Submarine pipeline internal repair verification system and verification method

The roller mechanism and test pipeline mechanism of the undersea pipeline repair verification system simulate the sea pipe structure and verify the internal coating repair technology, which solves the problem of special structure repair of the subsea pipeline, extends the service life of the subsea pipeline, reduces the cost of re-laying and cycle.

CN118999907APending Publication Date: 2024-11-22CNOOC PIPELINE ENG TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411103865.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-13
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The existing technology is difficult to effectively verify and repair the special structures of subsea pipelines, such as risers and expansion bends, resulting in an increased risk of leakage of old subsea pipelines, and new technologies are required to extend their service life.

Method used

Provide a repair verification system in the submarine pipeline, including a roller mechanism, flexible pipe, test pipeline mechanism, clamping mechanism and traction mechanism, simulate the sea pipe structure for process verification, and pass high-pressure water cleaning, density test and pressure test, Verify internal coating repair, lining repair and internal interpolation repair technologies.

Benefits of technology

It has achieved effective verification of special structures of subsea pipelines and repair technology, extended the service life of subsea pipelines, and reduced the high investment and cycle of re-laying.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118999907A_ABST
    Figure CN118999907A_ABST
Patent Text Reader

Abstract

The invention provides a submarine pipeline internal repair verification system and verification method, and relates to the technical field of oil and gas field development. The system comprises a roller mechanism; the flexible pipe is wound on the roller mechanism; the test pipeline mechanism comprises a pipeline assembly and a traction ball cylinder connected with the pipeline assembly, and a water injection pipeline is arranged on the traction ball cylinder; the clamping mechanism is arranged between the roller mechanism and the pipeline assembly, and the center line of the outlet end of the clamping mechanism is aligned with the center line of the free end of the pipeline assembly; the traction mechanism is arranged on one side of the traction ball cylinder, the method comprises the steps of pipeline assembly inner surface cleaning, traction and towing, flexible pipe traction, flexible pipe inspection and the like, special structures such as a real-size sea pipe stand pipe and a sea pipe expansion bend can be simulated, process verification can be provided for the inner coating repair technology, the lining repair technology and the inner penetrating repair technology, and the method is suitable for large-scale popularization and application. And meanwhile, process verification can be provided for new technologies such as cleaning, rust removal, descaling, inspection and monitoring of the submarine pipeline in the production period.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of oil and gas field development, and in particular to a submarine pipeline internal repair verification system and verification method. Background Art

[0002] Submarine pipelines are important facilities for offshore oil and gas transportation. Large-scale offshore oil and gas development has been going on for more than 20 years. Some submarine pipelines are close to or have exceeded their service life, and the risk of leakage is increasing. The only option is to abandon the old submarine pipelines and re-lay them. However, re-laying will bring high investment and long-term engineering development, which will have a huge impact on the output of the oil field. At this stage, there is an urgent need to apply new technologies to repair old submarine pipelines to increase their service life.

[0003] At present, for long-distance oil and gas pipelines on land, the internal coating repair technology and the inner liner repair technology are becoming more and more mature. However, due to the special structures of risers, expansion bends, etc. in submarine pipelines, verification tests need to be carried out on special structures when using the internal coating repair technology and the inner liner repair technology.

[0004] Therefore, there is an urgent need for a submarine pipeline in-repair verification system and verification method to solve the above technical problems. Summary of the invention

[0005] The purpose of the present invention is to provide a submarine pipeline internal repair verification system and verification method, using a dry dock to build a land verification system for submarine pipeline internal repair, simulating special structures such as risers and expansion bends in real size, realizing pilot verification of the process method, and providing a technical basis for the implementation of offshore engineering. The many technical effects that can be produced by the preferred technical solution among the many technical solutions provided by the present invention are described in detail below.

