Construction method of CFRP grid reinforced catenary linear concrete arch structure

Through the method of combining CFRP grid and flexible plastic film, concrete 3D printing technology is used to print concrete structures layer by layer and add grid reinforcement materials, solving the problems of large material consumption and complex construction in the existing technology, and achieving efficient and green concrete The construction of the arch structure reduces costs and improves construction efficiency and mechanical properties.

CN118876186APending Publication Date: 2024-11-01TONGJI UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411134360.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-19
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

The existing concrete arch structure construction methods have problems such as large material consumption, complex construction, high cost and low reuse rate, and it is difficult to achieve efficient, green and environmentally friendly construction methods.

Method used

The CFRP grid is used as the bottom formwork, combined with flexible plastic film and construction support, and the concrete structure is printed layer by layer through concrete 3D printing technology, and grid reinforcement materials are added during the printing process to achieve synchronous enhancement of the formwork and structure.

Benefits of technology

It reduces the consumption of other material formwork, reduces construction costs, improves construction efficiency, is suitable for the construction of arch structures of different sizes, conforms to the concept of green and low-carbon, and improves construction efficiency and mechanical properties.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118876186A_ABST
    Figure CN118876186A_ABST
Patent Text Reader

Abstract

The invention relates to a construction method of a CFRP grid reinforced catenary linear concrete arch structure. The construction method comprises the following steps that S1, the size of the needed catenary linear concrete arch structure is determined; s2, determining the size of a CFRP grid serving as a bottom template according to the size of the required arch structure, and preprocessing and cutting the CFRP grid; a flexible plastic film is fixed on one side of the CFRP grid; s3, construction supports on the two sides are manufactured, and the set distance between the supports is determined according to the size of the needed arch structure; the pretreated CFRP grids are fixed to construction supports on the two sides to serve as bottom formworks; one side covered with the plastic film faces downwards; s4, a concrete arch structure is printed through a concrete 3D printer by means of the CFRP grid bottom formwork, and curing forming is conducted; and S5, after the concrete arch structure is cured and formed, the concrete arch structure is erected, the plastic film is detached, and redundant CFRP grid parts are cut off. Compared with the prior art, the method has the advantages of improving the construction efficiency of the concrete arch structure, reducing the construction cost of the concrete arch structure and the like.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building engineering, and in particular to a construction method of a CFRP grid reinforced catenary linear concrete arch structure. Background Art

[0002] For the construction of building structural concrete components, especially structures that require openings, such as arch structures, the common practice is to first use other materials to make a template similar to the arch structure, and then pour concrete with the help of the template, or to make a template of the same size as the arch hole and use it as the bottom template to print the concrete structure using concrete 3D printing technology. The disadvantages of this construction method are as follows: (1) Construction with the help of templates made of other materials consumes a lot of materials, especially for 3D printing concrete technology, if it is printed with templates made of other materials, its advantage of being moldless cannot be reflected. (2) Traditional auxiliary templates made of foam, plastic, wood, steel, etc. are difficult to construct, the construction process is complicated, the construction cost is high, and the construction period is long. (3) Traditional foam, plastic, wood, and steel templates can only meet certain specific construction needs. When faced with needs of different shapes and sizes, the reuse rate is low. Templates of a single model are often discarded after being used a few times, which is a serious waste.

[0003] Therefore, there is an urgent need for a method that can improve the construction efficiency of concrete arch structures, reduce the construction cost of concrete arch structures, and be more environmentally friendly. Summary of the invention

[0004] The purpose of the present invention is to improve the shortcomings of the above-mentioned prior art and provide a construction method of a CFRP grid reinforced catenary concrete arch structure, thereby improving the construction efficiency of the concrete arch structure, reducing the construction cost of the concrete arch structure, and being more in line with the concept of green environmental protection.

[0005] The purpose of the present invention can be achieved by the following technical solutions:

[0006] The present invention provides a method for constructing a CFRP grid reinforced catenary concrete arch structure, comprising the following steps:

[0007] S1: Determine the dimensions of the required catenary concrete arch structure;

[0008] S2: Determine the size of the CFRP mesh used as the bottom template according to the required size of the arch structure, and perform pre-processing and cutting of the CFRP mesh; fix a flexible plastic film on one side of the CFRP mesh;

[0009] S3: Make construction supports on both sides and determine the spacing of the supports according to the required arch structure size; fix the pre-treated CFRP grid on the construction supports on both sides as the bottom template, with the side covered with plastic film facing downward;

[0010] S4: Use a concrete 3D printer and a CFRP grid bottom template to print the concrete arch structure and maintain it in shape. The concrete material used for 3D printing must ensure that it will not slip after being printed on the CFRP grid bottom template.

