Method and device for shortening single-phase earth fault handling time of power grid and medium
By calculating the change amount and probability of the grid grounding line selection data, the auxiliary dispatcher locks the fault line, solving the problem of insufficient grounding line selection criteria for the main grid station, achieving rapid and accurate fault handling, and improving the operating efficiency and safety of the grid sex.
Patent Information
- Application Number
- CN202411084895.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2024-11-12
AI Technical Summary
The grounding and line selection criteria of the main power grid station are insufficient, and relying on human judgment leads to high blindness, long road pulling time, large power outage range, and low disposal efficiency.
By obtaining the relevant data of the grid grounding line selection, the current change amount, the reactive power change amount and the zero-sequence current amplitude, the probability of grounding of each outgoing line is calculated by using the IQ fast line selection method and the zero-sequence current amplitude method, and the selection is determined. Line strategy, assists the dispatcher to quickly determine and lock the faulty line.
It effectively shortens the handling time of single-phase grounding faults in the power grid, reduces the power outage range, improves the handling efficiency, and improves the safe and stable operation of the power grid.
Smart Images

Figure CN118937896A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of methods for handling grounding faults in power grids, and in particular to a method for shortening the handling time of single-phase grounding faults in power grids. Background Art
[0002] Ground fault is one of the common faults in power system. Ground fault in power system refers to the short circuit between the live conductors such as phase line and neutral line in power system and "ground", which usually involves the connection problem between power equipment and the earth. Ground faults can include arc ground faults, DC system ground faults and single-phase ground faults, etc. These faults may be caused by broken wires, insulator breakdown, internal equipment failure or improper maintenance. Most of the power supply systems of my country's distribution networks and large industrial and mining enterprises adopt a small current grounding system, that is, the neutral point is not grounded, the neutral point is grounded through an arc suppression coil, or the neutral point is grounded through an arc suppression coil and a parallel (series) resistor, and the neutral point is grounded through a high resistance distribution system. After a 10 kV single-phase grounding fault occurs, such as Figure 1 As shown in Figure 1, one of the phases in the three-phase power system is short-circuited to the ground. When one of the phases is completely grounded, the voltage of the faulty phase will drop to 0, and the voltage of the non-faulty phase will rise to the line voltage.
[0003] In a low-current grounding system, methods for handling grounding faults include detailed inspection of electrical equipment for obvious signs of faults, and use of busbar segmentation and disconnection of reactive compensation capacitor circuit breakers to determine and locate the fault point. In addition, overcurrent protection, zero-sequence current, and residual current monitoring are also effective preventive and detection measures. When handling grounding faults, the operation and maintenance unit usually uses the pull-and-close method to find the fault point for all switches on the busbar where the grounding fault occurs, based on the length of the line, the weight of the load, and other conditions.
[0004] However, at present, there is insufficient criteria for grounding line selection at the main power grid station, and the grounding line search relies solely on manual judgment by dispatchers, which requires high levels of dispatchers, is highly blind, takes a long time to pull the line, covers a large power outage range, and has very low handling efficiency. Summary of the invention
[0005] The present invention aims to at least solve one of the technical problems in the prior art that the grounding line selection criteria for the main station of the power grid are insufficient, the grounding line search only relies on the manual judgment of the dispatcher, which has high requirements on the dispatcher's level, and is highly blind, has a long line selection time, a large power outage range, and low handling efficiency.
[0006] To this end, a first aspect of the present invention provides a method for shortening the handling time of a single-phase grounding fault in a power grid.
[0007] A second aspect of the present invention provides a computer device.
[0008] A third aspect of the present invention provides a computer-readable storage medium.
