Radiation well and tube well same-well combined structure and pumping and filling method

By setting up water inlet pipe wells in the reflux well and using high-pressure backflushing and dredging device, the synchronous pumping and refluxing of groundwater is achieved, which solves the problem of large-scale land and environmental impact in traditional technology, and improves the pumping efficiency and refluxing System stability.

CN119021311APending Publication Date: 2024-11-26CHONGQING HONGYUAN INFILTRATION WATER TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411283831.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-13
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The separate installation of traditional groundwater recharge wells and water intake wells results in a large area, which is suitable for places with tight land use inconvenience, and multi-point excavation has an impact on the environment, making it difficult to achieve synchronous and stable large-scale water pumping and recharge.

Method used

The combined structure of the radiation well and the pipe well is adopted. By setting up water inlet pipe wells in the reinjection radiation wells, the pumping and irrigation integration is achieved, the pipeline layout and drilling number is reduced, and the hot and cold load exchange is used for reinjection pipes and water inlet radiation pipes, combined with high-pressure reverse Flush and silt and replace devices to restore the permeability of the aquifer.

Benefits of technology

It realizes synchronous, continuous and stable large-scale water pumping and re-injection, saves land area, reduces environmental impact, improves the pumping and irrigation effect, and extends the service life of the re-injection system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021311A_ABST
    Figure CN119021311A_ABST
Patent Text Reader

Abstract

The invention provides a radiation well and tube well same-well combined structure and a pumping and recharging method. The radiation well and tube well same-well combined structure comprises a recharging radiation well, a desilting and backflushing replacement structure and a water taking tube well which is located in the recharging radiation well and is not directly communicated with the recharging radiation well. The recharge structure and the desilting and backflushing replacement structure are all or partially located near the aeration zone and the upper aquifer; the water taking pipe well (group) is located at the deep part of the aquifer, and the distance between the water taking pipe well (group) and the recharge structure meets the exchange requirement of cooling and heating loads. The water taking pipe well is arranged in the recharge radiation well, the three systems of the recharge radiation well, the backflushing desilting replacement and the water taking pipe well are organically combined together, a circulation system of pumping and recharge, desilting replacement and heat exchange is formed, investment and occupied area are saved, and operation management is centralized and simple.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of groundwater recharging and pumping, and in particular relates to a combined structure of a radiation well and a tube well and a pumping method. Background Art

[0002] As we all know, groundwater plays an important role in resource, geological and ecological functions, and over-exploitation of groundwater will lead to ecological and geological problems such as ground subsidence, ground fissures, seawater intrusion and wetland degradation. Therefore, groundwater recharge is needed to increase groundwater resources, control and increase groundwater levels, and prevent adverse consequences such as water quality deterioration, ground subsidence or seawater intrusion caused by a sharp drop in groundwater levels.

[0003] The traditional way is to set up a recharge well for recharging water into the ground separately from a water intake well for taking groundwater, such as the recharge well structure disclosed in CN201420872598.9, the groundwater recharge radiation well disclosed in CN202210216168.0, the foundation pit recharge well disclosed in CN202221766391.4, and the surface water intake well disclosed in CN201910446192.1, the radiation intake well disclosed in CN201320194278.8, and the radiation intake well structure disclosed in CN201621161467.5. The way of setting up the recharge well and the water intake well separately occupies a larger area overall and is not suitable for places with tight land use. Summary of the invention

[0004] The present invention aims to solve the technical problems existing in the prior art. The first purpose of the present invention is to provide a combined structure of a radial well and a tube well. The second purpose of the present invention is to provide a pumping method based on the combined structure of the radial well and the tube well.

[0005] To achieve the above-mentioned first purpose, the present invention adopts the following technical scheme: a combined structure of a radiation well and a pipe well, comprising a reinjection radiation well and a water intake pipe well located in the reinjection radiation well and not directly connected to the water in the reinjection radiation well, the water intake pipe well extending into the aquifer; the reinjection radiation well has a reinjection structure located in the shallow layer for reinjecting the water therein into the aquifer, the reinjection structure being wholly or partially located above the groundwater level of the aquifer; the side wall of the water intake pipe well is connected to a plurality of water intake radiation pipes radiating around it and inserted into the deep aquifer, the water intake radiation pipes being located below the reinjection structure and the distance between the two meeting the exchange requirements of cold and heat loads.

