Remote test method and system for 110kv spare power automatic throw-in device transmission
The automated transmission of the 110kV automatic transfer switch was tested remotely, which solved the problems of low efficiency and poor safety in the existing technology and achieved efficient and reliable transmission testing.
Patent Information
- Application Number
- CN202411265788.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-10
- Publication Date
- 2025-11-11
- Estimated Expiration
- 2044-09-10
AI Technical Summary
The existing verification methods for 110kV automatic transfer switch transmission are inefficient, have poor safety, and are complex to operate, which increases the workload of on-site operators and affects the system's operating efficiency and safety.
The remote testing method is adopted. The transmission operation ticket is generated through the power grid dispatching platform. The primary equipment of the target load station and the standby load station is remotely controlled by the main station of the power grid to simulate the busbar undervoltage environment and realize the automated transmission test of the 110kV standby automatic transfer device.
The automatic switching transmission test has been automated, which has improved test efficiency, reduced operational errors, enhanced the reliability of test results, and avoided the complexity and time-consuming nature of manual operation.
Smart Images

Figure CN119087093B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of automatic transfer switch (ATS) technology, and more specifically, to a remote testing method and system for the transmission of a 110kV ATS device. Background Technology
[0002] In multi-stage series-supply 110kV power systems, to improve power supply reliability, remote automatic transfer switch (ATS) systems are widely used to automatically connect a backup power source at the system open-loop point in the event of a 110kV busbar failure at a substation, quickly restoring power supply to the busbar of the substation that has lost voltage. The working principle of the ATS system is as follows: when a main power supply failure is detected and a series of logical conditions are met, the system will automatically trip the switch of the under-voltage line and close the backup switch at the open-loop point within a predetermined time, completing the automatic power switching and promptly restoring power supply to the busbar of the substation that has lost voltage.
[0003] Verifying the effectiveness of the 110kV automatic transfer switch (ATS) and ensuring its accurate operation in actual operation is a necessary step before the ATS is put into operation in a power system. In related technologies, the transmission verification of the 110kV ATS involves conducting a full-scale transmission test at the substation. This process includes adjusting the system to a specific operating state, putting the ATS in a charging state, and then manually disconnecting the main power supply line switch to simulate a busbar undervoltage scenario. Under this condition, the ATS should trigger an action, tripping the relevant switch and closing the open-loop backup switch after a delay to restore power supply. However, this traditional method has significant limitations, especially in terms of efficiency and operation time: First, the entire process requires manual operation, including adjusting the primary equipment to the required test state and disconnecting and closing switches, which is not only time-consuming but also prone to errors; second, the frequent and complex operations increase the workload of on-site operators, and the long test cycle affects the overall system operating efficiency; third, manual operation poses safety risks in high-voltage environments, especially when operators need to frequently access high-voltage equipment.
[0004] Therefore, the 110kV automatic transfer switching test method in related technologies has significant shortcomings in terms of efficiency, safety, and ease of operation, limiting the efficiency and safety of power system maintenance and commissioning. Currently, no effective solution has been proposed to address these issues. Summary of the Invention
[0005] This invention provides a remote testing method and system for the transmission of a 110kV automatic transfer switch, which at least solves the technical problem in the related art that the automatic transfer switch is often tested on-site manually before it is put into use, resulting in low testing efficiency.
[0006] According to one aspect of the present invention, a remote testing method for the operation of a 110kV automatic transfer switch (ATS) is provided, applied to a remote testing system for the operation of a 110kV ATS. The remote testing system for the 110kV ATS includes at least a power grid dispatching platform and a power supply and information management master station. The remote testing method for the 110kV ATS includes: determining the 110kV ATS to be tested, and determining the target load station affected by the 110kV ATS, the nearest standby load station to the target load station, and the standby load station closest to the target load station. The target load station is located at the nearest open-loop point; a transmission operation ticket is generated for the target load station and the standby load station based on the power grid dispatching platform, and the transmission operation ticket is sent to the main power supply station; the transmission operation ticket is executed based on the main power supply station; after the transmission operation ticket is executed, the status of the open-loop point and the bus voltage of the target load station are checked, and the transmission test results of the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station are determined based on the status of the open-loop point and the bus voltage of the target load station.
[0007] Optionally, the step of executing the transmission operation ticket based on the main station of the information security system includes: deactivating the reclosing soft pressure plate of the high-voltage side bus circuit breaker of the target load station based on the main station of the information security system; and executing a transmission command on the high-voltage side bus circuit breaker of the target load station based on the main station of the information security system, so that the high-voltage side bus circuit breaker of the target load station is in the open position.
[0008] Optionally, after executing the transmission operation ticket based on the main power station, the method further includes: determining the execution result of the transmission operation ticket based on the automatic transfer switch action criterion; and determining that the transmission operation ticket execution is completed if the power system where the target load station and the standby load station are located meets the automatic transfer switch action criterion.
[0009] Optionally, the automatic transfer switch (ATS) operation criteria include at least one of the following: the circuit breaker position signal of the target load station is inconsistent with the closed switch position signal; the voltage signal of the bus in the power system other than the bus of the target load station satisfies the reclosing waveform; the negative sequence voltage of the bus in the power system other than the bus of the target load station is greater than the negative sequence voltage threshold of the fault bus in the target time period; and the zero sequence voltage of the bus in the power system other than the bus of the target load station is greater than the zero sequence voltage threshold of the fault bus in the target time period.
[0010] Optionally, after determining the target load station, the nearest standby load station, and the nearest open-loop point of the 110kV automatic transfer switch to be tested, the method further includes: checking the operating status of the protection device of the target load station, checking the operating status of the 110kV automatic transfer switch of the target load station, and checking the operating status of the 110kV automatic transfer switch of the standby load station, and obtaining the inspection result; if the inspection result indicates that the inspection is passed, generating an inspection pass signal, and sending the inspection pass signal to the power grid dispatching platform.
[0011] Optionally, the step of checking the operating status of the protection device of the target load station includes: checking the operating status of the circuit breaker on the high-voltage side bus of the target load station, wherein the operating status includes at least one of the following: the communication status between the circuit breaker and the target load station, the operating status of the circuit breaker, the alarm information of the circuit breaker, the charging status of the reclosing circuit breaker, the remote operation hard switch of the circuit breaker, the remote uninterruptible power transmission soft switch of the circuit breaker, and the remote activation / deactivation soft switch of the circuit breaker.
[0012] Optionally, the step of checking the operating status of the 110kV standby automatic transfer device of the target load station includes: checking the charging status of the 110kV standby automatic transfer device of the target load station; checking the alarm information of the operating status of the 110kV standby automatic transfer device of the target load station; comparing the device data of the 110kV standby automatic transfer device of the target load station with the device data in the setting sheet; and checking the soft pressure plate engagement / disengagement status of the 110kV standby automatic transfer device of the target load station.
[0013] Optionally, the steps for checking the operating status of the 110kV automatic transfer switch of the standby load station include: checking the charging status of the 110kV automatic transfer switch of the standby load station; checking the alarm information of the operating status of the 110kV automatic transfer switch of the standby load station; comparing the device data of the 110kV automatic transfer switch of the standby load station with the device data in the setting sheet; and checking the soft pressure plate engagement / disengagement status of the 110kV automatic transfer switch of the standby load station.
[0014] Optionally, the step of checking the state of the open-loop point and the bus voltage of the target load station, and determining the transmission test results of the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station based on the state of the open-loop point and the bus voltage of the target load station includes: acquiring the circuit breaker position signal of the open-loop point, and comparing the circuit breaker position signal with the closed switch position signal to obtain a first comparison result; acquiring the bus voltage of the target load station, and comparing the bus voltage with the fault bus voltage threshold. The values are compared to obtain a second comparison result; based on the first comparison result and the second comparison result, the transmission test results of the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station are determined, wherein, if the first comparison result indicates that the circuit breaker position signal is consistent with the closed switch position signal and the bus voltage is greater than the fault bus voltage threshold, it is determined that the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station have passed the transmission test.