[0011] S5: After the concrete arch structure is cured and formed, it is erected, the plastic film is removed, and the redundant CFRP mesh part is cut off. The removed plastic film can be recycled.

[0012] Furthermore, the concrete arch structure includes multiple concrete layers.

[0013] Furthermore, in S1, the catenary equation of the arch axis is calculated according to the calculated span and the calculated arch rise of the required catenary arch structure; according to the arch axis equation, the axis equations of each concrete layer and the equations of the arch hole and the outer side curve of the arch are determined by translation, and the total span and total height of the arch structure are obtained from the outer side curve of the arch.

[0014] Furthermore, in S2, when the size of the CFRP mesh as the bottom formwork is determined, the width of the CFRP mesh as the bottom formwork is equal to the width of the mid-span section of the concrete arch structure; the length of the CFRP mesh as the bottom formwork is determined according to the arc length of the outer side curve of the arch structure, and the length of the connection between the CFRP mesh and the support is increased on the basis of the arc length of the outer side curve of the arch structure.

[0015] Furthermore, in S2, the size of the flexible plastic film fixed on the CFRP grid bottom template needs to be slightly larger in width than the width of the CFRP grid bottom template, slightly larger in length than the arc length of the outer curve of the arch structure, and smaller than the length of the CFRP grid bottom template; the plastic film is only connected and fixed to the CFRP grid near the support end.

[0016] Furthermore, in S2, the CFRP mesh reinforcement material can be replaced with other mesh and mesh cloth materials for structural reinforcement. If the concrete arch structure does not need to be reinforced, the CFRP mesh bottom template can be replaced with a recyclable, high-strength, smooth-surfaced flexible material.

[0017] Furthermore, in S3, the construction supports on both sides are made by pouring concrete, metal or setting up temporary supports; the width of the support is greater than the width of the CFRP grid used as the bottom formwork, and the height of the support is greater than the total height of the arch structure.

[0018] Furthermore, in S3, when arranging the construction supports on both sides, the net distance between the supports is equal to the total span of the arch structure.

[0019] Furthermore, in S3, the CFRP grid serving as the bottom formwork is fixed to the construction supports on both sides by means of clamps, or is hooked to the construction supports on both sides by means of grid hooks, and ensures that the connection of the grid single bundles in the two directions is not damaged.

[0020] Furthermore, in S4, when performing concrete 3D printing, a flat rectangular print head is used to print layer by layer on the bottom template; the length of the print head is equal to the width of the mid-span section of the arch structure; the width of the print head needs to ensure that the height of the mid-span section of the arch structure is an integer multiple of the width of the print head.

[0021] In S4, if additional CFRP mesh reinforcement is required for the concrete arch structure, the CFRP mesh is laid when printing to the concrete layer that needs to be reinforced, and the concrete printing continues after laying.

[0022] The device automation can be improved based on the construction method of the present invention; for example, by adding a slide rail to the construction support, the support spacing can be more conveniently adjusted according to different size requirements; by adding a hydraulic lifting device to the construction support, the support height can be more conveniently adjusted according to different size requirements; by adding a CFRP mesh discharging device to the construction support, the size of the CFRP mesh serving as the bottom template can be more conveniently adjusted.

[0023] Compared with the prior art, the present invention has the following advantages:

[0024] (1) The CFRP grid bottom template used in the present invention does not need to be removed after the concrete printing is completed. It becomes one with the concrete structure and serves as both a printing template for the concrete and a reinforcing material for the structure. The auxiliary plastic film is not damaged during the concrete printing process and can be recycled after being disassembled. In summary, this method of constructing a concrete arch greatly reduces the consumption of templates made of other materials, reduces construction costs, improves construction efficiency, and complies with the green and low-carbon concept.

