Design method and system of portable pipeline integration unit, storage medium and computer program product

Through the design method of convenient pipeline integration unit, computer programs are used to divide pipelines in the construction factory to form the largest size integrated unit, which solves the construction efficiency and safety hazards caused by two-dimensional drawings and manual calculations in the existing technology, and realizes the problem of low construction efficiency and safety hazards caused by two-dimensional drawings and manual calculations. Efficient and accurate pipeline construction.

CN119203446APending Publication Date: 2024-12-27CHINA NUCLEAR IND FIFTH CONSTR CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411236635.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-04
Publication Date
2024-12-27

AI Technical Summary

Technical Problem

The existing pipeline engineering construction methods rely on two-dimensional drawings and manual calculations, making it difficult to visually display the three-dimensional structure, which leads to deviations when constructors understand design intentions, and lacks effective simulation and optimization methods, resulting in low construction efficiency, high cost and safety hazards. .

Method used

By designing a convenient pipeline integration unit, using computer programs to divide pipelines in the construction plant to form an integrated unit of the largest size, assemble and simulate construction in advance, ensuring the smoothness of transportation and installation, and reducing construction risks and costs.

Benefits of technology

It realizes efficient and precise design of pipeline integrated units, simplifies operating processes, reduces learning costs, improves design and construction efficiency, and reduces construction problems and risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119203446A_ABST
    Figure CN119203446A_ABST
Patent Text Reader

Abstract

The invention provides a design method and system of a portable pipeline integration unit, a storage medium and a computer program product. The design method of the portable pipeline integration unit is used for designing pipelines in a construction plant. The design method comprises the steps that at least one room in the construction plant is selected as a to-be-divided room; according to the position of the to-be-divided room, determining a transportation path of a pipeline of the to-be-divided room; determining the maximum size of the pipeline integration unit according to the transportation path and the to-be-divided room; and according to the maximum size, the pipelines in the to-be-divided room are divided, and at least one pipeline integration unit is formed. According to the design method, the pipeline manufacturing precision and efficiency can be improved, and the construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of pipeline design, and in particular to a design method, system, storage medium and computer program product of a portable pipeline integrated unit. Background Art

[0002] In terms of pipeline engineering construction technology, the existing pipeline engineering construction methods mainly rely on traditional two-dimensional drawings and manual calculations.

[0003] However, it is difficult for two-dimensional drawings to intuitively display the three-dimensional structure of the pipeline, which leads to deviations in the understanding of design intent and construction operations by construction personnel. Manual calculations are also prone to introduce errors, affecting construction quality and efficiency. In addition, traditional construction methods lack effective simulation and optimization methods, making it difficult to discover and solve problems that may arise during construction in advance, which leads to low construction efficiency and high costs, and there are certain safety hazards. There are still problems in integration and convenience. Therefore, the above-mentioned traditional pipeline engineering construction schemes have problems such as long design cycle, low precision, and easy errors. Summary of the invention

[0004] The object of the present invention is to provide a design method, system, storage medium and computer program product for a convenient pipeline integrated unit, which can improve the design and construction efficiency of pipeline projects.

[0005] One aspect of the present invention provides a method for designing a portable pipeline integrated unit, which is used for designing pipelines in a construction plant. The method comprises: selecting at least one room in the construction plant as a room to be divided; determining a transportation path for the pipelines in the room to be divided according to the location of the room to be divided; determining a maximum size of the pipeline integrated unit according to the transportation path and the room to be divided; and dividing the pipelines in the room to be divided according to the maximum size to form at least one pipeline integrated unit.

[0006] In one embodiment, determining the maximum size of the pipeline integration unit based on the transportation path and the rooms to be divided includes: determining the maximum width and maximum height of the pipeline integration unit based on door openings of the rooms to be divided; determining the maximum length of the pipeline integration unit based on the transportation path; and using the maximum length, the maximum width, and the maximum height as the maximum size of the pipeline integration unit.

[0007] In one embodiment, determining the maximum length of the pipeline integrated unit based on the transport path includes: obtaining the action type of the pipeline integrated unit within the transport path; and determining the maximum length of the pipeline integrated unit in combination with the action type of the pipeline integrated unit and the transport path.

