Coupling simulation method and device based on dam BIM model and finite element model
By adopting a coupled simulation method based on the dam BIM model and finite element model in hydropower construction, the problem of difficulty in accurately controlling the construction progress and ensuring safety in traditional methods is solved, and a progress plan that meets the contract construction period and structural safety is realized, and the feasibility and safety of construction management are improved.
Patent Information
- Application Number
- CN202411494127.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-24
- Publication Date
- 2025-03-21
- Estimated Expiration
- 2044-10-24
AI Technical Summary
During the construction of hydropower projects, it is difficult for traditional methods to fully demonstrate the deviations of environmental factors and construction factors on the progress, and it is impossible to accurately estimate the quality and safety problems caused by the progress plan, resulting in severe challenges in the control and coordination of construction progress.
The coupled simulation method based on the dam BIM model and the finite element model is adopted, and the simulation boundary parameters are determined by obtaining construction environment data, construction plans and design plans, building information models with additional time dimensions are constructed, the scheduled construction period of each node is calculated, and structural safety review is conducted until the construction period and structural safety requirements of the contract node are met.
It realizes a progress plan that meets the construction period of the contract node and the structural safety results, ensuring the feasibility and safety of the progress plan, avoiding construction progress delays and safety hazards.
Smart Images

Figure CN119004639B_ABST
Abstract
Description
Technical Field
[0001] The embodiments of the present invention relate to the field of hydropower engineering, and in particular to a coupling simulation method and device based on a dam BIM model and a finite element model. Background Art
[0002] Large-scale hydropower projects are mostly located in areas with complex environments. The construction technology is difficult and the working area is limited. The overall construction efficiency is severely restricted. In addition, the quality requirements of hydropower projects are high and there are many participating units, which makes the construction process more and more complicated. Relying solely on traditional methods to formulate progress plans cannot fully demonstrate the deviations in the progress caused by environmental and construction factors, nor can it accurately estimate the quality and safety problems that will arise from construction according to the progress plan. The uncertainty of the construction process makes the control and coordination of the construction progress of the entire project face severe challenges. Summary of the invention
[0003] Based on the above technical problems, an embodiment of the present invention provides a coupling simulation method and device based on a dam BIM model and a finite element model, aiming to obtain a schedule that meets both the contract node construction period and the structural safety results, thereby ensuring the feasibility and safety of the schedule.
[0004] A first aspect of an embodiment of the present invention provides a coupled simulation method based on a dam BIM model and a finite element model, the method comprising:
[0005] Determine the value of the simulation boundary parameter based on the current construction environment data, construction plan information and design plan information of the target hydropower project; the current construction environment data at least includes: project terrain data, currently completed project parts, and on-site monitoring data;
[0006] Based on the values of the simulation boundary parameters, constructing a building information model with an additional time dimension;
[0007] Based on the building information model, obtaining the schedule of each node of the target hydropower project;
[0008] Determining whether the construction period of the target hydropower project meets the requirements based on the planned construction period of each node and the contractual construction period of the target hydropower project;
[0009] In the case that the construction period does not meet the requirements, based on the current construction environment data, the construction plan information and the design plan information, the values of the simulation boundary parameters are re-determined; based on the re-determined values of the simulation boundary parameters, the step of constructing the building information model with an additional time dimension is re-executed until the step of determining whether the construction period of the target hydropower project meets the requirements, until it is determined that the construction period of the target hydropower project meets the requirements;
[0010] In the case where the construction period meets the requirements, a structural safety review is performed based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project;
[0011] In the case that the structural safety result of the target hydropower project is that the schedule structure is unsafe, based on the current construction environment data, the construction plan information and the design plan information, the values of the simulation boundary parameters are re-determined; based on the re-determined values of the simulation boundary parameters, the step of constructing a building information model with an additional time dimension is re-executed until the step of determining whether the construction period of the target hydropower project meets the requirements, until it is determined that the structural safety result of the target hydropower project is that the schedule structure is safe.
[0012] Optionally, when the construction period meets the requirements, a structural safety review is performed based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project, including:
[0013] When the construction period meets the requirements, the unit, the node and the physical quantity information related to each unit or each node of the target hydropower project in the building information model are obtained through the model information acquirer in the finite element analysis model to generate engineering structure data;
[0014] By using the finite element analysis model, the structural stress of the target hydropower project in the time dimension is calculated based on the engineering structure data;
[0015] A structural safety review is performed based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project.
[0016] Optionally, performing a structural safety review based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project includes:
[0017] In the case where the structural stress satisfies the structural safety condition, determining the structural safety result of the target hydropower project as the schedule structural safety;
[0018] In the case where the structural stress does not satisfy the structural safety condition, the structural safety result of the target hydropower project is determined to be that the schedule structure is unsafe.
[0019] Optionally, determining the value of the simulation boundary parameter based on the acquired current construction environment data, construction plan information and design plan information of the target hydropower project includes:
[0020] Based on the construction plan information, determining a parameter range of the simulation boundary parameter;
[0021] Based on the current construction environment data and the design scheme information, obtaining an initial value of the simulation boundary parameter within a parameter range of the simulation boundary parameter;
[0022] The re-determining the value of the simulation boundary parameter based on the current construction environment data, the construction plan information and the design plan information includes:
[0023] Based on the current construction environment data and the design scheme information, the value of the simulation boundary parameter is re-drafted within the parameter range of the simulation boundary parameter to obtain a new value of the simulation boundary parameter.
[0024] Optionally, the simulation boundary parameters include at least one of the following: construction machinery information, maximum allowable height difference between adjacent dam sections, maximum height difference of the entire dam, maximum allowable cantilever height, monthly effective construction days, concrete age, and initial setting time of concrete;
[0025] After the values of the simulation boundary parameters are re-drafted, at least one of the simulation boundary parameters has an initial value that is different from the new value.
[0026] Optionally, the method further comprises:
[0027] Performing three-dimensional scene interaction and integration on the data between the building information model and the finite element analysis model to obtain achievement information of the target hydropower project, wherein the achievement information at least includes: a three-dimensional simulation result of the construction progress and a simulation result of the structural safety;
[0028] Display the achievement information of the target hydropower project.
[0029] Optionally, the method further comprises:
[0030] In the case where the construction period does not meet the requirements, a first construction site of the target hydropower project that is behind schedule is determined based on the comparison result of the planned construction period of each node and the contractual node construction period of the target hydropower project, and an early warning message is output, wherein the early warning message at least includes: the construction progress of the first construction site is behind schedule;
[0031] When the structural stress does not meet the structural safety condition, a second construction location in the target hydropower project where the structural stress exceeds the safety threshold is determined, and an alarm message is output, wherein the alarm message at least includes: the structural stress of the second construction location exceeds the threshold.
