resource allocation method, allocation system, medium and equipment for a ship production site. Background Art
[0002] With the rapid development of shipbuilding technology and the increasing shipbuilding volume, the limitation of site area has become a key factor restricting production efficiency. Limited site space restricts the flexibility of product storage and transfer, especially during product delivery, due to insufficient operating space, resulting in low on-time delivery rate.
[0003] In addition, the limited number of cranes further exacerbates this dilemma. Combined with factors such as working hours, material consumption, and construction quality, the flow of products on the production line becomes slow and inefficient.
[0004] The traditional resource scheduling method mainly relies on experience judgment, lacks scientific data support and precise algorithm guidance, which makes the resource allocation in the production process more random and uncertain. To solve this problem, it is urgent to introduce scientific solutions to optimize the resource allocation of the production site. Summary of the invention
[0005] The purpose of the embodiments of the present application is to provide a ship production site resource allocation method, allocation system, medium and equipment, which can achieve efficient and accurate allocation of site resources for multiple intermediate products within a predetermined time period by building a comprehensive information database and a refined resource scheduling calculation model.
[0006] In a first aspect, a method for allocating site resources for ship production is provided, which is used to allocate site resources for a plurality of intermediate products within a predetermined time period, comprising:
[0007] S1. Build a production site resource information database, an intermediate product engineering information database, and a crane resource information database;
[0008] The production site resource information database shall contain at least site size and site number;
[0009] The intermediate product engineering information database shall at least include the intermediate product code, start time and completion time;
[0010] The crane resource information database at least includes crane number, crane capacity, crane task, crane working time and crane maintenance time;
[0011] There is a binding relationship between the crane number and the site number of the production site where it is located. The location information of the crane corresponding to the crane number is the production site corresponding to the site number;
[0012] S2. Build an information base of intermediate product construction standards;
[0013] The intermediate product construction standard information database includes the intermediate product code and the standard floor space, standard weight, standard construction process, and standard construction period corresponding to the current intermediate product;
[0014] S3. Obtain the intermediate product codes in the production site resource information database in turn, and search the intermediate product construction standard information database in turn through each intermediate product code to find the standard floor space, standard weight, standard construction process, and standard construction period corresponding to each intermediate product corresponding to the code;
[0015] S4. Determine all possible site resource allocation plans for each intermediate product based on preset constraints;
[0016] S5. Establish a resource scheduling calculation model, input integration conditions into the resource scheduling calculation model, use the resource scheduling calculation model to combine all possible site allocation plans for each intermediate product into a feasible integration plan, and then select the plan that meets the integration conditions from the feasible integration plans as the final overall site resource allocation plan.
[0017] In an implementable solution, the preset constraints include at least:
[0018] The crane capacity is greater than or equal to the standard weight;
[0019] The crane tasks, crane working hours and crane maintenance time corresponding to the crane can meet the standard construction period, start time and completion time of the intermediate product;
[0020] The site size is greater than or equal to the standard floor space size.
[0021] In one feasible solution, in step S4, determining all possible site resource allocation solutions for each intermediate product includes:
[0022] S41, according to the preset condition that the crane capacity is greater than or equal to the standard weight, selecting the crane numbers that meet the condition to form an initial pre-selected crane number group;
[0023] S42, comparing the crane tasks, crane working hours and crane maintenance time corresponding to the cranes in the initial pre-selected crane number group, eliminating the crane numbers that do not meet the standard construction period, start time and completion time of the intermediate product from the pre-selected crane number group, and obtaining a mid-term pre-selected crane number group;
[0024] S43, obtaining the site number corresponding to each crane number in the mid-term pre-selected crane number group to form an initial pre-selected site number group;
[0025] S44, obtaining the venue size corresponding to each venue number in the initial pre-selected venue number group;
[0026] S45, comparing the site size corresponding to each site number in the initial pre-selected site number group with the standard site size corresponding to the current intermediate product, eliminating the site numbers corresponding to the site size smaller than the standard site size from the initial pre-selected site number group, and obtaining the final site number group corresponding to the intermediate product;
[0027] Among them, all the site numbers in the final site number group correspond to all possible site resource allocation plans for the intermediate products.
[0028] In an implementable solution, the production site resource information database also includes data on the daily staff of the site, and the intermediate product construction standard information database also includes standard man-day data; step S3 also includes searching the intermediate product construction standard information database in turn by each intermediate product code to find the standard man-day data corresponding to each intermediate product corresponding to the code;
[0029] The preset constraint conditions also include: the daily staff data of the production site corresponding to the site number meets the requirements of the standard man-day data.