[0008] In one embodiment, the obtaining of the movement type of the pipeline in the transportation path comprises at least one of translation, horizontal rotation, vertical flipping and horizontal turning.

[0009] In one embodiment, dividing the pipes in the room to be divided according to the maximum size to form at least one pipe integrated unit includes: determining the pipe division order according to the structure of the room to be divided; dividing the pipes in the room to be divided in combination with the division order and the maximum size; and integrating the divided pipes with corresponding pipe accessories to form at least one pipe integrated unit.

[0010] In one embodiment, the pipeline division order is determined according to the structure of the room to be divided, including: if the room to be divided is a non-annular room, the pipeline division order is determined to be wall-ceiling-floor according to each surface of the room to be divided; within each surface of the room to be divided, the pipeline division order is determined to be integrated layout area-parallel pipe section-scattered pipe section.

[0011] In one embodiment, determining the pipeline division order according to the structure of the room to be divided includes: if the room to be divided is an annular room, dividing the room to be divided into multiple sectors; in each sector of the room to be divided, determining the pipeline division order as radial-normal.

[0012] In one embodiment, determining the order of dividing the pipes according to the structure of the room to be divided further includes: dividing the pipes into large-diameter pipes and small-diameter pipes according to the pipe diameters of the pipes.

[0013] Another aspect of the present invention provides a design system for a portable pipeline integrated unit, comprising a memory, a processor and a computer program stored in the memory, wherein the processor executes the computer program to implement the steps of the design method for a portable pipeline integrated unit as described in any one of the above embodiments.

[0014] Another aspect of the present invention provides a storage medium for storing non-transitory computer instructions, which, when executed, executes the steps of the method for designing a portable pipeline integrated unit as described in any one of the above embodiments.

[0015] Another aspect of the present invention provides a computer program product, including a computer program, which, when executed by a processor, implements the steps of the method for designing a portable pipeline integrated unit as described in any one of the above embodiments.

[0016] The design method of the portable pipeline integrated unit of the present invention forms pipeline integrated units by dividing the pipeline. Under the premise of not changing the design minimum delivery unit, the three-dimensional pipeline integration design is integrated on a portable unit module. The pipeline assembly process can be performed before the pipeline is hoisted to the construction plant, and the pipeline integrated unit can be prefabricated to discover and solve problems in advance, ensure smooth transportation and installation, reduce construction risks and costs, and thus avoid construction problems after the pipeline is transported to the construction plant. The present invention can realize efficient and accurate design of pipeline integrated units, simplify operation procedures, reduce learning costs, improve design accuracy and efficiency, and improve the design and construction efficiency of pipeline projects. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The above and other features, properties and advantages of the present invention will become more apparent through the following description in conjunction with the accompanying drawings and embodiments, in which:

[0018] Figure 1 It is a flow chart of an embodiment of a method for designing a portable pipeline integrated unit according to the present invention;

[0019] Figure 2 is a flow chart of another embodiment of a method for designing a portable pipeline integrated unit according to the present invention;

[0020] Figure 3 yes Figure 2 A schematic diagram of a horizontal turn in the action type of the pipeline integration unit in step S321 of the design method shown;

[0021] Figure 4 yes Figure 2 A schematic diagram of the division process of a non-annular room of the design method shown;

[0022] Figure 5 yes Figure 2 A schematic diagram of the division process of the annular room of the design method shown;

[0023] Figure 6 It is a schematic diagram of a statistical list of the portable pipeline integrated unit of the present invention. DETAILED DESCRIPTION

[0024] Reference will now be made in detail to embodiments of the present invention, one or more examples of which are illustrated in the accompanying drawings. Each example is provided to explain the present invention, not to limit the present invention. In fact, it will be apparent to those skilled in the art that various modifications and variations may be made in the present invention without departing from the scope or spirit of the present invention. For example, a feature illustrated or described as part of one embodiment may be used together with another embodiment to produce yet another embodiment. Therefore, the present invention is intended to cover these modifications and variations within the scope of the appended claims and their equivalents.