[0006] The above technical solution sets a water intake pipe well in the reinjection radiation well, organically combines reinjection and pumping, realizes the integration of pumping and injection, reduces pipeline layout, saves floor space, and makes operation and management centralized and simple. It also reduces the number of drilling wells and the impact of multiple excavations on the environment, making it more environmentally friendly. The present invention can realize synchronous, continuous and stable large-volume water pumping and large-volume water reinjection, greatly improving the efficiency of pumping and injection.

[0007] In a preferred embodiment of the present invention, the recharge structure includes a multi-layer recharge pipe group arranged crosswise in a vertical direction and connected to the interior of the recharge radiation well, all or part of the recharge pipe group is located above the groundwater level of the aquifer, and each layer of the recharge pipe group includes a plurality of recharge pipes arranged circumferentially at intervals.

[0008] The above technical solution connects a reinjection pipe inserted into the aquifer to the reinjection radiation well, so that water can be reinjected into the ground by pressure-free infiltration through the reinjection pipe without pressurization for vertical downward infiltration.

[0009] In a preferred embodiment of the present invention, a dredging device for backwashing and dredging connected to the recharging pipe is also included, and the dredging device uses high-pressure fluid to backwash the blocked zone around the recharging pipe.

[0010] The above technical solution backwashes the blocked zone around the reinjection pipe through high-pressure backwashing to restore the permeability of the aquifer.

[0011] In a preferred embodiment of the present invention, the re-injection radiation well is also connected to a multi-layer silt drainage pipe group corresponding to the multi-layer re-injection pipe group. The position of the silt drainage pipe group is lower than the re-injection pipe group. Each layer of the silt drainage pipe group includes a plurality of silt drainage pipes arranged at circumferential intervals, and the outlets of the silt drainage pipes are connected to the re-injection radiation well.

[0012] The above technical solution, by setting up a silt discharge pipe to discharge the backwashed blockage, reduces the amount of silt seepage, and is conducive to restoring the permeability of the aquifer.

[0013] In a preferred embodiment of the present invention, a plurality of silt removal pipes are arranged below the recharge pipe; and / or the silt removal pipes have a silt removal slope inclined toward one side of the recharge radiation well; and / or the recharge pipes are also connected to a displacement device, which injects clean gravel into the periphery of the recharge pipe by means of high pressure, and the silt removal pipes discharge the silt around the wall of the recharge pipe.

[0014] In the above technical scheme, high-pressure fluid is used to flush the blocked zone around the recharge pipe. The flushing water scatters and seeps downward, which is conducive to the flushed silt entering the silt discharge pipe; the recharge pipe is used to inject pure gravel with good permeability into the periphery of the recharge pipe wall, and the silt around the recharge pipe wall is discharged through the silt discharge pipe. A replacement circulation system is formed by injection and discharge, so as to displace the silt around the recharge pipe wall, increase the permeability of the aquifer, and ensure continuous and stable recharge.

[0015] In another preferred embodiment of the present invention, a control conversion device located in the reinjection radiation well is connected to the reinjection pipe, and the dredging device and the replacement device are both connected to the control conversion device and switched through the control conversion device.

[0016] In the above technical solution, the silting device and the replacement device are switched by controlling the conversion device, and the operation is simple.

[0017] In another preferred embodiment of the present invention, an exhaust pipe is inserted into the reinjection radiation well; and / or a plurality of exhaust pipes arranged outside the reinjection radiation well are inserted from the ground into the aquifer.

[0018] The above technical solution discharges the gas in the reinjection water of the reinjection radiation well through the exhaust pipe, reduces the gas in the reinjection water reinjected into the aquifer through the reinjection pipe, and reduces the occurrence of gas blockage; discharges the gas that forms blockage in the aquifer through the exhaust pipe, thereby improving the permeability of the aquifer.

[0019] In another preferred embodiment of the present invention, a silt removal device for extracting dirt from the bottom of the re-injection radiation well is installed in the re-injection radiation well; and / or a silt removal device for adding coagulant precipitant thereto is installed in the re-injection radiation well, and a turbidity meter for detecting the turbidity of the water therein is also installed in the re-injection radiation well, the signal output end of the turbidity meter is connected to the turbidity input end of the controller, and the delivery output control end of the controller is connected to the enable end of the silt removal device.