[0030] In an practicable solution, step S4 further includes:
[0031] S46, obtaining daily staff data corresponding to each venue number in the final selection venue number group;
[0032] S47, comparing the daily staff data corresponding to each site number in the final site number group with the standard man-day data corresponding to the current intermediate product, removing the site numbers whose daily staff data do not meet the standard man-day data from the final site number group, and obtaining the preferred site number group corresponding to the intermediate product;
[0033] Among them, all the site numbers in the preferred site number group correspond to all possible site resource allocation solutions for the intermediate products.
[0034] In an implementable solution, in step S5, the overall site resource allocation solution is presented in the form of a visual site allocation map, which at least includes a production site size schematic diagram, site number, crane number, and intermediate product code.
[0035] In a second aspect, a ship production site resource allocation system is provided, comprising:
[0036] The database building module is used to build the production site resource information database, the intermediate product engineering information database, and the crane resource information database; it is also used to build the intermediate product construction standard information database;
[0037] The production site resource information database at least includes the site size and site number; the intermediate product engineering information database at least includes the intermediate product code, start time and completion time; the crane resource information database at least includes the crane number, crane capacity, crane task, crane working time and crane maintenance time; the crane number is bound to the site number of the production site, and the location information of the crane corresponding to the crane number is the production site corresponding to the site number; the intermediate product construction standard information database includes the intermediate product code and the standard floor space, standard weight, standard construction process and standard construction period corresponding to the current intermediate product;
[0038] The search module is used to sequentially obtain the intermediate product codes in the production site resource information library, and sequentially search the intermediate product construction standard information library through each intermediate product code to find the standard floor space size, standard weight, standard construction process, and standard construction period corresponding to each intermediate product corresponding to the code;
[0039] A calculation module is used to determine all possible site resource allocation schemes for each intermediate product according to preset constraints;
[0040] The production scheduling module is used to combine all possible site allocation plans for each intermediate product through the established resource scheduling calculation model to form an overall site resource allocation plan that does not conflict with each other and produces the most intermediate products.
[0041] In a third aspect, a computer-readable storage medium is also provided, on which a computer program is stored. When the computer program is executed by a processor, the method for calculating the inflation pressure value of the mechanical stress release of the marine C-type storage tank in the aforementioned scheme is implemented.
[0042] In a fourth aspect, an electronic device is also provided, the device comprising a memory and a processor. The memory stores a computer program, the processor is in communication with the memory, and when the computer program is called, the method for calculating the inflation pressure value of the mechanical stress release of the marine C-type storage tank in the above scheme is executed.
[0043] Compared with the prior art, the beneficial effects of this application include at least:
[0044] The ship production site resource allocation method of the present application realizes efficient and accurate allocation of site resources for multiple intermediate products within a predetermined time period by constructing a comprehensive information database and a refined resource scheduling calculation model. Specifically, it includes:
[0045] Improve resource utilization: By building a production site resource information database, an intermediate product engineering information database, and a crane resource information database, this method can fully grasp the real-time status of the site and equipment, avoid resource waste, and improve resource utilization;
[0046] Optimize production scheduling: Through the establishment of a standard information base for intermediate product construction, this method can provide standardized construction processes and cycles for each intermediate product, ensuring the rationality and efficiency of production scheduling;
[0047] Enhance the flexibility of production planning: This method can flexibly adjust the site resource allocation plan according to the preset constraints to adapt to various changes that may occur in the production process, thereby enhancing the adaptability and flexibility of the production plan;
[0048] Reduce production costs: By optimizing the allocation of site resources, production delays caused by insufficient sites or equipment can be reduced, thereby reducing the additional costs caused by waiting or repeated operations;
[0049] Improve production efficiency: This method can quickly calculate the optimal site resource allocation plan by establishing a resource scheduling calculation model, shorten decision-making time, speed up the production process, and improve overall production efficiency;
[0050] Realize the traceability of the production process: This method can record the production process of each intermediate product and the use of site resources through the construction of an information database, which facilitates the monitoring and traceability of the production process. BRIEF DESCRIPTION OF THE DRAWINGS
[0051] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.