[0015] According to another aspect of the present invention, a remote testing system for the transmission of a 110kV automatic transfer switch is also provided, comprising: a dispatching system, configured to determine the 110kV automatic transfer switch to be tested, and to determine the target load station, the nearest standby load station, and the nearest open-loop point of the 110kV automatic transfer switch to be tested; a power grid dispatching platform, configured to generate transmission operation tickets for the target load station and the standby load station based on the power grid dispatching platform; a security master station, configured to receive the transmission operation tickets issued by the power grid dispatching platform and execute the transmission operation tickets; and a security master station, configured to check the status of the open-loop point and the bus voltage of the target load station after the transmission operation tickets are executed, and to determine the transmission test results of the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station based on the status of the open-loop point and the bus voltage of the target load station.
[0016] Optionally, the information protection master station includes: a first exit module, used to exit the reclosing soft pressure plate of the high-voltage side bus circuit breaker of the target load station based on the information protection master station; and a first execution module, used to execute a transmission command on the high-voltage side bus circuit breaker of the target load station based on the information protection master station, so that the high-voltage side bus circuit breaker of the target load station is in the open position.
[0017] Optionally, the remote testing system for the 110kV automatic transfer switch transmission further includes: a first determining module, used to determine the execution result of the transmission operation ticket based on the automatic transfer action criterion; and a second determining module, used to determine that the transmission operation ticket has been executed if the power system where the target load station and the standby load station are located meets the automatic transfer action criterion.
[0018] Optionally, the automatic transfer switch (ATS) operation criteria include at least one of the following: the circuit breaker position signal of the target load station is inconsistent with the closed switch position signal; the voltage signal of the bus in the power system other than the bus of the target load station satisfies the reclosing waveform; the negative sequence voltage of the bus in the power system other than the bus of the target load station is greater than the negative sequence voltage threshold of the fault bus in the target time period; and the zero sequence voltage of the bus in the power system other than the bus of the target load station is greater than the zero sequence voltage threshold of the fault bus in the target time period.
[0019] Optionally, the remote testing system for the 110kV standby automatic transfer device transmission further includes: a first inspection module, used to inspect the working status of the protection device of the target load station, inspect the working status of the 110kV standby automatic transfer device of the target load station and inspect the working status of the 110kV standby automatic transfer device of the standby load station, and obtain inspection results; and a first generation module, used to generate an inspection pass signal when the inspection result indicates that the inspection has passed, and send the inspection pass signal to the power grid dispatching platform.
[0020] Optionally, the first inspection module includes: a first inspection submodule, used to inspect the operating status of the circuit breaker on the high-voltage side bus of the target load station, the operating status including at least one of the following: the communication status between the circuit breaker and the target load station, the operating status of the circuit breaker, the alarm information of the circuit breaker, the charging status of the reclosing of the circuit breaker, the remote operation hard plate engagement status of the circuit breaker, the remote uninterruptible power transmission soft plate engagement status of the circuit breaker, and the remote activation / deactivation soft plate engagement status of the circuit breaker.
[0021] Optionally, the first inspection module further includes: a second inspection submodule for inspecting the charging status of the 110kV automatic transfer switch of the target load station; a third inspection submodule for inspecting the alarm information of the operating status of the 110kV automatic transfer switch of the target load station; a first comparison submodule for comparing the device data of the 110kV automatic transfer switch of the target load station with the device data in the setting sheet; and a fourth inspection submodule for inspecting the soft pressure plate activation / deactivation status of the 110kV automatic transfer switch of the target load station.
[0022] Optionally, the first inspection module further includes: a fifth inspection submodule for checking the charging status of the 110kV automatic transfer switch of the standby load station; a sixth inspection submodule for checking the alarm information of the operating status of the 110kV automatic transfer switch of the standby load station; a second comparison submodule for comparing the device data of the 110kV automatic transfer switch of the standby load station with the device data in the setting sheet; and a seventh inspection submodule for checking the soft pressure plate engagement / disengagement status of the 110kV automatic transfer switch of the standby load station.
[0023] Optionally, the automatic transfer station includes: a first acquisition module, used to acquire the circuit breaker position signal at the open loop point and compare the circuit breaker position signal with the closed switch position signal to obtain a first comparison result; a first acquisition module, used to acquire the bus voltage of the target load station and compare the bus voltage with a fault bus voltage threshold to obtain a second comparison result; and a third determination module, used to determine the transmission test results of the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station based on the first comparison result and the second comparison result, wherein, if the first comparison result indicates that the circuit breaker position signal is consistent with the closed switch position signal and the bus voltage is greater than the fault bus voltage threshold, it is determined that the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station have passed the transmission test.
[0024] In this application, the following steps are taken: First, the 110kV standby automatic transfer device to be tested is determined, and the target load station, the nearest standby load station, and the nearest open-loop point of the 110kV standby automatic transfer device to be tested are determined. Then, a transmission operation ticket is generated for the target load station and the standby load station based on the power grid dispatching platform, and the transmission operation ticket is sent to the power grid control station. Then, the transmission operation ticket is executed based on the power grid control station. Finally, after the transmission operation ticket is executed, the status of the open-loop point and the bus voltage of the target load station are checked. Based on the status of the open-loop point and the bus voltage of the target load station, the transmission test results of the 110kV standby automatic transfer device of the target load station and the 110kV standby automatic transfer device of the standby load station are determined.
[0025] In this application, a transmission operation ticket is generated through the one-click sequential control function of the power grid dispatching platform in the power grid dispatching system and sent to the power supply and information control main station. The operation ticket is executed through the remote uninterrupted transmission function of the power supply and information control main station to remotely control the primary equipment of the target load station and the standby load station, simulating the power system bus undervoltage environment. This allows for remote automatic transmission testing of the 110kV automatic transfer switch, realizing the automation of the automatic transfer switch transmission test, avoiding the complexity and time-consuming nature of manual judgment in on-site testing, improving test efficiency, reducing operational errors, and improving the reliability of test results. This solves the technical problem in related technologies where, before the 110kV automatic transfer switch is put into use, it is often tested on-site manually, resulting in low testing efficiency. Attached Figure Description
[0026] The accompanying drawings, which are included to provide a further understanding of the invention and form part of this application, illustrate exemplary embodiments of the invention and, together with their description, serve to explain the invention and do not constitute an undue limitation thereof. In the drawings:
[0027] Figure 1 This is a flowchart of an optional remote test method for the transmission of a 110kV automatic transfer switch according to an embodiment of the present invention;
[0028] Figure 2 This is an optional primary wiring diagram of a power system according to an embodiment of the present invention;
[0029] Figure 3 This is an architecture diagram of an optional 110kV automatic transfer switch drive remote test system according to an embodiment of the present invention.
[0030] Figure 4 This is a schematic diagram of a remote test procedure for an optional 110kV automatic transfer switch drive according to an embodiment of the present invention.
[0031] Figure 5 This is a schematic diagram of an optional 110kV automatic transfer switch drive remote test system according to an embodiment of the present invention.
[0032] Figure 6 This is a hardware structure block diagram of an electronic device (or mobile device) for a remote testing method of a 110kV automatic transfer switch transmission according to an embodiment of the present invention. Detailed Implementation
[0033] To enable those skilled in the art to better understand the present invention, the technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort should fall within the scope of protection of the present invention.
