High-proportion new energy power grid two-step recovery method based on load optimization
By adopting load optimization and electrical-gas-thermal coupling system calculation model in the context of high proportion of new energy, the load to be restored is reduced, and combined with the characteristics of new energy and traditional energy, the recovery instability and high cost of new energy distribution networks is solved. The problem of this has achieved more efficient and stable power distribution network recovery.
Patent Information
- Application Number
- CN202411059492.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-04
- Publication Date
- 2024-11-19
AI Technical Summary
In the context of high proportion of new energy, the recovery of traditional new energy distribution networks has problems of instability and high cost, especially due to changes in weather and natural environment, the increase and decrease of new energy makes the grid voltage unstable and generate frequency volatility, and the use of fossil fuels in thermal and gas networks is environmentally harmful and costly.
Using a two-step recovery method of high-proportion new energy grid based on load optimization, the calculation model of the electric-gas-thermal coupling system is established to reduce the charge to be recovered, and the effect of the distribution network recovery strategy of traditional high-proportion new energy access is improved, combined with the new The characteristics of energy and traditional energy reduce the load to be restored by the thermal network and gas network, and support the recovery of the distribution network.
It significantly improves the voltage stability and efficiency after the power distribution network recovery, fills the shortcomings of the high proportion of new energy access distribution network recovery research on the load side, forms a complementary relationship with the power supply and grid side research, and verifies two steps Strategy is more reliable than traditional strategies.
Smart Images

Figure CN118983816A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of integrated energy systems, and in particular to a two-step restoration method for a high-proportion new energy power grid based on load optimization. Background Art
[0002] Renewable energy plays a supporting role in the restoration of the distribution network. Renewable energy supports the grid through distributed power generation. The traditional restoration of the distribution network of new energy is based on the island division of the distribution network to allow new energy to supply power independently. However, due to many factors, new energy is extremely unstable. For example, the weather and natural environment will produce intermittent changes. The increase or decrease of new energy will make the grid voltage unstable and produce certain frequency fluctuations. However, distributed power generation makes the support effect of new energy on the restoration of the distribution network significant. The application of distributed power generation system can connect new energy to the distribution network closer to the load point, thereby reducing transmission losses and improving the support effect of new energy on the restoration of the distribution network.
[0003] The integrated energy system is relatively stable, but the use of heat and gas networks to power the restoration of the distribution network has the disadvantages of being unclean and costly. There are shortcomings in directly using the energy of the heat and gas networks for the restoration of the distribution network. First, since the heat and gas networks usually use fossil fuels as energy, they will emit a large amount of greenhouse gases such as carbon dioxide, which is not good for the environment. Second, since the construction and maintenance costs of heat and gas networks are high, using them to support the restoration of the distribution network will also increase the cost of the overall energy system.
[0004] Therefore, how to overcome the defects of renewable energy output and carry out stable and efficient distribution network restoration is a problem that distribution network restoration has to face in the context of a high proportion of renewable energy. Summary of the invention
[0005] The present invention adopts the method of increasing the output of the gas network and the heat network, and based on the integrated energy system, transfers the charge pressure of the power grid to the heat network and the power grid, reduces the charge to be restored, and improves the effect of the traditional distribution network recovery strategy with a high proportion of new energy access, filling the deficiency of the research on distribution network recovery with a high proportion of new energy access on the load side, and can complement the relevant research on the power supply side and the power grid side.
[0006] The technical solution adopted by the present invention is:
[0007] A two-step restoration method for a high-proportion renewable energy power grid based on load optimization comprises the following steps:
[0008] Step 1, establishing an electric-gas-heat coupling system calculation model;
[0009]
[0010] Where: N g is the set of all generators in the distribution network; Pg,max With P g,min is the upper and lower limits of the active power output of the g-th generator; Q g,max With Q g,min is the upper and lower limits of the reactive power output of the g-th generator; U g,max with U g,min is the upper and lower limits of the working voltage of the g-th generator; P g , Q g with U g are respectively the active power, reactive power and operating voltage of the g-th generator at the current moment.
[0011] P CHP =c p,gas q m,CHP (T s -T r ),
[0012] Where: P CHP is the thermal power of CHP; c p,gas is the specific heat capacity of natural gas at constant pressure; q m,CHP is the heat medium flow rate flowing through CHP; T s and T r They are the temperatures of steam or hot water flowing into and out of the heat source in the heating network respectively.
