Reinforced cement stabilized macadam base road construction process

By using lift adjustment sleeves and linkage components in the steel brazing support mechanism, the problem of inconvenient adjustment of the horizontal position of the wire rope connection point is solved, and the convenient arrangement and fixation of the wire rope is achieved, and the efficiency and stability of the cement-stabilized gravel base road construction is improved. sex.

CN119021052APending Publication Date: 2024-11-26浙江锦圣建设有限公司
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411258642.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-09
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

In the construction of cement-stabilized gravel base roads, it is inconvenient to adjust the connection points between the wire rope and the steel brazing in the horizontal direction, which affects the construction efficiency.

Method used

The steel brazing support mechanism with lifting and lowering adjusting sleeves and linkage components is adopted to facilitate the arrangement and fixation of the wire rope through arcuate grooves and elastic components, ensuring that the wire rope remains tight during installation and automatically reset when removed.

Benefits of technology

It improves the layout and adjustment efficiency of the wire rope, simplifies the construction process, ensures accurate control of the pavement elevation, and improves construction efficiency and stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021052A_ABST
    Figure CN119021052A_ABST
Patent Text Reader

Abstract

The invention discloses an enhanced cement stabilized macadam base road construction process, which is characterized in that during material mixing and paving, a paver controls the elevation of a road surface through a steel wire rope on the road side and a guide beam on the middle line of the road, and a large number of steel chisel supporting mechanisms need to be matched for use when the steel wire rope is unwound; the height of the lifting adjusting sleeve on the steel chisel and the horizontal position of the supporting shaft on the lifting adjusting sleeve need to be adjusted, so that the steel wire rope can be locally embedded in the designed position of the arc-shaped groove of the supporting shaft, the steel wire rope needs to be kept in a tightened state in the arrangement process, and therefore the steel wire rope has downward acting force on the arc-shaped groove in the support; therefore, the pressing column can move downwards in the installation process of the steel wire rope, the elastic force of the first elastic assembly and the elastic force of the second elastic assembly are overcome through the linkage assembly so that the fixing spikes of the supporting rod can pierce into rubber filler strips of the lifting adjusting sleeve to be fixed, and the effect that the horizontal position of the supporting shaft on the lifting adjusting sleeve can be conveniently adjusted and fixed is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of road construction, in particular to a construction process for a reinforced cement-stabilized crushed stone base road. Background Art

[0002] Because cement-stabilized gravel base has the advantages of good mechanical strength, frost resistance, stability and durability, it has good overall performance and is widely used in road projects. The construction technology of cement-stabilized gravel base is also quite mature. Appropriate cement and water are added to the sand and gravel mixture prepared in a certain proportion. After mixing and spreading, it can be formed by compaction and maintenance at the optimal moisture content.

[0003] When the paver is working, it controls the elevation of the road surface through the steel wire rope on the road side and the guide beam on the center line of the road. When arranging the steel wire rope, usually multiple steel chisels are inserted on the ground, and then the steel wire rope is fixed on the multiple steel chisels for arrangement. At this time, there are multiple connection points between the steel wire rope and the multiple steel chisels, and these connection points need to be at the required positions during design.

[0004] The height adjustment of the connection point between the wire rope and the steel bar is relatively convenient, and it is usually fixed after adjusting the height. However, the horizontal position of the connection point is related to the insertion point of the steel bar on the ground, the verticality of the steel bar when inserted, etc. If the horizontal position of the connection point deviates, it will be inconvenient to adjust. Summary of the invention

[0005] The invention aims to provide a reinforced cement-stabilized crushed stone base road construction process, which has the function of facilitating the arrangement of steel wire ropes.

[0006] The above technical objectives of the present invention are achieved through the following technical solutions: A reinforced cement-stabilized gravel base road construction process, comprising the following steps: (S1) construction preparation: inserting steel bar support mechanisms at intervals on both sides of the road, setting steel wire ropes between multiple steel bar support mechanisms on the same side, setting guide beams on the center line of the road, and regularly sprinkling water on the ground to keep it moist; (S2) mixing the mixture: adding cement and water in proportion to the mixed raw materials of sand and gravel prepared in proportion, and mixing to obtain a mixture; (S3) transporting the mixture: transporting the mixture with a dump truck and covering it with a tarpaulin during transportation; (S4) spreading the mixture: transporting the mixture to Two pavers of the same model are used. The distance between the two pavers is 5-10 meters. The pavers control the elevation of the road surface through the steel wire rope on the road side and the guide beam on the center line of the road. The two pavers overlap and pave 50-100 cm. The center seam is trimmed manually. (S5) Mixture rolling: The cement stabilized gravel base is compacted by rolling with a roller. (S6) Watering and curing: After the rolling is completed, the geotextile is covered on the rolled cement stabilized gravel base and watered by a watering mechanism. The steel bar support mechanism includes a steel bar for inserting into the ground, a lifting and adjusting sleeve arranged to be lifted and lowered along the direction of the steel bar and fixed at any position, and a lifting and adjusting sleeve arranged to be lifted and lowered along the direction of the steel bar and fixed at any position. A support shaft is telescopically arranged on a lifting and adjusting sleeve perpendicular to the extension direction of the steel drill and has an arc-shaped groove at one end for the steel wire rope to be partially embedded downward; the lifting and adjusting sleeve is provided with a telescopic hole for the support shaft to be telescopically arranged, the top of the telescopic hole is provided with a mounting groove extending along its length direction, a rubber pad is provided in the mounting groove, a central square hole is provided in the middle of the support shaft, a first through hole arranged and distributed along its length direction and communicating with the central square hole is provided at the top of one end of the support shaft, a second through hole communicating with the central square hole is provided at the bottom of the arc-shaped groove; a pressing column embedded in the central square hole is telescopically arranged at the second through hole, the A first elastic component for driving the pressing column to move upward is arranged between the lower end of the pressing column and the supporting shaft, a support rod is telescopically arranged in the central square hole, the support rod is provided with a plurality of fixed spikes which can pass through the first through hole and penetrate into the rubber pad strip as the support rod moves upward, an anti-detachment end cap is arranged at the end of the supporting shaft away from the arc-shaped groove, a second elastic component for driving the support rod to move downward so that the fixed spikes are in the first through hole is arranged between the support rod and the supporting shaft, and a linkage component for overcoming the elastic force of the first elastic component and the second elastic component to make the support rod move upward when the pressing column is pressed downward is arranged between the support rod and the pressing column.