[0025] (2) The concrete arch structure construction method provided by the present invention can meet the construction requirements of different catenary arch structures by only adjusting the spacing between the construction supports on both sides and the size of the CFRP grid used as the bottom formwork. For the construction requirements of parabolic arch structures, since the catenary and the parabola are very close, the scale of the concrete components can be basically considered to be the same. Therefore, the present method can also be used to construct parabolic arch structures of various sizes. It is difficult for traditional formwork to freely adjust the size of the formwork according to the requirements, while the construction method of the present invention can adjust the size of the formwork according to the requirements. In particular, for construction requirements with a large number of sizes and a small number of components of a single size, the construction method of the present invention can improve construction efficiency, save construction costs, and comply with the green and low-carbon concept.

[0026] (3) The concrete arch structure construction method provided by the present invention adopts a printing method of printing concrete layer by layer. During the printing process, when printing to the position that needs to be reinforced, grid reinforcement materials can be added manually or mechanically automatically, thereby realizing the simultaneous addition of reinforcement materials during the printing process and improving construction efficiency.

[0027] (4) The concrete arch structure construction method provided by the present invention, combined with concrete 3D printing technology, has high construction efficiency and is suitable for the construction and prefabrication of a large number of components, facilitating streamlined construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1a It is a schematic diagram of the curves on the side of the arch structure;

[0029] Figure 1b It is a schematic diagram of the dimensions of the side of the arch structure;

[0030] Figure 1c This is a schematic diagram of the multi-layer concrete on the side of the arch structure;

[0031] Figure 2 It is a cross-sectional view at the mid-span position of the catenary linear concrete arch structure constructed in the present invention, namely, the AA cross-sectional view;

[0032] Figure 3 It is a schematic diagram of the device of the construction method of the present invention;

[0033] Figure 4a The CFRP mesh used as the bottom formwork during concrete printing;

[0034] Figure 4b A diagram of printing concrete on the CFRP mesh bottom formwork;

[0035] Figure 4c This is the appearance of the catenary concrete arch after printing;

[0036] Figure 4d This is the appearance of the catenary concrete arch after curing;

[0037] Figure 4e This is the connection effect diagram between the CFRP grid and the concrete as the bottom formwork;

[0038] Figure 5 Schematic diagram of the arrangement position of CFRP grids in the concrete arch structure using the traditional construction method and the construction method proposed by the present invention in the example;

[0039] Figure 6a The printing process of the concrete arch using traditional construction methods;

[0040] Figure 6bThis is the appearance picture after the concrete is printed and cured using traditional construction methods;

[0041] Figure 7 The three-point compression-bending mechanical test results of the concrete arch structure printed by the traditional construction method and the construction method proposed by the present invention are shown in FIG.

[0042] Figure numerals: 1-curved segment in the arch structure; 11-outer contour line of the arch structure; 12-arch axis of the arch structure; 13-arch hole curve of the arch structure; 2-construction support; 21-clamp; 3-CFRP grid as bottom template; 4-concrete layer that has been printed. DETAILED DESCRIPTION

[0043] The present invention is described in detail below in conjunction with the accompanying drawings and specific embodiments. Component models, material names, connection structures, control methods, algorithms and other features not clearly described in this technical solution are all considered to be common technical features disclosed in the prior art.

[0044] Example 1

[0045] This embodiment provides a method for constructing a CFRP grid reinforced catenary concrete arch structure. Figure 1a , Figure 1b , Figure 1c , Figure 2 , Figure 3 As shown, the following steps are included:

[0046] S1: Determine the dimensions of the required catenary concrete arch structure;

[0047] S2: According to the required size of the arch structure, determine the size of the CFRP mesh 3 as the bottom template, and perform pre-processing and cutting of the CFRP mesh; fix a flexible plastic film on one side of the CFRP mesh; the processed CFRP mesh is as follows: Figure 4a shown.

[0048] S3: Make construction supports 2 on both sides, and determine the spacing of the supports according to the required arch structure size; fix the pre-treated CFRP grid on the construction supports 2 on both sides as the bottom template, with the side covered with plastic film facing downward;

[0049] S4: Use a concrete 3D printer to print a concrete arch structure with the help of a CFRP grid bottom template, and then maintain it to shape. The concrete material used for 3D printing must be guaranteed not to slip off after being printed on the CFRP grid bottom template. Figure 4b The appearance after printing is as shown below. Figure 4c shown.