[0025] In terms of pipeline engineering construction technology, the existing pipeline engineering construction methods mainly rely on traditional two-dimensional drawings and manual calculations, but there are the following problems:

[0026] First, although the existing 3D pipeline design software can realize 3D modeling and design of pipelines to a certain extent, it still needs to be improved in terms of integration and convenience. Existing software often has cumbersome functions and complex operations. For non-professional users, the learning cost is high and it is difficult to get started quickly. At the same time, the existing software also has certain limitations in data output, model transfer, etc., and cannot meet the actual needs of the project.

[0027] Secondly, the traditional pipeline construction method mainly relies on two-dimensional drawings and manual calculations, which have problems such as long design cycle, low precision, and easy errors. Two-dimensional drawings cannot intuitively display the three-dimensional structure of the pipeline, which leads to deviations in the understanding of design intent and construction operations by construction personnel. In addition, manual calculations are also prone to introduce errors, affecting construction quality and efficiency.

[0028] Finally, the existing pipeline construction methods lack effective simulation and optimization methods. During the construction process, it is often difficult to discover and solve possible problems in advance, resulting in increased construction risks and rising costs. At the same time, due to the lack of effective optimization methods, it is difficult to further improve construction efficiency.

[0029] Figure 1 The flowchart of an embodiment of the design method of the convenient pipe integrated unit of the present invention is shown. The design method of the convenient pipe integrated unit (CPIU module, pipe integrated unit and unit) of the present invention is used to design pipes in a construction plant, and can be applied to the pipe design of a nuclear power construction room. The design method of the present invention includes steps S100 to S400:

[0030] In step S100, at least one room in a construction plant is selected as a room to be divided.

[0031] In step S200, the transportation path of the pipes of the rooms to be divided is determined according to the locations of the rooms to be divided.

[0032] In step S300, the maximum size of the pipeline integration unit is determined according to the transportation route and the rooms to be divided.

[0033] In step S400, the pipelines in the room to be divided are divided according to the maximum size to form at least one pipeline integrated unit. The designer divides the pipelines in each room (or area) and divides all process pipelines in each room into several units.

[0034] The design method of the portable pipeline integrated unit of the present invention forms pipeline integrated units by dividing the pipeline. Under the premise of not changing the design minimum delivery unit, the three-dimensional pipeline integration design is integrated on a portable unit module. The pipeline assembly process can be performed before the pipeline is hoisted to the construction plant, and the pipeline integrated unit can be prefabricated to discover and solve problems in advance, ensure smooth transportation and installation, reduce construction risks and costs, and thus avoid construction problems after the pipeline is transported to the construction plant. The present invention can realize efficient and accurate design of pipeline integrated units, simplify operation procedures, reduce learning costs, improve design accuracy and efficiency, and improve the design and construction efficiency of pipeline projects.

[0035] In step S100, the designer determines the rooms to be divided. A room can be regarded as a division object, which serves as the basis for subsequent pipeline division.

[0036] Figure 2 Another embodiment of the design method of the present invention is shown. It is understandable that the maximum size of the pipeline integrated unit will be limited by the channel size on the transportation path. In one embodiment, step S300 further includes steps S310 to S330 to determine the maximum size (including maximum length, maximum width and maximum height) of the pipeline integrated unit:

[0037] In step S310, the maximum width and the maximum height of the pipeline integration unit are determined according to the door openings of the rooms to be divided.

[0038] The width of the pipeline integration unit is the width of the door opening of the room to be divided minus 250mm, which specifically includes a net width of 50mm on the left and right sides and a thickness of 150mm for the tooling.

[0039] The height of the pipeline integration unit is the height of the door opening of the room to be divided minus 150mm, which specifically includes the 50mm clearance above the unit and the 100mm thickness of the tooling at the bottom of the unit.

[0040] If the above maximum size is not conducive to the division of pipes, the room door opening can be considered for permanent expansion or secondary pouring. Specifically, the width of the room door opening can be adjusted to match the width of the pipe integration unit, and correspondingly, the height of the room door opening can be adjusted to match the height of the pipe integration unit. The specific door opening width adjustment and door opening height adjustment can be determined according to actual conditions. The above structural changes such as permanent expansion or secondary pouring of room door openings need to be funded by the structural professionals.