[0007] By adopting the above technical scheme, when paving the mixed material, the paver controls the elevation of the road surface through the steel wire rope on the road side and the guide beam of the center line of the road. When laying out the steel wire rope, it is necessary to cooperate with a large number of steel bar support mechanisms. During the use of the steel bar support mechanism, it is necessary to adjust the height of the lifting adjustment sleeve on the steel bar and the horizontal position of the support shaft on the lifting adjustment sleeve so that the designed position of the arc groove of the support shaft can be partially embedded with the steel wire rope. The steel wire rope needs to be kept in a taut state during the arrangement of the steel wire rope. Therefore, the steel wire rope has a downward force on the arc groove in the support, so that the pressing column can move downward during the installation of the steel wire rope. The linkage component overcomes the elastic force of the first elastic component and the second elastic component so that the fixed spike of the support rod is inserted into the rubber pad of the lifting adjustment sleeve for fixing, thereby facilitating the adjustment and fixing of the horizontal position of the support shaft on the lifting adjustment; at the same time, when removing the steel wire rope, the support rod moves downward under the resetting action of the second elastic component so that the fixed spike and the rubber pad are separated, and the support shaft can continue to be adjusted relative to the lifting adjustment sleeve; finally, it has the effect of facilitating the arrangement of the steel wire rope.

[0008] The present invention is further configured as follows: the upper and lower ends of the lifting and adjusting sleeve are respectively provided with metal springs with connecting holes that are sleeved on the steel bar, and the two metal springs extend in a direction away from the rear side of the support shaft. When an external force is applied to the two metal springs in a direction toward each other, the connecting holes of the metal springs are separated from the steel bar to allow the lifting and adjusting sleeve to move up and down; when the two metal springs are released, the inner sides of the connecting holes of the metal springs are pressed against the peripheral side of the steel bar for fixation.

[0009] By adopting the above technical solution, when an external force is applied to the two metal springs in a direction toward each other, the connecting holes of the metal springs are separated from the steel bar so that the lifting and adjusting sleeve moves up and down. When the two metal springs are released, the inner sides of the connecting holes of the metal springs are pressed against the peripheral sides of the steel bar for fixation, thereby facilitating the adjustment of the position of the lifting and adjusting sleeve on the steel bar.

[0010] The present invention is further configured as follows: a third through hole corresponding to the second through hole and communicating with the central square hole is provided at the bottom of the support shaft; the first elastic component includes a guide shaft provided at the lower end of the pressing column and passing through the third through hole, a first compression spring sleeved on the guide shaft and with both ends pressed against the lower surface of the pressing column and the bottom of the central square hole, and an anti-slip nut provided at the lower end of the guide shaft and pressed against the bottom of the support shaft; the second through hole can be used for the first compression spring to be embedded.

[0011] By adopting the above technical solution, during installation, the first compression spring is firstly sleeved on the guide shaft, so that the lower end of the guide shaft passes through the third through hole, and the anti-dropping nut is installed on the lower end of the guide shaft, so that the upper end of the pressing column is kept in the arc groove in a natural state. At the same time, when the wire rope is arranged, it is placed on the arc groove, and the wire rope exerts downward pressure on the pressing column, which overcomes the elastic force of the first compression spring and causes the pressing column to move downward.

[0012] The present invention is further configured as follows: two countersunk threaded holes communicating with the central square hole are configured at the upper end of the support shaft; the second elastic component includes a guide sleeve arranged on the upper surface of both ends of the support rod, a second compression spring sleeved on the threaded sleeve and pressed tightly between the upper surface of the support rod and the top of the central square hole, and an anti-slip bolt threadedly connected to the countersunk threaded hole and the lower end of which is embedded in the guide sleeve.

[0013] By adopting the above technical scheme, during installation, the second compression spring is first installed on the guide sleeves at both ends of the support rod, and then the support rod is installed in the central square hole of the support shaft, and then the anti-detachment bolt is threadedly connected to the countersunk threaded hole, so that the lower end of the anti-detachment bolt is embedded in the guide sleeve, thereby realizing positioning and guiding the lifting and lowering of the support rod, and preventing the second compression spring from falling off; when the linkage assembly drives the support rod to move upward, the second compression spring is compressed by force, and the fixed spikes on the support rod are inserted into the rubber pad strip for fixing; when the linkage assembly cancels the action on the support rod, under the resetting action of the second compression spring, the support rod moves downward and drives the fixed spikes to disengage from the rubber pad strip.