[0032] A second aspect of an embodiment of the present invention provides a coupled simulation device based on a dam BIM model and a finite element model, the device comprising:
[0033] The first parameter determination module is used to determine the value of the simulation boundary parameter based on the current construction environment data, construction plan information and design plan information of the target hydropower project obtained; the current construction environment data at least includes: project terrain data, currently completed project parts, and on-site monitoring data;
[0034] A model construction module, used to construct a building information model with an additional time dimension based on the values of the simulation boundary parameters;
[0035] A construction period determination module, used to obtain the construction period of each node of the target hydropower project based on the building information model;
[0036] A construction period comparison module, used to determine whether the construction period of the target hydropower project meets the requirements based on the construction period of each node schedule and the contract node construction period of the target hydropower project;
[0037] The second parameter determination module is used to, when the construction period does not meet the requirements, redetermine the value of the simulation boundary parameter based on the current construction environment data, the construction plan information and the design plan information; based on the redetermined value of the simulation boundary parameter, re-execute the step of constructing the building information model with an additional time dimension, to the step of determining whether the construction period of the target hydropower project meets the requirements, until it is determined that the construction period of the target hydropower project meets the requirements;
[0038] A safety review module, used to perform a structural safety review based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project;
[0039] The third parameter determination module is used to, when the structural safety result of the target hydropower project is that the schedule structure is unsafe, redetermine the value of the simulation boundary parameter based on the current construction environment data, the construction plan information and the design plan information; based on the redetermined values of the simulation boundary parameters, re-execute the step of constructing a building information model with an additional time dimension, to the step of determining whether the construction period of the target hydropower project meets the requirements, until it is determined that the structural safety result of the target hydropower project is that the schedule structure is safe.
[0040] Optionally, the safety review module includes:
[0041] A finite element analysis module is used to obtain, when the construction period meets the requirements, each unit, each node and physical quantity information related to each unit or each node of the target hydropower project in the building information model through a model information acquirer in the finite element analysis model to generate engineering structure data;
[0042] A stress determination module, used to calculate the structural stress of the target hydropower project in the time dimension based on the engineering structure data through the finite element analysis model;
[0043] The safety review submodule is used to perform a structural safety review based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project.
[0044] Optionally, the safety review module includes:
[0045] A first safety determination module is used to determine that the structural safety result of the target hydropower project is a schedule structural safety when the structural stress satisfies the structural safety condition;
[0046] The second safety determination module is used to determine that the structural safety result of the target hydropower project is that the schedule structure is unsafe when the structural stress does not meet the structural safety condition.
[0047] Optionally, the first parameter determination module includes:
[0048] A range determination module, used to determine the parameter range of the simulation boundary parameter based on the construction plan information;
[0049] An initial value determination module, used to obtain an initial value of the simulation boundary parameter within a parameter range of the simulation boundary parameter based on the current construction environment data and the design scheme information;
[0050] The second parameter determination module includes:
[0051] The new value determination module is used to re-determine the value of the simulation boundary parameter within the parameter range of the simulation boundary parameter based on the current construction environment data and the design scheme information to obtain the new value of the simulation boundary parameter.
[0052] Optionally, the first parameter determination module includes:
[0053] A range determination module, used to determine the parameter range of the simulation boundary parameter based on the construction plan information;
[0054] An initial value determination module, used to obtain an initial value of the simulation boundary parameter within a parameter range of the simulation boundary parameter based on the current construction environment data and the design scheme information;
[0055] The third parameter determination module comprises:
[0056] The new value determination module is used to re-determine the value of the simulation boundary parameter within the parameter range of the simulation boundary parameter based on the current construction environment data and the design scheme information to obtain the new value of the simulation boundary parameter.
[0057] Optionally, the simulation boundary parameters include at least one of the following: construction machinery information, maximum allowable height difference between adjacent dam sections, maximum height difference of the entire dam, maximum allowable cantilever height, monthly effective construction days, concrete age, and initial setting time of concrete;
[0058] After the values of the simulation boundary parameters are re-drafted, at least one of the simulation boundary parameters has an initial value that is different from the new value.
[0059] Optionally, the device further comprises:
[0060] A result determination module is used to perform three-dimensional scene interaction and integration of data between the building information model and the finite element analysis model to obtain result information of the target hydropower project, wherein the result information at least includes: a three-dimensional simulation result of construction progress and a simulation result of structural safety;
[0061] The achievement display module is used to display the achievement information of the target hydropower project.
[0062] Optionally, the device further comprises:
[0063] A first output module is used to determine, when the construction period does not meet the requirements, a first construction site of the target hydropower project that is behind schedule according to a comparison result of the planned construction period of each node and the contractual node construction period of the target hydropower project, and output warning information, wherein the warning information at least includes: the construction progress of the first construction site is behind schedule;
[0064] The second output module is used to determine a second construction location in the target hydropower project where the structural stress exceeds a safety threshold when the structural stress does not meet the structural safety conditions, and output an alarm message, wherein the alarm message at least includes: the structural stress of the second construction location exceeds the standard.
[0065] Through the coupled simulation method based on the dam BIM model and the finite element model of the embodiment of the present invention, first, based on the current construction environment data, construction plan information and design plan information of the acquired target hydropower project, the value of the simulation boundary parameter is determined; secondly, based on the value of the simulation boundary parameter, a building information model with an additional time dimension is constructed; then, based on the building information model, the progress plan construction period of each node of the target hydropower project is obtained; then, based on the progress plan construction period of each node and the contract node construction period of the target hydropower project, it is determined whether the construction period of the target hydropower project meets the requirements; finally, in the case that the construction period does not meet the requirements, based on the current construction environment data, construction plan information and design plan information, the value of the simulation boundary parameter is re-determined; based on the re-determined value of the simulation boundary parameter, the step of constructing is re-executed A building information model with an additional time dimension is constructed, until the step of determining whether the construction period of the target hydropower project meets the requirements, until it is determined that the construction period of the target hydropower project meets the requirements; if the construction period meets the requirements, a structural safety review is performed based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project; and if the structural safety result of the target hydropower project is that the schedule structure is unsafe, based on the current construction environment data, construction plan information and design plan information, the values of the simulation boundary parameters are re-determined; and based on the re-determined values of the simulation boundary parameters, the step of constructing a building information model with an additional time dimension is re-executed, until the step of determining whether the construction period of the target hydropower project meets the requirements, until it is determined that the structural safety result of the target hydropower project is that the schedule structure is safe.