[0020] The above technical scheme can effectively reduce the mud and sand content in the reinjection water, reduce the siltation of the aquifer, ensure the stability of the reinjection water volume and extend the maintenance cycle by setting up silt removal equipment; the turbidity meter monitors the turbidity of the reinjection water in real time, and according to the turbidity of the reinjection water, the silt removal device is operated to automatically add a certain amount of coagulant precipitant to remove turbidity and sedimentation of flocculants in the reinjection radiation well water, so as to avoid clogging of the aquifer by flocculants and stabilize the reinjection water volume.

[0021] In another preferred embodiment of the present invention, the water intake radiation pipe passes through the side wall of the re-injection radiation well and is inserted into the aquifer at an angle downward; and / or the water intake pipe well passes through the bottom of the re-injection radiation well and extends downward to the outside of the re-injection radiation well, and a water intake filter is provided on the side wall of the water intake pipe well outside the re-injection radiation well.

[0022] In the above technical solution, the inclined water-intake radiation pipe is inserted deeper, which is beneficial to heat and cold exchange; the water-intake filter is arranged to further increase the water-intake area and improve the water production of the water-intake pipe well.

[0023] To achieve the second object, the present invention adopts the following technical solution: a pumping and irrigation method of a combined structure of a radial well and a tube well, comprising the following steps:

[0024] Constructing a combined structure of the radiation well and the tube well;

[0025] By controlling the opening and closing of the recharging pipe and the water intake radiation pipe, it is possible to achieve water filling only, water intake only, or water intake and water filling at the same time;

[0026] When water is injected, the reinjected water enters the reinjection radiation well and is reinjected into the shallow layer of the formation through the reinjection structure. The reinjected water infiltrates into the formation and exchanges heat with the formation. The reinjected water infiltrates into the deep part of the aquifer. The silt removal device is started regularly or manually or automatically according to the water level data of the reinjection radiation well. The high-pressure fluid is transported to the surrounding blockage zone through the reinjection pipe for backwashing. The silt removal pipe discharges the backwashed silt to the reinjection radiation well; the replacement device is started regularly or manually, and clean gravel is injected into its periphery through the reinjection pipe. The silt removal pipe discharges the silt around the reinjection pipe to the reinjection radiation well; the replacement device works at the same time as the silt removal device, or the two work in different periods;

[0027] When taking water, the water intake radial pipe seeps water from deep in the aquifer and collects it in the water intake well.

[0028] Compared with the prior art, the preferred technical solution of the present invention has the following beneficial effects:

[0029] 1) The present invention integrates pumping and injection in the same well, can pump and inject synchronously, has independent deep pumping system and shallow reinjection system, can reinject and pump water at the same time, and is a circulation system for reinjection of shallow aeration zone in reinjection radiation well, formation heat exchange, and pumping of deep aquifer in water intake pipe well.

[0030] 2) Stable and sustainable shallow geothermal heat exchange can be achieved through shallow vertical reinjection of reinjection radiation wells, long-distance heat and cold load exchange of formations, and deep water extraction from water intake pipe wells.

[0031] 3) The water intake pipe well and water intake radiation pipe form a water intake pipe group, which increases the water intake area, absorbs groundwater at a large flow rate, greatly increases the water intake, and has a large daily water production.

[0032] 4) The reinjection pipe has the functions of reinjection, backwashing, desilting and replacement. The blocked zone around the reinjection pipe wall is backwashed through high-pressure backwashing, the silt is discharged through the sludge removal pipe, and the gas that forms the blockage in the aquifer is discharged through the exhaust pipe, so as to restore the permeability of the aquifer and stabilize the reinjection water volume. In addition, the reinjection pipe can be used to inject pure gravel with good permeability into the periphery of the reinjection pipe wall, and the silt is replaced through the sludge removal pipe. A replacement circulation system is formed with one injection and one discharge to ensure long-term and stable reinjection.