[0052] Figure 1 This is a flow chart of a method for allocating resources of a ship production site according to an embodiment of the present application;
[0053] Figure 2 It is a schematic diagram of the composition of a ship production site resource allocation system according to an embodiment of the present application;
[0054] Figure 3 It is a schematic diagram of the structure of an electronic device according to an embodiment of the present application. DETAILED DESCRIPTION
[0055] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, rather than all the embodiments. The components of the embodiments of the present application described and shown in the drawings here can be arranged and designed in various different configurations.
[0056] Therefore, the following detailed description of the embodiments of the present application provided in the accompanying drawings is not intended to limit the scope of the present application for which protection is sought, but merely represents selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.
[0057] like Figure 1 As shown, this embodiment first provides a ship production site resource allocation method, which is used to allocate site resources to multiple intermediate products within a predetermined time period, including:
[0058] S1. Build a production site resource information database, an intermediate product engineering information database, and a crane resource information database;
[0059] The production site resource information database shall contain at least site size and site number;
[0060] The intermediate product engineering information database shall at least include the intermediate product code, start time and completion time;
[0061] The crane resource information database at least includes crane number, crane capacity, crane task, crane working time and crane maintenance time;
[0062] There is a binding relationship between the crane number and the site number of the production site where it is located. The location information of the crane corresponding to the crane number is the production site corresponding to the site number;
[0063] S2. Build an information base of intermediate product construction standards;
[0064] The intermediate product construction standard information database includes the intermediate product code and the standard floor space, standard weight, standard construction process, and standard construction period corresponding to the current intermediate product;
[0065] S3. Obtain the intermediate product codes in the production site resource information database in turn, and search the intermediate product construction standard information database in turn through each intermediate product code to find the standard floor space, standard weight, standard construction process, and standard construction period corresponding to each intermediate product corresponding to the code;
[0066] S4. Determine all possible site resource allocation plans for each intermediate product based on preset constraints;
[0067] S5. Establish a resource scheduling calculation model, input integration conditions into the resource scheduling calculation model, use the resource scheduling calculation model to combine all possible site allocation plans for each intermediate product into a feasible integration plan, and then select the plan that meets the integration conditions from the feasible integration plans as the final overall site resource allocation plan.
[0068] In step S5, the resource scheduling calculation model is a pre-designed algorithm model, which can combine all possible site resource allocation schemes for each intermediate product into a feasible integration scheme. The feasible integration scheme at least meets the following requirements: each intermediate product is assigned an independent site number, and there is no overlap between site resource allocation schemes for different intermediate products.
[0069] In addition, the integration conditions can be one or more, for example, they may include: the maximum number of intermediate products produced within a preset time period; the shortest overall construction period under the premise of the same number of intermediate products; the maximum number of sites vacated before the scheduled time under the premise of the same number of intermediate products, etc.
[0070] The ship production site resource allocation method of this embodiment realizes efficient and accurate allocation of site resources for multiple intermediate products within a predetermined time period by constructing a comprehensive information database and a refined resource scheduling calculation model.
[0071] In this embodiment, the preset constraint conditions in step S4 may at least include:
[0072] The crane capacity is greater than or equal to the standard weight;
[0073] The crane tasks, crane working hours and crane maintenance time corresponding to the crane can meet the standard construction period, start time and completion time of the intermediate product;
[0074] The site size is larger than the standard floor space; the spacing between intermediate products on the production site must be at least 1m.
[0075] By setting specific preset constraints, the matching between crane resources and intermediate product demand is ensured, thereby improving the accuracy of resource allocation and the feasibility of production scheduling.
[0076] In this embodiment, in step S4, determining all possible site resource allocation solutions for each intermediate product may include:
[0077] S41, according to the preset condition that the crane capacity is greater than or equal to the standard weight, selecting the crane numbers that meet the condition to form an initial pre-selected crane number group;
[0078] S42, comparing the crane tasks, crane working hours and crane maintenance time corresponding to the cranes in the initial pre-selected crane number group, eliminating the crane numbers that do not meet the standard construction period, start time and completion time of the intermediate product from the pre-selected crane number group, and obtaining a mid-term pre-selected crane number group;
[0079] S43, obtaining the site number corresponding to each crane number in the mid-term pre-selected crane number group to form an initial pre-selected site number group;
[0080] S44, obtaining the venue size corresponding to each venue number in the initial pre-selected venue number group;
[0081] S45, comparing the site size corresponding to each site number in the initial pre-selected site number group with the standard site size corresponding to the current intermediate product, eliminating the site numbers corresponding to the site size smaller than the standard site size from the initial pre-selected site number group, and obtaining the final site number group corresponding to the intermediate product;
[0082] Among them, all the site numbers in the final site number group correspond to all possible site resource allocation plans for the intermediate products.