[0014] The present invention is further configured as follows: a mounting hole communicating with the central square hole is provided below the support shaft, a connecting protrusion is provided at a position below the mounting hole of the support shaft, the linkage assembly comprises a connecting column, a hinge shaft provided between the connecting protrusion and the connecting column, a first linkage arm provided at one end of the connecting column and having a first waist-shaped hole, and a second linkage arm provided at the other end of the connecting column; an annular groove extending upward is provided on the circumferential side of the lower end of the pressing column, the pressing column passes through the first waist-shaped hole and makes the first linkage arm abut against the upper surface of the annular groove, and the second linkage arm is supported on the lower surface of the support rod; in the process that the pressing column moves downward to drive the first linkage arm to rotate downward, the second linkage arm overcomes the action of the second elastic component to drive the support rod to move upward.

[0015] By adopting the above technical solution, when the pressing column moves downward and drives the first linkage arm to rotate downward, the second linkage arm overcomes the action of the second elastic component and drives the support rod to move upward, thereby driving the fixed spike to penetrate into the rubber pad. At the same time, when the pressing column is reset, the support rod and the linkage arm can be reset under the reset action of the second elastic component.

[0016] The present invention is further configured as follows: in step (S1), the operation steps of driving the steel drill support mechanism and arranging the steel wire rope are as follows: ① first, the steel drills of the multiple steel drill support mechanisms are driven into the ground at fixed points, and an external force is applied to the two metal spring plates of the lifting and adjusting sleeve in the direction of approaching each other, and the connecting holes of the metal spring plates are separated from the steel drill to make the lifting and adjusting sleeve move up and down, so that when the support shaft is adjusted to the required height, and then the two metal spring plates are released, the inner sides of the connecting holes of the metal spring plates are pressed against the peripheral side of the steel drill to fix it; ② then the support shaft is extended and retracted so that the arc on the support shaft The groove is in the position; ③ Arrange the wire rope. During the arrangement of the wire rope, it is placed in a taut state on the arc-shaped groove in the support of multiple steel drill support mechanisms. During the installation of the wire rope, the pressing column is driven to move downward, and the elastic force of the first elastic component and the second elastic component is overcome by the linkage component so that the fixed spike of the support rod is inserted into the rubber pad of the lifting adjustment sleeve for fixation; ④ If it is necessary to fine-tune the position of the arc-shaped groove of the support shaft, the wire rope and the pressing column are separated by applying an upward pulling force to the wire rope. At this time, the support shaft is in a movable and adjustable position again.

[0017] The present invention is further configured as follows: a plurality of the watering mechanisms are provided, and the watering mechanisms can move forward and backward along the steel wire ropes on both sides of the road.

[0018] The present invention is further configured as follows: the sprinkler mechanism includes a support beam, guide wheels arranged at both ends of the support beam and resting on steel wire ropes on both sides of the road, a spray pipe arranged on the support beam and having multiple spray joints, a water supply tank, a water pump connected to the water supply tank, a hose connected between the water pump and the spray pipe, and a push-pull handle arranged on the support beam; when the guide wheel is resting on the steel wire rope and passes the position of the support shaft, the guide wheel does not interfere with the support shaft.

[0019] By adopting the above technical scheme, in conventional watering and curing, a sprinkler truck is usually used for watering. However, the sprinkler truck causes local pressure on the cement-stabilized gravel base layer, which easily causes deformation of the cement-stabilized gravel base layer. At this time, the steel wire ropes on both sides of the road are used in conjunction, so that the sprinkler mechanism can move back and forth along the steel wire ropes on both sides, and cooperate with the multiple sprinkler heads on the sprinkler pipe to evenly sprinkle water, thereby improving the effect of watering and curing.

[0020] The present invention is further configured as follows: the arc-shaped groove is connected to a receiving groove communicated with the second through hole, and the upper end of the pressing column is provided with an arc-shaped portion which protrudes from the arc-shaped groove in an initial state and is located in the receiving groove when under pressure; and also includes a reinforcement mechanism which drives the pressing column to maintain a state of protruding from the arc-shaped groove and reinforces the steel chisel support mechanism during the use of the sprinkler mechanism, the reinforcement mechanism includes a base, a support rod arranged on the base, and a threaded tube threadedly connected to the support rod, and the upper end of the threaded tube is provided with an embedding hole for embedding the guide shaft.

[0021] By adopting the above technical solution, during the use of the sprinkler mechanism, the guide wheel is supported on the steel wire rope at the end of the support shaft, and the steel chisel support mechanism is unstable at this time; by setting up a reinforcement mechanism, the threaded tube can be embedded in the lower end of the guide shaft during the rotation of the thread, so as to support the guide shaft, and cooperate with the anti-slip nut to adjust downward. At this time, when the threaded tube continues to rotate upward, the pressing column can be driven to maintain a state of protruding from the arc-shaped groove, thereby ensuring that the guide wheel avoids interference with the support shaft during the shaping process.

[0022] The present invention is further configured as follows: in step (S6), the operating steps of installing the guide wheel on the wire rope include the following: ① first rotate the anti-dropping nut of the first elastic component of the steel drill support mechanism downward so that the pressing column has an active stroke in the upward direction; ② then install the reinforcement mechanism below the end of the support shaft of the corresponding steel drill support mechanism, and after the threaded tube is connected to the lower end of the guide shaft by rotating the threaded tube upward, the guide shaft is driven to move upward, so that the pressing column drives the wire rope upward; ③ place the guide wheels at both ends of the support beam on the two wire ropes on both sides of the road. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a partial structural schematic diagram of multiple steel drill support mechanisms and steel wire ropes in the present invention; Figure 2 It is a partial structural schematic diagram of a single steel drill support mechanism and a steel wire rope in the present invention; Figure 3 It is a partial structural schematic diagram of a single steel drill support mechanism in the present invention; Figure 4 It is a structural cross-sectional view of a single steel drill support mechanism and a steel wire rope in the present invention; Figure 5 Figure 4 Schematic diagram of the local structure; Figure 6 It is a structural schematic diagram of the steel drill support mechanism, the water sprinkling mechanism, and the reinforcement mechanism in the present invention; Figure 7 yes Figure 6 A partial enlarged view of point A in the figure.