[0033] 5) The reinjection system (including reinjection radiation well and reinjection pipe), water intake system (including water intake pipe well and water intake radiation pipe) and dredging and replacement system (including dredging device, replacement device, sludge removal pipe and exhaust pipe) of the present invention can operate independently and cross-operate, and can realize pumping and injection in different time periods or simultaneously.

[0034] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:

[0036] Figure 1 It is a front structural schematic diagram of the combined structure of the radiation well and the tube well in the embodiment.

[0037] Figure 2 It is a top view schematic diagram of the combined structure of the radiation well and the tube well in the embodiment.

[0038] The figure marks in the drawings of the specification include: reinjection radiation well 1, reinjection pipe 2, silt discharge pipe 3, control conversion device 4, exhaust pipe 5, silt removal device 6, turbidity meter 7, silt discharge equipment 8, silt discharge pipe 9, water intake pipe well 10, water intake filter 11, water intake radiation pipe 12, water intake backwash device 13, reinjection range A. DETAILED DESCRIPTION

[0039] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.

[0040] In the description of the present invention, it is to be understood that the terms “longitudinal”, “lateral”, “vertical”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside” and “outside” etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0041] In the description of the present invention, unless otherwise specified and limited, it should be noted that the terms "installed", "connected" and "connected" should be understood in a broad sense. For example, it can be a mechanical connection or an electrical connection, or it can be the internal connection between two components. It can be a direct connection or an indirect connection through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to the specific circumstances.

[0042] Embodiment 1

[0043] This embodiment provides a combined structure of a radial well and a tube well, such as Figure 1 and Figure 2 As shown, in a preferred embodiment, the combined structure includes a reinjection radiation well 1, and a water intake pipe well 10 located in the reinjection radiation well 1 and not directly connected to the water in the reinjection radiation well 1, the water intake pipe well 10 extends into the aquifer, preferably, the water intake pipe well 10 is arranged at the center of the reinjection radiation well 1. The reinjection radiation well 1 is a large well, and its diameter is preferably 8-10m, and the diameter of the water intake pipe well 10 is preferably 0.5-0.8m. The bottoms of the reinjection radiation well 1 and the water intake pipe well 10 are located at a certain depth below the groundwater level, and the depth of the water intake pipe well 10 is preferably 80-100 meters.

[0044] Among them, the recharge radiation well 1 has a recharge structure located in a shallow layer for recharging the water therein into the aquifer, for example, it is located 10-20 meters underground, and the recharge structure is completely or partially located above the groundwater level of the aquifer. In one embodiment, the recharge structure can adopt existing technology, such as setting a recharge filter structure on the well wall of the recharge radiation well 1, and the recharge filter structure is a reverse wedge-shaped filter structure made of concrete, stainless steel or fiberglass, which is a lateral recharge.

[0045] The side wall of the water intake pipe well 10 is connected with a number of water intake radiation pipes 12 that diverge around it and are inserted into the deep aquifer. Preferably, the water intake radiation pipes 12 are inserted obliquely downward into the aquifer; the water intake radiation pipes 12 are located below the recharging structure, and the water intake radiation pipes 12 can be inserted to a depth of 80-100 meters, so that the vertical distance between the recharging part of the recharging radiation well 1 and the water intake part of the water intake pipe well 10 differs by more than 50 meters, and the distance between the recharging part of the recharging radiation well 1 and the water intake part of the water intake pipe well 10 meets the exchange requirements of cold and hot loads. According to the amount of water intake, multiple oblique water intake radiation pipes 12 can be set at the bottom and sealed and connected to the water intake pipe well 10 to form a water intake pipe group, with a large amount of water intake.

[0046] The present invention organically combines the recharge of the recharge radiation well 1 and the water extraction of the water intake pipe well 10, realizing the integration of pumping and injection, and can simultaneously carry out shallow recharge and deep water extraction, synchronous pumping and injection, and the vertical distance between the recharge water and the water extraction reaches 50-80 meters, that is, the cold and heat exchange distance reaches 50-80 meters, which meets the conditions of cold and heat exchange, so that the recharge water can fully absorb geothermal energy and then extract water from the water intake pipe well 10. It is known that the cold and heat exchange distance of 5-8 meters can reach a temperature difference of about 3°, and the cold and heat exchange distance of 50-80 meters of the present invention can reach a temperature difference of 5-8°, with a good heat exchange effect, which can better meet the temperature difference requirements of the water source heat pump.