[0050] S5: After the concrete arch structure is cured and formed, it is erected, the plastic film is removed, and the excess CFRP mesh is cut off. The removed plastic film can be recycled. The appearance of the component after curing is as follows Figure 4d As shown in the figure, the connection between the CFRP grid and the concrete after removing the plastic film is as follows: Figure 4e shown.

[0051] In a specific implementation, in order to make the construction process more in line with the characteristics of 3D printing concrete technology, the concrete arch will be composed of many concrete layers, such as Figure 1c As shown, when printing concrete, the concrete arch is also printed layer by layer.

[0052] In this embodiment: l-span of the arch structure; l0-clear span of the arch structure; l1-total span of the arch structure; f-slope of the arch structure; f0-clear slope of the arch structure; H-total height of the arch structure; d-width of the arch foot of the arch structure; n-number of concrete layers constituting the arch structure; h0-single-layer thickness of the concrete layers constituting the arch structure; b-width of the cross-sectional rectangle of the arch structure across the span; h-height of the cross-sectional rectangle of the arch structure across the span; l2-length required for fixing the CFRP grid serving as the bottom formwork to the construction support (on one side); H1-height of the construction support.

[0053] In this example, the single layer thickness of the concrete layer is h0=10 mm.

[0054] In order to determine the size of the concrete arch structure, the catenary equation of the arch axis is calculated according to the calculated span and arch rise of the required catenary arch structure. Based on the obtained arch axis equation, in order to determine the shape and size of other curved segments of the arch structure, the axis equation of each concrete layer and the curve equation of the arch hole and the outer side of the arch are determined by translation. Figure 1a The curved segment 1 in the arch structure includes: an outer contour line 11 of the arch structure, an arch axis line 12 of the arch structure, and an arch hole curve 13 of the arch structure.

[0055] In this example, the arch size is selected as span l = 600mm and sagitta f = 150mm. With the axis of symmetry as the y-axis and the line connecting the arch feet as the x-axis, the unit is mm, a plane rectangular coordinate system is established, and the equation of the arch axis is obtained as follows:

[0056]

[0057] In this example, the mid-span cross-sectional dimensions of the arch structure are selected as b×h=120mm×90mm, that is, the number of concrete layers is n=9.

[0058] The dimensions of the side and cross-section of the arch structure are as follows: Figure 1b , 2 shown.

[0059] In order to enable the CFRP mesh to function as a bottom formwork, the size of the CFRP mesh 3 as the bottom formwork is determined so that its width is equal to the width of the mid-span section of the concrete arch structure.

[0060] In order to make the catenary arch shape formed by the concrete after printing under the action of gravity consistent with the design, the length of the CFRP mesh 3 as the bottom template needs to be determined according to the arc length of the outer curve of the arch structure. In order to connect the CFRP mesh with the construction supports 2 on both sides, the length of the connection between the CFRP mesh and the support needs to be increased on the basis of the arc length of the outer curve of the arch structure.

[0061] Because concrete has a certain fluidity, in order to prevent leakage, a layer of plastic film needs to be fixed on the opposite side of the CFRP grid printed concrete. At the same time, the size of the flexible plastic film fixed on the CFRP grid bottom template needs to be slightly larger in width than the width of the CFRP grid bottom template, slightly larger in length than the arc length of the outer curve of the arch structure, and smaller in length than the CFRP grid bottom template.

[0062] The grid size used in this example is a grid with a pitch of 20 mm.

[0063] In order to make the plastic film recyclable, the plastic film only needs to be connected and fixed to the CFRP mesh part near the support end. After the maintenance is completed, the plastic film can be easily removed and recycled by simply cutting the connection here. The CFRP mesh reinforcement material can be replaced with other reinforcement mesh and mesh cloth materials. If the concrete arch structure is not reinforced, the bottom template of the CFRP mesh can be replaced with a higher strength and smooth surface flexible material.

[0064] In order to fix the CFRP grid and finally form the required catenary shape according to the required arch structure size, the assistance of the construction supports 2 on both sides is required. The construction supports 2 can be reused. The construction supports 2 on both sides can be made of poured concrete, metal, etc., or temporary supports can be set up. In this example, a temporary support is used.