[0041] In step S320, the maximum length of the pipeline integration unit is determined according to the transportation path. Further, step S320 includes steps S321 to S322:

[0042] In step S321, the action type of the pipeline integration unit in the transportation path is obtained, wherein the action type includes at least one of translation, horizontal rotation, vertical flipping and horizontal turning.

[0043] The translation of the pipeline integrated unit means that the unit moves in a straight line, including vertical descent from the lifting hole and forward along the channel. Horizontal rotation means that the unit rotates horizontally around a point. Vertical flip means that the unit rotates vertically around a point in the vertical plane. Horizontal turning means that the unit turns from one channel to another. Figure 3 As shown, taking horizontal turning as an example, the pipeline integrated unit will be restricted in making horizontal turns at the bends of the channel in the transportation path.

[0044] In step S322, the maximum length of the pipeline integration unit is determined in combination with the action type and the transportation path of the pipeline integration unit.

[0045] In step S330, the maximum length, the maximum width, and the maximum height are taken as the maximum dimensions of the pipeline integration unit.

[0046] The construction site can determine the length limit of each action on the unit by laying out the lines, and determine the height of the unit. The size of the pipeline integration unit is limited by the size of long-distance transportation and manufacturing capacity. It is not recommended to exceed 12m×2.5m×2.5m, which is the maximum size. Of course, the specific size is determined by actual analysis or calculation.

[0047] If the divided pipeline integration unit is still larger than the above maximum size, considering its large size, the pipeline integration unit can be regarded as a large equipment for subsequent lifting.

[0048] In one embodiment, step S400 further includes steps S410 to S430, which are intended to divide the pipeline in an orderly manner through a certain division sequence:

[0049] In step S410, the order of dividing the pipelines is determined according to the structure of the room to be divided. According to the structure of the room to be divided, it can be divided into a non-annular room and annular room. Step S410 includes the following steps:

[0050] First, it is necessary to determine whether the room to be divided is a non-annular room or annular room, that is, in step S410-a, determine whether the room to be divided is annular room.

[0051] In step S411, if the room to be divided is a non-annular room, the order of pipe division is determined to be wall-ceiling-ground according to the surfaces of the room to be divided. Since the pipes in a room are mostly arranged against the wall, for a room in a rectangular shape (i.e., non-annular), the division should start from the pipes near the wall, and then consider the pipes arranged along the ceiling and the ground.

[0052] In step S412, within each surface of the room to be divided, the order of pipe division is determined to be integrated layout area - parallel pipe segments - scattered pipe segments.

[0053] Specifically, when dividing each surface of the room, the division is performed in the order of step S412, that is, when dividing each surface of the room, the integrated pipelines should be considered first, then the parallel pipelines should be considered, and finally the scattered pipe sections should be considered, such as Figure 4 shown.

[0054] In step S413, if the room to be divided is an annular room, the room to be divided is divided into a plurality of sectors. The annular room (or pipe gallery) can be divided into six sectors (0°-60°, 60°-120°, 120°-180°, 180°-240°, 240°-300°, 300°-360°) for further division.

[0055] In step S414, in each sector of the room to be divided, the pipeline division order is determined to be radial-normal. Since the process pipeline arrangement in the annular room area is usually divided into pipelines arranged along the radial direction and pipelines arranged along the normal direction, the division is carried out according to the order in step S414, such as Figure 5 As shown in the figure, the radial direction is the direction passing through the center of the annular room, and the normal direction is the tangent direction of the outer edge of the annular room.

[0056] Among them, steps S411 to S412 and steps S413 to S414 are parallel steps. If it is determined that the room to be divided is one of a non-annular room and an annular room, the corresponding steps are executed.

[0057] In one embodiment, step S410 further includes step S415:

[0058] In step S415, the pipelines are divided into large-diameter pipelines and small-diameter pipelines according to the diameter of the pipelines. According to the relevant provisions of hoisting, large-diameter pipelines refer to pipelines larger than 2 inches, and small-diameter pipelines refer to pipelines smaller than 2 inches.