[0066] In this embodiment, taking into account the uncertainty of the construction process, in order to control and coordinate the construction progress of the target hydropower project, this embodiment proposes a coupled simulation method based on construction progress and structural safety, and simulates the simulation boundary parameters corresponding to the current construction plan to obtain the schedule period. When the schedule period does not meet the contract node period of the target hydropower project, the simulation boundary parameters are adjusted to obtain a new construction plan and then simulate it until the schedule period meets the contract node period of the target hydropower project. In this way, a feasible schedule is obtained; further, in order to ensure the safety of the feasible schedule, the simulation boundary parameters corresponding to the feasible schedule are simulated to obtain the structural safety result of the target hydropower project. When the structural safety result of the target hydropower project is that the schedule structure is unsafe, the simulation boundary parameters are adjusted to obtain a new construction plan and then simulate it until the new construction plan meets both the contract node period of the target hydropower project and the structural safety result is that the schedule structure is safe, and finally a feasible and safe schedule is obtained. Through simulation, this embodiment can predict in advance whether the current construction plan meets the contract node duration of the target hydropower project, and when the current construction plan does not meet the contract node duration of the target hydropower project, by multiple adjustments to the simulation boundary parameters corresponding to the current construction plan, a schedule that meets both the contract node duration of the target hydropower project and the structural safety results is obtained, thereby ensuring the feasibility and safety of the schedule. This embodiment couples the feasibility and safety of the adjusted schedule through multiple adjustments of the simulation boundary parameters, thereby avoiding the delay in construction progress due to uncertainty in the construction process in related technologies, which leads to the failure to meet the contract node duration of the target hydropower project, and also avoids safety issues caused by arbitrary adjustments to the current schedule. BRIEF DESCRIPTION OF THE DRAWINGS
[0067] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments of the present invention will be briefly introduced below. Obviously, the accompanying drawings in the following description are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative labor.
[0068] Figure 1 It is a flow chart of a coupling simulation method based on a dam BIM model and a finite element model shown in one embodiment of the present invention;
[0069] Figure 2 It is a general flow chart of a method for coupling simulation of construction progress and structural safety of a hydropower project based on BIM according to an embodiment of the present invention;
[0070] Figure 3It is an architecture diagram of a BIM-based hydropower project construction progress and structural safety coupling simulation system according to an embodiment of the present invention;
[0071] Figure 4 It is a structural block diagram of a coupled simulation device based on a dam BIM model and a finite element model provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0072] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0073] Please refer to Figure 1 , Figure 1 FIG. 1 is a flow chart of a coupled simulation method based on a dam BIM model and a finite element model according to an embodiment of the present invention. Figure 1 As shown, the method may include steps S11 to S15:
[0074] Step S11: Determine the value of the simulation boundary parameter based on the acquired current construction environment data, construction plan information and design plan information of the target hydropower project; the current construction environment data at least includes: project terrain data, currently completed project parts, and on-site monitoring data.
[0075] In this embodiment, for the target hydropower project, the current construction environment data, construction plan information and design plan information of the target hydropower project can be obtained first. Among them, the target hydropower project is a hydropower project that needs to be evaluated for construction progress and structural safety. The current construction environment data at least includes: project terrain data, currently completed project parts, and on-site monitoring data, such as the currently completed part of the project and the topographic parameters of the project.
[0076] Among them, based on the current construction environment data, an engineering database and an initial building information model (Building Information Modeling, BIM) can be established to realize the visualization and integrated unified management of the current construction environment information. The initial building information model and engineering database can be directly obtained through the data interface engine to avoid data loss and omission caused by repeated input and output during the data acquisition process.
[0077] In this embodiment, the values of the simulation boundary parameters can be determined based on the acquired current construction environment data, construction plan information and design plan information of the target hydropower project. In this embodiment, the values corresponding to multiple simulation boundary parameters can be formulated.
[0078] Furthermore, in one embodiment, the values of the simulation boundary parameters can be determined based on water conservancy construction specifications, on-site construction resources, design plan information, construction plan information, and contract node duration.
[0079] Step S12: constructing a building information model with an additional time dimension based on the values of the simulation boundary parameters.
[0080] In this embodiment, a building information model of an additional time dimension (i.e., a dam BIM model) can be constructed based on the determined values of the simulation boundary parameters, wherein the building information model of the additional time dimension is a building information model related to the engineering schedule of the additional time dimension.
[0081] For example, a building information model with an additional time dimension may be constructed based on the proposed values of the simulation boundary parameters and the initial building information model.
[0082] Step S13: Based on the building information model, the schedule of each node of the target hydropower project is obtained.
[0083] In this embodiment, after the building information model with the additional time dimension is constructed, the construction period of each node schedule of the target hydropower project can be predicted based on the building information model with the additional time dimension.
[0084] Step S14: Based on the planned construction periods of each node and the contractual node construction periods of the target hydropower project, determine whether the construction period of the target hydropower project meets the requirements.
[0085] In this embodiment, after obtaining the schedule construction period of each node output by the building information model with an additional time dimension, the schedule construction period of each node can be compared with the contract node construction period corresponding to the target hydropower project to determine whether the contract construction period of the target hydropower project meets the requirements, that is, to determine whether the schedule of the target hydropower project meets the contract construction period.
[0086] Step S15: When the construction period does not meet the requirements, based on the current construction environment data, the construction plan information and the design plan information, the values of the simulation boundary parameters are re-determined; based on the re-determined values of the simulation boundary parameters, the step of constructing a building information model with an additional time dimension is re-executed until the step of determining whether the construction period of the target hydropower project meets the requirements, until it is determined that the construction period of the target hydropower project meets the requirements.
[0087] In this embodiment, when it is determined that the contract duration of the target hydropower project does not meet the requirements based on the planned construction period of each node and the contract node duration corresponding to the target hydropower project, that is, when it is determined that the progress plan of the target hydropower project does not meet the contract duration, the values of each simulation boundary parameter can be re-determined based on the current construction environment data, construction plan information and design plan information obtained.
[0088] In this embodiment, the building information model with an additional time dimension can be reconstructed based on the re-determined values of the simulation boundary parameters; then, based on the reconstructed building information model with an additional time dimension, a new node schedule corresponding to the target hydropower project can be obtained; finally, based on the new node schedule corresponding to the target hydropower project and the contract node schedule of the target hydropower project, it is re-determined whether the construction period of the target hydropower project meets the requirements, until it is determined that the construction period of the target hydropower project meets the requirements.
[0089] Step S16: When the construction period meets the requirements, a structural safety review is performed based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project.
[0090] In this embodiment, when it is determined that the contractual construction period of the target hydropower project meets the requirements based on the planned construction period of each node and the contractual node construction period corresponding to the target hydropower project, the structural safety of the target hydropower project can be reviewed according to the structural stress of the target hydropower project in the time dimension to obtain the structural safety result of the target hydropower project.