[0034] It should be noted that the terms "first," "second," etc., in the specification, claims, and accompanying drawings of this invention are used to distinguish similar objects and are not necessarily used to describe a specific order or sequence. It should be understood that such data can be interchanged where appropriate so that the embodiments of the invention described herein can be implemented in orders other than those illustrated or described herein. Furthermore, the terms "comprising" and "having," and any variations thereof, are intended to cover a non-exclusive inclusion; for example, a process, method, system, product, or apparatus that comprises a series of steps or units is not necessarily limited to those steps or units explicitly listed, but may include other steps or units not explicitly listed or inherent to such processes, methods, products, or apparatus.
[0035] It should be noted that the remote testing method and apparatus for the 110kV automatic transfer switch transmission in this application can be used in the field of automatic transfer switch control technology for 110kV automatic transfer switch transmission tests based on remote uninterrupted power supply function, and can also be used in any field other than the field of automatic transfer switch control technology for 110kV automatic transfer switch transmission tests based on remote uninterrupted power supply function. This application does not limit the application field of the remote testing method and apparatus for the 110kV automatic transfer switch transmission.
[0036] The following embodiments of the present invention can be applied to remote testing systems / applications / equipment for various 110kV automatic transfer switch drives. The present invention issues drive operation tickets to the main power supply station via the one-click sequential control function of the power grid dispatching platform. Through the remote uninterrupted power transmission function of the main power supply station, it controls the primary equipment in the target load station and the standby load station, tripping the main power supply switch of the non-open-loop substation, remotely simulating a busbar undervoltage environment, thereby realizing automated drive testing of 110kV automatic transfer switches. This avoids the complexity and time-consuming nature of manual judgment in traditional testing, significantly improving the efficiency and accuracy of the test.
[0037] The present invention will now be described in detail with reference to various embodiments.
[0038] Example 1
[0039] According to an embodiment of the present invention, a method for remote testing of a 110kV automatic transfer switch drive is provided. It should be noted that the steps shown in the flowchart in the accompanying drawings can be executed in a computer system such as a set of computer-executable instructions. Furthermore, although a logical order is shown in the flowchart, in some cases, the steps shown or described may be executed in a different order than that shown here.
[0040] Figure 1 This is a flowchart of an optional remote testing method for the transmission of a 110kV automatic transfer switch according to an embodiment of the present invention, as shown below. Figure 1 As shown, the method includes the following steps:
[0041] Step S101: Determine the 110kV standby automatic transfer device to be tested, and determine the target load station, the standby load station closest to the target load station, and the open loop point closest to the target load station.
[0042] It should be noted that the 110kV automatic transfer switch (ATS) is used in multi-stage series-powered 110kV systems to activate the backup power supply at the system open-loop point when the 110kV busbar of a substation loses power, thus promptly restoring power to the lost substation busbar. To verify the correctness of the wiring and logic function of the 110kV ATS circuit and ensure its reliable operation after commissioning, a full-scale transmission test needs to be conducted before commissioning the 110kV ATS.
[0043] It should be noted that when conducting transmission tests, the 110kV automatic transfer switch (ATS) to be tested must first be identified, and the load station acting on the ATS should be designated as the target load station. The load station closest to the target load station should be designated as the backup load station. The open-loop point of the ATS needs to be located. In a power system, a load station refers to a station used to supply power to the load, such as a substation. Generally, two or more adjacent load stations serve as backups for each other. When the busbar of one load station loses voltage, the load station with the lost voltage is disconnected, the open-loop point is closed, and the backup load station is switched to supply power. This allows for rapid power restoration of the faulty distribution network, ensuring the stable operation of the power system. By determining the 110kV ATS, target load station, backup load station, and open-loop point before the experiment, automated remote testing can be performed on the ATS, accurately and quickly completing the transmission test and ensuring the normal operation of the 110kV ATS after it is put into operation.
[0044] Optionally, after determining the target load station, the nearest standby load station, and the nearest open-loop point of the 110kV automatic transfer switch to be tested, the process further includes: checking the operating status of the protection device of the target load station, checking the operating status of the 110kV automatic transfer switch of the target load station, and checking the operating status of the 110kV automatic transfer switch of the standby load station to obtain the inspection results; if the inspection results indicate that the inspection has passed, generating an inspection pass signal and sending the inspection pass signal to the power grid dispatching platform.
[0045] It should be noted that after determining the target load station, the nearest standby load station, and the nearest open-loop point of the 110kV automatic transfer switch to be tested, the power system of the target load station and the standby load station must first be checked to ensure that the protection device of the target load station is working properly and that the 110kV automatic transfer switch of the standby load station is working properly. This is a prerequisite for remotely executing the automatic transfer switch transmission test.
[0046] Optionally, the steps for checking the operating status of the protection devices of the target load station include: checking the operating status of the circuit breakers on the high-voltage side bus of the target load station, the operating status including at least one of the following: the communication status between the circuit breaker and the target load station, the operating status of the circuit breaker, the alarm information of the circuit breaker, the charging status of the reclosing of the circuit breaker, the remote operation hard switch of the circuit breaker, the remote uninterruptible power transmission soft switch of the circuit breaker, and the remote activation / deactivation soft switch of the circuit breaker.
[0047] It should be noted that the inspection of the operating status of the protection devices at the target load station is performed by the power system's main information control station. The main information control station needs to check whether the protection devices at the target load station are in normal operating condition. The protection devices here include at least the circuit breaker on the high-voltage side bus of the target load station. This circuit breaker plays a key role in simulating the busbar undervoltage of the target load station. Therefore, it is necessary to ensure that the circuit breaker can work normally before the experiment. The specific checks on the operating status of the circuit breaker can include: communication status, confirming whether the communication channel between the circuit breaker and the target load station is unobstructed and without communication abnormalities, so as to ensure that the circuit breaker on the busbar of the target load station can be remotely tripped during the subsequent test to simulate the busbar undervoltage environment; operating status, the circuit breaker should be in the operating state, i.e., the closed state, and the circuit breaker should not have any abnormal alarms or fault signals; reclosing status, for circuit breaker reclosing, it is necessary to check whether the reclosing is charging normally and whether there are any reclosing-related alarms; soft and hard pressure plates, confirming that the remote uninterruptible transmission soft pressure plate and the remote activation / deactivation hard pressure plate of the circuit breaker are in the correct activation / deactivation state to ensure the feasibility of remote operation.
[0048] Optionally, the steps for checking the operating status of the 110kV automatic transfer switch of the target load station include: checking the charging status of the 110kV automatic transfer switch of the target load station; checking the alarm information of the operating status of the 110kV automatic transfer switch of the target load station; comparing the device data of the 110kV automatic transfer switch of the target load station with the device data in the setting sheet; and checking the activation / deactivation status of the soft pressure plate of the 110kV automatic transfer switch of the target load station.
[0049] It should be noted that the check of the operating status of the 110kV automatic transfer switch at the target load station is performed by the power system's safety control station. The safety control station communicates with the automatic transfer switches at each load station to check their operating status, specifically including: checking the charging status of the 110kV automatic transfer switch at the target load station (a charging status indicates the switch is ready and can automatically start); checking the alarm information of the 110kV automatic transfer switch at the target load station to ensure there are no potential faults or abnormalities; and checking whether the device data of the 110kV automatic transfer switch at the target load station matches the data in the setting sheet. Consistency is key. The setting sheet contains preset parameters for the automatic transfer switch (ATS), such as voltage threshold and time delay. These parameters determine the conditions under which the device operates. Comparing the current configuration data of the ATS with the setting sheet confirms whether the device settings are correct and consistent with the expected test conditions. If inconsistencies are found, adjustments are needed to ensure the accuracy of the test conditions. Finally, the activation / deactivation status of the soft switch of the 110kV ATS at the target load station needs to be checked. The soft switch is a logic switch that controls the activation or deactivation of the ATS function. The soft switch for remote operation needs to be in the activated state so that it can be remotely controlled through the main station.