[0047] In the present invention, the water intake radiation pipe 12 is installed in the aquifer by synchronous pipe drilling technology, and the maximum drilling distance can reach 60-80m, which effectively improves the water intake radiation range; the water intake radiation pipe 12 adopts a new filter produced by foreign advanced technology, which has a large porosity (effective porosity is 40%-50%), improved rust-proof material, good hydraulic conditions, and is not prone to recharge blockage. Preferably, the water intake pipe well 10 passes through the bottom of the recharge radiation well 1 and extends downward to the outside of the recharge radiation well 1. The water intake filter 11 is provided on the side wall of the water intake pipe well 10 located outside the recharge radiation well 1 to increase the water intake.

[0048] In another preferred embodiment, the reinjection structure includes a multi-layer reinjection pipe group connected to the inside of the reinjection radiation well 1 and arranged crosswise in the vertical direction. All or part of the reinjection pipe group is located above the groundwater level of the aquifer. Each layer of the reinjection pipe group includes a plurality of reinjection pipes 2 arranged at intervals in the circumference. Preferably, the reinjection pipe 2 is arranged in the aquifer with good permeability between the aeration zone and the groundwater level. The reinjection pipe 2 is inserted horizontally into the aquifer to realize the vertical infiltration reinjection of groundwater. Among them, the reinjection pipe 2 is constructed by synchronous follow-up pipe drilling, and the radial length can reach 30 to 50 meters, forming a nearly 3000 to 8000m 2 The recharge area greatly increases the recharge range A of the recharge radiation well 1; the effective porosity of the filtering structure adopted by the recharge pipe 2 is increased by more than 80%, and it is not easy to be blocked, ensuring stable recharge.

[0049] Further preferably, the combined structure also includes a dredging device (not shown in the figure) connected to the recharge pipe 2 for backwashing and dredging. The dredging device uses high-pressure fluid (high-pressure water or high-pressure air) to backwash the blocked zone around the recharge pipe 2 (this is the prior art and will not be described in detail here), thereby restoring the permeability of the aquifer around the recharge pipe 2 and extending its service life.

[0050] In another preferred embodiment, the reinjection radiation well 1 is also connected to a multi-layer desilting pipe group corresponding to the multi-layer reinjection pipe group, one layer of the reinjection pipe group corresponds to a layer of the desilting pipe group, the position of the desilting pipe group is lower than the reinjection pipe group, each layer of the desilting pipe group includes a plurality of desilting pipes 3 arranged at intervals in the circumferential direction, and the outlet of the desilting pipe 3 is connected to the reinjection radiation well 1. Preferably, the end of the desilting pipe 3 is located inside the end of the reinjection pipe 2; a desilting pipe 3 is arranged on both sides below the reinjection pipe 2; the desilting pipe 3 has a desilting slope inclined toward one side of the reinjection radiation well 1, that is, the end of the desilting pipe 3 close to the reinjection radiation well 1 is inclined upward and downward.

[0051] Specifically, the dredging device can be started periodically or manually. During dredging, the high-pressure water provided by the dredging device enters the reinjection pipe 2, and the surrounding blockage zone is backwashed with high pressure through the reinjection pipe 2. The flushed silt (including blockages such as fine particles and scaling) is transported to the reinjection radiation well 1 through the silt discharge pipe 3, and the silt is finally settled to the bottom of the reinjection radiation well 1.

[0052] In another preferred embodiment, the recharging pipe 2 is also connected to a replacement device (not shown in the figure), which injects pure gravel with good permeability into the periphery of the wall of the recharging pipe 2 by high pressure, and at the same time, the sludge removal pipe 3 discharges the sludge formed by sludge, one injection and one discharge, so as to replace the sludge around the recharging pipe 2, increase the permeability of the aquifer, and ensure continuous and stable recharging. Among them, the recharging pipe 2 is connected to a control conversion device 4 located in the recharging radiation well 1, and the dredging device and the replacement device are both connected to the control conversion device 4, and the switching operation is controlled by the control conversion device 4.