[0024] Figure numerals: 1, steel drill support mechanism; 11, steel drill; 12, lifting adjustment sleeve; 121, telescopic hole; 122, mounting groove; 123, rubber pad; 13, support shaft; 131, arc-shaped groove; 132, central square hole; 133, first through hole; 134, second through hole; 135, third through hole; 136, threaded hole; 137, mounting hole; 138, connecting protrusion; 139, accommodating groove; 14, pressing column; 141, annular groove; 142, arc-shaped portion; 15, first elastic component; 151, guide shaft; 152, first compression spring; 153, anti-drop nut; 16, support rod; 161, fixing spike; 17. Anti-slip end cover; 18. Second elastic component; 181. Guide sleeve; 182. Second compression spring; 183. Anti-slip bolt; 19. Linkage component; 191. Connecting column; 192. Articulated shaft; 193. First linkage arm; 1931. First waist-shaped hole; 194. Second linkage arm; 110. Metal spring; 1101. Connecting hole; 2. Sprinkler mechanism; 21. Support beam; 22. Guide wheel; 23. Sprinkler pipe; 231. Sprinkler joint; 24. Water supply tank; 25. Water pump; 26. Hose; 27. Push-pull handle 3. Reinforcement mechanism; 31. Base; 32. Support rod; 33. Threaded pipe; 331. Embedded hole. DETAILED DESCRIPTION

[0025] The present invention is further described in detail below in conjunction with the accompanying drawings.

[0026] Embodiment: A construction process for an enhanced cement-stabilized gravel base road comprises the following steps: (S1) construction preparation: driving steel bar support mechanisms 1 at intervals on both sides of the road, setting steel wire ropes between multiple steel bar support mechanisms 1 on the same side, setting guide beams on the center line of the road, and regularly sprinkling water on the ground to keep it moist; (S2) mixing the mixture: adding cement and water in proportion to the mixed raw materials of sand and gravel prepared in proportion, and mixing to obtain a mixture; (S3) transporting the mixture: transporting the mixture with a dump truck, and covering it with a tarpaulin during transportation; ( S4) Mixture spreading: The mixture is transported to two pavers of the same model. The two pavers are 5-10 meters apart during paving. The pavers control the elevation of the road surface through the steel wire ropes on the side of the road and the guide beams on the center line of the road. The two pavers overlap and pave 50-100 cm, and the center seam is trimmed manually; (S5) Mixture rolling: The cement-stabilized gravel base is compacted by a roller; (S6) Watering and curing: After the rolling is completed, the geotextile is covered on the rolled cement-stabilized gravel base, and water is sprinkled for curing by the watering mechanism 2.

[0027] like Figure 1 and Figure 2As shown, the steel drill support mechanism 1 includes a steel drill 11 for inserting into the ground, a lifting and adjusting sleeve 12 which is lifted and lowered along the direction of the steel drill 11 and can be fixed at any position, and a support shaft 13 which is telescopically set in the lifting and adjusting sleeve 12 along the extending direction perpendicular to the steel drill 11 and has an arc-shaped groove 131 at one end for the steel wire rope to be partially embedded downward.

[0028] like Figure 2 As shown, the upper and lower ends of the lifting and adjusting sleeve 12 are respectively provided with metal springs 110 with connecting holes 1101 that are sleeved on the steel bar 11. The two metal springs 110 extend in a direction away from the rear side of the support shaft 13. When an external force is applied to the two metal springs 110 in a direction toward each other, the connecting holes 1101 of the metal springs 110 are separated from the steel bar 11 to allow the lifting and adjusting sleeve 12 to move up and down. When the two metal springs 110 are released, the inner sides of the connecting holes 1101 of the metal springs 110 are pressed against the peripheral side of the steel bar 11 for fixation.

[0029] like Figures 2 to 5 As shown, the lifting and lowering adjustment sleeve 12 is provided with a telescopic hole 121 for the support shaft 13 to be telescopically set, the top of the telescopic hole 121 is provided with a mounting groove 122 extending along its length direction, a rubber pad 123 is provided in the mounting groove 122, a central square hole 132 is provided in the middle of the support shaft 13, a first through hole 133 arranged along its length direction and communicating with the central square hole 132 is provided at the top of one end of the support shaft 13, and a second through hole 134 communicating with the central square hole 132 is provided at the bottom of the arc groove 131. A pressing column 14 embedded in the central square hole 132 is telescopically arranged at the second through hole 134, a first elastic component 15 for driving the pressing column 14 to move upward is arranged between the lower end of the pressing column 14 and the support shaft 13, a support rod 16 is telescopically arranged in the central square hole 132, and a plurality of fixed spikes 161 are arranged on the support rod 16, which can pass through the first through hole 133 and penetrate into the rubber pad 123 as the support rod 16 moves upward, an anti-dropping end cap 17 is arranged at one end of the support shaft 13 away from the arc-shaped groove 131, a second elastic component 18 for driving the support rod 16 to move downward so that the fixed spikes 161 are located in the first through hole 133 is arranged between the support rod 16 and the support shaft 13, and a linkage component 19 is arranged between the support rod 16 and the pressing column 14 for overcoming the elastic force of the first elastic component 15 and the second elastic component 18 to move the support rod 16 upward during the downward pressing of the pressing column 14. At the same time, the arc groove 131 is connected to a receiving groove 139 communicating with the second through hole 134 , and the upper end of the pressing column 14 is provided with an arc portion 142 which protrudes from the arc groove 131 in the initial state and is located in the receiving groove 139 in the compressed state.