[0013] The output power of electrical energy and thermal energy of CHP units is positively correlated.
[0014] P out =ηP in
[0015] Where P out is the output power of the electric boiler, P in is the input power of the electric boiler, and η is the energy conversion efficiency.
[0016]
[0017] Where: P e , P g , P h are the input of electricity, gas and heat energy respectively; L e , L h , L c are the output of electricity, heat and cold energy respectively; L, C, P are the output matrix, energy coupling coefficient matrix and input matrix of EH respectively.
[0018]
[0019] Where: x e are power system variables, such as voltage amplitude, phase, active power, reactive power, etc.; x gare natural gas system variables, such as node pressure and injection flow rate; x h are thermal system variables, such as node injection power, branch flow, heating and reheating temperature, etc.; F e , F g , F h Represent the power flow equations of the electrical, gas and thermal systems respectively.
[0020] Step 2, reducing the charge to be recovered;
[0021] The goal of this step is to reduce the load pressure of distribution network restoration, so the objective function is set as the load to be restored, and its minimum value is obtained by the interior point method, and the line on-off state of the integrated energy system when the load to be restored takes the minimum value is retained. This step can be regarded as an optimal power flow calculation problem. The traditional optimal power flow calculation problem is to find the state of the integrated energy system under the premise of maximizing economic benefits, and the objective function is the operating cost.
[0022] Step 3: Restore the distribution network.
[0023] This step regards the distribution network restoration problem as a second-order cone optimization problem. The objective function is the network loss. Under the state of the integrated energy system after executing the first step, the minimum network loss is calculated, and the line connection and disconnection status when the network loss reaches the minimum value is calculated, and the voltage of each node after restoration is recorded.
[0024] Step 2 and step 3 can be described by the following unified mathematical model:
[0025]
[0026] Where: f is the objective function, which is generally the system operating cost or network loss; g(x) is the equality constraint, that is, the node power flow balance equation; h(x) is the inequality constraint.
[0027] Since the goal of step 2 is to minimize the replaceable load, and the only thing in the system that converts electrical energy into non-electrical energy is the electric boiler, the objective function of step 2 can be set as the power of the electric boiler. g(x) and h(x) are constraints related to power flow calculation.
[0028] The objective function of step 3 is the network loss, and g(x) and h(x) are the constraints of the distribution network restoration problem in the form of second-order cone programming.
[0029] Beneficial effects of the present invention:
[0030] This method creatively combines the characteristics of new energy and traditional energy, allowing new energy to directly supply energy for the restoration of the distribution network, and the output of the heat network and gas network reduces the load to be restored, thus supporting the restoration of the distribution network in disguise. This method fills the gap in the research on the load side of the restoration of the distribution network with a high proportion of new energy access, and can complement the relevant research on the power supply side and the grid side. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 This is a calculation example of Embodiment 1;
[0032] Figure 2 is the result of comparative example 1;
[0033] Figure 3 This is the result of Example 1. DETAILED DESCRIPTION
[0034] Example 1
[0035] like Figure 1 , the simulation verification is carried out using the improved IEEE33 bus system, that is, coupling it with the Belgian 20-bus system and the 5-bus heating network system. The system consists of the IEEE33 bus system, the 6-bus heating system and the Belgian 20-bus natural gas system. The voltage in the power system is between 0.95 (pu) and 1.05 (pu). The pressure in the gas pipe is 0.02~0.075bar (1bar=100000Pa), and the capacity constraint is 1400m 3 / h. The thermal system operating mass is 5kg / s. The power factor of WT and PV is 0.95. The capacity of each PV is 500kW, 300kW, and 400kW respectively.
[0036] The present invention uses the voltage level of each node after the distribution network is restored to judge the restoration effect.
[0037] like Figure 3 This embodiment is tested on a test system. Considering multi-energy coupling and substitution, the results are as follows: after recovery, the voltage of each node of the distribution network is basically between 0.978 and 0.995, with a maximum value of 1.003 and a minimum value of 0.972.
[0038] Comparative Example 1
[0039] The test system is tested without taking step 1. Figure 2 ,Through MATLAB, with the help of YALMIP and CPLEX solvers, the traditional distribution network restoration results are calculated as follows: the voltage of each node is basically between 0.964 and 0.977. The maximum value is 1 and the minimum value is 0.964.