[0091] Step S17: When the structural safety result of the target hydropower project is that the schedule structure is unsafe, based on the current construction environment data, the construction plan information and the design plan information, the values of the simulation boundary parameters are re-determined; based on the re-determined values of the simulation boundary parameters, the step of constructing a building information model with an additional time dimension is re-executed until the step of determining whether the construction period of the target hydropower project meets the requirements, until it is determined that the structural safety result of the target hydropower project is that the schedule structure is safe.
[0092] In this embodiment, when the structural safety result of the target hydropower project is determined to be that the schedule structure of the target hydropower project is unsafe, the values of each simulation boundary parameter can be re-determined based on the acquired current construction environment data, construction plan information and design plan information.
[0093] After obtaining the re-determined values of each simulation boundary parameter, the building information model of the additional time dimension can be reconstructed based on the re-determined values of the simulation boundary parameters; secondly, based on the reconstructed building information model of the additional time dimension, the new node schedule plan period corresponding to the target hydropower project is obtained; then, based on the new node schedule plan period corresponding to the target hydropower project and the contract node schedule of the target hydropower project, it is re-determined whether the construction period of the target hydropower project meets the requirements, until it is determined that the construction period of the target hydropower project meets the requirements; then, based on the new structural stress of the target hydropower project in the time dimension, a structural safety review is performed to obtain the structural safety result of the target hydropower project, until it is determined that the new structural safety result of the target hydropower project is the schedule structural safety of the target hydropower project, and it is determined that the construction progress of the target hydropower project is in line with expectations and the structural safety assessment result.
[0094] In the coupled simulation method based on the dam BIM model and the finite element model proposed in this embodiment, considering the uncertainty of the construction process, in order to control and coordinate the construction progress of the target hydropower project, this embodiment proposes a coupled simulation method based on the construction progress and structural safety, the simulation boundary parameters corresponding to the current construction plan are simulated to obtain the schedule construction period, and when the schedule construction period does not meet the contract node construction period of the target hydropower project, the simulation boundary parameters are adjusted to obtain a new construction plan and then simulated until the schedule construction period meets the contract node construction period of the target hydropower project, so that a feasible schedule is obtained; further, in order to ensure the safety of the feasible schedule, the simulation boundary parameters corresponding to the feasible schedule are simulated to obtain the structural safety result of the target hydropower project, and when the structural safety result of the target hydropower project is that the schedule structure is unsafe, the simulation boundary parameters are adjusted to obtain a new construction plan and then simulated until the new construction plan meets both the contract node construction period of the target hydropower project and the structural safety result is that the schedule structure is safe, and finally a feasible and safe schedule is obtained. Through simulation, this embodiment can predict in advance whether the current construction plan meets the contract node duration of the target hydropower project, and when the current construction plan does not meet the contract node duration of the target hydropower project, by multiple adjustments to the simulation boundary parameters corresponding to the current construction plan, a schedule that meets both the contract node duration of the target hydropower project and the structural safety results is obtained, thereby ensuring the feasibility and safety of the schedule. This embodiment couples the feasibility and safety of the adjusted schedule through multiple adjustments of the simulation boundary parameters, thereby avoiding the delay in construction progress due to uncertainty in the construction process in related technologies, which leads to the failure to meet the contract node duration of the target hydropower project, and also avoids safety issues caused by arbitrary adjustments to the current schedule.
[0095] In combination with the above embodiments, in one implementation, the present invention further provides a coupling simulation method based on a dam BIM model and a finite element model. In the method, the above step S16 may specifically include steps S21 to S23:
[0096] Step S21: When the construction period meets the requirements, the model information acquirer in the finite element analysis model is used to acquire the physical quantity information related to each unit, each node and each unit or each node of the target hydropower project in the building information model to generate engineering structure data.
[0097] In this embodiment, when it is determined that the contractual construction period of the target hydropower project meets the requirements based on the planned construction period of each node and the contractual node construction period corresponding to the target hydropower project, the building information model with an additional time dimension can be imported into the finite element analysis model through the data interface for calculation, and the structural safety of the target hydropower project can be reviewed to obtain the structural safety results of the current construction project of the target hydropower project.
[0098] Specifically, in this embodiment, for building information models in different file formats, a model information acquirer is defined in the finite element analysis model, and the model information acquirer in the finite element analysis model can be used to obtain each unit, each node and physical quantity information related to each unit or each node of the target hydropower project in the building information model of the additional time dimension to generate engineering structure data; wherein, the engineering structure data is a general data structure.
[0099] It can be understood that what can be obtained through the model information acquirer is the physical quantity information related to each unit of the target hydropower project that meets the construction period requirements in the building information model, or the physical quantity information related to each node, or the physical quantity information related to each node and each unit, thereby obtaining the general engineering structure data corresponding to the target hydropower project.
[0100] Step S22: using the finite element analysis model, based on the engineering structure data, calculate the structural stress of the target hydropower project in the time dimension.
[0101] In this embodiment, after obtaining the general engineering structure data corresponding to the target hydropower project, the structural stress of the target hydropower project in the time dimension of each unit and / or node can be calculated based on the acquired engineering structure data through a finite element analysis model (also called a finite element model).
[0102] Step S23: Performing a structural safety review based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project.
[0103] In this embodiment, after obtaining the structural stress of the target hydropower project in the time dimension, the structural safety of the target hydropower project can be reviewed according to the structural stress of the target hydropower project in the time dimension to obtain the structural safety result of the target hydropower project.
[0104] In this embodiment, construction information and current construction conditions are monitored in real time, a construction schedule that meets the construction period requirements is formulated through a building information model with an additional time dimension, the physical quantities of each unit node of the target hydropower project in the building information model are extracted and analyzed in combination with finite elements, and the structural stress of the target hydropower project under the time dimension of each unit node is verified by the extracted engineering structure data through the finite element analysis model. Through the coupling of the building information model with an additional time dimension and the finite element analysis model, the construction progress and structural safety of the hydropower project are mutually bounded, the feasibility and safety of the real-time schedule of the target hydropower project are fully verified, and scientific, refined and intelligent methods and means are provided for the full process, dynamic and visual control of the integrated progress of the hydropower project, and the construction progress and safety of the current hydropower project construction are displayed in real time.
[0105] In combination with the above embodiments, in one implementation, the present invention further provides a coupling simulation method based on a dam BIM model and a finite element model. In the method, the above step S16 may specifically include steps S31 to S32:
[0106] Step S31: When the structural stress satisfies the structural safety condition, determining the structural safety result of the target hydropower project as the schedule structural safety.