[0030] like Figure 4 and Figure 5As shown, a third through hole 135 corresponding to the second through hole 134 and communicating with the central square hole 132 is provided at the bottom of the support shaft 13, the first elastic component 15 includes a guide shaft 151 arranged at the lower end of the pressing column 14 and passing through the third through hole 135, a first compression spring 152 sleeved on the guide shaft 151 and with both ends pressed against the lower surface of the pressing column 14 and the bottom of the central square hole 132, and an anti-slip nut 153 arranged at the lower end of the guide shaft 151 and pressed against the bottom of the support shaft 13, and the second through hole 134 can be used for the first compression spring 152 to be embedded.

[0031] like Figure 4 and Figure 5 As shown, two countersunk threaded holes 136 communicating with the central square hole 132 are set at the upper end of the support shaft 13, and the second elastic component 18 includes a guide sleeve 181 arranged on the upper surface of both ends of the support rod 16, a second compression spring 182 sleeved on the threaded sleeve and pressed between the upper surface of the support rod 16 and the top of the central square hole 132, and an anti-slip bolt 183 threadedly connected to the countersunk threaded hole 136 and the lower end of which is embedded in the guide sleeve 181.

[0032] like Figure 4 and Figure 5 As shown, a mounting hole 137 communicating with the central square hole 132 is provided below the support shaft 13, a connecting protrusion 138 is provided at a position below the mounting hole 137 of the support shaft 13, and the linkage assembly 19 includes a connecting column 191, a hinge shaft 192 arranged between the connecting protrusion 138 and the connecting column 191, a first linkage arm 193 arranged at one end of the connecting column 191 and having a first waist-shaped hole 1931, and a second linkage arm 194 arranged at the other end of the connecting column 191; an annular groove 141 extending upward is provided on the circumferential side of the lower end of the pressing column 14, the pressing column 14 passes through the first waist-shaped hole 1931 and makes the first linkage arm 193 abut against the upper surface of the annular groove 141, and the second linkage arm 194 is supported on the lower surface of the support rod 16; in the process of the pressing column 14 moving downward to drive the first linkage arm 193 to rotate downward, the second linkage arm 194 overcomes the action of the second elastic component 18 to drive the support rod 16 to move upward.

[0033] In step (S1), the operation steps of driving the steel drill support mechanism 1 and arranging the steel wire rope are as follows: ① first, the steel drills 11 of the multiple steel drill support mechanisms 1 are driven into the ground at a fixed point, and an external force is applied to the two metal spring plates 110 of the lifting and adjusting sleeve 12 in a direction of approaching each other, and the connecting holes 1101 of the metal spring plates 110 are separated from the steel drill 11 so that the lifting and adjusting sleeve 12 moves up and down, so that when the support shaft 13 is adjusted to the required height, and then the two metal spring plates 110 are released, the inner side of the connecting hole 1101 of the metal spring plate 110 is pressed against the peripheral side of the steel drill 11 for fixing; ② then the support shaft 13 is extended and retracted so that the arc groove 11 on the support shaft 13 31 is in the position; ③ arrange the wire rope. During the arrangement process, the wire rope is placed in a taut state on the arc-shaped groove 131 in the support of multiple steel drill support mechanisms 1. During the installation of the wire rope, the pressing column 14 is driven to move downward, and the elastic force of the first elastic component 15 and the second elastic component 18 is overcome by the linkage component 19 so that the fixed spike 161 of the support rod 16 penetrates into the rubber pad 123 of the lifting and adjusting sleeve 12 for fixation; ④ If it is necessary to fine-tune the position of the arc-shaped groove 131 of the support shaft 13, the wire rope and the pressing column 14 are separated by applying an upward pulling force to the wire rope, and the support shaft 13 is in a movable and adjustable position again.

[0034] like Figure 6 and Figure 7 As shown, the sprinkler mechanism 2 is provided with multiple sprinklers, and the sprinkler mechanism 2 can move forward and backward along the steel wire ropes on both sides of the road. The sprinkler mechanism 2 includes a support beam 21, guide wheels 22 arranged at both ends of the support beam 21 and placed on the steel wire ropes on both sides of the road, a spray pipe 23 arranged on the support beam 21 and having multiple spray joints 231, a water supply tank 24, a water pump 25 connected to the water supply tank 24, a hose 26 connected between the water pump 25 and the sprinkler pipe 23, and a push-pull handle 27 arranged on the support beam 21; when the guide wheel 22 is placed on the steel wire rope and passes the position of the support shaft 13, the guide wheel 22 does not interfere with the support shaft 13. It also includes a reinforcement mechanism 3 for driving the pressing column 14 to maintain the state of protruding the arc groove 131 and reinforcing the steel chisel support mechanism 1 during the use of the sprinkler mechanism 2. The reinforcement mechanism 3 includes a base 31, a support rod 32 arranged on the base 31, and a threaded tube 33 threadedly connected to the support rod 32. The upper end of the threaded tube 33 is provided with an embedding hole 331 for the guide shaft 151 to be embedded.