[0006] To achieve the above object, the present invention provides the following technical solutions:

[0007] The present invention provides a submarine pipeline internal repair verification system, comprising:

[0008] Roller mechanism;

[0009] A flexible tube, wound on the roller mechanism;

[0010] The test pipeline mechanism comprises a pipeline assembly and a traction ball connected to the pipeline assembly, wherein a water injection pipeline is arranged on the traction ball;

[0011] A clamping mechanism is disposed between the roller mechanism and the pipeline assembly, wherein the center line of the outlet end of the clamping mechanism is aligned with the center line of the free end of the pipeline assembly;

[0012] A traction mechanism is arranged on one side of the traction ball.

[0013] Preferably, the traction speed of the traction mechanism is the same as the operating speed of the clamping mechanism and the rolling speed of the roller mechanism to release the flexible tube.

[0014] Preferably, the submarine pipeline internal repair verification system further comprises a guide mechanism, which is arranged between the roller mechanism and the clamping mechanism, and is used to allow the flexible pipe to vertically enter the clamping mechanism from the inlet end of the clamping mechanism.

[0015] Preferably, the test pipeline comprises a first riser, a first expansion elbow, a routing pipe section, a second expansion elbow and a second riser connected in sequence by a flange assembly, wherein:

[0016] The centerline of the outlet end of the clamping mechanism is aligned with the centerline of the free end of the first riser;

[0017] The traction ball is connected to the second vertical pipe through a flange assembly.

[0018] Preferably, the test pipeline mechanism further comprises a traction end plate, and the traction mechanism is connected to the traction ball cylinder via a central sealing mechanism of the traction end plate.

[0019] Preferably, the test pipeline mechanism further comprises a pressure gauge, and the pressure gauge is arranged on the traction ball cylinder.

[0020] Preferably, the submarine pipeline internal repair verification system further comprises a rust inhibitor and a descaling agent, and the rust inhibitor and the descaling agent are injected through the water injection pipeline.

[0021] Preferably, the submarine pipeline repair verification system further comprises a pipe cleaner, which is placed in a traction ball, and the water injection line is used to inject high-pressure water that can push the pipe cleaner to move in the pipeline assembly.

[0022] A method for verifying the in-submarine pipeline repair, using the above-mentioned in-submarine pipeline repair verification system, comprises the following steps:

[0023] S1: Clean the inner surface of the pipeline assembly. Place the pipe cleaner on the traction ball barrel, inject high-pressure water through the water injection pipeline, and use the high-pressure water to push the pipe cleaner to clean the inner surface of the pipeline assembly;

[0024] S2: Towing the towing belt, connecting the towing rope of the towing mechanism to the pipe cleaner, pushing the pipe cleaner with high-pressure water through the towing ball, and pushing the towing rope to the free end of the pipeline assembly;

[0025] S3: flexible tube traction, connecting the traction rope and the flexible tube, and sequentially opening the roller mechanism, the clamping mechanism and the traction mechanism, so that the traction speed of the traction mechanism is the same as the running speed of the clamping mechanism and the rolling speed of the roller mechanism releasing the flexible tube, and during the traction process, the pipeline assembly is kept full of water, and the pressure gauge is kept at a standard atmospheric pressure;

[0026] S4: Flexible pipe inspection: performing a tightness test and a pressure test on the flexible pipe.

[0027] Preferably, while high-pressure water is injected into the water injection pipeline and the pipe cleaner is driven by the high-pressure water to clean the inner surface of the pipeline component, a descaling agent and a rust inhibitor are added to the water injection pipeline.

[0028] The submarine pipeline internal repair verification system provided by the present invention includes a roller mechanism, a flexible pipe, a test pipeline mechanism, a clamping mechanism and a traction mechanism. The flexible pipe is wound on the roller mechanism. The test pipeline mechanism includes a pipeline assembly and a traction ball connected to the pipeline assembly. A water injection pipeline is arranged on the traction ball. The test pipeline mechanism simulates the actual submarine pipeline. The water injection pipeline is configured according to the design requirements of the submarine pipeline. The roller mechanism, the clamping mechanism and the traction mechanism operate synchronously, which can provide process verification for the internal coating repair technology, the lining repair technology and the internal insertion repair technology. At the same time, it can also provide process verification for new technologies such as cleaning, rust removal, descaling, inspection and monitoring of submarine pipelines during the production period.