[0107] In this embodiment, a safety threshold of structural stress is set in advance. After the structural stress of the target hydropower project in the time dimension is obtained, the structural stress of the target hydropower project in the time dimension can be compared with the safety threshold of the structural stress. When it is determined that the structural stress of the target hydropower project in the time dimension is lower than the safety threshold of the structural stress, it is determined that the structural stress of the target hydropower project in the time dimension meets the structural safety condition. When the structural stress meets the structural safety condition, the structural safety result of the target hydropower project is determined to be the schedule plan structural safety of the target hydropower project.
[0108] Step S32: when the structural stress does not satisfy the structural safety condition, determining the structural safety result of the target hydropower project as a schedule-planned structural unsafety.
[0109] In this embodiment, when it is determined that the structural stress of the target hydropower project in the time dimension is higher than the safety threshold of the structural stress, it is determined that the structural stress of the target hydropower project in the time dimension does not meet the structural safety conditions. When the structural stress does not meet the structural safety conditions, the structural safety result of the target hydropower project is determined to be that the schedule plan structure of the target hydropower project is unsafe.
[0110] In combination with the above embodiments, in one implementation, the present invention further provides a coupling simulation method based on a dam BIM model and a finite element model. In the method, the above step S11 may specifically include steps S51 to S52, and the above step S15 or step S17 may specifically include S53:
[0111] Step S51: Based on the construction plan information, determine the parameter range of the simulation boundary parameter.
[0112] In this embodiment, the parameter range of each simulation boundary parameter can be determined based on the construction plan information of the target hydropower project. The parameter range is the value range of the parameter, and any value within the parameter range is acceptable.
[0113] Step S52: Based on the current construction environment data and the design scheme information, an initial value of the simulation boundary parameter is obtained within the parameter range of the simulation boundary parameter.
[0114] In this embodiment, after the parameter range of each simulation boundary parameter is determined, the initial value of each simulation boundary parameter can be obtained within the parameter range of each simulation boundary parameter based on the acquired current construction environment data and design scheme information.
[0115] Step S53: Based on the current construction environment data and the design scheme information, the value of the simulation boundary parameter is re-determined within the parameter range of the simulation boundary parameter to obtain a new value of the simulation boundary parameter.
[0116] In this embodiment, in the process of redetermining the values of the simulation boundary parameters, the values of the simulation boundary parameters are re-determined within the parameter range of the simulation boundary parameters determined in step S51 based on the current construction environment data and design scheme information of the target hydropower project to obtain new values of the simulation boundary parameters.
[0117] In combination with the above embodiments, in one implementation, the present invention also provides a coupled simulation method based on a dam BIM model and a finite element model, in which the simulation boundary parameters include at least one of the following: construction machinery information, the maximum allowable height difference between adjacent dam sections, the maximum height difference of the entire dam, the maximum allowable cantilever height, the monthly effective construction days, the age of concrete, and the initial setting time of concrete.
[0118] And, in this embodiment, after the values of the simulation boundary parameters are re-drafted, the initial value of at least one simulation boundary parameter among the simulation boundary parameters is different from the new value. That is, when the simulation boundary parameters are re-drafted, for the multiple simulation boundary parameters, the value of at least one simulation boundary parameter changes, that is, the initial value of at least one simulation boundary parameter is different from the new value.
[0119] In combination with the above embodiments, in one implementation, the present invention further provides a coupled simulation method based on a dam BIM model and a finite element model. In this method, in addition to the above steps, steps S61 and S62 may also be included:
[0120] Step S61: performing three-dimensional scene interaction and integration on the data between the building information model and the finite element analysis model to obtain achievement information of the target hydropower project.
[0121] In this embodiment, data interaction and integration can be performed between the building information model with an additional time dimension and the finite element analysis model, while providing good three-dimensional scene interaction to obtain the result information of the target hydropower project. The result information of the target hydropower project at least includes: the three-dimensional simulation result of the construction progress of the target hydropower project and the structural safety simulation result of the target hydropower project.
[0122] Step S62: Displaying the achievement information of the target hydropower project.
[0123] In this embodiment, the obtained achievement information of the target hydropower project can be displayed to achieve visualization of the achievement information of the target hydropower project. In addition, in this embodiment, the building information model can be used to more vividly display the construction process of the target hydropower project, which can provide effective support and intuitive visual effects for real-time adjustment of progress.
[0124] In combination with the above embodiments, in one implementation, the present invention further provides a coupled simulation method based on a dam BIM model and a finite element model. In this method, in addition to the above steps, steps S71 and S72 may also be included:
[0125] Step S71: When the construction period does not meet the requirements, the first construction site with delayed progress in the target hydropower project is determined based on the comparison results of the planned construction period of each node and the contract node construction period of the target hydropower project, and an early warning message is output. The early warning message at least includes: the construction progress of the first construction site is delayed.
[0126] In this embodiment, when it is determined that the construction period does not meet the requirements, the first construction site of the target hydropower project that is lagging behind in progress can be determined based on the comparison results of the planned construction period of each node and the contract node construction period of the target hydropower project, and an early warning message is output. Among them, the first construction site is a construction site in the target hydropower project where the construction progress does not meet the construction period requirements and is in a lagging state; the early warning information is warning information of the construction progress, and the early warning information at least includes: the construction progress of the first construction site is lagging behind. This embodiment can push the early warning information and make relevant reminders: such as flashing the screen, issuing an early warning sound, etc.
[0127] Step S72: When the structural stress does not meet the structural safety condition, determine a second construction location in the target hydropower project where the structural stress exceeds the safety threshold, and output an alarm message, wherein the alarm message at least includes: the structural stress of the second construction location exceeds the standard.
[0128] In this embodiment, when it is determined that the structural stress does not meet the structural safety conditions, the second construction site where the structural stress in the target hydropower project exceeds the corresponding safety threshold can be determined, and an alarm message can be output. Among them, the second construction site is the construction site where the structural stress in the target hydropower project exceeds the corresponding safety threshold; the alarm message is the warning message of the structural stress, and the alarm message at least includes: the structural stress of the second construction site exceeds the standard. This embodiment can push the alarm message and make relevant reminders: such as flashing the screen, issuing an alarm sound, etc. Among them, the alarm sound and the early warning sound of this embodiment can be the same or different, and can be freely set.