[0035] In step (S6), the operating steps for installing the guide wheel 22 on the wire rope include the following: ① first rotate the anti-slip nut 153 of the first elastic component 15 of the steel drill support mechanism 1 downward, so that the pressing column 14 has an active stroke in the upward direction; ② then install the reinforcement mechanism 3 below the end of the support shaft 13 of the corresponding steel drill support mechanism 1, and rotate the threaded tube 33 upward so that the threaded tube 33 is connected to the lower end of the guide shaft 151, and then drive the guide shaft 151 to move upward, so that the pressing column 14 drives the wire rope upward; ③ place the guide wheels 22 at both ends of the support beam 21 on the two wire ropes on both sides of the road.

[0036] Implementation effect: When paving the mixed material, the paver controls the elevation of the road surface through the steel wire rope on the road side and the guide beam on the center line of the road. When the steel wire rope is laid out, it needs to be used in conjunction with a large number of steel chisel support mechanisms 1. During the use of the steel chisel support mechanism 1, it is necessary to adjust the height of the lifting adjustment sleeve 12 on the steel chisel 11 and the horizontal position of the support shaft 13 on the lifting adjustment sleeve 12, so that the arc groove 131 of the support shaft 13 is designed to be located at a position where the steel wire rope can be partially embedded. The steel wire rope needs to be kept in a taut state during the arrangement process, so that the steel wire rope has a downward force on the arc groove 131 in the support, so that the steel wire rope can be installed in the process. During the lifting and lowering process, the pressing column 14 can be moved downward, and the elastic force of the first elastic component 15 and the second elastic component 18 can be overcome by the linkage component 19 so that the fixed spike 161 of the support rod 16 can penetrate into the rubber pad 123 of the lifting and lowering adjustment sleeve 12 for fixation, thereby facilitating the adjustment and fixing of the horizontal position of the support shaft 13 on the lifting and lowering adjustment; at the same time, when the wire rope is removed, the support rod 16 moves downward under the resetting action of the second elastic component 18, so that the fixed spike 161 and the rubber pad 123 are separated, and the support shaft 13 can continue to be adjusted relative to the lifting and lowering adjustment sleeve 12; finally, it is convenient to arrange the wire rope.

[0037] When an external force is applied to the two metal springs 110 in a direction of approaching each other, the connection holes 1101 of the metal springs 110 are separated from the steel drill 11 so that the lifting and adjusting sleeve 12 moves up and down. When the two metal springs 110 are released, the inner side of the connection holes 1101 of the metal springs 110 is pressed against the peripheral side of the steel drill 11 for fixing, thereby facilitating the adjustment of the position of the lifting and adjusting sleeve 12 on the steel drill 11. During installation, the first compression spring 152 is first sleeved on the guide shaft 151, so that the lower end of the guide shaft 151 passes through the third through hole 135, and the anti-slip nut 153 is installed on the lower end of the guide shaft 151, so that the upper end of the pressing main body remains in the state of being located in the arc groove 131 in a natural state. At the same time, when the steel wire rope is arranged, it is placed on the arc groove 131, and the steel wire rope applies downward pressure to the pressing column 14, and after overcoming the elastic force of the first compression spring 152, the pressing column 14 moves downward. During installation, the second compression spring 182 is first installed on the guide sleeves 181 at both ends of the support rod 16, and then the support rod 16 is installed in the central square hole 132 of the support shaft 13, and then the anti-detachment bolt 183 is threadedly connected to the countersunk threaded hole 136, so that the lower end of the anti-detachment bolt 183 is embedded in the guide sleeve 181, thereby realizing the positioning and guiding of the lifting and lowering of the support rod 16, and preventing the second compression spring 182 from falling off; when the linkage component 19 drives the support rod 16 to move upward, the second compression spring 182 is compressed by force, and the fixed spike 161 on the support rod 16 penetrates into the rubber pad 123 for fixing; when the linkage component 19 cancels the action on the support rod 16, under the resetting action of the second compression spring 182, the support rod 16 moves downward and drives the fixed spike 161 to disengage from the rubber pad 123. When the pressing column 14 moves downward and drives the first linkage arm 193 to rotate downward, the second linkage arm 194 overcomes the action of the second elastic component 18 and drives the support rod 16 to move upward, thereby driving the fixed spike 161 to penetrate into the rubber pad 123. At the same time, when the pressing column 14 is reset, the support rod 16 and the linkage arm can be reset under the reset action of the second elastic component 18.

[0038] In conventional watering and curing, a watering truck is usually used for watering. However, the watering truck may locally pressurize the cement-stabilized gravel base, which may easily cause deformation of the cement-stabilized gravel base. At this time, the steel wire ropes on both sides of the road are used in conjunction with each other, so that the watering mechanism 2 can move forward and backward along the steel wire ropes on both sides, and cooperate with the multiple sprinkler heads on the sprinkler pipe 23 to evenly sprinkle water, thereby improving the effect of watering and curing. During the use of the watering mechanism 2, because the guide wheel 22 is supported on the steel wire rope at the end of the support shaft 13, the steel chisel support mechanism 1 is unstable at this time; by setting the reinforcement mechanism 3, the threaded tube 33 can be embedded in the lower end of the guide shaft 151 during the thread rotation process, so as to support the guide shaft 151, and cooperate with the anti-slip nut 153 to adjust downward. At this time, when the threaded tube 33 continues to rotate upward, the pressing column 14 can be driven to maintain the state of protruding the arc groove 131, thereby ensuring that the guide wheel 22 avoids interference with the support shaft 13 during the shaping process.