[0009] The present invention provides a method for shortening the processing time of a single-phase grounding fault in a power grid, comprising:
[0010] Acquire grid grounding line selection related data, the grid grounding line selection related data including: bus phase voltage and line voltage, outgoing line active power, reactive power and phase current;
[0011] Determine the grounding status of the power grid based on the bus phase voltage and identify the grounded bus;
[0012] According to the grid grounding line selection related data before and after the grounding busbar is grounded, the current change, reactive power change and zero-sequence current amplitude change of each outgoing line before and after the grounding are calculated;
[0013] According to the current change and reactive power change, an IQ fast line selection method is used to calculate the first probability of grounding of each outgoing line; according to the zero-sequence current amplitude change, a zero-sequence current amplitude method is used to calculate the second probability of grounding of each outgoing line;
[0014] A line selection strategy is determined according to a first probability and a second probability of grounding of each outgoing line; wherein the line selection strategy includes a line sorting result, and the line sorting result is used to indicate the line search order of the operator.
[0015] The method for shortening the handling time of a single-phase grounding fault in a power grid according to the above technical solution of the present invention may also have the following additional technical features:
[0016] In the above technical solution, the grid grounding line selection related data includes: bus data, outgoing line data and protection equipment data; wherein, the bus data includes the bus phase A voltage, B phase voltage, C phase voltage and line voltage, the outgoing line data includes the outgoing line active power, reactive power, A phase current, B phase current, C phase current and switch status, and the protection equipment data includes the grounding alarm information issued by the protection equipment.
[0017] In the above technical solution, judging the grounding state of the power grid according to the bus phase voltage and identifying the grounded bus includes:
[0018] Within the set time, when any phase voltage of the three-phase bus voltage is higher than the set first threshold value and any phase voltage of the other two phases is lower than the set second threshold value, it is determined that the current bus has a ground fault and a bus grounding signal is issued.
[0019] In the above technical solution, the current change, reactive power change and zero-sequence current amplitude change of each outgoing line before and after grounding are calculated based on the grid grounding line selection related data before and after the grounding busbar is grounded, including:
[0020] After obtaining the bus grounding signal, all outgoing lines of the grounded bus are scanned to obtain outgoing line data at a first moment before grounding occurs, outgoing line data at a second moment after grounding occurs, and outgoing line data at a third moment after grounding occurs; wherein the third moment is greater than the second moment;
[0021] Calculate the current change and reactive power change of each outgoing line at the second moment relative to the first moment;
[0022] Calculate the current change and reactive power change of each outgoing line at the third moment relative to the first moment;
[0023] The moment with the largest reactive power change between the second moment and the third moment is selected as the post-fault data section, that is, the IQ fast line selection method and the zero-sequence current amplitude method are calculated based on the data at the selected moment.
[0024] In the above technical solution, the IQ fast line selection method is used according to the current change and the reactive power change to calculate the first probability of grounding of each outgoing line, including:
[0025] Calculating the third probability of grounding of each outgoing line by using the phase current difference method according to the current variation, including:
[0026] PI j =ΔI j / (ΔI1+ΔI2+…+ΔI j +…+ΔI n-2 +ΔI n-1 +ΔI n )*100%
[0027] Among them, PI j represents the third probability, ΔI j represents the current change before and after the jth outgoing line is grounded, and n represents the number of outgoing lines connected to the grounding busbar;
[0028] Calculating the fourth probability of grounding of each outgoing line by using a reactive difference method according to the reactive power variation, including:
[0029] PQ j =ΔQ j / (ΔQ1+ΔQ2+…+ΔQ j +…+ΔQ n-2 +ΔQ n-1 +ΔQ n )*100%
[0030] Among them, PQ j represents the third probability, ΔQ j It represents the reactive power change before and after the jth outgoing line is grounded;
[0031] The first probability is calculated by using an IQ fast line selection method according to the weight values of the third probability and the fourth probability, including:
[0032] P j =xPI j +yPQ j
[0033] Among them, P j represents the first probability, x represents the weight value of the third probability, y represents the weight value of the fourth probability, x∈[0,1], y∈[0,1], and x+y=1.
[0034] In the above technical scheme, the weight value of the third probability and the weight value of the fourth probability are set according to the significance of the current change and reactive power change of the grounding line in the historical action data; wherein, the weight value of the fourth probability is increased for the lines with excessive capacitance current and / or the lines belonging to the core area of the urban network.