[0083] By refining the process of determining the site resource allocation plan, the accuracy of site resource allocation is further improved, ensuring that each intermediate product can be produced at a site that meets the conditions.
[0084] In this embodiment, the production site resource information library may also include site daily staff data, and the intermediate product construction standard information library may also include standard man-day data; step S3 may also include searching the intermediate product construction standard information library by each intermediate product code in turn to find the standard man-day data corresponding to each intermediate product code. Therefore, the preset constraint condition also includes: the daily staff data of the production site corresponding to the site number meets the requirements of the standard man-day data.
[0085] By considering site staff data and standard man-day data, this claim ensures the rational allocation of human resources and avoids production delays caused by insufficient human resources.
[0086] In this embodiment, step S4 may further include:
[0087] S46, obtaining daily staff data corresponding to each venue number in the final selection venue number group;
[0088] S47, comparing the daily staff data corresponding to each site number in the final site number group with the standard man-day data corresponding to the current intermediate product, removing the site numbers whose daily staff data do not meet the standard man-day data from the final site number group, and obtaining the preferred site number group corresponding to the intermediate product;
[0089] Among them, all the site numbers in the preferred site number group correspond to all possible site resource allocation solutions for the intermediate products.
[0090] By further screening the site numbers, it is ensured that the human resources of the site can meet the production needs of intermediate products, further improving the practicality and effectiveness of the site resource allocation plan.
[0091] In this embodiment, in step S5, the overall site resource allocation plan may be presented in the form of a visual site allocation map, which at least includes a production site size schematic diagram, a site number, a crane number, and an intermediate product code.
[0092] By presenting the overall site resource allocation plan in the form of a visual site allocation map, the allocation of site resources is clear at a glance, making it easier for production personnel and managers to quickly understand and implement it, thereby improving communication efficiency and work efficiency.
[0093] Among them, the types of intermediate products can include the leading stage and the trailing stage. The leading stage can include the total section, the total assembly, the subsection, the large assembly, the medium assembly, the small assembly, etc. The medium assembly can include the straight medium assembly, the curved medium assembly, etc. The straight medium assembly can include the bottom straight medium assembly, the side straight medium assembly, the deck straight medium assembly, etc. The intermediate products of the trailing stage are generally assembled from the intermediate products of the leading stage.
[0094] In summary, the ship production site resource allocation method of this embodiment realizes efficient and accurate allocation of site resources for multiple intermediate products within a predetermined time period by building a comprehensive information database and a refined resource scheduling calculation model. Specifically, it includes:
[0095] Improve resource utilization: By accurately constructing the production site resource information database, intermediate product engineering information database and crane resource information database, this method can fully grasp the real-time status of the site and equipment, avoid resource waste and improve resource utilization;
[0096] Optimize production scheduling: Through the establishment of a standard information base for intermediate product construction, this method can provide standardized construction processes and cycles for each intermediate product, ensuring the rationality and efficiency of production scheduling;
[0097] Enhance the flexibility of production planning: This method can flexibly adjust the site resource allocation plan according to the preset constraints to adapt to various changes that may occur in the production process, thereby enhancing the adaptability and flexibility of the production plan;
[0098] Reduce production costs: By optimizing the allocation of site resources, production delays caused by insufficient sites or equipment can be reduced, thereby reducing the additional costs caused by waiting or repeated operations;
[0099] Improve production efficiency: This method can quickly calculate the optimal site resource allocation plan by establishing a resource scheduling calculation model, shorten decision-making time, speed up the production process, and improve overall production efficiency;
[0100] Realize the traceability of the production process: This method can record the production process of each intermediate product and the use of site resources through the construction of an information database, which is convenient for monitoring and tracing the production process;
[0101] Support decision-making: The data analysis and visual site allocation map provided by this method provide strong decision-making support for management, which helps to formulate more scientific and reasonable production plans and resource allocation strategies;
[0102] Promoting intelligent production: The implementation of this method will help promote the development of ship production towards intelligence and automation, and improve the technical level and competitiveness of the entire industry.