[0129] like Figure 2 As shown, Figure 2 This is a general flow chart of a method for coupling simulation of hydropower project construction progress and structural safety based on BIM according to an embodiment of the present invention. Figure 2In the process, first, the current construction environment data of the target hydropower project is obtained; secondly, simulation boundary parameters are formulated according to existing resources and conditions, such as water conservancy construction construction specifications, on-site construction resources, design plans, construction plans, and contract node durations; then, a building information model (BIM model) with an additional time dimension is established, such as a BIM model with an additional time dimension is established according to the proposed simulation boundary parameters; then, the schedule of the target hydropower project is determined based on the BIM model with an additional time dimension, and whether the contract is met by comparing the schedule with the contract node duration is determined. The same construction period node requirements; if the contract construction period node requirements are not met, the simulation boundary parameters are redetermined until the contract construction period node requirements are met; if the contract construction period node requirements are met, the BIM model of the additional time dimension that meets the construction period requirements is obtained, and the finite element analysis model is used to conduct a structural safety review to determine whether the structural safety requirements are met; if the structure meets the safety requirements, the schedule planning and safety verification of the target hydropower project are completed, and construction continues according to the schedule; if the structure does not meet the safety requirements, the simulation boundary parameters are redetermined until the schedule planning and safety verification of the target hydropower project are finally completed.
[0130] like Figure 3 As shown, Figure 3 This is a diagram showing an architecture of a BIM-based hydropower project construction progress and structural safety coupling simulation system according to an embodiment of the present invention. Figure 3 The BIM-based hydropower engineering construction progress and structural safety coupling simulation system includes at least: a system management module, an information management center, a progress simulation module, and a finite element module.
[0131] The system management module realizes the unified management of users, roles and permissions; it is the only way for the client to log in to the information management center, which meets the interface connection and data management of the progress simulation module, finite element module and field monitoring equipment. The field monitoring equipment uses different interfaces to compile messages through wireless bridges or wired optical fibers to achieve real-time communication with the system.
[0132] The information management center realizes the centralized management and display of the dam 3D structural model, geological 3D structural model and simulation model files, the upload, download, format conversion and full-text search of finite element calculation files, the upload and download of on-site construction data, and the information warning and information push of delayed progress; among them, through on-site monitoring equipment and on-site construction reporting, the current construction environment data on site can be input and uploaded to the information management center. In addition, the information management center can also determine the construction site with delayed progress based on the comparison results of the current progress and the planned progress, and push warning information and reminders.
[0133] The progress simulation module realizes the acquisition of current construction environment data and the upload of construction progress plan. It obtains current construction environment data, construction plan and design plan through the information management center, formulates the boundary parameters of progress simulation based on the acquired information, and establishes progress simulation BIM model, that is, BIM model with additional time dimension.
[0134] The finite element module obtains the progress simulation BIM model through the information management center, and after downloading the model, it combines the general finite element components to calculate the structural stress, and uploads the calculation results to the information management center. Among them, the finite element module is an external general finite element component to realize the import of the progress plan model and the stress calculation of the simulation model. For models in different file formats, a model information acquirer is defined to correctly obtain the unit, node and physical quantity information related to the unit or node, and generate a general data structure; VTK is used to display the physical quantities of the thematic analysis in the form of cloud maps, vector maps, contour maps, etc.
[0135] The BIM-based hydropower project construction progress and structural safety coupling simulation system provided by the embodiment of the present invention realizes the formulation, safety review and visualization of the construction progress plan, providing a scientific and refined method for adjusting the on-site construction progress.
[0136] It should be noted that, for the sake of simplicity, the method embodiments are described as a series of action combinations, but those skilled in the art should be aware that the embodiments of the present invention are not limited by the order of the actions described, because according to the embodiments of the present invention, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions involved are not necessarily required by the embodiments of the present invention.
[0137] Based on the same inventive concept, an embodiment of the present invention provides a coupled simulation device 400 based on a dam BIM model and a finite element model. Figure 4 , Figure 4 FIG. 1 is a structural block diagram of a coupled simulation device based on a dam BIM model and a finite element model provided by an embodiment of the present invention. Figure 4 As shown, the coupled simulation device 400 based on the dam BIM model and the finite element model includes:
[0138] The first parameter determination module 401 is used to determine the value of the simulation boundary parameter based on the current construction environment data, construction plan information and design plan information of the target hydropower project obtained; the current construction environment data at least includes: project terrain data, currently completed project parts, and on-site monitoring data;
[0139] A model building module 402, for building a building information model with an additional time dimension based on the values of the simulation boundary parameters;
[0140] The construction period determination module 403 is used to obtain the construction period of each node of the target hydropower project based on the building information model;
[0141] The construction period comparison module 404 is used to determine whether the construction period of the target hydropower project meets the requirements based on the construction period of each node schedule and the contract node construction period of the target hydropower project;
[0142] The second parameter determination module 405 is used to, if the construction period does not meet the requirements, re-determine the value of the simulation boundary parameter based on the current construction environment data, the construction plan information and the design plan information; based on the re-determined value of the simulation boundary parameter, re-execute the step of constructing the building information model with an additional time dimension, to the step of determining whether the construction period of the target hydropower project meets the requirements, until it is determined that the construction period of the target hydropower project meets the requirements;
[0143] A safety review module 406 is used to perform a structural safety review based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project when the construction period meets the requirements;
[0144] The third parameter determination module 407 is used to, when the structural safety result of the target hydropower project is that the schedule structure is unsafe, redetermine the value of the simulation boundary parameter based on the current construction environment data, the construction plan information and the design plan information; based on the redetermined values of the simulation boundary parameters, re-execute the step of constructing the building information model with an additional time dimension, until the step of determining whether the construction period of the target hydropower project meets the requirements, until it is determined that the structural safety result of the target hydropower project is that the schedule structure is safe.
[0145] Optionally, the safety review module 406 includes:
[0146] A finite element analysis module is used to obtain, when the construction period meets the requirements, each unit, each node and physical quantity information related to each unit or each node of the target hydropower project in the building information model through a model information acquirer in the finite element analysis model to generate engineering structure data;
[0147] A stress determination module, used to calculate the structural stress of the target hydropower project in the time dimension based on the engineering structure data through the finite element analysis model;
[0148] The safety review submodule is used to perform a structural safety review based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project.
[0149] Optionally, the safety review module 406 includes:
[0150] A first safety determination module is used to determine that the structural safety result of the target hydropower project is a schedule structural safety when the structural stress satisfies the structural safety condition;
[0151] The second safety determination module is used to determine that the structural safety result of the target hydropower project is that the schedule structure is unsafe when the structural stress does not meet the structural safety condition.
[0152] Optionally, the first parameter determination module 401 includes:
[0153] A range determination module, used to determine the parameter range of the simulation boundary parameter based on the construction plan information;
[0154] An initial value determination module, used to obtain an initial value of the simulation boundary parameter within a parameter range of the simulation boundary parameter based on the current construction environment data and the design scheme information;
[0155] The second parameter determination module 405 includes:
[0156] The new value determination module is used to re-determine the value of the simulation boundary parameter within the parameter range of the simulation boundary parameter based on the current construction environment data and the design scheme information to obtain the new value of the simulation boundary parameter.