[0035] In the above technical solution, the second probability of grounding of each outgoing line is calculated by using the zero-sequence current amplitude method according to the zero-sequence current amplitude change, including:
[0036]
[0037] in, represents the second probability, ΔI0 j It represents the change in zero-sequence current amplitude before and after the jth outgoing line is grounded, and n represents the number of outgoing lines connected to the grounding bus.
[0038] In the above technical solution, determining the line selection strategy according to the first probability and the second probability of grounding of each outgoing line includes:
[0039] Sort the possibility of grounding of each outgoing line according to the first probability and the second probability respectively, and obtain a first sorting result and a second sorting result;
[0040] If the outgoing line with the highest probability of grounding in the first sorting result and the second sorting result is the same outgoing line, the first sorting result is used as the line pulling sorting result;
[0041] If the outgoing line with the highest probability of grounding in the first sorting result and the second sorting result are not the same outgoing line, and the change in zero-sequence current amplitude of the outgoing line with the highest probability of grounding in the second sorting result before and after the fault is greater than the threshold value, then this outgoing line is ranked first in the route sorting result, and the order of the remaining outgoing lines is sorted according to the first sorting result; otherwise, the first sorting result is used as the route sorting result.
[0042] A computer device provided by the present invention comprises a processor and a memory, wherein a computer program is stored in the memory, and when the computer program is loaded and executed by the processor, a method for shortening the handling time of a single-phase grounding fault in a power grid as described in any one of claims 1 to 8 is implemented.
[0043] The present invention provides a computer-readable storage medium storing a program, which, when loaded by a processor, implements the method for shortening the handling time of a single-phase grounding fault in a power grid as described in any one of claims 1 to 8.
[0044] In summary, due to the adoption of the above technical features, the beneficial effects of the present invention are:
[0045] The method proposed in the present invention for shortening the handling time of a single-phase grounding fault in a power grid monitors the bus voltage and outgoing line telemetry data in real time, analyzes the data immediately when a grounding warning occurs, and automatically collects relevant grounding fault data after determining the grounding bus signal, and performs algorithm analysis. According to the set weights, the probability calculation is performed and the line pulling strategy is compared and analyzed again to obtain the probability values of grounding faults occurring in all outgoing lines on the grounding bus, and the values are arranged in order to provide guidance for the dispatcher's line selection and line pulling. The method of the present invention can assist the on-duty dispatcher to quickly determine the grounding line, select the line and pull the line until the fault is eliminated. By efficiently locking the faulty line, the line pulling time can be effectively shortened, the scope of power outage can be reduced, the handling efficiency can be improved, and the safe and stable operation of the power grid can be protected.
[0046] Additional aspects and advantages of the present invention will become apparent from the following description or may be learned by practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0047] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:
[0048] Figure 1 This is a schematic diagram of the power grid phenomenon after a single-phase grounding fault occurs in a 10 kV line of a three-phase power system;
[0049] Figure 2 is a flow chart of a method for shortening the handling time of a single-phase grounding fault in a power grid according to an embodiment of the present invention;
[0050] Figure 3 It is a schematic diagram of the current flow principle after a single-phase grounding fault;
[0051] Figure 4 It is a schematic diagram of the principle of transient zero-sequence current flow of the fault line after a single-phase grounding fault;
[0052] Figure 5 is a schematic diagram of a system application architecture of an embodiment of the present invention;
[0053] Figure 6 It is a schematic diagram of the software module interface design of an embodiment of the present invention. DETAILED DESCRIPTION
[0054] In order to more clearly understand the above-mentioned purpose, features and advantages of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.
[0055] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways different from those described herein. Therefore, the protection scope of the present invention is not limited to the specific embodiments disclosed below.
[0056] Refer to the following Figures 2 to 6 The following describes methods, devices and media for shortening the handling time of a single-phase grounding fault in a power grid according to some embodiments of the present invention.
[0057] Some embodiments of the present application provide a method for shortening the processing time of a single-phase grounding fault in a power grid.