[0053] The blockage problem in the process of groundwater pumping is mainly due to the changes in groundwater flow state, oxygen content and water quality, which will produce a series of physical, chemical and biological effects such as gas blockage, compaction, oxidation and scaling, forming blockage within a certain range around the filtration structure. Therefore, it is necessary to discharge the gas that causes blockage in the aquifer.

[0054] Specifically, an exhaust pipe 5 can be inserted into the reinjection radiation well 1 to discharge the gas in the reinjection water of the reinjection radiation well 1, reduce the gas in the reinjection water reinjected into the aquifer through the reinjection pipe 2, and reduce the occurrence of gas blockage in the aquifer; and / or a plurality of exhaust pipes 5 arranged outside the reinjection radiation well 1 can be inserted from the ground into the aquifer to discharge the gas that forms a blockage in the aquifer, restore the permeability of the aquifer, and stabilize the amount of reinjection water.

[0055] In this embodiment, the outlet of the sludge discharge pipe 3 is connected or disconnected with the exhaust pipe 5. When the outlet of the sludge discharge pipe 3 is not connected with the exhaust pipe 5, the sludge in the aquifer discharged by the sludge discharge pipe 3 directly enters the reinjection radiation well 1, and finally sinks to the bottom of the reinjection radiation well 1, and the gas sludge in the aquifer discharged by the sludge discharge pipe 3 also enters the reinjection radiation well 1 and is discharged by the exhaust pipe 5 inserted into the reinjection radiation well 1; when the outlet of the sludge discharge pipe 3 is connected with the exhaust pipe 5, the sludge in the aquifer discharged by the sludge discharge pipe 3 falls to the bottom of the reinjection radiation well 1 through the exhaust pipe 5, and the gas sludge in the aquifer discharged by the sludge discharge pipe 3 directly enters the exhaust pipe 5 and is discharged by the exhaust pipe 5.

[0056] The recharging pipe 2 of the present invention has the functions of recharging, backwashing, desilting and replacement. Specifically, the blocked zone around the wall of the recharging pipe 2 is backwashed by high-pressure backwashing, the sludge is discharged by the sludge discharge pipe 3, and the gas that forms the blockage in the aquifer is discharged through the exhaust pipe 5, so as to restore the permeability of the aquifer and stabilize the amount of recharging water; and the recharging pipe 2 can also be used to inject pure gravel with good permeability into the wall of the recharging pipe 2, and the sludge is replaced by the sludge discharge pipe 3, so as to increase the permeability of the aquifer.

[0057] In another preferred embodiment, a desilting device 8 for extracting dirt from the bottom of the recharge radiation well 1 is installed in the recharge radiation well 1. The desilting device 8 is a desilting pump installed at the bottom of the recharge radiation well 1. The outlet of the desilting device 8 is connected to a desilting pipe 9, and the outlet of the desilting pipe 9 extends to the ground. The muddy material and flocculants in the recharge radiation well 1 are precipitated to the bottom of the recharge radiation well 1 and discharged through the desilting device 8, which can effectively reduce the mud and flocculant content in the water in the recharge radiation well 1. Specifically, the desilting device 8 can be started regularly or manually to discharge the silt (including muddy material and flocculants) at the bottom of the recharge radiation well 1.

[0058] In another preferred embodiment, a silt removal device 6 for delivering coagulant precipitant into the re-injection radiation well 1 is installed. Specifically, the silt removal device 6 can be started periodically or manually. The silt removal device 6 delivers the coagulant precipitant into the re-injection radiation well 1 to remove turbidity and sedimentation from the water in the re-injection radiation well 1. The precipitated mud and sand are located at the bottom of the re-injection radiation well 1 and are then discharged by the silt removal equipment 8, thereby effectively reducing the flocculant content in the water of the re-injection radiation well 1 and reducing the siltation during the re-injection process of the re-injection radiation well 1, thereby ensuring the stability of the water quality and water volume of the re-injection radiation well 1 and extending the maintenance cycle.