[0157] Optionally, the first parameter determination module 401 includes:
[0158] A range determination module, used to determine the parameter range of the simulation boundary parameter based on the construction plan information;
[0159] An initial value determination module, used to obtain an initial value of the simulation boundary parameter within a parameter range of the simulation boundary parameter based on the current construction environment data and the design scheme information;
[0160] The third parameter determination module 407 includes:
[0161] The new value determination module is used to re-determine the value of the simulation boundary parameter within the parameter range of the simulation boundary parameter based on the current construction environment data and the design scheme information to obtain the new value of the simulation boundary parameter.
[0162] Optionally, the simulation boundary parameters include at least one of the following: construction machinery information, maximum allowable height difference between adjacent dam sections, maximum height difference of the entire dam, maximum allowable cantilever height, monthly effective construction days, concrete age, and initial setting time of concrete;
[0163] After the values of the simulation boundary parameters are re-drafted, at least one of the simulation boundary parameters has an initial value that is different from the new value.
[0164] Optionally, the coupled simulation device 400 based on the dam BIM model and the finite element model further includes:
[0165] A result determination module is used to perform three-dimensional scene interaction and integration of data between the building information model and the finite element analysis model to obtain result information of the target hydropower project, wherein the result information at least includes: a three-dimensional simulation result of construction progress and a simulation result of structural safety;
[0166] The achievement display module is used to display the achievement information of the target hydropower project.
[0167] Optionally, the coupled simulation device 400 based on the dam BIM model and the finite element model further includes:
[0168] A first output module is used to determine, when the construction period does not meet the requirements, a first construction site of the target hydropower project that is behind schedule according to a comparison result of the planned construction period of each node and the contractual node construction period of the target hydropower project, and output warning information, wherein the warning information at least includes: the construction progress of the first construction site is behind schedule;
[0169] The second output module is used to determine a second construction location in the target hydropower project where the structural stress exceeds a safety threshold when the structural stress does not meet the structural safety conditions, and output an alarm message, wherein the alarm message at least includes: the structural stress of the second construction location exceeds the standard.
[0170] As for the device embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment.
[0171] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.
[0172] Those skilled in the art will appreciate that embodiments of the present invention may be provided as methods, devices, or computer program products. Therefore, embodiments of the present invention may take the form of complete hardware embodiments, complete software embodiments, or embodiments combining software and hardware. Furthermore, embodiments of the present invention may take the form of computer program products implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program codes.
[0173] The embodiments of the present invention are described with reference to the flowcharts and / or block diagrams of the methods, terminal devices (systems), and computer program products according to the embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of the processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing terminal device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing terminal device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0174] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing terminal device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce a manufactured product including an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0175] These computer program instructions can also be loaded onto a computer or other programmable data processing terminal device so that a series of operating steps are executed on the computer or other programmable terminal device to produce a computer-implemented process, thereby providing instructions for executing on the computer or other programmable terminal device to implement the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0176] Although the preferred embodiments of the present invention have been described, those skilled in the art may make additional changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the embodiments of the present invention.
[0177] Finally, it should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or terminal device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or terminal device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or terminal device including the elements.
[0178] The above is a detailed introduction to a coupling simulation method and device based on a dam BIM model and a finite element model provided by the present invention. Specific examples are used in this article to illustrate the principles and implementation methods of the present invention. The description of the above embodiments is only used to help understand the method of the present invention and its core idea; at the same time, for those skilled in the art, according to the idea of the present invention, there will be changes in the specific implementation methods and application scopes. In summary, the content of this specification should not be understood as a limitation on the present invention.
Claims
1. A coupling simulation method based on a dam BIM model and a finite element model, characterized in that: The method comprises: Determine the value of the simulation boundary parameter based on the current construction environment data, construction plan information and design plan information of the target hydropower project; the current construction environment data at least includes: project terrain data, currently completed project parts, and on-site monitoring data; Based on the values of the simulation boundary parameters, constructing a building information model with an additional time dimension; Based on the building information model, obtaining the schedule of each node of the target hydropower project; Determining whether the construction period of the target hydropower project meets the requirements based on the planned construction period of each node and the contractual construction period of the target hydropower project; In the case that the construction period does not meet the requirements, based on the current construction environment data, the construction plan information and the design plan information, the values of the simulation boundary parameters are re-determined; based on the re-determined values of the simulation boundary parameters, the step of constructing the building information model with an additional time dimension is re-executed until the step of determining whether the construction period of the target hydropower project meets the requirements, until it is determined that the construction period of the target hydropower project meets the requirements; In the case where the construction period meets the requirements, a structural safety review is performed based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project; In the case where the structural safety result of the target hydropower project is that the schedule structure is unsafe, based on the current construction environment data, the construction plan information and the design plan information, the value of the simulation boundary parameter is re-determined; based on the re-determined value of the simulation boundary parameter, the step of constructing the building information model with an additional time dimension is re-executed until the step of determining whether the construction period of the target hydropower project meets the requirements, until it is determined that the structural safety result of the target hydropower project is that the schedule structure is safe; When the construction period meets the requirements, a structural safety review is performed based on the structural stress of the target hydropower project in the time dimension to obtain the structural safety result of the target hydropower project, including: In the case where the construction period meets the requirements, the physical quantity information related to each unit of the target hydropower project in the building information model, or the physical quantity information related to each node, or the physical quantity information related to each node and each unit is obtained through a model information acquirer in the finite element analysis model to generate engineering structure data; By using the finite element analysis model, the structural stress of the target hydropower project in the time dimension is calculated based on the engineering structure data; Performing a structural safety review based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project; The simulation boundary parameters include at least one of the following: construction machinery information, maximum allowable height difference between adjacent dam sections, maximum height difference of the entire dam, maximum allowable cantilever height, effective construction days per month, concrete age, and initial setting time of concrete; After the values of the simulation boundary parameters are re-determined, at least one of the simulation boundary parameters has an initial value that is different from the new value.
2. The coupling simulation method based on the dam BIM model and the finite element model according to claim 1 is characterized in that: The structural safety review based on the structural stress of the target hydropower project in the time dimension to obtain the structural safety result of the target hydropower project includes: In the case where the structural stress satisfies the structural safety condition, determining the structural safety result of the target hydropower project as the schedule structural safety; In the case where the structural stress does not satisfy the structural safety condition, the structural safety result of the target hydropower project is determined to be that the schedule structure is unsafe.