[0050] Optionally, the steps for checking the operating status of the 110kV automatic transfer switch of the standby load station include: checking the charging status of the 110kV automatic transfer switch of the standby load station; checking the alarm information of the operating status of the 110kV automatic transfer switch of the standby load station; comparing the device data of the 110kV automatic transfer switch of the standby load station with the device data in the setting sheet; and checking the activation / deactivation status of the soft pressure plate of the 110kV automatic transfer switch of the standby load station.
[0051] Similarly, before conducting formal transmission tests, the Anzhi substation needs to check the operating status of the 110kV automatic transfer switch of the standby load station, which is the same as the check of the 110kV automatic transfer switch of the target load station. The specific checks on the operating status of the 110kV automatic transfer switch of the standby load station include: checking whether the 110kV automatic transfer switch of the standby load station is in charging state; checking whether there are any alarm messages in the operating status of the 110kV automatic transfer switch of the standby load station; checking whether the device data of the 110kV automatic transfer switch of the standby load station is consistent with the data configured in the setting sheet; and checking whether the soft pressure plate of the 110kV automatic transfer switch of the standby load station is in the engaged state, thereby ensuring that the 110kV automatic transfer switch of the standby load station is available.
[0052] Step S102: Generate transmission operation tickets for the target load station and the standby load station based on the power grid dispatching platform, and send the transmission operation tickets to the main station of the power grid dispatching platform.
[0053] It should be noted that the safety control station and the security information control station upload the inspection results to the power grid dispatching platform. If the inspection is confirmed to be problem-free, the power grid dispatching platform generates transmission operation tickets for the target load station and the standby load station, and sends the transmission operation tickets to the security information control station to realize intelligent dispatching and control of the power grid. The power grid dispatching platform is deployed in the control center and can be used to generate operation tickets and send operation instructions to the dispatch automation system to complete primary equipment control, send operation instructions to the security information control station to complete the control of protection devices, and send operation commands to the safety control station to complete the control of safety control devices. The transmission operation ticket contains transmission test instructions, which are used to control the security information control station to execute transmission test instructions to simulate the test environment of bus undervoltage of the target load station.
[0054] Step S103: Execute the transmission operation ticket based on the main station of the information security system.
[0055] It should be noted that the transmission operation ticket is used to control the primary equipment of the target load station and the standby load station based on the main station of the power supply and control system, thereby tripping the switch of the target load station, causing the busbar of the target load station to lose voltage, and thus conducting a transmission test on the 110kV standby automatic transfer device.
[0056] Optionally, the steps of executing the transmission operation ticket based on the main station of the power supply and information technology bureau include: removing the reclosing soft pressure plate of the high-voltage side bus circuit breaker of the target load station based on the main station of the power supply and information technology bureau; and executing the transmission command on the high-voltage side bus circuit breaker of the target load station based on the main station of the power supply and information technology bureau, so that the high-voltage side bus circuit breaker of the target load station is in the open position.
[0057] It should be noted that, based on the transmission test command in the transmission operation ticket, the main station of the power supply and control station first disconnects the reclosing soft pressure plate of the high-voltage side bus circuit breaker of the target load station to prevent the reclosing function from automatically closing the circuit breaker after it is tripped, thus affecting the normal operation of the 110kV standby automatic transfer switch. Secondly, it is necessary to execute the transmission command on the high-voltage side bus circuit breaker of the target load station to trip the circuit breaker switch, so that the circuit breaker is in the open position, thereby simulating the scenario of the target load station bus losing voltage.
[0058] Optionally, after executing the transmission operation ticket based on the main station of the power supply and control system, the process further includes: determining the execution result of the transmission operation ticket based on the automatic transfer switch action criteria; and determining that the transmission operation ticket execution has ended if the power system where the target load station and the standby load station are located meets the automatic transfer switch action criteria.
[0059] It should be noted that after simulating the scenario of busbar undervoltage at the target load station, the power system where the target load station and the standby load station are located is judged by the pre-set standby automatic transfer action criteria to determine whether the transmission operation ticket has been executed and whether the simulated busbar undervoltage scenario meets the expected requirements.
[0060] Optionally, the automatic transfer switch (ATS) operation criteria include at least one of the following: the circuit breaker position signal of the target load station is inconsistent with the closed switch position signal; the voltage signal of the bus in the power system other than the bus of the target load station meets the reclosing waveform; the negative sequence voltage of the bus in the power system other than the bus of the target load station is greater than the negative sequence voltage threshold of the fault bus in the target time period; and the zero sequence voltage of the bus in the power system other than the bus of the target load station is greater than the zero sequence voltage threshold of the fault bus in the target time period.
[0061] Specifically, the power system is considered to have successfully executed the transmission operation ticket if at least one of the following conditions is met: First, the circuit breaker position signal of the target load station is inconsistent with the closed switch position signal, that is, in the simulation environment, the bus circuit breaker of the target load station is in the open position; Second, the voltage of any non-maintenance bus in the power system meets the reclosing waveform. The waveform discrimination conditions are as follows: First, the bus voltage should meet the process of "voltage present → voltage absent → voltage present", that is, after the three-phase voltage of the bus is lower than the voltage absent value for more than the first time delay, within the start-up delay Tq of the 110kV automatic transfer switch, the voltage of any phase of any bus is higher than 0.5Un for more than the second time delay, where Un represents the rated voltage of the bus. Second, within at least the second time delay, the negative sequence voltage of any non-maintenance bus is greater than the negative sequence voltage threshold of the fault bus. When a fault occurs in the power system, a negative sequence voltage may be generated. By checking the negative sequence voltage of any non-maintenance bus, it is ensured that the power system will not affect the start-up of the 110kV automatic transfer switch. Third, within at least the second time delay, the zero sequence voltage of any non-maintenance bus is greater than the zero sequence voltage threshold of the fault bus, thereby ensuring that the 110kV automatic transfer switch can start normally.
[0062] Step S104: After the transmission operation ticket is executed, check the status of the open loop point and the bus voltage of the target load station. Based on the status of the open loop point and the bus voltage of the target load station, determine the transmission test results of the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station.
[0063] It should be noted that, under normal circumstances, when the 110kV automatic transfer switch detects the busbar voltage loss at the target load station, it will automatically switch to the backup power supply to power the load. In order to obtain the transmission test results of the automatic transfer switch, after the transmission operation ticket is executed, the open-loop circuit breaker and the busbar voltage of the target load station are checked to determine whether the 110kV automatic transfer switch has been successfully started.
[0064] Optionally, the step of checking the status of the open-loop point and the bus voltage of the target load station, and determining the transmission test results of the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station based on the status of the open-loop point and the bus voltage of the target load station includes: acquiring the circuit breaker position signal of the open-loop point and comparing the circuit breaker position signal with the closed switch position signal to obtain a first comparison result; acquiring the bus voltage of the target load station and comparing the bus voltage with the fault bus voltage threshold to obtain a second comparison result; determining the transmission test results of the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station based on the first comparison result and the second comparison result, wherein, if the first comparison result indicates that the circuit breaker position signal is consistent with the closed switch position signal and the bus voltage is greater than the fault bus voltage threshold, it is determined that the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station have passed the transmission test.
[0065] It should be noted that when verifying the results of the transmission test, the circuit breaker position information at the open loop point is first obtained to determine whether the circuit breaker position signal is consistent with the closed switch position signal. The bus voltage of the target load station is also collected to determine whether the bus undervoltage fault of the target load station has been recovered. If the circuit breaker position signal is consistent with the closed switch position signal and the bus voltage is greater than the fault bus voltage threshold, it indicates that the 110kV standby automatic transfer device has been successfully started in the simulated environment and can be put into operation in the actual scenario, thus obtaining the test results of the 110kV standby automatic transfer device passing the transmission test.