[0059] Further preferably, a turbidity meter 7 for detecting the turbidity of the water therein is also installed in the reinjection radiation well 1, and the signal output end of the turbidity meter 7 is connected to the turbidity input end of the controller, and the delivery output control end of the controller is connected to the enabling end of the desilting delivery device 6. The turbidity meter 7 monitors the turbidity of the water in the reinjection radiation well 1 in real time, and the controller controls the desilting delivery device 6 to work according to the turbidity of the water in the reinjection radiation well 1, so as to automatically add a quantitative coagulant precipitant.

[0060] In another preferred embodiment, control valves for controlling the channels of the re-injection pipe 2 and the water intake radiation pipe 12 are provided at their roots. By controlling the opening and closing of the re-injection pipe 2 and the water intake radiation pipe 12, only filling, only water intake, or both water intake and filling can be achieved to meet the different needs of users.

[0061] According to engineering practice, the amount of recharge water in traditional recharge wells decreases by about 5% each year and is generally scrapped in 3-5 years. The present invention reduces the amount of recharge water to 1-2% each year through backwashing, dredging, replacement and exhaust resistance, and the service life can reach more than 15 years, which is 4-5 times longer.

[0062] According to the on-site monitoring data of many large wells that have been constructed (in Sichuan, Hunan, Jiangxi, Guangxi and other places in the south, and Liaoning, Heilongjiang and other places in the north), the single hole water output of the water intake hole is 2000-3000m 3 / d. In aquifers with good permeability, the water production of a single well can reach 25,000-30,000 m 3 / d, the recharge volume is about 60%-70% of the water production (15,000-20,000 m 3 / d). In addition, according to the relevant data of the constructed water intake wells, in the aquifer with good permeability, the water production of the water intake pipe group can reach 5,000-6,000 m 3 / d.

[0063] Embodiment 2

[0064] This embodiment provides a pumping and irrigation method based on the combined structure of the radial well and the tube well in the first embodiment, and the pumping and irrigation method includes the following steps:

[0065] Constructing the combined structure of the radiation well and the tube well of the first embodiment;

[0066] By controlling the opening and closing of the recharging pipe 2 and the opening and closing of the water taking radiation pipe 12, it is possible to achieve only filling, or only taking, or taking and filling at the same time;

[0067] When water is injected, the reinjected water enters the reinjection radiation well 1 and is reinjected to the shallow layer of the formation through the reinjection pipe 2. The reinjected water infiltrates the formation and exchanges heat with the formation. The reinjected water infiltrates to the deep part of the aquifer. The silt removal device is started regularly or manually or automatically according to the water level data of the reinjection radiation well. The high-pressure fluid is transported to the surrounding blockage zone through the reinjection pipe 2 for backwashing. The silt removal pipe 3 discharges the backwashed silt to the reinjection radiation well 1; the replacement device is started regularly or manually, and clean gravel is injected into the surrounding area through the reinjection pipe 2. The silt removal pipe 3 discharges the silt around the reinjection pipe 2 to the reinjection radiation well 1. One injection and one discharge form a replacement circulation system; the replacement device works at the same time as the silt removal device, or the two work in different periods;

[0068] When water is drawn, the water-drawing radiation pipe 12 infiltrates water from the deep part of the aquifer and collects the water into the water-drawing pipe well 10 .

[0069] The present invention can be widely used in municipal administration, ecological restoration and water source heat pump projects, mainly including: 1. original groundwater pumping and recharging in urban construction, including water source heat pump system and circulating water; 2. groundwater recharging in urban sewage recycling; 3. centralized recharging of riverside surface water; 4. recharging to prevent seawater intrusion; 5. restorative recharging of ecological environment.

[0070] In the description of this specification, the description with reference to the terms "preferred embodiment", "one embodiment", "some embodiments", "example", "specific example" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.

[0071] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the claims and their equivalents.

Claims

1. A combined structure of a radial well and a tube well, characterized in that: It includes a reinjection radiation well and a water intake pipe well located in the reinjection radiation well and not directly connected to the water in the reinjection radiation well, wherein the water intake pipe well extends into the aquifer; The reinjection radiation well has a reinjection structure located in a shallow layer for reinjecting water therein into the aquifer, and the reinjection structure is entirely or partially located above the groundwater level of the aquifer; The side wall of the water intake pipe well is connected with a plurality of water intake radiation pipes which are divergent around it and inserted into the deep aquifer. The water intake radiation pipes are located below the recharging structure and the distance between the two meets the exchange requirements of cold and hot loads.