[0039] This specific embodiment is merely an explanation of the present invention and is not a limitation of the present invention. After reading this specification, those skilled in the art may make non-creative modifications to the present embodiment as needed. However, as long as they are within the scope of the claims of the present invention, they are protected by the patent law.

Claims

1. A reinforced cement-stabilized crushed stone base road construction process, characterized in that: The steps include: (S1) Construction preparation: driving steel drill support mechanisms (1) at intervals on both sides of the road, setting steel wire ropes between multiple steel drill support mechanisms (1) on the same side, setting guide beams on the center line of the road, and regularly sprinkling water on the ground to keep it moist; (S2) Mixing the mixture: adding cement and water in proportion to the mixed raw materials of sand and crushed stone prepared in proportion, and mixing them to obtain a mixture; (S3) Mixture transportation: The mixture is transported by dump truck and covered with tarpaulin during transportation; (S4) Mixture paving: The mixture is transported to two pavers of the same model. The two pavers are 5-10 meters apart when paving. The pavers control the road surface elevation through the steel wire ropes on the road side and the guide beams on the center line of the road. The two pavers overlap and pave 50-100 cm, and the center seam is trimmed manually. (S5) Mixture rolling: The cement-stabilized crushed stone base layer is compacted by a road roller; (S6) Watering and curing: After compaction, the geotextile is covered on the compacted cement-stabilized crushed stone base and watered and cured by the watering mechanism (2); The steel drill support mechanism (1) comprises a steel drill (11) for inserting into the ground, a lifting and adjusting sleeve (12) which is arranged to be lifted and lowered along the direction of the steel drill (11) and can be fixed at any position, and a support shaft (13) which is arranged to be telescopically disposed on the lifting and adjusting sleeve (12) along an extension direction perpendicular to the steel drill (11) and has an arc-shaped groove (131) at one end for partially embedding a steel wire rope downward; The lifting adjustment sleeve (12) is provided with a telescopic hole (121) for the support shaft (13) to be telescopically set, the top of the telescopic hole (121) is provided with a mounting groove (122) extending along the length direction thereof, a rubber pad strip (123) is provided in the mounting groove (122), a central square hole (132) is provided in the middle of the support shaft (13), a first through hole (133) arranged and distributed along the length direction thereof and communicating with the central square hole (132) is provided at the top of one end of the support shaft (13), and a second through hole (134) communicating with the central square hole (132) is provided at the bottom of the arc-shaped groove (131); A pressing column (14) is telescopically arranged at the second through hole (134) and is embedded in the central square hole (132). A first elastic component (15) is arranged between the lower end of the pressing column (14) and the support shaft (13) to drive the pressing column (14) to move upward. A support rod (16) is telescopically arranged in the central square hole (132). The support rod (16) is provided with a plurality of fixed spikes (161) that can pass through the first through hole (133) and then penetrate into the rubber pad (123) as the support rod (16) moves upward. (13) An anti-drop end cap (17) is provided at one end away from the arc-shaped groove (131), a second elastic component (18) is provided between the support rod (16) and the support shaft (13) to drive the support rod (16) to move downward so that the fixed spike (161) is located in the first through hole (133), and a linkage component (19) is provided between the support rod (16) and the pressing column (14) to overcome the elastic force of the first elastic component (15) and the second elastic component (18) during the downward pressing process of the pressing column (14) so ​​as to make the support rod (16) move upward.

2. The construction process of an enhanced cement-stabilized crushed stone base road according to claim 1, characterized in that: The upper and lower ends of the lifting and adjusting sleeve (12) are respectively provided with metal springs (110) having connection holes (1101) sleeved on the steel bar (11), and the two metal springs (110) extend in a direction away from the rear side of the support shaft (13). When an external force is applied to the two metal springs (110) in a direction toward each other, the connection holes (1101) of the metal springs (110) are separated from the steel bar (11) so that the lifting and adjusting sleeve (12) moves up and down. When the two metal springs (110) are released, the inner sides of the connection holes (1101) of the metal springs (110) are pressed against the peripheral side of the steel bar (11) to fix it.

3. The construction process of a reinforced cement-stabilized macadam base road according to claim 2 is characterized in that: The bottom of the support shaft (13) is provided with a third through hole (135) corresponding to the second through hole (134) and communicating with the central square hole (132); the first elastic component (15) comprises a guide shaft (151) arranged at the lower end of the pressing column (14) and passing through the third through hole (135); a first compression spring (152) sleeved on the guide shaft (151) and with both ends pressed against the lower surface of the pressing column (14) and the bottom of the central square hole (132); and an anti-slip nut (153) arranged at the lower end of the guide shaft (151) and pressed against the bottom of the support shaft (13); and the second through hole (134) is provided for the first compression spring (152) to be inserted.

4. The construction process of a reinforced cement-stabilized crushed stone base road according to claim 3 is characterized by: The upper end of the support shaft (13) is provided with two countersunk threaded holes (136) communicating with the central square hole (132); the second elastic component (18) comprises a guide sleeve (181) provided on the upper surface of both ends of the support rod (16), a second compression spring (182) sleeved on the threaded sleeve and pressed between the upper surface of the support rod (16) and the top of the central square hole (132), and an anti-dropping bolt (183) threadedly connected to the countersunk threaded hole (136) and with the lower end embedded in the guide sleeve (181).