[0066] In another embodiment, when the 110kV standby automatic transfer device passes the transmission test, the transmission test results are uploaded to the distribution network dispatching platform. The distribution network dispatching platform generates a restoration operation ticket and sends the restoration operation ticket to the power supply and information control main station. The power supply and information control main station executes the restoration command and puts the soft pressure plate of the circuit breaker reclosing outlet on the high-voltage side bus of the target load station into operation. This allows the reclosing to automatically restore the disconnected circuit breaker switch, relieve the simulated busbar undervoltage environment, and allow the power system to return to normal.
[0067] Through the above steps, the 110kV standby automatic transfer switch to be tested is first determined, along with the target load station, the nearest standby load station, and the nearest open-loop point. Based on the power grid dispatch platform, transmission operation tickets are generated for the target load station and the standby load station, and these tickets are then sent to the main power grid control station. The main power grid control station then executes the transmission operation tickets. Finally, after the execution of the transmission operation tickets, the status of the open-loop point and the bus voltage of the target load station are checked. Based on the status of the open-loop point and the bus voltage of the target load station, the transmission test results of the 110kV standby automatic transfer switch at the target load station and the 110kV standby automatic transfer switch at the standby load station are determined.
[0068] In this embodiment, a transmission operation ticket is generated through the one-click sequential control function of the power grid dispatching platform in the power grid dispatching system and sent to the power supply and information control main station. The operation ticket is executed through the remote uninterrupted power transmission function of the power supply and information control main station to remotely control the primary equipment of the target load station and the standby load station, simulating the power system bus undervoltage environment. This allows for remote automatic transmission testing of the 110kV automatic transfer switch, realizing the automation of the automatic transfer switch transmission test. This avoids the complexity and time-consuming nature of manual judgment in on-site testing, improves test efficiency, reduces operational errors, and enhances the reliability of test results. This solves the technical problem in related technologies where, before the 110kV automatic transfer switch is put into use, it is often tested manually on-site, resulting in low testing efficiency.
[0069] The following describes in detail another optional implementation method.
[0070] The remote testing method for the transmission of 110kV automatic transfer switch (ATS) devices according to this invention is applied to a remote testing system for the transmission of 110kV ATS devices. Besides 110kV power systems, this invention can also be used to conduct transmission tests on ATS devices in other power systems. Figure 2 This is an optional primary wiring diagram of a power system according to an embodiment of the present invention, such as... Figure 2As shown, on the 110kV busbar, stations A and D are power supply stations, while stations B and C are backup load stations for each other. Stations A and B are connected via line AB, stations B and C are connected via line BC, and stations C and D are connected via line CD. With the position of circuit breaker BC as the open loop point, circuit breaker BC at station B is open, and circuit breaker CB at station C is closed. Station B is powered by station A via line AB, and station C is powered by station D via line CD. Stations B and C are each equipped with a 110kV automatic transfer switch (ATS) device. Its operating logic is as follows: When Station C detects no voltage on the 110kV busbar and no current on the main supply line, and meets the KRU condition (corresponding to the aforementioned ATS action criterion), the Station C 110kV ATS is activated. After a delay, the Station C CD circuit breaker trips. The ATS device detects that the CD circuit breaker has tripped and, after a delay, sends a remote closing command to the Station B 110kV ATS device via the channel. The Station B 110kV ATS device then closes the Station B BC circuit breaker, switching power supply to Station B and restoring power supply to Station C.
[0071] Figure 3 This is an architecture diagram of an optional 110kV automatic transfer switch drive remote testing system according to an embodiment of the present invention, as shown below. Figure 3 As shown, the remote testing system for the 110kV automatic transfer switch includes: a DICP system, a firewall, a protection and information system, an automatic safety system, and a remote control system. The DICP system communicates with the automatic safety system, the protection and information system, and the remote control system via the firewall. The automatic safety system consists of automatic safety stations, which connect to the 110kV automatic transfer switches at load stations in the power system via the dispatch data network. The protection and information system consists of a main protection and information station and several protection and information substations deployed in the power system, connecting to the protection devices in the power system. The remote control system consists of an OSC system, which connects to the measurement and control devices at various power stations or load stations via remote control units deployed in the power system. Specifically…
[0072] OCS (Operating Control System) refers to the Dispatch Automation System, deployed in the control center. It is a system that directly collects and monitors data for power grid operation. It can monitor the operating status of primary equipment (switches, disconnectors, etc.) in real time and complete the operation of primary equipment. It communicates with remote control units deployed in substations through the dispatch data network, and then controls the protection devices of the substations through the remote control units.
[0073] The DICP system refers to the power grid dispatching platform, which is deployed in the control center. It can generate operation tickets and send operation commands to the OCS system to complete a single equipment operation, send operation commands to the protection and information master station to complete the operation of protection devices, and send operation commands to the safety and automation master station to complete the operation of safety and automation devices.
[0074] The main station of the protection system is deployed in the control center and connects to the substations of the protection system through the dispatch data network. It collects data from the protection equipment in real time and completes the operation of the protection equipment through the substations of the protection system. It can realize operations such as remote activation and deactivation of soft pressure plates, remote modification of set values, and remote uninterrupted power transmission of the protection device.
[0075] Remote uninterrupted power transmission refers to the process where the main power supply station sends a transmission command to the protection device, and the protection device completes the protection tripping and reclosing of the switch after receiving the command. The entire process can be executed remotely without causing power outages for users.
[0076] The automatic transfer station is deployed in the control center and communicates with the 110kV standby automatic transfer device of the load station through the dispatch data network. It is used to forward the remote control commands of the low-frequency low-voltage load shedding device issued by the DICP system and has functions such as remotely activating and deactivating soft pressure plates and remotely modifying setpoints.
[0077] The protection information substation includes intelligent waveform recorders, control substations, etc., and is deployed in the substation. It is used to forward the data of the protection device to the protection information master station, and forward the remote activation / deactivation soft switch, remote setting modification, and remote non-power-off transmission commands of the protection information master station to the protection device.
[0078] The data from the protection device includes analog quantities, input quantities, soft pressure plates, set values, alarm information, etc.
[0079] Remote control units (RTUs) are deployed in substations and can perform functions such as remote control, remote signaling, remote measurement, and remote adjustment.
[0080] The remote testing system for the drive of a 110kV automatic transfer switch according to this invention is used to perform a remote testing method for the drive of a 110kV automatic transfer switch. Figure 4 This is a schematic diagram of an optional remote testing process for a 110kV automatic transfer switch drive according to an embodiment of the present invention. Figure 2 Station C is the target load station for this test, and station B is the backup load station. Figure 4 As shown, the transmission test steps before the automatic switching device is put into use include:
[0081] Step 1, Initialization;
[0082] Step 2: The OSC system checks whether the open loop point is at station B. If yes, proceed to step 3. If no, adjust the open loop point to station B and then proceed to step 2 again.
[0083] Step 3: The main station of the security system checks whether the protection device (i.e., CD circuit breaker) of the CD line of station C is operating normally and whether the reclosing is charging normally. If yes, proceed to step 4. If no, check and handle the protection device of CD line of station C and then proceed to step 3 again.
[0084] Step 4: Check whether the automatic transfer switches of stations B and C are operating normally and whether they are charging normally. If yes, proceed to step 5. If not, check and handle the automatic transfer switches of stations B and C and then proceed to step 4 again.
[0085] Step 5: The DICP system generates a test operation ticket for the 110V standby automatic transfer device and sends it to the main station of the security information system.
[0086] Step 6, Baoxin main station executes operation ticket: Exit CD line protection device reclosing output soft pressure plate;
[0087] Step 7, Baoxin main station executes operation ticket: remote uninterruptible power transmission trips C station CD line switch (i.e. CD circuit breaker);
[0088] Step 8: Check whether the automatic transfer switches of stations B and C are operating correctly: Check whether the BC switch of station B is closed and whether the bus voltage of station C has been restored. If yes, proceed to step 9; otherwise, skip step 9 and proceed to step 10.