[0029] The submarine pipeline internal repair verification method provided by the present invention can provide process verification for internal coating repair technology, internal lining repair technology, and internal insertion repair technology through steps such as cleaning the inner surface of the pipeline component, traction and towing, flexible pipe traction, and flexible pipe inspection. At the same time, it can also provide process verification for new technologies such as cleaning, rust removal, descaling, inspection, and monitoring of submarine pipelines during the production period. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0031] Figure 1 It is a structural schematic diagram of an embodiment of a submarine pipeline repair verification system of the present invention;

[0032] Figure 2 It is a flow chart of an embodiment of a method for verifying the repair of a submarine pipeline according to the present invention.

[0033] In the figure: 1. roller mechanism; 2. flexible pipe; 3. test pipeline mechanism; 30. free end; 31. pipeline assembly; 311. first riser; 312. first expansion elbow; 313. routing pipe section; 314. second expansion elbow; 315. second riser; 32. traction ball; 4. clamping mechanism; 401. inlet end; 402. outlet end; 5. traction mechanism; 6. water injection pipeline; 7. guide mechanism; 8. flange assembly; 9. pressure gauge; 80. traction end plate. DETAILED DESCRIPTION

[0034] To make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be described in detail below. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other implementation methods obtained by ordinary technicians in this field without creative work belong to the scope of protection of the present invention.

[0035] In the description of the present invention, it is to be understood that the terms “center”, “lateral”, “length”, “width”, “height”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “side”, etc., indicating orientations or positional relationships are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0036] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.

[0037] Figure 1 Schematic diagram of the structure of this embodiment. Figure 1 As shown, the present invention provides a submarine pipeline internal repair verification system, comprising: a roller mechanism 1, a flexible pipe 2, a test pipeline mechanism 3, a clamping mechanism 4 and a traction mechanism 5.

[0038] The roller mechanism 1 can carry the flexible tube 2, and the flexible tube 2 is wound on the roller mechanism 1. When used, the flexible tube 2 is released by rolling the roller mechanism 1, and the release speed of the flexible tube 2 can be effectively controlled by controlling the rolling speed of the roller mechanism 1.

[0039] The test pipeline mechanism 3 in this embodiment includes a pipeline assembly 31 and a traction ball 32 connected to the pipeline assembly 31 , and a water injection pipeline 6 is arranged on the traction ball 32 .

[0040] The pipeline assembly 31 includes a first riser 311, a first expansion elbow 312, a routing pipe section 313, a second expansion elbow 314, and a second riser 315 connected in sequence through a flange assembly 8, and the traction ball 32 is connected to the second riser 315 through the flange assembly 8. The inclination, length, and bending radius of the first riser 311, the first expansion elbow 312, the routing pipe section 313, the second expansion elbow 314, and the second riser 315 in the pipeline assembly 31 are manufactured in a 1:1 ratio according to the design requirements of the sea pipe, and the water injection pipeline 6 is configured according to the design requirements of the sea pipe.

[0041] The clamping mechanism 4 is arranged between the roller mechanism 1 and the pipeline assembly 31, and the center line of the outlet end 402 of the clamping mechanism 4 is aligned with the center line of the free end 30 of the pipeline assembly 31. Specifically, in this embodiment, the center line of the outlet end 402 of the clamping mechanism 4 is aligned with the center line of the free end of the first vertical pipe 311. This ensures that the verification is carried out smoothly and the accuracy of the structure can be verified. The traction mechanism 5 is arranged on one side of the traction ball barrel 32, and the traction mechanism 5 in this embodiment adopts a winch.

[0042] During the repair verification process in the submarine pipeline, it is necessary to connect the flexible traction rope of the traction mechanism 5 to the flexible tube 2. Optionally, in this embodiment, the traction speed of the traction mechanism 5 is set to be the same as the running speed of the clamping mechanism 4 and the rolling speed of the roller mechanism 1 to release the flexible tube 2.