2. The combined structure of radial well and tube well according to claim 1 is characterized in that: The reinjection structure includes a multi-layer reinjection pipe group arranged crosswise in a vertical direction and connected to the inside of the reinjection radiation well. All or part of the reinjection pipe group is located above the groundwater level of the aquifer, and each layer of the reinjection pipe group includes a plurality of reinjection pipes arranged at circumferential intervals.

3. The combined structure of radial well and tube well according to claim 2 is characterized in that: It also includes a dredging device connected to the recharging pipe for backwashing and dredging, and the dredging device uses high-pressure fluid to backwash the blocked zone around the recharging pipe.

4. The combined structure of radial well and tube well according to claim 3 is characterized in that: The reinjection radiation well is also connected to a multi-layer silt discharge pipe group corresponding to the multi-layer reinjection pipe group. The position of the silt discharge pipe group is lower than the reinjection pipe group. Each layer of the silt discharge pipe group includes a plurality of silt discharge pipes arranged at circumferential intervals. The outlets of the silt discharge pipes are connected to the reinjection radiation well.

5. The combined structure of radial well and tube well according to claim 4 is characterized in that: A plurality of silt discharge pipes are arranged below the recharging pipe; And / or the desilting pipe has a desilting slope inclined toward one side of the reinjection radiation well; And / or the recharging pipe is also connected to a replacement device, which injects clean gravel into the periphery of the recharging pipe by means of high pressure, and the silt removal pipe discharges the silt around the wall of the recharging pipe.

6. The combined structure of radial well and tube well according to claim 5 is characterized in that: The reinjection pipe is connected to a control conversion device located in the reinjection radiation well. The dredging device and the replacement device are both connected to the control conversion device and are switched through the control conversion device.

7. The combined structure of a radial well and a tube well according to any one of claims 1 to 6, characterized in that: An exhaust pipe is inserted into the reinjection radiation well; And / or a plurality of exhaust pipes arranged outside the reinjection radiation well are inserted from the ground into the aquifer.

8. The combined structure of a radial well and a tube well according to any one of claims 1 to 6, characterized in that: The reinjection radiation well is equipped with a desilting device for extracting dirt from the bottom of the reinjection radiation well; And / or the reinjection radiation well is equipped with a desilting device for injecting coagulant precipitant therein, and the reinjection radiation well is also equipped with a turbidity meter for detecting the turbidity of the water quality therein, the signal output end of the turbidity meter is connected to the turbidity input end of the controller, and the injection output control end of the controller is connected to the enable end of the desilting device.

9. The combined structure of a radial well and a tube well according to any one of claims 1 to 6, characterized in that: The water intake radiation pipe passes through the side wall of the reinjection radiation well and is inserted into the aquifer in a downwardly inclined manner; And / or the water intake pipe well passes through the bottom of the reinjection radiation well and extends downward to the outside of the reinjection radiation well, and a water intake filter is provided on the side wall of the water intake pipe well located outside the reinjection radiation well.

10. A pumping and irrigation method based on the combined structure of radial well and tube well according to claim 8, characterized in that: The steps include: Constructing a combined structure of the radiation well and the tube well; By controlling the opening and closing of the recharging pipe and the water intake radiation pipe, it is possible to realize only pumping, or only taking water, or taking water and filling water at the same time; When water is injected, the reinjection water enters the reinjection radiation well and is reinjected into the shallow layer of the formation through the reinjection structure. The reinjection water infiltrates into the formation and exchanges heat with the formation. The reinjection water infiltrates into the deep part of the aquifer. The silt removal device is started regularly or manually or automatically according to the water level data of the reinjection radiation well. The high-pressure fluid is transported to the surrounding blockage zone through the reinjection pipe for backwashing. The silt removal pipe discharges the backwashed silt to the reinjection radiation well; the replacement device is started regularly or manually, and clean gravel is injected into the surrounding area through the reinjection pipe. The silt removal pipe discharges the silt around the reinjection pipe to the reinjection radiation well; the replacement device works at the same time as the silt removal device, or the two work in different periods; When taking water, the water intake radial pipe seeps water from deep in the aquifer and collects it in the water intake well.