5. The construction process of a reinforced cement-stabilized macadam base road according to claim 4 is characterized in that: A mounting hole (137) communicating with the central square hole (132) is provided below the support shaft (13); a connecting protrusion (138) is provided on the support shaft (13) below the mounting hole (137); the linkage assembly (19) comprises a connecting column (191), a hinge shaft (192) provided between the connecting protrusion (138) and the connecting column (191), a first linkage arm (193) provided at one end of the connecting column (191) and having a first waist-shaped hole (1931); and a second linkage arm (193) provided at the other end of the connecting column (191). 194); an annular groove (141) extending upward is arranged on the circumferential side of the lower end of the pressing column (14); the pressing column (14) passes through the first waist-shaped hole (1931) and causes the first linkage arm (193) to abut against the upper surface of the annular groove (141); the second linkage arm (194) is supported on the lower surface of the support rod (16); in the process of the pressing column (14) moving downward and driving the first linkage arm (193) to rotate downward, the second linkage arm (194) overcomes the action of the second elastic component (18) and drives the support rod (16) to move upward.

6. The construction process of a reinforced cement-stabilized crushed stone base road according to claim 1, characterized in that: In step (S1), the operation steps of driving the steel drill support mechanism (1) and arranging the steel wire rope are as follows: ① first, the steel drills (11) of the plurality of steel drill support mechanisms (1) are driven into the ground at a fixed point, and an external force is applied to the two metal spring plates (110) of the lifting and adjusting sleeve (12) in a direction of approaching each other, so that the connecting holes (1101) of the metal spring plates (110) are separated from the steel drill (11) to allow the lifting and adjusting sleeve (12) to move up and down, so that when the support shaft (13) is adjusted to a desired height, and then when the two metal spring plates (110) are released, the inner side of the connecting hole (1101) of the metal spring plate (110) is pressed against the peripheral side of the steel drill (11) to fix it; ② then, the support shaft (13) is extended and retracted so that the arc-shaped groove on the support shaft (13) (131) is in the position; ③ arranging the steel wire rope, during which the steel wire rope is placed in a taut state on the arc-shaped groove (131) in the support of the multiple steel drill support mechanisms (1), and during the installation of the steel wire rope, the pressing column (14) is driven to move downward, and the elastic force of the first elastic component (15) and the second elastic component (18) is overcome by the linkage component (19) so that the fixed spike (161) of the support rod (16) penetrates into the rubber pad (123) of the lifting adjustment sleeve (12) for fixing; ④ If it is necessary to fine-tune the position of the arc-shaped groove (131) of the support shaft (13), an upward pulling force is applied to the steel wire rope so that the steel wire rope and the pressing column (14) are separated, and the support shaft (13) is in a movable and adjustable position again.

7. The construction process of a reinforced cement-stabilized crushed stone base road according to claim 5, characterized in that: A plurality of the watering mechanisms (2) are provided, and the watering mechanisms (2) can move forward and backward along the steel wire ropes on both sides of the road.

8. The construction process of a reinforced cement-stabilized macadam base road according to claim 7 is characterized by: The watering mechanism (2) comprises a support beam (21), guide wheels (22) arranged at both ends of the support beam (21) and resting on steel wire ropes on both sides of the road, a spray pipe (23) arranged on the support beam (21) and having a plurality of spray joints (231), a water supply tank (24), a water pump (25) connected to the water supply tank (24), a hose (26) connected between the water pump (25) and the spray pipe (23), and a push-pull handle (27) arranged on the support beam (21); when the guide wheel (22) rests on the steel wire rope and passes the position of the support shaft (13), the guide wheel (22) does not interfere with the support shaft (13).

9. The construction process of a reinforced cement-stabilized crushed stone base road according to claim 8, characterized in that: The arc-shaped groove (131) is connected to a receiving groove (139) which communicates with the second through hole (134); the upper end of the pressing column (14) is provided with an arc-shaped portion (142) which protrudes from the arc-shaped groove (131) in an initial state and is located in the receiving groove (139) in a compressed state; and the reinforcing mechanism (3) is also included for driving the pressing column (14) to maintain a state of protruding from the arc-shaped groove (131) during use of the watering mechanism (2) and for reinforcing the steel bar supporting mechanism (1); the reinforcing mechanism (3) comprises a base (31), a supporting rod (32) arranged on the base (31), and a threaded tube (33) threadedly connected to the supporting rod (32); the upper end of the threaded tube (33) is provided with an embedding hole (331) for embedding the guide shaft (151).

10. The construction process of a reinforced cement-stabilized macadam base road according to claim 1, characterized in that: In step (S6), the operation steps of installing the guide wheel (22) on the wire rope include the following: ① firstly rotate the anti-drop nut (153) of the first elastic component (15) of the steel drill support mechanism (1) downward, so that the pressing column (14) has a movable stroke in the upward direction; ② then install the reinforcement mechanism (3) below the end of the support shaft (13) of the corresponding steel drill support mechanism (1), and rotate the threaded tube (33) upward so that the threaded tube (33) is connected to the lower end of the guide shaft (151), and then drive the guide shaft (151) to move upward, so that the pressing column (14) drives the wire rope upward; ③ place the guide wheels (22) at both ends of the support beam (21) on the two wire ropes on both sides of the road.

Citation Information

Patent Citations

  • Supporting frame applicable to poured floor

    CN106522582A

  • Assembled component supporting frame

    CN107558754A

  • Building external wall scaffold connecting structure and installation method

    CN108442681A

  • Clamp connector for assembly of prefabricated shaped-section bars to form scaffolding

    CN1150465A

  • Mortise and tenon joint with pin

    FR2941022A1