Sunken load transverse turnout system for movable pedestal and transfer method

By designing a sinking load transverse switch system in the beam field, the prefabricated longitudinal displacement area and beam storage area is used to connect the prefabricated longitudinal displacement area and the beam storage area, the simultaneous transverse movement of the mobile pedestal and prefabricated beam is achieved, which solves the problem of large space and high cost of existing equipment. , The problem of relying on large-scale lifting equipment improves operation efficiency and space utilization, simplifies on-site layout and reduces safety risks.

CN118880671APending Publication Date: 2024-11-01山东东方路桥建设有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411324883.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-23
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

The existing mobile pedestal pedestal pedestal equipment has problems such as large space occupation, high cost, large-scale lifting equipment, and low operation efficiency. It is especially difficult to achieve the operation of simultaneously moving prefabricated beams and mobile pedestals in the beam yard.

Method used

A sinking load transverse switch system is designed. By laying transverse tracks in the tensioning lifting area, and using a trolley to connect the prefabricated longitudinal displacement area and the beam storage area, the transverse movement of the mobile pedestal and prefabricated beam is realized, reducing the transverse movement of the mobile pedestal and the prefabricated beam. In order to rely on gantry cranes or beam lifters, the transition surface and transition rails are used for smooth transitions. The trolley is equipped with limiting parts and a support jack to ensure safety and stability.

Benefits of technology

It improves space utilization, reduces construction costs, reduces dependence on large lifting equipment, realizes simultaneous transverse operation of mobile pedestals and prefabricated beams, improves operation efficiency, simplifies on-site layout, and reduces safety risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118880671A_ABST
    Figure CN118880671A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of bridge engineering construction equipment, and relates to a sinking type load transverse moving turnout system for a movable pedestal and a transfer method.The sinking type load transverse moving turnout system is characterized in that a plurality of transverse moving rails are laid on the top face of a transverse moving tensioning lifting area, matched trolleys are movably installed on the transverse moving rails, and the top face of a prefabricated longitudinal moving area is higher than the top face of the transverse moving tensioning lifting area; the prefabricated longitudinal movement area is connected with the transverse movement tensioning lifting area through a transition face, the beam storage area is located between the gantry crane rails, and a transition rail is arranged on the transition face. The longitudinal moving rail and the return rail are movably connected with the trolley through transition rails. According to the sinking type load transverse moving turnout trolley, a prefabricating area and a beam storage area can be effectively linked, a transverse moving gantry crane or a beam lifter does not need to be used, meanwhile, the equipment cost is low, and therefore the construction investment is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge engineering construction equipment, and in particular to a sinking load-transferring turnout system for a mobile pedestal and a transfer method. Background Art

[0002] Currently, the equipment for horizontal movement of the mobile pedestal includes gantry crane mobile pedestal, beam shifting trolley mobile pedestal, and double-deck track ferry flat car.

[0003] The gantry crane moving platform mainly utilizes the horizontal movement of the beam moving trolley to realize the reverse rotation through the gantry crane. It requires that sufficient distance must be reserved at the intersection of the beam moving trolley track and the gantry crane track to meet the needs of the gantry crane. In comparison, the gantry crane equipment is larger in size and occupies more space; it is generally placed outdoors and is affected by the natural environment. It needs to be fixed and protected when not working; the investment cost and daily use and maintenance costs are relatively high.

[0004] The transverse shifting trolley is a device that moves on tracks (its tracks are on the same plane as the beam shifting tracks). It is small in size and convenient to carry. However, due to the height limitation of the transverse shifting trolley itself, this type of transverse shifting trolley is only suitable for carrying beam shifting pedestals with higher chassis.

[0005] The double-deck track ferry flat car can be operated by using the top lifting and the horizontal movement of the chassis of the sunken double-deck track ferry flat car. The trolley is used in the prefabrication area and the tensioning area of ​​the beam yard. After the beam is hoisted away, the flat car transports the pedestal to the revolving track, and the beam-moving pedestal rotates to the prefabrication area to continue transporting the beam, which can realize the horizontal movement of the mobile pedestal without affecting the tensioning operation. However, the premise of this operation is that the gantry crane or beam lifting machine lifts the beam from the mobile pedestal, and the mobile pedestal moves horizontally without load. This equipment is dependent on the lifting equipment and cannot move horizontally with the prefabricated beam.