3. The coupling simulation method based on the dam BIM model and the finite element model according to claim 1 is characterized in that: Determining the values of the simulation boundary parameters based on the acquired current construction environment data, construction plan information, and design plan information of the target hydropower project includes: Based on the construction plan information, determining a parameter range of the simulation boundary parameter; Based on the current construction environment data and the design scheme information, obtaining an initial value of the simulation boundary parameter within a parameter range of the simulation boundary parameter; The re-determining the value of the simulation boundary parameter based on the current construction environment data, the construction plan information and the design plan information includes: Based on the current construction environment data and the design scheme information, the value of the simulation boundary parameter is re-drafted within the parameter range of the simulation boundary parameter to obtain a new value of the simulation boundary parameter.
4. The coupling simulation method based on the dam BIM model and the finite element model according to claim 1 is characterized in that: The method further comprises: Performing three-dimensional scene interaction and integration on the data between the building information model and the finite element analysis model to obtain achievement information of the target hydropower project, wherein the achievement information at least includes: a three-dimensional simulation result of the construction progress and a simulation result of the structural safety; The achievement information of the target hydropower project is displayed.
5. The coupled simulation method based on the dam BIM model and the finite element model according to claim 2 is characterized in that: The method further comprises: In the case where the construction period does not meet the requirements, a first construction site of the target hydropower project that is behind schedule is determined based on the comparison result of the planned construction period of each node and the contractual node construction period of the target hydropower project, and an early warning message is output, wherein the early warning message at least includes: the construction progress of the first construction site is behind schedule; When the structural stress does not meet the structural safety condition, a second construction location in the target hydropower project where the structural stress exceeds the safety threshold is determined, and an alarm message is output, wherein the alarm message at least includes: the structural stress of the second construction location exceeds the threshold.
6. A coupled simulation device based on a dam BIM model and a finite element model, characterized in that: The device comprises: The first parameter determination module is used to determine the value of the simulation boundary parameter based on the current construction environment data, construction plan information and design plan information of the target hydropower project obtained; the current construction environment data at least includes: project terrain data, currently completed project parts, and on-site monitoring data; A model construction module, used to construct a building information model with an additional time dimension based on the values of the simulation boundary parameters; A construction period determination module, used to obtain the construction period of each node of the target hydropower project based on the building information model; A construction period comparison module, used to determine whether the construction period of the target hydropower project meets the requirements based on the construction period of each node schedule and the contract node construction period of the target hydropower project; The second parameter determination module is used to, when the construction period does not meet the requirements, redetermine the value of the simulation boundary parameter based on the current construction environment data, the construction plan information and the design plan information; based on the redetermined value of the simulation boundary parameter, re-execute the step of constructing the building information model with an additional time dimension, to the step of determining whether the construction period of the target hydropower project meets the requirements, until it is determined that the construction period of the target hydropower project meets the requirements; A safety review module, used to perform a structural safety review based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project when the construction period meets the requirements; A third parameter determination module is used for, when the structural safety result of the target hydropower project is that the schedule structure is unsafe, re-determining the value of the simulation boundary parameter based on the current construction environment data, the construction plan information and the design plan information; based on the re-determined value of the simulation boundary parameter, re-executing the step of constructing the building information model with an additional time dimension, to the step of determining whether the construction period of the target hydropower project meets the requirements, until it is determined that the structural safety result of the target hydropower project is that the schedule structure is safe; The safety review module comprises: A finite element analysis module is used to obtain physical quantity information related to each unit of the target hydropower project in the building information model, or physical quantity information related to each node, or physical quantity information related to each node and each unit through a model information acquirer in the finite element analysis model when the construction period meets the requirements, and generate engineering structure data; A stress determination module, used to calculate the structural stress of the target hydropower project in the time dimension based on the engineering structure data through the finite element analysis model; A safety review submodule, used to perform a structural safety review based on the structural stress of the target hydropower project in the time dimension to obtain a structural safety result of the target hydropower project; The simulation boundary parameters include at least one of the following: construction machinery information, maximum allowable height difference between adjacent dam sections, maximum height difference of the entire dam, maximum allowable cantilever height, effective construction days per month, concrete age, and initial setting time of concrete; After the values of the simulation boundary parameters are re-determined, at least one of the simulation boundary parameters has an initial value that is different from the new value.
7. The coupled simulation device based on the dam BIM model and the finite element model according to claim 6, characterized in that: The safety review module comprises: A first safety determination module is used to determine that the structural safety result of the target hydropower project is a schedule structural safety when the structural stress satisfies the structural safety condition; The second safety determination module is used to determine that the structural safety result of the target hydropower project is that the schedule structure is unsafe when the structural stress does not meet the structural safety condition.
8. The coupled simulation device based on the dam BIM model and the finite element model according to claim 6, characterized in that: The first parameter determination module includes: A range determination module, used to determine the parameter range of the simulation boundary parameter based on the construction plan information; An initial value determination module, used to obtain an initial value of the simulation boundary parameter within a parameter range of the simulation boundary parameter based on the current construction environment data and the design scheme information; The second parameter determination module includes: The new value determination module is used to re-determine the value of the simulation boundary parameter within the parameter range of the simulation boundary parameter based on the current construction environment data and the design scheme information to obtain the new value of the simulation boundary parameter.
9. The coupled simulation device based on the dam BIM model and the finite element model according to claim 6, characterized in that: The first parameter determination module includes: A range determination module, used to determine the parameter range of the simulation boundary parameter based on the construction plan information; An initial value determination module, used to obtain an initial value of the simulation boundary parameter within a parameter range of the simulation boundary parameter based on the current construction environment data and the design scheme information; The third parameter determination module comprises: The new value determination module is used to re-determine the value of the simulation boundary parameter within the parameter range of the simulation boundary parameter based on the current construction environment data and the design scheme information to obtain the new value of the simulation boundary parameter.
10. The coupled simulation device based on the dam BIM model and the finite element model according to claim 6, characterized in that: The device also includes: A result determination module is used to perform three-dimensional scene interaction and integration of data between the building information model and the finite element analysis model to obtain result information of the target hydropower project, wherein the result information at least includes: a three-dimensional simulation result of construction progress and a simulation result of structural safety; The achievement display module is used to display the achievement information of the target hydropower project.
11. The coupled simulation device based on the dam BIM model and the finite element model according to claim 7, characterized in that: The device also includes: A first output module is used to determine, when the construction period does not meet the requirements, a first construction site of the target hydropower project that is behind schedule according to a comparison result of the planned construction period of each node and the contractual node construction period of the target hydropower project, and output warning information, wherein the warning information at least includes: the construction progress of the first construction site is behind schedule; The second output module is used to determine a second construction location in the target hydropower project where the structural stress exceeds a safety threshold when the structural stress does not meet the structural safety conditions, and output an alarm message, wherein the alarm message at least includes: the structural stress of the second construction location exceeds the standard.