[0058] like Figure 2 As shown, the first embodiment of the present invention proposes a method for shortening the handling time of a single-phase grounding fault in a power grid, comprising the following steps S1-S5. It should be noted that the order of the following steps S1 to S5 is not fixed, and those skilled in the art can adjust the order of the steps according to actual needs, and different steps can also be executed at the same time.
[0059] S1. Obtaining grid grounding line selection related data, wherein the grid grounding line selection related data includes: phase voltage and line voltage of the busbar, active power, reactive power and phase current of the outgoing line.
[0060] Among them, the selection of grid grounding line selection related data is based on the analysis of historical grounding fault related data. The applicant inquired about the grounding phase current, active power, and reactive power of all outgoing line circuits of the grounding busbar in the 1 minute before and after the grounding of a certain 10kV line in the IES600 (dispatching automation) historical comprehensive data, and calculated the difference, and then summarized and analyzed whether the three difference data of the grounding outgoing line were significant compared with other lines.
[0061] After summary analysis, it was found that the grounding probability of the main switch, section switch, and grounding station transformer is extremely low and can be ignored, so it can be excluded from line selection; the fault phase current change difference or reactive power change difference of the faulty equipment (line) will be significantly greater than that of the non-faulty equipment (line).
[0062] Based on the above summary and analysis, theoretical research is carried out, such as Figure 3 As shown in the figure, after a small current single-phase ground short circuit occurs, a ground loop is formed at the grounding point in the moments before and after the fault occurs, resulting in the three-phase capacitive current I of A, B, and C of all load lines (outgoing lines) on the busbar to ground. C All of them will flow through the low-voltage side circuit of the main transformer to the fault grounding point of the fault line, thus generating a large capacitive current I at the grounding point. C , with the load current I f After the vectors are superimposed, the phase current after the fault changes to a certain extent compared with that before the fault.
[0063] At the same time, a large capacitive current I will be generated at the grounding point C , which is equivalent to injecting a part of reactive power Q at the fault point. Since the reactive power consumed by the load remains basically unchanged before and after the fault, the reactive power value collected by the SCADA (supervisory control and data acquisition system) at the load switch is reduced.
[0064] Therefore, the fault phase current change difference or reactive power change difference of the faulty equipment will be significantly greater than that of the non-faulty equipment. The relevant data can be used as the criterion for grid grounding line selection.
[0065] In addition, if Figure 4 As shown, after grounding, the fault line will generate a zero-sequence current with the opposite polarity to that of the non-fault line, so the amplitude of the zero-sequence current of the fault line will also change significantly.
[0066] According to the above statistical analysis and theoretical analysis, in some embodiments, the power grid grounding line selection related data includes: bus data, outgoing line data and protection equipment data; wherein, the bus data includes the bus phase A voltage, B phase voltage, C phase voltage and line voltage, the outgoing line data includes the outgoing line active power, reactive power, A phase current, B phase current, C phase current and switch status, and the protection equipment data includes the grounding alarm information issued by the protection equipment.
[0067] In a specific embodiment, the data buffer set at the master station can be used to cache the data of the low current system within 10 minutes before the current moment, with a data collection time interval of 1 second and rolling refresh. The selected line data, collection method and collection cycle are shown in Table 1.
[0068] Table 1 List of relevant data for grid grounding line selection
[0069]
[0070] Specifically, the telemetry data is collected periodically by the analysis service through the bus order; the telesignaling data is collected by the analysis service through the bus order during initialization, and the telesignaling changes of the real-time service are actively received after the initialization is completed.
[0071] S2. Determine the grounding status of the power grid based on the bus phase voltage and identify the grounded bus.
[0072] Since the bus voltage will be in a three-phase unbalanced state when grounded, this phenomenon can be used as a criterion for issuing a bus grounding signal; in some embodiments, within a set time period, when any phase voltage of the three-phase bus voltage is higher than a set first threshold value, and any phase voltage of the other two phases is lower than a set second threshold value, it is determined that a ground fault has occurred in the current bus and a bus grounding signal is issued.
[0073] In a specific embodiment, the set time length may be 30 seconds, that is, the above two conditions are satisfied simultaneously within 30 seconds. The first threshold value and the second threshold value may be flexibly set according to the bus voltage level, as long as the three-phase unbalanced state can be detected.