[0043] During the specific working process, the flexible traction rope is towed by the winch, and the towing speed of the winch is consistent with the running speed of the clamping mechanism 4 and the release speed of the roller mechanism 1, which can ensure the smooth progress of the verification. In the actual use and verification process, the traction speed of the traction mechanism 5 can be consistent with the running speed of the clamping mechanism 4 and the rolling speed of the roller mechanism 1 releasing the flexible tube 2 through the stepper motor and the counter.

[0044] As an optional embodiment, the submarine pipeline internal repair verification system further includes a guide mechanism 7, which is disposed between the roller mechanism 1 and the clamping mechanism 4, and is used to allow the flexible pipe 2 to vertically enter the clamping mechanism 4 from the inlet end 401 of the clamping mechanism 4. In order to prevent the guide mechanism 7 from affecting the flexible pipe 2 and to avoid damaging the flexible pipe 2, the surface of the guide mechanism 7 in this embodiment is provided with an arc surface.

[0045] The test pipeline mechanism in this embodiment also includes a traction end plate 80 , a flexible sealing mechanism is provided at the center of the traction end plate 80 , and the traction mechanism 5 is connected to the traction ball cylinder 32 via the central sealing mechanism of the traction end plate 80 .

[0046] As an optional implementation, the test pipeline mechanism in this embodiment further includes a pressure gauge 9, which is arranged on the traction ball 32. The pressure gauge is configured according to the design requirements of the sea pipeline. During the test, the test pipeline mechanism 3 needs to be kept full of water and the pressure is maintained at a standard atmospheric pressure.

[0047] As an optional embodiment, the submarine pipeline internal repair verification system further includes a rust preventer and a descaling agent, which are injected through the water injection pipeline 6. During the cleaning process of the inner surface of the pipeline, the rust preventer and the descaling agent are injected through the water injection pipeline 6 to ensure that the inner surface of the pipeline is cleaned. At the same time, the oil-containing surface treatment must meet the emission standards.

[0048] To ensure the cleaning effect, the submarine pipeline repair verification system also includes a pipe cleaner, which is placed in the traction ball 32. High-pressure water that can push the pipe cleaner to move in the pipeline assembly is injected through the water injection pipeline 6. The high-pressure water pushes the pipe cleaner to clean the inner surface of the pipe.

[0049] This embodiment also provides a method for verifying the in-submarine pipeline repair, using the above-mentioned in-submarine pipeline repair verification system. Figure 2 FIG. 1 is a flow chart of the method for verifying the repair of a submarine pipeline in this embodiment. Figure 2 As shown, the following steps are included:

[0050] S1: cleaning the inner surface of the pipeline assembly 31, placing the pipe cleaner on the traction ball 32, injecting high-pressure water through the water injection pipeline, and using the high-pressure water to push the pipe cleaner to clean the inner surface of the pipeline assembly.

[0051] Optionally, while high-pressure water is injected into the water injection pipeline and the pipe cleaner is driven by the high-pressure water to clean the inner surface of the pipeline component, a descaling agent and a rust inhibitor are added to the water injection pipeline, and the oil-containing surface treatment must meet the emission standards.

[0052] S2: Towing the towing belt, connect the towing rope of the towing mechanism to the pipe cleaner, use the towing ball 32 to push the pipe cleaner with high-pressure water, and push the towing rope to the free end 30 of the pipeline assembly 31;

[0053] S3: Pulling of the flexible tube 2: connecting the pulling rope to the flexible tube 2, and sequentially opening the roller mechanism 1, the clamping mechanism 4 and the pulling mechanism 5, so that the pulling speed of the pulling mechanism 5 is the same as the running speed of the clamping mechanism 4 and the rolling speed of the roller mechanism 1 when releasing the flexible tube 2, and during the pulling process, the pipeline assembly 31 is kept filled with water, and the pressure gauge maintains a standard atmospheric pressure.