[0103] Second, as Figure 2 As shown, this embodiment also provides a ship production site resource allocation system, including:
[0104] The database building module 10 is used to build a production site resource information database, an intermediate product engineering information database, and a crane resource information database; it is also used to build an intermediate product construction standard information database;
[0105] The production site resource information database at least includes the site size and site number; the intermediate product engineering information database at least includes the intermediate product code, start time and completion time; the crane resource information database at least includes the crane number, crane capacity, crane task, crane working time and crane maintenance time; the crane number is bound to the site number of the production site, and the location information of the crane corresponding to the crane number is the production site corresponding to the site number; the intermediate product construction standard information database includes the intermediate product code and the standard floor space, standard weight, standard construction process and standard construction period corresponding to the current intermediate product;
[0106] The search module 20 is used to sequentially obtain the intermediate product codes in the production site resource information library, and sequentially search the intermediate product construction standard information library through each intermediate product code to find the standard floor space size, standard weight, standard construction process, and standard construction period corresponding to each intermediate product corresponding to the code;
[0107] A calculation module 30, for determining all possible site resource allocation schemes for each intermediate product according to preset constraints;
[0108] The production scheduling module 40 is used to input integration conditions into the resource scheduling calculation model, use the resource scheduling calculation model to combine all possible site allocation plans for each intermediate product into a feasible integration plan, and then select the plan that meets the integration conditions from the feasible integration plans as the final overall site resource allocation plan.
[0109] In a third aspect, the present application also provides a computer-readable storage medium having a computer program stored thereon, characterized in that: when the computer program is executed by a processor, the ship production site resource allocation method in the aforementioned scheme is implemented.
[0110] A person of ordinary skill in the art can understand that all or part of the steps in the method for implementing the above-mentioned embodiment can be completed by instructing the processor through a program, and the program can be stored in a computer-readable storage medium, and the storage medium is a non-transitory medium, such as a random access memory, a read-only memory, a flash memory, a hard disk, a solid-state hard disk, a magnetic tape, a floppy disk, an optical disc, and any combination thereof. The above-mentioned storage medium can be any available medium that can be accessed by a computer or a data storage device such as a server or a data center that includes one or more available media. The available medium can be a magnetic medium (for example, a floppy disk, a hard disk, a tape), an optical medium (for example, a digital video disc (DVD)), or a semiconductor medium (for example, a solid-state disk (SSD)), etc.
[0111] Fourthly, Figure 3 As shown, the present application also provides an electronic device 100, which includes a memory 101 and a processor 102. The memory 101 stores a computer program. The processor 102 is connected to the memory 101 for communication, and executes the ship production site resource allocation method in the above scheme when the computer program is called.
[0112] In some possible implementations, the memory 101 may include various media that can store program codes, such as ROM, RAM, magnetic disk, U disk, memory card or optical disk. Specifically, the memory 101 may include a computer system readable medium in the form of a volatile memory, such as a random access memory (RAM) and / or a cache memory. The electronic device 100 may further include other removable / non-removable, volatile / non-volatile computer system storage media. The memory 101 may include at least one program product, which has a group (e.g., at least one) of program modules, which are configured to perform the functions of various embodiments of the present invention. The processor 102 may be a general-purpose processor, including a central processing unit (CPU), a network processor (NP), etc.; it may also be a digital signal processor (DSP), an application specific integrated circuit (ASIC), a field programmable gate array (FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components.
[0113] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A method for allocating site resources for ship production, used for allocating site resources for multiple intermediate products within a predetermined time period, characterized in that: include: S1. Build a production site resource information database, an intermediate product engineering information database, and a crane resource information database; The production site resource information database shall contain at least site size and site number; The intermediate product engineering information database shall at least include the intermediate product code, start time and completion time; The crane resource information database at least includes crane number, crane capacity, crane task, crane working time and crane maintenance time; There is a binding relationship between the crane number and the site number of the production site where it is located. The location information of the crane corresponding to the crane number is the production site corresponding to the site number; S2. Build an information base of intermediate product construction standards; The intermediate product construction standard information database includes the intermediate product code and the standard floor space, standard weight, standard construction process, and standard construction period corresponding to the current intermediate product; S3. Obtain the intermediate product codes in the production site resource information database in turn, and search the intermediate product construction standard information database in turn through each intermediate product code to find the standard floor space, standard weight, standard construction process, and standard construction period corresponding to each intermediate product code; S4. Determine all possible site resource allocation plans for each intermediate product based on preset constraints; S5. Establish a resource scheduling calculation model, input integration conditions into the resource scheduling calculation model, use the resource scheduling calculation model to combine all possible site allocation plans for each intermediate product into a feasible integration plan, and then select the plan that meets the integration conditions from the feasible integration plans as the final overall site resource allocation plan.