[0006] Although the existing mobile platform lateral movement technologies each have their own advantages, they all have limitations to varying degrees. Summary of the invention

[0007] In order to solve the above problems, transverse grooves are dug and transverse tracks are laid in the tensioning and lifting area, and a device that can carry a mobile pedestal and prefabricated beams at the same time is designed. The present invention provides a sinking load transverse turnout system and a transfer method for a mobile pedestal.

[0008] The technical solution of the present invention is realized by the following solution: a sinking load transverse turnout system for a mobile pedestal, comprising a transverse tensioning and lifting area, a prefabricated longitudinal movement area, a beam storage area and a gantry crane track, a plurality of transverse movement tracks are laid on the top surface of the transverse tensioning and lifting area, and a plurality of matching trolleys are movably installed on the transverse movement tracks, a top surface of the prefabricated longitudinal movement area is higher than a top surface of the transverse tensioning and lifting area, the prefabricated longitudinal movement area is connected to the transverse tensioning and lifting area through a transition surface, the beam storage area is located between the gantry crane tracks, and a transition rail is provided on the transition surface; The top surface of the prefabricated longitudinal movement area is provided with a moving platform, a longitudinal movement track and a return track. The longitudinal movement track and the return track are arranged in parallel. The moving platform is movably installed on the matching longitudinal movement track. The moving platform is matched with the return track. A prefabricated beam is carried on the moving platform. The longitudinal movement track and the return track are both movably connected to the trolley through a transition rail.

[0009] Through the above technical scheme, by setting up a sunken load-transverse switch trolley, the prefabrication area and the beam storage area can be effectively linked. The trolley has a simple structure, the mobile pedestal is easy to operate, and the beam yard layout is compact, which effectively improves the space utilization rate. The introduction of the trolley reduces the use of transverse gantry cranes or beam lifting machines, and there is no need to use large-scale lifting equipment. At the same time, the equipment cost is low, which reduces the cost investment in beam yard construction. The mobile pedestal and the trolley do not run on the same plane, and the longitudinal track, return track and transverse track do not intersect and affect each other in space. The site is not messy, but simple and orderly, and the trolley can carry the mobile pedestal and prefabricated beams for transverse operations at the same time, thereby improving the operation efficiency.

[0010] Preferably, the trolley includes a main beam, a limit member, a moving platform running track and a moving wheel assembly, a plurality of symmetrically arranged moving wheel assemblies are installed on the bottom surface of the main beam, a limit member is installed on the end of the top surface of the main beam away from the prefabricated longitudinal movement zone, a moving platform running track is installed on the top surface of the main beam, one end of the moving platform running track is abutted against the limit member, and the moving platform running track is movably connected to the longitudinal movement track and the return track through a transition rail. Preferably, a supporting jack is installed at one end of the bottom surface of the main beam close to the prefabricated longitudinal displacement zone, and a mounting surface is provided on a single moving wheel assembly, and the mounting surface is detachably connected to the supporting fixing component.

[0011] Preferably, the supporting and fixing assembly comprises fasteners and supporting wheels, and every two of the fasteners and every two of the supporting wheels can be detachably mounted on relatively symmetrical mounting surfaces, and the supporting wheels are connected to the prefabricated beams via spiral struts.

[0012] The transfer method of the mobile pedestal using a sinking load transverse turnout system has the following specific processing steps: Step A: The trolley moves horizontally without load and docks with the track in the prefabricated longitudinal movement area; Step B: The mobile platform carries the beam and moves it longitudinally to the top of the trolley and fixes it; Step C: The trolley is moved horizontally to the designated position of the tensioning and lifting area to perform tensioning operations; Step D: The gantry crane lifts the prefabricated beam off the movable platform and into the beam storage area; Step E: The trolley returns with the empty mobile pedestal; Step F: The mobile platform moves longitudinally onto the return track, and the trolley circulates empty.

[0013] Preferably, the specific steps of step A include: a1, drives the empty trolley in the transverse tensioning and lifting area, and the trolley moves transversely on the transverse track; a2, the trolley moves horizontally to the designated position where it docks with the longitudinal track; a3, the trolley is fixed on the transverse track through fasteners on the mounting surface.