[0074] S3. Calculate the current change, reactive power change and zero-sequence current amplitude change of each outgoing line before and after the grounding of the grounding busbar according to the grid grounding line selection related data before and after the grounding of the grounding busbar.
[0075] After the bus grounding signal is sent, the grounded bus is determined, and all outgoing lines of the grounded bus are scanned to collect data before and after grounding. In some embodiments, in order to improve the accuracy of grounding line selection, data at three moments are collected for comparative analysis to determine the value data section used for subsequent calculations.
[0076] Specifically, after obtaining the bus grounding signal, all outgoing lines of the grounded bus are scanned to obtain outgoing line data at a first time t0 before grounding occurs (for example, 15s before grounding), outgoing line data at a second time after grounding occurs (for example, 20s after grounding), and outgoing line data at a third time after grounding occurs (for example, 30s after grounding); wherein the third time is greater than the second time;
[0077] Calculate the current change and reactive power change of each outgoing line at the second moment relative to the first moment;
[0078] Calculate the current change and reactive power change of each outgoing line at the third moment relative to the first moment;
[0079] The moment with the largest reactive power change between the second moment and the third moment is selected as the post-fault data section, that is, the data at the selected moment is used to calculate the IQ fast line selection method and the zero-sequence current amplitude method. For example, if the reactive power change between the third moment and the first moment is greater than the reactive power change between the second moment and the first moment, the collected data corresponding to the third moment is selected for subsequent IQ fast line selection method and zero-sequence current amplitude method calculations. Through this step, it can be ensured that the data section used for calculation can highlight the current change and reactive power change as much as possible.
[0080] S4. According to the current change and reactive power change, the IQ fast line selection method is used to calculate the first probability of grounding of each outgoing line; according to the zero-sequence current amplitude change, the zero-sequence current amplitude method is used to calculate the second probability of grounding of each outgoing line.
[0081] In some embodiments, the IQ fast line selection method includes the following steps S401-S403.
[0082] S401, calculating a third probability of grounding of each outgoing line by using a phase current difference method according to the current variation, including:
[0083] PI j =ΔI j / (ΔI1+ΔI2+…+ΔI j +…+ΔI n-2 +ΔI n-1 +ΔI n )*100%
[0084] Among them, PI j represents the third probability, ΔI j It represents the current change before and after the jth outgoing line is grounded, and n represents the number of outgoing lines connected to the grounding busbar.
[0085] S402, calculating a fourth probability of grounding of each outgoing line by using a reactive difference method according to the reactive power variation, including:
[0086] PQ j =ΔQ j / (ΔQ1+ΔQ2+…+ΔQ j +…+ΔQ n-2 +ΔQ n-1 +ΔQ n )*100%
[0087] Among them, PQ j represents the third probability, ΔQ j It represents the change of reactive power before and after the jth outgoing line is grounded.
[0088] S403, calculating the first probability by using an IQ fast line selection method according to the weight values of the third probability and the fourth probability, including:
[0089] P j =xPI j +yPQ j
[0090] Among them, P j represents the first probability, x represents the weight value of the third probability, y represents the weight value of the fourth probability, x∈[0,1], y∈[0,1], and x+y=1.
[0091] In some embodiments, in step S403, the weight value of the third probability and the weight value of the fourth probability are set according to the significance of the current change and the reactive power change of the grounding line in the historical action data; wherein, the weight value of the fourth probability is increased for the lines with excessive capacitance current and / or the lines belonging to the core area of the urban network.
[0092] In a specific embodiment, by statistically analyzing the historical action data, including the phase current difference and the reactive power difference, analyzing whether the two difference data of the grounding line are significant compared with other lines, setting different weights for comparison, and determining the weight with higher line selection accuracy to write into the program. In this embodiment, the analysis results of the relevant historical action data of multiple substations show that most substations generally present the law that the calculation results of the two algorithms are basically consistent; but among them, the capacitance current of Huilongwan, Xiakou, Tianwen and other substations changes greatly, and the reactive power difference changes more significantly; in view of this phenomenon, further investigations were conducted on the electrical characteristics of Huilongwan, Xiakou, Tianwen and other substations, and it was found that the 10 kV outgoing lines of these substations are mostly cable lines, and the total length of the 10 kV cable outgoing lines of each station exceeds 50 kilometers on average, and there is a common situation of excessive capacitance current. When a ground fault occurs in the line, the capacitance current is large, the change is significant, and it is easy to damage the cable and expand the accident. The grounding abnormality must be eliminated quickly.