[0089] Step nine: The automatic transfer devices at stations B and C are successfully activated.
[0090] Step 10: The automatic transfer device at stations B and C failed to operate.
[0091] Step 11, Baoxin main station executes operation ticket: Activate the reclosing output soft pressure plate of the protection device for C station CD line.
[0092] In this embodiment of the invention, a transmission operation ticket is issued to the main station of the power grid dispatching platform through the one-click sequential control function. The primary equipment in the target load station and the standby load station is controlled through the remote uninterrupted transmission function of the main station of the power grid dispatching platform. The main power supply switch of the non-open loop substation is tripped, and the busbar undervoltage environment is simulated remotely. This realizes the 110kV standby automatic transfer automatic transmission test, avoiding the complexity and time-consuming nature of manual judgment in traditional tests, and significantly improving the efficiency and accuracy of the test.
[0093] The following is a detailed description with reference to another embodiment.
[0094] Example 2
[0095] The remote testing system for the transmission of a 110kV automatic switching device provided in this embodiment includes multiple implementation units. Each implementation unit corresponds to a specific implementation step in the above embodiment one. The specific implementation method and beneficial effects can be referred to the aforementioned method embodiment, and will not be repeated here.
[0096] Figure 5 This is a schematic diagram of a remote testing system for an optional 110kV automatic transfer switch drive according to an embodiment of the present invention, as shown below. Figure 5As shown, the remote testing device for the 110kV automatic transfer switch transmission may include: a dispatching system 51, a power grid dispatching platform 52, a power supply and information control main station 53, and an automatic safety control station 54, wherein,
[0097] The dispatch system 51 is used to determine the 110kV standby automatic transfer device to be tested, and to determine the target load station, the standby load station closest to the target load station, and the open loop point closest to the target load station.
[0098] The power grid dispatching platform 52 is used to generate transmission operation tickets for target load stations and standby load stations based on the power grid dispatching platform;
[0099] The main station 53 is used to receive and execute transmission operation tickets issued by the power grid dispatching platform.
[0100] Anzhi Station 54 is used to check the status of the open loop point and the bus voltage of the target load station after the transmission operation ticket is executed, and to determine the transmission test results of the 110kV standby automatic transfer device of the target load station and the 110kV standby automatic transfer device of the standby load station based on the status of the open loop point and the bus voltage of the target load station.
[0101] The aforementioned remote testing system for the 110kV automatic transfer switch (ATS) transmission determines the 110kV ATS to be tested through the dispatch system 51, and identifies the target load station, the nearest standby load station, and the nearest open-loop point of the ATS. The system then generates transmission operation tickets for the target load station and the standby load station through the power grid dispatch platform 52. The system receives and executes the transmission operation tickets from the power grid dispatch platform through the security and information control master station 53. After the transmission operation tickets are executed, the system checks the status of the open-loop point and the bus voltage of the target load station through the safety and security master station 54, and determines the transmission test results of the 110kV ATS at the target load station and the 110kV ATS at the standby load station based on these parameters.
[0102] In this embodiment, a transmission operation ticket is generated through the one-click sequential control function of the power grid dispatching platform in the power grid dispatching system and sent to the power supply and information control main station. The operation ticket is executed through the remote uninterrupted power transmission function of the power supply and information control main station to remotely control the primary equipment of the target load station and the standby load station, simulating the power system bus undervoltage environment. This allows for remote automatic transmission testing of the 110kV automatic transfer switch, realizing the automation of the automatic transfer switch transmission test. This avoids the complexity and time-consuming nature of manual judgment in on-site testing, improves test efficiency, reduces operational errors, and enhances the reliability of test results. This solves the technical problem in related technologies where, before the 110kV automatic transfer switch is put into use, it is often tested manually on-site, resulting in low testing efficiency.
[0103] Optionally, the main station 53 includes: a first exit module, used to exit the reclosing soft pressure plate of the high-voltage side bus circuit breaker of the target load station based on the main station; and a first execution module, used to execute a transmission command on the high-voltage side bus circuit breaker of the target load station based on the main station, so that the high-voltage side bus circuit breaker of the target load station is in the open position.
[0104] Optionally, the remote testing system for the 110kV automatic transfer switch transmission also includes: a first determining module, used to determine the execution result of the transmission operation ticket based on the automatic transfer action criteria; and a second determining module, used to determine the completion of the transmission operation ticket execution if the power system where the target load station and the standby load station are located meets the automatic transfer action criteria.
[0105] Optionally, the automatic transfer switch (ATS) operation criteria include at least one of the following: the circuit breaker position signal of the target load station is inconsistent with the closed switch position signal; the voltage signal of the bus in the power system other than the bus of the target load station meets the reclosing waveform; the negative sequence voltage of the bus in the power system other than the bus of the target load station is greater than the negative sequence voltage threshold of the fault bus in the target time period; and the zero sequence voltage of the bus in the power system other than the bus of the target load station is greater than the zero sequence voltage threshold of the fault bus in the target time period.
[0106] Optionally, the remote testing system for the 110kV standby automatic transfer device transmission further includes: a first inspection module, used to inspect the working status of the protection device of the target load station, inspect the working status of the 110kV standby automatic transfer device of the target load station and inspect the working status of the 110kV standby automatic transfer device of the standby load station, and obtain the inspection results; and a first generation module, used to generate an inspection pass signal when the inspection result indicates that the inspection has passed, and send the inspection pass signal to the power grid dispatching platform.
[0107] Optionally, the first inspection module includes: a first inspection submodule, used to inspect the operating status of the circuit breaker on the high-voltage side bus of the target load station, the operating status including at least one of the following: the communication status between the circuit breaker and the target load station, the operating status of the circuit breaker, the alarm information of the circuit breaker, the charging status of the reclosing of the circuit breaker, the remote operation hard plate engagement status of the circuit breaker, the remote uninterruptible power transmission soft plate engagement status of the circuit breaker, and the remote activation / deactivation soft plate engagement status of the circuit breaker.
[0108] Optionally, the first inspection module further includes: a second inspection submodule for checking the charging status of the 110kV automatic transfer switch of the target load station; a third inspection submodule for checking the alarm information of the operating status of the 110kV automatic transfer switch of the target load station; a first comparison submodule for comparing the device data of the 110kV automatic transfer switch of the target load station with the device data in the setting sheet; and a fourth inspection submodule for checking the soft pressure plate activation / deactivation status of the 110kV automatic transfer switch of the target load station.
[0109] Optionally, the first inspection module further includes: a fifth inspection submodule for checking the charging status of the 110kV automatic transfer switch of the standby load station; a sixth inspection submodule for checking the alarm information of the operating status of the 110kV automatic transfer switch of the standby load station; a second comparison submodule for comparing the device data of the 110kV automatic transfer switch of the standby load station with the device data in the setting sheet; and a seventh inspection submodule for checking the soft pressure plate activation / deactivation status of the 110kV automatic transfer switch of the standby load station.
[0110] Optionally, the automatic transfer station 54 includes: a first acquisition module, used to acquire the circuit breaker position signal at the open loop point and compare the circuit breaker position signal with the closed switch position signal to obtain a first comparison result; a first acquisition module, used to acquire the bus voltage of the target load station and compare the bus voltage with the fault bus voltage threshold to obtain a second comparison result; and a third determination module, used to determine the transmission test results of the 110kV automatic transfer device of the target load station and the 110kV automatic transfer device of the standby load station based on the first comparison result and the second comparison result, wherein, if the first comparison result indicates that the circuit breaker position signal is consistent with the closed switch position signal and the bus voltage is greater than the fault bus voltage threshold, it is determined that the 110kV automatic transfer device of the target load station and the 110kV automatic transfer device of the standby load station have passed the transmission test.