[0014] Preferably, the specific steps of step B include: b1, the longitudinal track is connected to the moving platform running track through the transition track; b2, driving the mobile platform to make it move longitudinally; b3, the mobile pedestal carries the beam longitudinally to the top of the trolley and fixes it.

[0015] Preferably, in step C, the trolley is moved horizontally to the tensioning position, the spiral struts are released, and the trolley is further fixed by fasteners to tension the beam. Preferably, the specific steps of step F include: f1, the running track of the mobile platform connects to the return track through the transition track; f2, drives the mobile platform to move longitudinally into the return track; f3, at this time the trolley is in an unloaded state and is driven to move horizontally to the next designated position to repeat the next cycle operation.

[0016] In summary, the present invention has the following beneficial effects: 1. The present invention can effectively link the prefabrication area with the beam storage area by arranging a sunken load-transverse shifting switch trolley. The trolley has a simple structure, the mobile pedestal is easy to operate, the beam yard layout is compact, and the space utilization rate is effectively improved. The introduction of the trolley reduces the use of transverse shifting gantry cranes or beam lifting machines, and there is no need to use large-scale lifting equipment. At the same time, the equipment cost is low, which reduces the investment in beam yard construction. The mobile pedestal and the trolley do not run in the same plane, and the longitudinal track, return track and transverse track do not intersect and affect each other in space. The site is not messy, but simple and orderly, and the trolley can carry the mobile pedestal and prefabricated beams for transverse shifting operations at the same time, thereby improving the operation efficiency.

[0017] 2. By digging horizontal grooves and laying transverse tracks in the tensioning and lifting area, as well as designing transition surfaces and transition rails, the space between the prefabricated longitudinal movement area, the beam storage area and the gantry crane track is effectively utilized. The sunken design avoids the large amount of reserved space required for traditional gantry cranes and other equipment, thereby compacting the beam yard layout and improving the overall space utilization.

[0018] 3. The setting of the limiter effectively limits the maximum displacement of the mobile pedestal on the trolley, and effectively prevents the mobile pedestal from moving vertically during the lateral movement, thereby preventing derailment or collision accidents caused by excessive moving distance. The support jack provides additional support force at key positions, and multiple fasteners are used to further enhance the safety of the trolley during the process of being incorporated into the mobile pedestal. The beam is supported on the trolley by the support wheels and spiral struts to prevent instability and overturning during lateral movement.

[0019] 4. The "sinking load-transverse switch trolley" replaces the "gantry crane beam shifting" or "beam lifting machine beam shifting", and the "transverse shifting trolley carrying the mobile pedestal" replaces the "gantry crane lifting the mobile pedestal" for the return trip, realizing the multiple uses of the trolley and reducing the dependence on the gantry crane.

[0020] 5. The "grid-based, three-dimensional operation mode" replaces the "gantry beam shifting mode", and uses the sunken load-transferring turnout trolley system to form a three-dimensional operation mode in which the processes do not affect each other. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a schematic diagram of the workflow of the present invention; Figure 2 It is a schematic diagram of the top plan structure of the present invention; Figure 3 is a schematic diagram of the trolley of the present invention from a side view; Figure 4 It is a schematic diagram of the structure of a partial segment of the trolley of the present invention from a top view; Figure 5 It is a schematic diagram of the structure after the trolley and the transverse track of the present invention are fixed; Figure 6 It is a schematic diagram of the structure of the trolley of the present invention after additional support wheels are installed; Figure 7 yes Figure 6 Schematic diagram of the fixed assembly structure with prefabricated beams.

[0022] Description of reference numerals: 101, transverse tensioning and hoisting area; 102, prefabrication longitudinal movement area; 103, gantry crane track; 104, transverse movement track; 105, beam storage area; 1. Trolley; 11. Main beam; 12. Limiting parts; 13. Moving platform running track; 2. Return track; 3. Moving platform; 4. Support jack; 5. 40m support wheel; 6. 30m support wheel; 7. Mounting surface; 8. Fasteners; 9. Screw struts. DETAILED DESCRIPTION

[0023] In order to more clearly understand the above-mentioned objects, features and advantages of the present invention, the present invention is further described below with reference to the accompanying drawings and embodiments.