[0093] Therefore, the weight of the reactive power difference method, i.e., the fourth probability, is increased for 36 substations with excessive capacitance current, such as Huilongwan, Xiakou, and Tianwen. Specifically, the weight is allocated according to the degree of excessive capacitance current, and finally the weights of the two algorithms for each station are adjusted as shown in Table 2. For other substations, since the calculation results of reactive power difference and phase current difference are generally consistent, the weight coefficients of the two algorithms are set to 0.5.
[0094] Table 2 Weight coefficient distribution of substations with excessive capacitance current
[0095]
[0096]
[0097]
[0098] In some embodiments, the zero-sequence current amplitude method includes:
[0099]
[0100] in, represents the second probability, ΔI0 j It represents the change in zero-sequence current amplitude before and after the jth outgoing line is grounded, and n represents the number of outgoing lines connected to the grounding bus.
[0101] S5. Determine a line selection strategy based on the first probability and the second probability of grounding of each outgoing line; wherein the line selection strategy includes a line sorting result, and the line sorting result is used to indicate the line search order of the operator. Specifically, based on practical experience and a large number of experimental verifications, it is found that the line selection strategy determined by the IQ fast line selection method or the zero-sequence current amplitude method alone is still insufficient in accuracy and has a large fluctuation in accuracy. Therefore, the present disclosure combines the two and determines the final line selection strategy based on the different situations of the first probability and the second probability. Compared with the IQ fast line selection method or the zero-sequence current amplitude method alone, a more accurate line selection strategy can be obtained.
[0102] In some embodiments, step S5 comprehensively provides a line selection strategy based on the IQ fast line selection method and the zero-sequence current amplitude method, specifically including:
[0103] The possibility of grounding of each outgoing line is sorted according to the first probability and the second probability respectively, and a first sorting result and a second sorting result are obtained; that is, the higher the first probability or the second probability of an outgoing line is, the more likely it is that the outgoing line has a grounding fault.
[0104] If the outgoing line with the highest probability of grounding in the first sorting result and the second sorting result is the same outgoing line, the first sorting result is used as the line pulling sorting result;
[0105] If the outgoing line with the highest probability of grounding in the first sorting result and the second sorting result are not the same outgoing line, and the change in the zero-sequence current amplitude of the outgoing line with the highest probability of grounding in the second sorting result before and after the fault is greater than the threshold value, then the outgoing line is ranked first in the line pulling sorting result, and the order of the remaining outgoing lines is sorted according to the first sorting result;
[0106] In other cases, the IQ quick line selection method is used to determine the route sorting results.
[0107] Some other embodiments of the present invention provide a computer device, including a processor and a memory, wherein the memory stores a computer program, and when the computer program is loaded and executed by the processor, the method for shortening the handling time of a single-phase grounding fault in a power grid as described in any of the above embodiments is implemented.
[0108] In some embodiments, the grounding line selection program can be embedded into the server, workstation and network equipment of the existing power grid dispatching control system without separately configuring related hardware devices. The service is deployed on the system server, and the application display is deployed on the monitoring workstation. The system application architecture is as follows Figure 5 shown.
[0109] The application software can include functions such as grounding fault warning, intelligent grounding line selection, line selection parameter setting, line selection record statistics, grounding record query, etc. The software module interface is designed according to the functions that the software needs to implement. Figure 6 A software module interface design is shown. In this system interface, three strategies are displayed, namely IQ fast line selection, zero-sequence current amplitude line selection, and IQI0 comprehensive line selection. When selecting a line, the default strategy is IQI0 comprehensive line selection, that is, the line sorting result given in step S5.