[0111] The remote test system for the aforementioned 110kV automatic transfer switch can also include a processor and a memory. The aforementioned dispatching system 51, power grid dispatching platform 52, information protection master station 53, and safety self-control station 54 are all stored in the memory as program units, and the processor executes the aforementioned program units stored in the memory to realize the corresponding functions.
[0112] The aforementioned processor contains a kernel, which retrieves the corresponding program units from memory. One or more kernels can be configured, and by adjusting kernel parameters, remote uninterrupted power supply tests can be conducted on the 110kV automatic transfer switch.
[0113] The aforementioned memory may include non-permanent memory in computer-readable media, such as random access memory (RAM) and / or non-volatile memory, such as read-only memory (ROM) or flash memory, and the memory includes at least one memory chip.
[0114] According to another aspect of the present invention, a computer-readable storage medium is also provided, the computer-readable storage medium including a stored computer program, wherein, when the computer program is running, it controls the device where the computer-readable storage medium is located to perform any of the above-described remote test methods for the transmission of a 110kV automatic transfer switch.
[0115] According to another aspect of the present invention, an electronic device is also provided, including one or more processors and a memory, the memory being used to store one or more programs, wherein when the one or more programs are executed by the one or more processors, the one or more processors cause the one or more processors to implement any of the above-described remote testing methods for the 110kV automatic transfer switch drive.
[0116] According to another aspect of the present invention, a computer program product is also provided, the computer program product including a computer program, wherein when the computer program is executed by a processor, it implements any of the above-described remote test methods for the transmission of a 110kV automatic transfer switch.
[0117] This application also provides a computer program product, which, when executed on a data processing device, is suitable for executing an initialization program with the following method steps: determining the 110kV automatic transfer switch to be tested, and determining the target load station, the nearest standby load station, and the nearest open-loop point of the 110kV automatic transfer switch to be tested; generating transmission operation tickets for the target load station and the standby load station based on the power grid dispatching platform, and issuing the transmission operation tickets to the power grid control master station; executing the transmission operation tickets based on the power grid control master station; after the transmission operation tickets are executed, checking the status of the open-loop point and the bus voltage of the target load station, and determining the transmission test results of the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station based on the status of the open-loop point and the bus voltage of the target load station.
[0118] This application also provides a computer program product, which, when executed on a data processing device, is also suitable for executing an initialization program with the following method steps: the steps of executing a transmission operation ticket based on the main station of the information security system include: based on the main station of the information security system, exiting the reclosing soft pressure plate of the high-voltage side bus circuit breaker of the target load station; based on the main station of the information security system, executing a transmission command on the high-voltage side bus circuit breaker of the target load station, causing the high-voltage side bus circuit breaker of the target load station to be in the open position.
[0119] This application also provides a computer program product, which, when executed on a data processing device, is also suitable for executing an initialization program with the following method steps: after executing the transmission operation ticket based on the main station, it further includes: determining the execution result of the transmission operation ticket based on the backup automatic transfer action criterion; and determining that the transmission operation ticket execution has ended if the power system where the target load station and the standby load station are located meets the backup automatic transfer action criterion.
[0120] This application also provides a computer program product, which, when executed on a data processing device, is also suitable for executing an initialization program having the following method steps: the automatic transfer switch action criterion includes at least one of the following: the circuit breaker position signal of the target load station is inconsistent with the closed switch position signal; the voltage signal of the bus in the power system other than the bus of the target load station satisfies the reclosing waveform; the negative sequence voltage of the bus in the power system other than the bus of the target load station in the target time period is greater than the negative sequence voltage threshold of the fault bus; the zero sequence voltage of the bus in the power system other than the bus of the target load station in the target time period is greater than the zero sequence voltage threshold of the fault bus.
[0121] This application also provides a computer program product, which, when executed on a data processing device, is further adapted to execute an initialization program having the following method steps: after determining the target load station, the nearest standby load station, and the nearest open-loop point of the 110kV automatic transfer switch to be tested, the program further includes: checking the operating status of the protection device of the target load station, checking the operating status of the 110kV automatic transfer switch of the target load station and checking the operating status of the 110kV automatic transfer switch of the standby load station, and obtaining the check result; if the check result indicates that the check has passed, generating a check pass signal and sending the check pass signal to the power grid dispatching platform.
[0122] This application also provides a computer program product, which, when executed on a data processing device, is also suitable for executing an initialization program having the following method steps: the step of checking the operating status of the protection device of the target load station includes: checking the operating status of the circuit breaker on the high-voltage side bus of the target load station, the operating status including at least one of the following: the communication status between the circuit breaker and the target load station, the operating status of the circuit breaker, the alarm information of the circuit breaker, the charging status of the reclosing of the circuit breaker, the remote operation hard plate engagement status of the circuit breaker, the remote uninterruptible power transmission soft plate engagement status of the circuit breaker, and the remote activation / deactivation soft plate engagement status of the circuit breaker.
[0123] This application also provides a computer program product, which, when executed on a data processing device, is also suitable for executing an initialization program with the following method steps: the step of checking the working status of the 110kV automatic transfer switch of the target load station includes: checking the charging status of the 110kV automatic transfer switch of the target load station; checking the alarm information of the operating status of the 110kV automatic transfer switch of the target load station; comparing the device data of the 110kV automatic transfer switch of the target load station with the device data in the setting sheet; and checking the soft pressure plate engagement / disengagement status of the 110kV automatic transfer switch of the target load station.
[0124] This application also provides a computer program product, which, when executed on a data processing device, is also suitable for executing an initialization program with the following method steps: the step of checking the working status of the 110kV automatic transfer switch of the standby load station includes: checking the charging status of the 110kV automatic transfer switch of the standby load station; checking the alarm information of the operating status of the 110kV automatic transfer switch of the standby load station; comparing the device data of the 110kV automatic transfer switch of the standby load station with the device data in the setting sheet; and checking the soft pressure plate engagement / disengagement status of the 110kV automatic transfer switch of the standby load station.
[0125] This application also provides a computer program product, which, when executed on a data processing device, is further adapted to execute an initialization program having the following method steps: checking the state of the open-loop point and the bus voltage of the target load station, and determining the transmission test results of the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station based on the state of the open-loop point and the bus voltage of the target load station. The steps include: acquiring the circuit breaker position signal of the open-loop point, comparing the circuit breaker position signal with the closed switch position signal to obtain a first comparison result; collecting the target load station's... The bus voltage of the target load station is measured and compared with the fault bus voltage threshold to obtain a second comparison result. Based on the first and second comparison results, the transmission test results of the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station are determined. Among them, if the circuit breaker position signal indicated by the first comparison result is consistent with the closed switch position signal and the bus voltage is greater than the fault bus voltage threshold, it is determined that the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station have passed the transmission test.
[0126] Figure 6 This is a hardware structure block diagram of an electronic device (or mobile device) for a remote testing method of a 110kV automatic transfer switch transmission according to an embodiment of the present invention. Figure 6 As shown, an electronic device may include one or more ( Figure 6 The processor 602 (which may include, but is not limited to, a microprocessor MCU or a programmable logic device FPGA, etc.) and a memory 604 for storing data may also be included. In addition, it may include: a display, an input / output interface (I / O interface), a universal serial bus (USB) port (which may be included as one of the ports of the I / O interface), a network interface, a keyboard, a power supply, and / or a camera. Those skilled in the art will understand that... Figure 6 The structure shown is for illustrative purposes only and does not limit the structure of the electronic device described above. For example, the electronic device may also include components that are more... Figure 6 The more or fewer components shown, or having the same Figure 6 The different configurations shown.
[0127] The sequence numbers of the above embodiments of the present invention are for descriptive purposes only and do not represent the superiority or inferiority of the embodiments.