[0059] The execution order of step S415 is not limited to after S412 or S414, and can be adjusted according to actual conditions. That is, the pipes are first divided according to the pipe diameters, and then the structure of the room to be divided is determined to execute steps S411 to S412 or steps S413 to S414. Figure 2 shown.

[0060] In step S420, the pipes in the room to be divided are divided according to the division order and the maximum size.

[0061] In step S430, the divided pipelines are integrated with corresponding pipeline accessories to form at least one pipeline integrated unit. The pipeline accessories include but are not limited to instruments, valves and flanges. Based on the maximum size of the pipeline integrated unit calculated in step S330, the designer divides the pipelines in the room, sets field welds or factory welds on the pipeline 3D model, and divides the pipelines into units.

[0062] The division principles of the pipeline integrated units of the present invention include the overall principle and the construction feasibility principle. Among them, the overall principle includes: 1) The pipe section within the unit should be located in a plane; if there is a pipeline beyond the plane, the excess length cannot exceed the predetermined height value. 2) When the diameter of the main pipe is 4 times larger than the diameter of the branch pipe, it should be disconnected into different units. However, pipelines with instrument root valves are excluded. The construction feasibility principle includes: 1) The installation logic should be set in the order of "from inside to outside, from high to low" to ensure the feasibility of the division plan. Ensure the feasibility of introducing units outside the transportation path (or the starting end). 2) When setting on-site welds, ensure that there is enough operating space for welding and non-destructive testing. 3) The division of units needs to take into account the layout of process equipment such as tanks, heat exchangers, and pumps, and their introduction and placement must not be affected by the equipment. 4) The construction logic of the unit should comprehensively consider the introduction of other professions such as ventilation, cables and equipment.

[0063] After step S430, the design method of the present invention may further include the following steps:

[0064] According to the preliminary installation logic, the order of introduction and installation of units in the room is explained, and the order of introduction and installation of each unit is marked with serial numbers for reference in design optimization. A preliminary list of data such as pipes, valves, and welds contained in each unit is also compiled.

[0065] After the design selection is completed, the designers will verify and optimize the selection results, and optimize the units based on the actual manufacturing, hoisting, transportation, installation and other capabilities of the project site, pressure testing, purging and flushing, etc., and submit the results to the project for corresponding evaluation to achieve the purpose of successful installation on site. Among them, some optimization projects are as follows:

[0066] 1) Instrument parts that do not participate in pipeline-related tests will not be integrated.

[0067] 2) Pipe caps, ray plugs, quick connectors (welding), etc. are installed only after pressure testing and flushing and do not participate in integration.

[0068] 3) Online components (welded form) that cannot participate in the flushing test, such as some steam traps (PU), control valves (cage-type control valves, three-way control valves, needle control valves, back pressure control valves, manual single-seat control valves), shut-off valves, breathing valves, safety valves, electric valves, pneumatic valves, etc., will not be integrated if they are welded. However, components that can be tested through core pulling and other schemes can be integrated according to the actual situation of the project.

[0069] 4) Before integrating valves and online components without flanges on the isometric drawing, it is necessary to determine the equipment / valve type and whether it has a matching flange (check the valve / equipment drawing). For valves and online components with matching flanges, the equipment body / valve body should be determined to be integrated based on its weight and pressure test and flushing requirements.

[0070] 5) The flow orifice plate (KD) and other integrally supplied equipment do not participate in the pressure test (the pressure test has been completed before leaving the factory). Among them, the "Venturi tube" type is a multi-stage orifice plate that cannot be integrated, while other types can participate in the integration and no special remarks are required.

[0071] 6) In general, the length of small branch pipes is short and there are not too many turns. The on-site port is set by default with the main pipe through the connecting socket. The integration is considered on site based on the direction, quantity, size, length, weight of the main pipe, space factors, etc. The integration location belongs to the prefabrication plant or on-site workshop.

[0072] 7) Flange-connected equipment and valves can be normally integrated into the corresponding flanges. The equipment should be considered whether to integrate the main body based on weight and protection needs; especially for some equipment that does not participate in pressure testing or flushing, it only needs to be integrated into the equipment flange.