[0024] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways different from those described herein. Therefore, the present invention is not limited to the specific embodiments of the following disclosure. The present invention is further described in detail below in conjunction with the accompanying drawings.

[0025] Embodiment 1: A sinking load-transfer turnout system for a movable pedestal, such as Figure 1-Figure 7 As shown, it includes a transverse tensioning and lifting area 101, a prefabricated longitudinal movement area 102, a beam storage area 105 and a gantry crane track 103. A plurality of transverse movement tracks 104 are laid on the top surface of the transverse tensioning and lifting area 101. A corresponding trolley 1 is movably installed on the plurality of transverse movement tracks 104. The top surface of the prefabricated longitudinal movement area 102 is higher than the top surface of the transverse tensioning and lifting area 101. The prefabricated longitudinal movement area 102 is connected to the transverse tensioning and lifting area 101 through a transition surface. The beam storage area 105 is located between the gantry crane tracks 103. A transition rail is provided on the transition surface. A groove is dug in the tensioning and lifting area to lay the transverse movement track. Track 104 constitutes a transverse movement, tensioning and lifting area 101. The elevation difference between the prefabricated longitudinal movement area 102 and the transverse movement, tensioning and lifting area 101 is 826mm, and a transition surface is provided at the height difference between the two areas. The trolley 1 is driven by a motor, and the transverse movement, tensioning and lifting area 101 is divided into a tensioning area and a lifting area. The two areas have one elevation, and the gantry crane track 103 partially passes through the transverse movement track 104. A cross transition rail is provided at the staggered position to prevent the movement of the trolley 1 and the gantry crane from interfering with each other. The entire device is controlled by an electronic control system to achieve accurate docking, reduce manual operation, and improve production efficiency.

[0026] The top surface of the prefabricated longitudinal movement area 102 is provided with a moving pedestal 3, a longitudinal movement track and a return track 2, the longitudinal movement track and the return track 2 are arranged in parallel, the moving pedestal 3 is movably installed on the matching longitudinal movement track, the moving pedestal 3 is matched with the return track 2, the moving pedestal 3 is equipped with a prefabricated beam, the longitudinal movement track and the return track 2 are both movably connected to the trolley 1 through the transition rail, the moving pedestal 3 is 42 meters, so the trolley 1 is built according to 43 meters, the length of the trolley 1 is customized according to the length of the moving pedestal 3, to ensure that the moving pedestal 3 can be fully included in the support of the trolley 1, and the moving pedestal 3 is also driven by a motor for longitudinal movement After the mobile pedestal 3 receives the bottom membrane of the beam from the prefabrication area, it moves longitudinally and slides onto the trolley 1 that has been connected. The transition surface and transition rail are used to make a smooth transition between the prefabricated longitudinal movement area 102 and the transverse movement tensioning and lifting area 101, which is convenient for the transfer of the mobile pedestal 3 between different areas. The investment of the trolley 1 can avoid the use of transverse movement gantry cranes or beam lifting machines. At the same time, the trolley 1 has a low cost, which reduces the investment in the construction cost of the beam yard. The "grid-based, spatial three-dimensional operation mode" replaces the "gantry beam moving mode", and the sinking load transverse movement switch trolley 1 system is used to form a spatial three-dimensional operation mode in which the processes do not affect each other.

[0027] The trolley 1 includes a main beam 11, a limiter 12, a mobile pedestal running track 13 and a moving wheel assembly. The bottom surface of the main beam 11 is installed with a plurality of symmetrically arranged moving wheel assemblies. The top surface of the main beam 11 is installed with a limiter 12 at one end away from the prefabricated longitudinal shifting area 102. The top surface of the main beam 11 is installed with a mobile pedestal running track 13. The mobile pedestal running track 13 is adapted to the mobile pedestal 3 to ensure smooth operation of the mobile pedestal 3. One end of the mobile pedestal running track 13 abuts against the limiter 12. The side of the limiter 12 close to the running track is installed with an anti-collision layer. After the mobile pedestal 3 enters the trolley 1, the limiter 1 2 effectively limits the maximum longitudinal movement position of the mobile platform 3, and effectively prevents the longitudinal movement of the mobile platform 3 during the lateral movement, ensuring the safety of the device. The mobile platform running track 13 is movably connected to the longitudinal movement track and the return track 2 through the transition rail. The main beam 11 adopts an assembled structure, which is assembled in four sections and bolted. It can be adjusted according to the required length. All welds of the main beam 11 are fully welded, and the straightness error of the main beam 11 is <0.5mm, the diagonal error is <1mm, the flatness is <1mm, the plate edge straightness is <1mm, the size error is 0-0.5mm, and the deformation is controlled at ±0.5mm / m.