[0110] The grounding line selection display interface is implemented by embedding the human-machine interface. The line selection results exclude situations where the probability of grounding is negligible, such as the main line, section, grounding station transformer, capacitor, etc., and display the probability ranking of the line selection results at a glance, which is convenient for dispatchers to quickly find the priority lines. By adding the grounding pop-up window warning function of the intelligent line selection system of the control master station, optimizing the system cache and improving the operating speed, the dispatcher can directly enter the line selection interface from the pop-up window to view the line selection results, simplifying the operation steps, avoiding unnecessary freezes, and improving the operation speed.
[0111] When the grounding alarm signal is issued, the grounding line selection software automatically refreshes the grounding judgment information. The grounding line selection software gives the probability of grounding faults occurring on each outgoing line on the grounding busbar, and shows a probability value ranking table. The dispatcher pulls the line based on the given probability value ranking table.
[0112] In a specific embodiment, taking the 10kVI bus grounding of the 35kV Huimin Station as an example, in a grounding fault, the first order of the pull-out sequence given by the line selection software is the Huiyong 913 switch loop; after the pull-out of Huiyong 913, the grounding protection is restored, proving that the line selection is accurate. The results show that with the assistance of the grounding software, the dispatcher can quickly and accurately handle single-phase grounding faults.
[0113] Still other embodiments of the present invention provide a computer-readable storage medium storing a program, which, when loaded by a processor, implements the method for shortening the handling time of a single-phase grounding fault in a power grid as described in any of the above embodiments.
[0114] In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0115] Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for shortening the handling time of a single-phase grounding fault in a power grid, characterized in that: include: Acquire grid grounding line selection related data, the grid grounding line selection related data including: bus phase voltage and line voltage, outgoing line active power, reactive power and phase current; Determine the grounding status of the power grid based on the bus phase voltage and identify the grounded bus; According to the grid grounding line selection related data before and after the grounding busbar is grounded, the current change, reactive power change and zero-sequence current amplitude change of each outgoing line before and after the grounding are calculated; According to the current change and reactive power change, an IQ fast line selection method is used to calculate the first probability of grounding of each outgoing line; according to the zero-sequence current amplitude change, a zero-sequence current amplitude method is used to calculate the second probability of grounding of each outgoing line; A line selection strategy is determined according to a first probability and a second probability of grounding of each outgoing line; wherein the line selection strategy includes a line sorting result, and the line sorting result is used to indicate the line search order of the operator.
2. The method for shortening the handling time of a single-phase grounding fault in a power grid according to claim 1, characterized in that: The grid grounding line selection related data include: bus data, outgoing line data and protection equipment data; wherein, the bus data include the bus phase A voltage, B phase voltage, C phase voltage and line voltage, the outgoing line data include the outgoing line active power, reactive power, A phase current, B phase current, C phase current and switch status, and the protection equipment data include the grounding alarm information issued by the protection equipment.
3. The method for shortening the handling time of a single-phase grounding fault in a power grid according to claim 2, characterized in that: The method of judging the grounding state of the power grid according to the bus phase voltage and identifying the grounded bus comprises: Within the set time, when any phase voltage of the three-phase bus voltage is higher than the set first threshold value and any phase voltage of the other two phases is lower than the set second threshold value, it is determined that the current bus has a ground fault and a bus grounding signal is issued.
4. The method for shortening the handling time of a single-phase grounding fault in a power grid according to claim 3, characterized in that: The method of calculating the current change, reactive power change and zero-sequence current amplitude change of each outgoing line before and after the grounding of the grounding busbar based on the grid grounding line selection related data before and after the grounding of the grounding busbar comprises: After obtaining the bus grounding signal, all outgoing lines of the grounded bus are scanned to obtain outgoing line data at a first moment before grounding occurs, outgoing line data at a second moment after grounding occurs, and outgoing line data at a third moment after grounding occurs; wherein the third moment is greater than the second moment; Calculate the current change and reactive power change of each outgoing line at the second moment relative to the first moment; Calculate the current change and reactive power change of each outgoing line at the third moment relative to the first moment; The moment with the largest reactive power change between the second moment and the third moment is selected as the post-fault data section, that is, the IQ fast line selection method and the zero-sequence current amplitude method are calculated based on the data at the selected moment.