[0128] In the above embodiments of the present invention, the descriptions of each embodiment have different focuses. For parts not described in detail in a certain embodiment, please refer to the relevant descriptions of other embodiments.
[0129] In the several embodiments provided in this application, it should be understood that the disclosed technical content can be implemented in other ways. The device embodiments described above are merely illustrative; for example, the division of units can be a logical functional division, and in actual implementation, there may be other division methods. For instance, multiple units or components may be combined or integrated into another system, or some features may be ignored or not executed. Furthermore, the displayed or discussed mutual coupling, direct coupling, or communication connection may be through some interfaces; the indirect coupling or communication connection between units or modules may be electrical or other forms.
[0130] The units described as separate components may or may not be physically separate. The components shown as units may or may not be physical units; that is, they may be located in one place or distributed across multiple units. Some or all of the units can be selected to achieve the purpose of this embodiment according to actual needs.
[0131] Furthermore, the functional units in the various embodiments of the present invention can be integrated into one processing unit, or each unit can exist physically separately, or two or more units can be integrated into one unit. The integrated unit can be implemented in hardware or as a software functional unit.
[0132] If the integrated unit is implemented as a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, or all or part of the technical solution, can be embodied in the form of a software product. This computer software product is stored in a storage medium and includes several instructions to cause a computer device (which may be a personal computer, server, or network device, etc.) to execute all or part of the steps of the methods described in the various embodiments of the present invention. The aforementioned storage medium includes various media capable of storing program code, such as USB flash drives, read-only memory (ROM), random access memory (RAM), portable hard drives, magnetic disks, or optical disks.
[0133] The above description is only a preferred embodiment of the present invention. It should be noted that for those skilled in the art, several improvements and modifications can be made without departing from the principle of the present invention, and these improvements and modifications should also be considered within the scope of protection of the present invention.
Claims
1. A remote testing method for the transmission of a 110kV automatic transfer switch, characterized in that, A remote testing system for 110kV automatic transfer switch (ATS) drives, comprising at least a power grid dispatching platform and a data transmission and information security master station, and a remote testing method for the 110kV ATS drives, including: Identify the 110kV standby automatic transfer device to be tested, and determine the target load station, the nearest standby load station, and the nearest open-loop point of the 110kV standby automatic transfer device to be tested. Based on the power grid dispatching platform, transmission operation tickets are generated for the target load station and the standby load station, and the transmission operation tickets are sent to the main station of the power grid dispatching platform. The transmission operation ticket is executed based on the aforementioned security information main station; After the transmission operation ticket is executed, check the status of the open loop point and the bus voltage of the target load station. Based on the status of the open loop point and the bus voltage of the target load station, determine the transmission test results of the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station.
2. The method according to claim 1, characterized in that, The steps for executing the transmission operation ticket based on the aforementioned security information main station include: Based on the reclosing soft pressure plate of the high-voltage side bus circuit breaker of the target load station, the main station of the information security system exits the target load station; Based on the transmission command executed by the main station of the power supply and control system to the high-voltage side bus circuit breaker of the target load station, the high-voltage side bus circuit breaker of the target load station is opened.
3. The method according to claim 1, characterized in that, After the transmission operation ticket is executed based on the main station of the information security system, the following is also included: The execution result of the transmission operation ticket is determined based on the automatic switching action criterion; If the power system where the target load station and the standby load station are located meets the automatic transfer switch action criterion, the transmission operation ticket is determined to have been executed.
4. The method according to claim 3, characterized in that, The automatic transfer switch (ATS) operation criteria include at least one of the following: the circuit breaker position signal of the target load station is inconsistent with the closed switch position signal; the voltage signal of the bus in the power system other than the bus of the target load station satisfies the reclosing waveform; the negative sequence voltage of the bus in the power system other than the bus of the target load station is greater than the negative sequence voltage threshold of the fault bus in the target time period; and the zero sequence voltage of the bus in the power system other than the bus of the target load station is greater than the zero sequence voltage threshold of the fault bus in the target time period.
5. The method according to claim 1, characterized in that, After determining the target load station for the 110kV automatic transfer switch to be tested, the nearest standby load station, and the nearest open-loop point to the target load station, the process further includes: Check the working status of the protection device of the target load station, check the working status of the 110kV standby automatic transfer device of the target load station and check the working status of the 110kV standby automatic transfer device of the standby load station, and obtain the inspection results. If the inspection result indicates that the inspection has passed, an inspection pass signal is generated and sent to the power grid dispatching platform.
6. The method according to claim 5, characterized in that, The steps for checking the operational status of the protection devices at the target load station include: Check the operating status of the circuit breaker on the high-voltage side bus of the target load station. The operating status includes at least one of the following: the communication status between the circuit breaker and the target load station, the operating status of the circuit breaker, the alarm information of the circuit breaker, the charging status of the reclosing circuit breaker, the remote operation hard switch of the circuit breaker, the remote uninterruptible power transmission soft switch of the circuit breaker, and the remote activation / deactivation soft switch of the circuit breaker.
7. The method according to claim 5, characterized in that, The steps for checking the operating status of the 110kV automatic transfer switch at the target load substation include: Check the charging status of the 110kV standby automatic transfer device at the target load station; Check the alarm information regarding the operating status of the 110kV automatic transfer switch at the target load station; Compare the device data of the 110kV standby automatic transfer device of the target load station with the device data in the setting sheet; Check the activation / deactivation status of the soft pressure plate of the 110kV standby automatic transfer device at the target load station.
8. The method according to claim 5, characterized in that, The steps for checking the operating status of the 110kV automatic transfer switch of the standby load substation include: Check the charging status of the 110kV automatic transfer switch of the standby load station; Check the alarm information regarding the operating status of the 110kV automatic transfer switch of the standby load station; Compare the device data of the 110kV automatic transfer switch of the standby load station with the device data in the setting sheet; Check the activation / deactivation status of the soft pressure plate of the 110kV automatic transfer switch at the standby load station.
9. The method according to claim 1, characterized in that, The steps for checking the status of the open-loop point and the bus voltage of the target load station, and determining the transmission test results of the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station based on the status of the open-loop point and the bus voltage of the target load station include: Obtain the circuit breaker position signal at the open loop point, and compare the circuit breaker position signal with the closed switch position signal to obtain the first comparison result; The bus voltage of the target load station is collected, and the bus voltage is compared with the fault bus voltage threshold to obtain a second comparison result; Based on the first comparison result and the second comparison result, the transmission test results of the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station are determined. In the case that the first comparison result indicates that the circuit breaker position signal is consistent with the closed switch position signal and the bus voltage is greater than the fault bus voltage threshold, it is determined that the 110kV automatic transfer switch of the target load station and the 110kV automatic transfer switch of the standby load station have passed the transmission test.
10. A remote testing system for the transmission of a 110kV automatic transfer switch, characterized in that, include: The dispatching system is used to determine the 110kV standby automatic transfer device to be tested, and to determine the target load station affected by the 110kV standby automatic transfer device to be tested, the standby load station closest to the target load station, and the open loop point closest to the target load station. A power grid dispatching platform is used to generate transmission operation tickets for the target load station and the standby load station based on the power grid dispatching platform; The main station is used to receive transmission operation tickets issued by the power grid dispatching platform and execute the transmission operation tickets. An autonomous station is used to check the status of the open-loop point and the bus voltage of the target load station after the transmission operation ticket is executed, and to determine the transmission test results of the 110kV standby automatic transfer device of the target load station and the 110kV standby automatic transfer device of the standby load station based on the status of the open-loop point and the bus voltage of the target load station.
Citation Information
Patent Citations
Spare power automatic switching logic test method for verifying automatic switching modes of high voltage side buscouple switch
CN102023271A
Control method and device for spare power automatic switching device of transformer substation and storage medium
CN118137670A