2. The ship production site resource allocation method according to claim 1, characterized in that: The preset constraints include at least: The crane capacity is greater than or equal to the standard weight; The crane tasks, crane working hours and crane maintenance time corresponding to the crane can meet the standard construction period, start time and completion time of the intermediate product; The site dimensions are larger than the standard floor space dimensions.
3. The method for allocating resources of a ship production site according to claim 2, characterized in that: In step S4, all possible site resource allocation schemes for each intermediate product are determined, including: S41, according to the preset condition that the crane capacity is greater than or equal to the standard weight, selecting the crane numbers that meet the condition to form an initial pre-selected crane number group; S42, comparing the crane tasks, crane working hours and crane maintenance time corresponding to the cranes in the initial pre-selected crane number group, eliminating the crane numbers that do not meet the standard construction period, start time and completion time of the intermediate product from the pre-selected crane number group, and obtaining a mid-term pre-selected crane number group; S43, obtaining the site number corresponding to each crane number in the mid-term pre-selected crane number group to form an initial pre-selected site number group; S44, obtaining the venue size corresponding to each venue number in the initial pre-selected venue number group; S45, comparing the site size corresponding to each site number in the initial pre-selected site number group with the standard site size corresponding to the current intermediate product, eliminating the site numbers corresponding to the site size smaller than the standard site size from the initial pre-selected site number group, and obtaining the final site number group corresponding to the intermediate product; Among them, all the site numbers in the final site number group correspond to all possible site resource allocation plans for the intermediate products.
4. The method for allocating resources of a ship production site according to claim 3, characterized in that: The production site resource information database also includes data on the daily staff of the site, and the intermediate product construction standard information database also includes standard man-day data; step S3 also includes searching the intermediate product construction standard information database in turn by each intermediate product code to find the standard man-day data corresponding to each intermediate product corresponding to the code; The preset constraint condition also includes: the daily staff data of the production site corresponding to the site number meets the requirements of standard man-day data.
5. The ship production site resource allocation method according to claim 4, characterized in that: Step S4 also includes: S46, obtaining daily staff data corresponding to each venue number in the final selection venue number group; S47, comparing the daily staff data corresponding to each site number in the final site number group with the standard man-day data corresponding to the current intermediate product, removing the site numbers whose daily staff data do not meet the standard man-day data from the final site number group, and obtaining the preferred site number group corresponding to the intermediate product; Among them, all the site numbers in the preferred site number group correspond to all possible site resource allocation solutions for the intermediate products.
6. The method for allocating resources of a ship production site according to any one of claims 1 to 5, characterized in that: In the step S5, the overall site resource allocation plan is presented in the form of a visual site allocation map, which at least includes a production site size schematic diagram, site number, crane number, and intermediate product code.
7. A ship production site resource allocation system, characterized in that: include: A database building module (10) is used to build a production site resource information database, an intermediate product engineering information database, and a crane resource information database; it is also used to build an intermediate product construction standard information database; The production site resource information database at least includes the site size and site number; the intermediate product engineering information database at least includes the intermediate product code, start time and completion time; the crane resource information database at least includes the crane number, crane capacity, crane task, crane working time and crane maintenance time; the crane number is bound to the site number of the production site, and the location information of the crane corresponding to the crane number is the production site corresponding to the site number; the intermediate product construction standard information database includes the intermediate product code and the standard floor space, standard weight, standard construction process and standard construction period corresponding to the current intermediate product; A search module (20) is used to sequentially obtain the intermediate product codes in the production site resource information library, and sequentially search the intermediate product construction standard information library through each intermediate product code to find the standard floor space size, standard weight, standard construction process, and standard construction period corresponding to each intermediate product corresponding to the code; A calculation module (30), used to determine all possible site resource allocation schemes for each intermediate product according to preset constraints; The production scheduling module (40) is used to input the integration conditions into the resource scheduling calculation model, use the resource scheduling calculation model to combine all possible site allocation plans for each intermediate product into a feasible integration plan, and then select the plan that meets the integration conditions from the feasible integration plans as the final overall site resource allocation plan.
8. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the ship production site resource allocation method according to any one of claims 1 to 6 is implemented.
9. An electronic device, characterized in that: The device comprises: a memory storing a computer program; A processor is communicatively connected to the memory, and executes the ship production site resource allocation method described in any one of 1 to 6 when calling the computer program.