[0073] 8) The length of on-site pipelines generally does not exceed 6 meters. The transportation weight is determined based on the transportation machinery and lifting tools, and relevant verification is carried out in advance.

[0074] 9) Based on the division of the on-site construction plan, try to distinguish between on-site nuclear-grade pipelines and non-nuclear-grade pipelines.

[0075] After the CPIU optimization of each layer is completed, the designer should first analyze the size, shape and weight of each layer unit, and then carry out the corresponding tooling design based on the results.

[0076] The designed tooling must meet the requirements of temporary support for CPIU during prefabrication, transportation, and installation, while ensuring the convenience of CPIU transportation. The specific requirements are as follows: 1) Structural versatility: The components of the portable tooling are easy to adjust. A portable tooling can meet the support requirements of multiple integrated units. The corresponding tooling can be designed according to different pipe diameters and weight ranges. At the same time, the tooling materials should be mainly auxiliary materials commonly found on site. Avoid structural and complex situations. 2) Flexible disassembly and assembly: The various components of the portable tooling (steel, pipe clamps) can be flexibly disassembled and recombined to meet the support requirements of integrated units of different shapes. 3) Easy to load and unload: The fixation of the unit and the tooling should be firm and reliable to avoid looseness and sliding. Under the premise of ensuring reliability, try to use quick-open pipe clamps to facilitate the loading and unloading requirements of the integrated unit.

[0077] After the formal division of the pipeline is completed, the pipelines, valves and welds contained in each unit are counted and provided to the project for corresponding preparatory work, including but not limited to the list of materials, unit introduction channel and unit model, drawings (isometric drawings, three-view drawings, etc., if necessary) and other results.

[0078] Figure 6 The CPIU statistical list is shown. Among them, the unit data table contains four types of information, namely room information, unit overall information, unit item information and unit weld statistics, which can be modified according to the actual needs of the project. The room information includes the room number, introduction size limit, introduction path and civil engineering change requirements. The unit overall information includes the unit number, unit size, and the upstream and downstream interface relationship of the unit. The item information contained in the unit includes the model number and the special item position number corresponding to each model (valves, flow limiting orifices, etc.). The unit weld statistics include the number of prefabricated welds and on-site welds for each model, the number of prefabricated welds and on-site welds for the entire unit, and the proportion of prefabricated welds in the unit.

[0079] The present invention aims to provide a convenient pipeline integrated unit design method, which integrates the three-dimensional pipeline design into a convenient unit module without changing the design of the minimum delivery unit, completes the relevant process review through software, and outputs the handover model, data, module number, positioning mark, material list, weld list, transportation path, construction logic chart, etc., which can extract the main and auxiliary material data for unloading, assembly, welding and inspection in the factory or workshop. After manufacturing is completed, the efficient and accurate construction of the pipeline project is achieved by simulating construction logic, assembly and disassembly, hoisting and transportation tooling / equipment, transportation path, channel inspection function, finished product storage, arrival tracking and guiding on-site construction. The specific technical scheme is as follows:

[0080] A pipeline integrated unit model is established using 3D design software, which includes detailed information such as the structure, size, and material of the pipeline.

[0081] Conduct process review on the piping integration unit model in the software to ensure that the design meets engineering requirements and specification standards.

[0082] Output handover model, data, module number, location mark, material list, weld list, transportation route, construction logic diagram and other information for subsequent manufacturing and construction.

[0083] Extract main and auxiliary material data from the model for the factory or workshop to carry out cutting, assembly, welding and inspection.

[0084] After manufacturing is completed, software is used to simulate construction logic, assembly and disassembly, hoisting and transportation of tooling / equipment, transportation routes, channel inspection functions, finished product storage and other processes to ensure smooth construction.

[0085] The software can track the arrival of goods and guide on-site construction to achieve efficient management of pipeline projects.