[0028] like Figure 4 As shown, the moving wheel assembly is driven by four motors, including four driving wheels and seven driven wheels. When moving sideways, the load is simultaneously applied. Both ends of the four driving wheels and the seven driven wheels are mounting surfaces 7.

[0029] like Figure 3As shown, a supporting jack 4 is installed at one end of the bottom surface of the main beam 11 close to the prefabricated longitudinal shift area 102. The supporting jack 4 adopts a 32t jack (4 pieces) and is used to support the main beam 11 to prevent the beam from vibrating when it is transported from the prefabricated area to the transverse shift area, thereby affecting the beam.

[0030] like Figure 5-Figure 6 As shown, a single moving wheel assembly is provided with a mounting surface 7, and the mounting surface 7 is detachably connected to a supporting and fixing component, and the supporting and fixing component includes a fastener 8 and a supporting wheel, and every two fasteners 8 and every two supporting wheels can be detachably mounted on the relatively symmetrical mounting surface 7, and the supporting wheel is connected to the precast beam through a spiral strut 9, and the spiral strut 9 supports the beam body on the trolley 1 to prevent the moving base 3 and the precast beam from becoming unstable and overturning during transverse movement, causing danger. The mounting positions of the fasteners 8 and the supporting wheels can be replaced back and forth as needed, and are bolted to the mounting surface 7. After the trolley 1 runs to the specified position, the trolley 1 needs to be fixed to the transverse track 104 by the fasteners 8 before tensioning and beam shifting can be performed to ensure that the trolley 1 will not be moved under force, and can be disassembled when the time comes.

[0031] Embodiment 2: A method for transporting a sinking load-transferring turnout system for a mobile pedestal, such as Figure 1-Figure 7 As shown, the following steps are included: Step A: The trolley 1 moves horizontally without load and docks with the track of the prefabricated longitudinal movement area 102; a1, driving the empty trolley 1 in the transverse tensioning and lifting area 101, and the trolley 1 performs transverse movement on the transverse track 104; a2, the trolley 1 moves horizontally to the designated position where it docks with the longitudinal track; a3, the trolley 1 is fixed on the transverse track 104 through the fasteners 8 on the mounting surface 7.

[0032] The trolley 1 is in an unloaded state and is driven by a motor to move horizontally until it docks with the longitudinal track in the prefabricated longitudinal zone 102. In conjunction with the transition rail, the three tracks of the mobile base running track 13, the transition rail and the longitudinal track of the trolley 1 are now in a connected state. Multiple symmetrical mounting surfaces 7 are bolted to fasteners 8, and the trolley 1 and the transverse track 104 are fixed to each other through the fasteners 8.

[0033] Step B: The mobile base 3 is moved longitudinally with the beam to the top of the trolley 1 and fixed; b1, the longitudinal track is connected to the moving platform running track 13 through the transition track; b2, driving the mobile platform 3 to make it move longitudinally; b3, the mobile base 3 moves longitudinally with the beam to the top of the trolley 1 and fixes it.

[0034] The support wheel position is configured according to the shape of the beam, and the beam is fixedly supported by the spiral strut 9. The support wheels are divided into 40-meter support wheels 5 and 30-meter support wheels 6 according to the size and position of the beam. The spiral strut 9 is also divided into 40-meter spiral strut 9 and 30-meter spiral strut 9. The mobile pedestal 3 moves longitudinally into the trolley 1, and smoothly transitions from the longitudinal movement track to the mobile pedestal running track 13. The mobile pedestal 3 carries the beam until it stops at the abutment limit piece 12. At this time, the fastener 8 is removed, and the relative support wheel is installed as needed. The spiral strut 9 is further set at the beam end to avoid the partition position, and the other end is bolted to the top surface of the support wheel to support the beam and prevent large shaking during walking.