[0040] Will Figure 2 , 3 Comparing the results shown, we get:
[0041] 1) The overall value of directly executing distribution network restoration at nodes 0-5 is between 0.995-1, while the overall value of first performing load optimization and then performing distribution network restoration is greater than 1;
[0042] 2) At the 5th node, the direct execution of distribution network restoration is at 0.966, while the load optimization followed by distribution network restoration is at 1.003, which is higher than the direct execution of distribution network restoration;
[0043] 3) The peak value of 5-18 nodes directly executing distribution network restoration is 0.977, and the average value is 0.971, while the peak value of first performing load optimization and then performing distribution network restoration is 0.983, and the average value is 0.980, which is higher than the direct execution of distribution network restoration as a whole;
[0044] 4) The peak value of directly executing the distribution network restoration of nodes 19-25 is 0.996, and the average value is 0.975, while the peak value of first performing load optimization and then performing distribution network restoration is 0.999, and the average value is 0.988, which is higher than directly executing the distribution network restoration;
[0045] 5) The average value of directly executing distribution network restoration for nodes 26-30 is 0.967, while the average value of first performing load optimization and then performing distribution network restoration is 0.978, which is higher than directly executing distribution network restoration.
[0046] In summary, the node voltage is significantly improved, and the effectiveness and feasibility of this method are verified.
[0047] The results of the control test show that the energy replacement process before recovery can better improve the effectiveness of reconstruction. The root cause is that step 1 minimizes the load to be recovered by pre-processing the variable load, so the stress of recovery is significantly reduced.
[0048] The experimental results verify that the two-step strategy is more reliable than the traditional one-step strategy. Since the test cases are often used in actual project engineering, it can be said that the two-step strategy is an improvement on the traditional recovery strategy.
Claims
1. A two-step restoration method for a high-proportion renewable energy grid based on load optimization, characterized in that: The steps include: Step 1, establishing an electric-gas-heat coupling system calculation model; Step 2, reducing the charge to be recovered; The objective function is set as the load to be restored, and its minimum value is obtained by the interior point method, and the line on-off state of the integrated energy system when the load to be restored takes the minimum value is retained; Step 3, restore the distribution network; The objective function is network loss. The minimum network loss is calculated, and the line connection and disconnection status when the network loss reaches the minimum value is calculated. The voltage of each node after recovery is recorded.
2. A two-step restoration method for a high-proportion new energy power grid based on load optimization according to claim 1, characterized in that: The calculation model of the electric-gas-thermal coupling system established in step 1 is: Where: N g is the set of all generators in the distribution network; P g,max With P g,min is the upper and lower limits of the active power output of the g-th generator; Q g,max With Q g,min is the upper and lower limits of the reactive power output of the g-th generator; U g,max with U g,min is the upper and lower limits of the working voltage of the g-th generator; P g , Q g with U g are respectively the active power, reactive power and working voltage of the g-th generator at the current moment; P CHP =c p,gas q m,CHP (T s -T r ), Where: P CHP is the thermal power of CHP; c p,gas is the specific heat capacity of natural gas at constant pressure; q m,CHP is the heat medium flow rate flowing through CHP; T s and T r are the temperatures of steam or hot water flowing into and out of the heat source in the heat network respectively; P out =ηP in Where P out is the output power of the electric boiler, P in is the input power of the electric boiler, and η is the energy conversion efficiency. Where: P e , P g , P h are the input of electricity, gas and heat energy respectively; L e , L h , L c are the output of electricity, heat and cold energy respectively; L, C, P are the output matrix, energy coupling coefficient matrix and input matrix of EH respectively; Where: x e are power system variables, such as voltage amplitude, phase, active power, reactive power, etc.; x g are natural gas system variables, such as node pressure and injection flow rate; x h are thermal system variables, such as node injection power, branch flow, heating and reheating temperature, etc.; F e , F g , F h Represent the power flow equations of the electrical, gas and thermal systems respectively.
3. A two-step restoration method for a high-proportion new energy power grid based on load optimization according to claim 2, characterized in that: Step 2 and step 3 are described by the following unified mathematical model: Where: f is the objective function, which is generally the system operating cost or network loss; g(x) is the equality constraint, that is, the node power flow balance equation; h(x) is the inequality constraint.