[0065] The width of the construction support 2 must be greater than the width of the CFRP grid 3 as the bottom formwork, and the height of the construction support 2 must be greater than the total height of the arch structure. In order to make the catenary shape formed by the concrete under the action of gravity consistent with the design, when arranging the construction supports 2 on both sides, the net distance between the supports should be equal to the total span of the arch structure.

[0066] The CFRP mesh 3 as the bottom template can be fixed to the construction supports 2 on both sides by means of a clamp 21, or can be hung on the construction supports 2 on both sides by means of a mesh hook, such as Figure 3 shown.

[0067] CFRP mesh materials are usually woven from single mesh bundles in two directions. When fixing to the support, it is necessary to ensure that the connection of the single mesh bundles in two directions will not be damaged. The concrete material used for 3D printing must be guaranteed not to slip after printing on the bottom template of the CFRP mesh. The printing material in this example is ECC material (engineering cement-based composite material), and the fiber added is 12mm PE fiber with a fiber content of 1.5%.

[0068] For the convenience of construction, a relatively flat rectangular print head is used during concrete 3D printing, and printing is performed layer by layer on the bottom template. The print head length is equal to the width of the mid-span section of the arch structure. The print head width must be guaranteed, and the height of the mid-span section of the arch structure is an integer multiple of the print head width. The print head size used in this example is a rectangular print head with a width of 120mm and a height of 10mm, and the printed concrete strip size is the same.

[0069] If the concrete arch structure needs to be reinforced with additional CFRP mesh, the CFRP mesh can be laid when printing the concrete layer to be reinforced, and the concrete printing can continue after the laying is completed. The CFRP mesh 3 as the bottom template is the concrete layer 4 that has been printed.

[0070] After the construction of the concrete arch is completed, the removed plastic film can be recycled because no additional treatment is required.

[0071] At the same time, the automation of the device is improved based on the construction method of the present invention; for example, by adding a slide rail to the construction support 2, the support spacing can be more conveniently adjusted according to different size requirements; by adding a hydraulic lifting device to the construction support 2, the support height can be more conveniently adjusted according to different size requirements; by adding a CFRP mesh discharging device to the construction support 2, the size of the CFRP mesh 3 serving as the bottom template can be more conveniently adjusted.

[0072] In order to demonstrate the mechanical properties of the concrete arch structure constructed by the construction method of the present invention, a comparative example is provided to compare the mechanical properties of the CFRP reinforced concrete arch structure constructed by the construction method of the present invention and the conventional construction method. The concrete arch example of the conventional construction method is consistent in shape and size with the concrete arch of the construction method of the present invention described above.

[0073] The layout position of the CFRP grid in the concrete arch structure is consistent with the layout amount, but because the construction method of the present invention uses the CFRP grid as the bottom template, it can only be arranged on the outermost layer of the arch structure, while the traditional construction method cannot arrange the CFRP grid on the outermost layer of the arch structure. The grid layout position is slightly adjusted, such as Figure 5 shown.

[0074] The bottom formwork of the traditional construction method uses cut-to-shape foam material, on which concrete is printed layer by layer, and CFRP mesh is arranged at the designed CFRP mesh reinforcement position; the printing process of the traditional construction method is as follows Figure 6a As shown in the figure, the arch structure after printing and curing is as follows Figure 6b shown.

[0075] The traditional construction method and the construction method proposed in the present invention are referred to as "traditional method" and "catenary method" respectively.

[0076] Through the three-point compression and bending mechanical properties test, it was found that the mechanical properties of the concrete arch structure constructed by the catenary method and the traditional method are basically the same, and the bearing capacity is basically the same. The stiffness of the catenary method is slightly smaller than that of the traditional method. The mechanical properties test results are as follows Figure 7 The present invention can ensure mechanical properties while optimizing the construction method: the template size can be flexibly adjusted, and the template is used as a reinforcing material, which greatly reduces material consumption, is more in line with the requirements of green and low-carbon, and is more suitable for large-scale assembly line production.

[0077] Components not described in detail in this embodiment are all existing components that can be purchased through public channels.