[0035] Step C: the trolley 1 is loaded and moved horizontally to the designated position of the tensioning and lifting area for tensioning operation; The trolley 1 is moved horizontally to the tensioning position, the spiral strut 9 is released, and the trolley 1 is further fixed by the fastener 8 to tension the beam. The installation positions of the fastener 8 and the support wheel are the installation surfaces 7 at both ends of the moving wheel assembly. Bolt connections are used to install according to the engineering steps, and can be easily replaced to adapt to different conditions.

[0036] Step D: The gantry crane lifts the prefabricated beam from the movable platform 3 and lifts it into the beam storage area 105; After the prefabricated beam is lifted off, the movable platform 3 is in an empty state.

[0037] Step E: the trolley 1 returns with the empty mobile platform 3; Trolley 1 carries the empty mobile pedestal 3 back to the designated position of the return track 2, and the "sunken load-transferring turnout trolley 1" replaces the "gantry crane beam shifting" or "beam lifting machine beam shifting", and the "transverse trolley 1 carrying the mobile pedestal 3" replaces the "gantry crane lifting the mobile pedestal 3" on the return trip, realizing the multi-purpose use of trolley 1 and avoiding the dependence on the gantry crane. Only one gantry crane is used for beam lifting, which not only reduces the equipment purchase and maintenance costs, but also saves site space, making the construction site layout more compact and efficient, reducing the dependence on high-risk lifting equipment such as gantry cranes, and reducing the risk of safety accidents caused by improper lifting operations. At the same time, the stability and reliability of the trolley 1 system itself have also been improved, providing a strong guarantee for construction safety.

[0038] Step F: The mobile platform 3 moves longitudinally onto the return track 2, and the trolley 1 circulates without load; f1, the mobile platform running track 13 is connected to the return track 2 through the transition track; f2, drives the mobile platform 3 to move longitudinally into the return track 2; f3, at this time, the trolley 1 is in an unloaded state and is driven to move horizontally to the next designated position to repeat the next cycle operation.

[0039] The movable platform 3 moves longitudinally into the return track 2 and separates from the trolley 1. The movable platform 3 and the load-transferring switch trolley 1 do not run in the same plane. The longitudinal track, the return track 2 and the transverse track 104 do not intersect and affect each other in space. The site is not messy but simple and orderly.

[0040] The parts and equipment all adopt conventional models in the prior art, and the circuit connections adopt conventional connection methods in the prior art, which will not be described in detail here. The contents not described in detail in this manual belong to the prior art known to professional and technical personnel in this field.

[0041] The above description is only a preferred embodiment of the present invention and does not limit the present invention in other forms. Any technician familiar with the profession may use the technical content disclosed above to change or modify it into an equivalent embodiment with equivalent changes for application in other fields. However, any simple modification or equivalent change made to the above embodiment based on the technical essence of the present invention without departing from the content of the technical solution of the present invention still falls within the protection scope of the technical solution of the present invention.

Claims

1. A sinking load-transfer turnout system for a mobile pedestal, characterized in that: It comprises a transverse tensioning and lifting area (101), a prefabricated longitudinal displacement area (102), a beam storage area (105) and a gantry crane track (103); the top surface of the transverse tensioning and lifting area (101) is paved with a plurality of transverse displacement tracks (104); a plurality of the transverse displacement tracks (104) are movably mounted with corresponding trolleys (1); the top surface of the prefabricated longitudinal displacement area (102) is higher than the top surface of the transverse tensioning and lifting area (101); the prefabricated longitudinal displacement area (102) is connected to the transverse tensioning and lifting area (101) via a transition surface; the beam storage area (105) is located between the gantry crane tracks (103); and a transition rail is provided on the transition surface; The top surface of the prefabricated longitudinal shift area (102) is provided with a movable pedestal (3), a longitudinal shift track and a return track (2); the longitudinal shift track and the return track (2) are arranged in parallel; the movable pedestal (3) is movably mounted on a matching longitudinal shift track; the movable pedestal (3) is matched with the return track (2); a prefabricated beam is mounted on the movable pedestal (3); and the longitudinal shift track and the return track (2) are both movably connected to the trolley (1) via a transition track.