5. The method for shortening the handling time of a single-phase grounding fault in a power grid according to claim 1, characterized in that: The method of using an IQ fast line selection method according to the current variation and reactive power variation to calculate a first probability of grounding of each outgoing line includes: Calculating the third probability of grounding of each outgoing line by using the phase current difference method according to the current variation, including: PI j =ΔI j / (ΔI1+ΔI2+…+ΔI j +…+ΔI n-2 +ΔI n-1 +ΔI n )*100% Among them, PI j represents the third probability, ΔI j represents the current change before and after the jth outgoing line is grounded, and n represents the number of outgoing lines connected to the grounding busbar; Calculating the fourth probability of grounding of each outgoing line by using a reactive difference method according to the reactive power variation, including: PQ j =ΔQ j / (ΔQ1+ΔQ2+…+ΔQ j +…+ΔQ n-2 +ΔQ n-1 +ΔQ n )*100% Among them, PQ j represents the third probability, ΔQ j It represents the reactive power change before and after the jth outgoing line is grounded; The first probability is calculated by using an IQ fast line selection method according to the weight values of the third probability and the fourth probability, including: P.S j XxPI j +yPQ j Among them, P j represents the first probability, x represents the weight value of the third probability, y represents the weight value of the fourth probability, x∈[0,1], y∈[0,1], and x+y=1.
6. The method for shortening the handling time of a single-phase grounding fault in a power grid according to claim 5, characterized in that: The weight value of the third probability and the weight value of the fourth probability are set according to the significance of the current change and reactive power change of the grounded outgoing line in the historical action data; wherein, the weight value of the fourth probability is increased for the outgoing lines with excessive capacitance current and / or the outgoing lines belonging to the core area of the urban network.
7. The method for shortening the handling time of a single-phase grounding fault in a power grid according to claim 1, characterized in that: Calculating the second probability of grounding of each outgoing line by using a zero-sequence current amplitude method according to the zero-sequence current amplitude change, including: in, represents the second probability, ΔI0 j It represents the change in zero-sequence current amplitude before and after the jth outgoing line is grounded, and n represents the number of outgoing lines connected to the grounding bus.
8. The method for shortening the handling time of a single-phase grounding fault in a power grid according to claim 1, characterized in that: The determining of the line selection strategy according to the first probability and the second probability of grounding of each outgoing line comprises: Sort the possibility of grounding of each outgoing line according to the first probability and the second probability respectively, and obtain a first sorting result and a second sorting result; If the outgoing line with the highest probability of grounding in the first sorting result and the second sorting result is the same outgoing line, the first sorting result is used as the line pulling sorting result; If the outgoing line with the highest probability of grounding in the first sorting result and the second sorting result are not the same outgoing line, and the change in zero-sequence current amplitude of the outgoing line with the highest probability of grounding in the second sorting result before and after the fault is greater than the threshold value, then this outgoing line is ranked first in the route sorting result, and the order of the remaining outgoing lines is sorted according to the first sorting result; otherwise, the first sorting result is used as the route sorting result.
9. A computer device, characterized in that: The method comprises a processor and a memory, wherein a computer program is stored in the memory, and when the computer program is loaded and executed by the processor, the method for shortening the handling time of a single-phase grounding fault in a power grid as described in any one of claims 1 to 8 is implemented.
10. A computer-readable storage medium, characterized in that: A program is stored, and when the program is loaded by a processor, a method for shortening the processing time of a single-phase grounding fault in a power grid as claimed in any one of claims 1 to 8 is implemented.
Citation Information
Cited By
Platform for monitoring low current by apparent power and processing in real time
CN110988455A
Auxiliary decision-making method and system for single-phase earth fault transformer substation switching-off method
CN120300744A
A method and system for auxiliary decision-making in single-phase ground fault substations using the circuit-based approach.
CN120300744B