[0054] S4: Inspection of the flexible pipe 2, performing a tightness test and a pressure test on the flexible pipe 2. Specifically, according to the factory technical standards for flexible pipes, a tightness test and a pressure test are performed on the flexible pipe to verify the integrity requirements of the flexible pipe.

[0055] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A submarine pipeline repair verification system, characterized in that: include: Roller mechanism; A flexible tube, wound on the roller mechanism; The test pipeline mechanism comprises a pipeline assembly and a traction ball connected to the pipeline assembly, wherein a water injection pipeline is arranged on the traction ball; A clamping mechanism is disposed between the roller mechanism and the pipeline assembly, wherein the center line of the outlet end of the clamping mechanism is aligned with the center line of the free end of the pipeline assembly; A traction mechanism is arranged on one side of the traction ball.

2. The submarine pipeline internal repair verification system according to claim 1 is characterized in that: The traction speed of the traction mechanism is the same as the operating speed of the clamping mechanism and the rolling speed of the roller mechanism for releasing the flexible tube.

3. The submarine pipeline internal repair verification system according to claim 1 or 2, characterized in that: The submarine pipeline internal repair verification system further comprises a guide mechanism, which is arranged between the roller mechanism and the clamping mechanism, and is used to allow the flexible pipe to vertically enter the clamping mechanism from the inlet end of the clamping mechanism.

4. The submarine pipeline repair verification system according to claim 3 is characterized in that: The test pipeline comprises a first riser, a first expansion elbow, a routing pipe section, a second expansion elbow and a second riser connected in sequence by a flange assembly, wherein: The centerline of the outlet end of the clamping mechanism is aligned with the centerline of the free end of the first riser; The traction ball is connected to the second vertical pipe through a flange assembly.

5. The submarine pipeline repair verification system according to claim 1 or 2, characterized in that: The test pipeline mechanism also includes a traction end plate, and the traction mechanism is connected to the traction ball cylinder through a central sealing mechanism of the traction end plate.

6. The submarine pipeline internal repair verification system according to claim 1 or 2, characterized in that: The test pipeline mechanism also includes a pressure gauge, which is arranged on the traction ball.

7. The submarine pipeline repair verification system according to claim 1 or 2, characterized in that: The submarine pipeline internal repair verification system also includes a rust preventive and a descaling agent, and the rust preventive and the descaling agent are injected through the water injection pipeline.

8. The submarine pipeline repair verification system according to claim 7, characterized in that: The submarine pipeline internal repair verification system also includes a pipe cleaner, which is placed on a traction ball barrel and is injected with high-pressure water capable of pushing the pipe cleaner to move in the pipeline assembly through the water injection pipeline.

9. A method for verifying the repair of a submarine pipeline, characterized in that: The submarine pipeline internal repair verification system according to any one of claims 1 to 8 comprises the following steps: S1: Clean the inner surface of the pipeline assembly. Place the pipe cleaner on the traction ball barrel, inject high-pressure water through the water injection pipeline, and use the high-pressure water to push the pipe cleaner to clean the inner surface of the pipeline assembly; S2: Towing the towing belt, connecting the towing rope of the towing mechanism to the pipe cleaner, pushing the pipe cleaner with high-pressure water through the towing ball, and pushing the towing rope to the free end of the pipeline assembly; S3: flexible tube traction, connecting the traction rope and the flexible tube, and sequentially opening the roller mechanism, the clamping mechanism and the traction mechanism, so that the traction speed of the traction mechanism is the same as the running speed of the clamping mechanism and the rolling speed of the roller mechanism releasing the flexible tube, and during the traction process, the pipeline assembly is kept full of water, and the pressure gauge is kept at a standard atmospheric pressure; S4: Flexible pipe inspection: performing a tightness test and a pressure test on the flexible pipe.

10. The method for verifying the repair of a submarine pipeline according to claim 9, characterized in that: While high-pressure water is injected into the water injection pipeline and the pipe cleaner is driven by the high-pressure water to clean the inner surface of the pipeline components, a descaling agent and a rust inhibitor are added to the water injection pipeline.