2. According to claim 1, a sinking load-transfer turnout system for a movable pedestal, characterized in that: The trolley (1) comprises a main beam (11), a limiting member (12), a movable platform running track (13) and a movable wheel assembly. The bottom surface of the main beam (11) is mounted with a plurality of symmetrically arranged movable wheel assemblies. The top surface of the main beam (11) is mounted with a limiting member (12) at one end away from the prefabricated longitudinal shift zone (102). The top surface of the main beam (11) is mounted with a movable platform running track (13). One end of the movable platform running track (13) is in contact with the limiting member (12). The movable platform running track (13) is movably connected to the longitudinal shift track and the return track (2) via a transition track.

3. According to claim 2, a sinking load-transfer turnout system for a movable pedestal, characterized in that: A support jack (4) is installed at one end of the bottom surface of the main beam (11) close to the prefabricated longitudinal shifting area (102), and a mounting surface (7) is provided on a single moving wheel assembly, wherein the mounting surface (7) is detachably connected to a supporting fixing component.

4. A sinking load-transfer turnout system for a movable pedestal according to claim 3, characterized in that: The support fixing assembly comprises a fastener (8) and a support wheel, and every two of the fasteners (8) and every two of the support wheels can be detachably mounted on a relatively symmetrical mounting surface (7), and the support wheels are connected to the prefabricated beam via a spiral support rod (9).

5. A method for transporting a sinking load-transferring turnout system for a mobile pedestal, characterized in that: The operation of the mobile pedestal sinking load traverse turnout system of claim 4 comprises the following steps: Step A: The trolley (1) moves horizontally without any load and docks with the track of the prefabricated longitudinal movement area (102); Step B: The mobile base (3) carries the beam and moves longitudinally to the top of the trolley (1) and fixes it; Step C: The trolley (1) is loaded and moved horizontally to a designated position in the tensioning and lifting area to perform tensioning operations; Step D: The gantry crane lifts the prefabricated beam off the movable platform (3) and into the beam storage area (105); Step E: the trolley (1) returns with the empty mobile pedestal (3); Step F: The mobile platform (3) moves longitudinally onto the return track (2), and the trolley (1) circulates without load.

6. A method for transporting a sinking load-transferring turnout system for a mobile pedestal according to claim 5, characterized in that: The specific steps of step A include: a1, driving an empty trolley (1) in the transverse tensioning and lifting area (101), so that the trolley (1) performs transverse movement on the transverse track (104); a2, the trolley (1) moves horizontally to a designated position where it docks with the longitudinal track; a3, the trolley (1) is fixed on the transverse track (104) via the fasteners (8) on the mounting surface (7).

7. The method for transporting a sinking load-transferring turnout system for a mobile pedestal according to claim 5, characterized in that: The specific steps of step B include: b1, the longitudinal track is connected to the moving platform running track (13) through the transition track; b2, driving the movable platform (3) to move longitudinally; b3, the mobile pedestal (3) is moved longitudinally with the beam to the top of the trolley (1) and fixed.

8. A method for transporting a sinking load-transferring turnout system for a mobile pedestal according to claim 7, characterized in that: In the above b3, the position of the support wheel is configured according to the shape of the beam body, and the beam body is fixedly supported by the spiral strut (9). The support wheel is divided into a 40-meter support wheel (5) and a 30-meter support wheel (6) according to the size and position of the beam body, and the spiral strut (9) is also divided into a 40-meter spiral strut (9) and a 30-meter spiral strut (9).

9. A method for transporting a sinking load-transferring turnout system for a mobile pedestal according to claim 6, characterized in that: In step C, the trolley (1) is moved horizontally to the tensioning position, the spiral struts (9) are released, and the trolley (1) is further fixed by fasteners (8) to perform beam tensioning.

10. A method for transporting a sinking load-transferring turnout system for a mobile pedestal according to claim 6, characterized in that: The specific steps of step F include: f1, the moving platform running track (13) is connected to the return track (2) through the transition track; f2, drives the movable platform (3) to move longitudinally into the return track (2); f3, at this time, the trolley (1) is in an unloaded state and is driven to move horizontally to the next designated position to repeat the next cycle operation.