[0078] The above description of the embodiments is to facilitate the understanding and use of the invention by those skilled in the art. It is obvious that those skilled in the art can easily make various modifications to these embodiments and apply the general principles described herein to other embodiments without creative work. Therefore, the present invention is not limited to the above embodiments, and improvements and modifications made by those skilled in the art based on the disclosure of the present invention without departing from the scope of the present invention should be within the scope of protection of the present invention.

Claims

1. A method for constructing a CFRP grid reinforced catenary concrete arch structure, characterized in that: The following steps are involved: S1: Determine the dimensions of the required catenary concrete arch structure; S2: Determine the size of the CFRP mesh used as the bottom template according to the required size of the arch structure, and perform pre-processing and cutting of the CFRP mesh; fix a flexible plastic film on one side of the CFRP mesh; S3: Make construction supports on both sides and determine the spacing of the supports according to the required arch structure size; fix the pre-treated CFRP grid on the construction supports on both sides as the bottom template; Place the side covered with plastic wrap down; S4: Use a concrete 3D printer to print the concrete arch structure with the help of a CFRP grid bottom template, and then maintain it in shape; S5: After the concrete arch structure is cured and formed, it is erected, the plastic film is removed, and the excess CFRP mesh part is cut off.

2. The method for constructing a CFRP grid reinforced catenary concrete arch structure according to claim 1, characterized in that: The concrete arch structure includes a plurality of concrete layers.

3. The method for constructing a CFRP grid reinforced catenary concrete arch structure according to claim 1, characterized in that: In S1, the catenary equation of the arch axis is calculated according to the calculated span and arch rise of the required catenary arch structure; according to the arch axis equation, the axis equations of each concrete layer and the equations of the arch hole and the outer side curve of the arch are determined by translation, and the total span and total height of the arch structure are obtained from the outer side curve of the arch.

4. The method for constructing a CFRP grid reinforced catenary concrete arch structure according to claim 1, characterized in that: In S2, when the size of the CFRP mesh as the bottom formwork is determined, the width of the CFRP mesh as the bottom formwork is equal to the width of the mid-span section of the concrete arch structure; The length of the CFRP mesh used as the bottom template is determined according to the arc length of the outer curve of the arch structure, and the length of the connection between the CFRP mesh and the support is increased based on the arc length of the outer curve of the arch structure.

5. The method for constructing a CFRP grid reinforced catenary concrete arch structure according to claim 1, characterized in that: In S2, the size of the flexible plastic film fixed on the CFRP grid bottom template is greater in width than the width of the CFRP grid bottom template, and greater in length than the arc length of the outer curve of the arch structure, and less than the length of the CFRP grid bottom template; The plastic film is only connected and fixed to the CFRP grid near the support end.

6. The method for constructing a CFRP grid reinforced catenary concrete arch structure according to claim 1, characterized in that: In S2, the CFRP mesh reinforcement material can be replaced by other mesh and mesh cloth materials for structural reinforcement.

7. The method for constructing a CFRP grid reinforced catenary concrete arch structure according to claim 1, characterized in that: In S3, the construction supports on both sides are made by pouring concrete, metal or setting up temporary supports; the support width is greater than the width of the CFRP grid used as the bottom formwork, and the support height is greater than the total height of the arch structure.

8. The method for constructing a CFRP grid reinforced catenary concrete arch structure according to claim 1, characterized in that: In S3, when arranging the construction supports on both sides, the net distance between the supports is equal to the total span of the arch structure.

9. The method for constructing a CFRP grid reinforced catenary concrete arch structure according to claim 1, characterized in that: In S3, the CFRP grid used as the bottom formwork is fixed to the construction supports on both sides by clamps, or is hooked to the construction supports on both sides by the grid, and ensures that the connection of the grid single bundles in two directions will not be damaged.

10. The method for constructing a CFRP grid reinforced catenary concrete arch structure according to claim 1, characterized in that: In S4, when performing concrete 3D printing, a flat rectangular print head is used to print layer by layer on the bottom template; the length of the print head is equal to the width of the mid-span section of the arch structure; The print head width must be guaranteed, and the mid-span section height of the arch structure is an integer multiple of the print head width; In S4, if additional CFRP mesh reinforcement is required for the concrete arch structure, the CFRP mesh is laid when printing to the concrete layer that needs to be reinforced, and the concrete printing continues after laying.