[0086] The design method of the portable pipeline integrated unit of the present invention utilizes three-dimensional construction software to realize the design, review, data output, manufacturing simulation and construction guidance of the pipeline integrated unit, simplifies the operation process, and improves the design accuracy and efficiency. At the same time, by simulating the construction logic and process, problems are discovered and solved in advance, and construction costs and risks are reduced. The method aims to realize the efficient and accurate design of pipeline integrated units through three-dimensional design software, simplify the operation process, and reduce learning costs. At the same time, by optimizing the data output and model handover functions, the actual needs of the project are met. In addition, the present invention also simulates the construction logic and process to discover and solve problems in advance, thereby reducing construction risks and costs. Ultimately, the goal of the present invention is to improve the design and construction efficiency of pipeline projects and promote technological progress in the industry.

[0087] The design system of the portable pipeline integrated unit of the present invention includes a memory, a processor and a computer program stored in the memory, and the processor executes the computer program to implement the steps of the design method of the portable pipeline integrated unit of any of the above embodiments.

[0088] The storage medium of the present invention is used to store non-transitory computer instructions. When the non-transitory computer instructions are executed, the steps of the design method of the portable pipeline integrated unit of any of the above embodiments are executed.

[0089] The computer program product of the present invention includes a computer program, which, when executed by a processor, implements the steps of the method for designing a portable pipeline integrated unit of any of the above-mentioned embodiments.

[0090] Embodiments of the subject matter described in this specification may be implemented as one or more computer programs, i.e., one or more modules of computer program instructions encoded on a tangible, non-transitory program carrier to be executed by a data processing apparatus or to control the operation of the data processing apparatus. Alternatively or additionally, the program instructions may be encoded on an artificially generated propagated signal, such as a machine-generated electrical, optical, or electromagnetic signal, which is generated to encode information and transmit it to a suitable receiver apparatus for execution by the data processing apparatus.

[0091] The computer storage medium may be a machine-readable storage device, a machine-readable storage substrate, a random or serial access memory device, or a combination of one or more of them.

[0092] Computers suitable for executing computer programs include, for example, general and / or special microprocessors, or any other type of central processing unit. Typically, the central processing unit will receive instructions and data from a read-only memory and / or a random access memory. The basic components of a computer include a central processing unit for implementing or executing instructions and one or more memory devices for storing instructions and data. Typically, the computer will also include one or more large-capacity storage devices for storing data, such as magnetic disks, magneto-optical disks, or optical disks, or the computer will be operably coupled to this large-capacity storage device to receive data from it or to transmit data to it, or both. However, the computer does not necessarily have such a device. In addition, the computer can be embedded in another device, such as a mobile phone, a personal digital assistant (PDA), a mobile audio or video player, a game console, a global positioning system (GPS) receiver, or a portable storage device such as a universal serial bus (USB) flash drive, to name a few.

[0093] Computer readable media suitable for storing computer program instructions and data include all forms of non-volatile memory, media and memory devices, including, for example, semiconductor memory devices (e.g., EPROM, EEPROM and flash memory devices), magnetic disks (e.g., internal hard disks or removable disks), magneto-optical disks, and CD ROM and DVD-ROM disks. The processor and memory may be supplemented by, or incorporated in, special purpose logic circuitry.

[0094] Although the present invention is disclosed as above with preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art may make possible changes and modifications without departing from the spirit and scope of the present invention. Therefore, any modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present invention shall fall within the protection scope defined by the claims of the present invention.

Claims

1. A method for designing a portable pipeline integrated unit, used for designing pipelines in a construction plant, characterized in that: The design method comprises: Select at least one room in the construction plant as a room to be divided; Determining the transportation path of the pipeline of the room to be divided according to the location of the room to be divided; Determining the maximum size of the pipeline integration unit according to the transportation path and the rooms to be divided; According to the maximum size, the pipes in the room to be divided are divided to form at least one pipe integration unit.

2. The design method according to claim 1, characterized in that: The step of determining the maximum size of the pipeline integration unit according to the transportation path and the rooms to be divided includes: Determine the maximum width and maximum height of the pipeline integration unit according to the door openings of the rooms to be divided; Determining the maximum length of the pipeline integration unit according to the transportation path; The maximum length, the maximum width and the maximum height are taken as the maximum dimensions of the pipeline integration unit.

3. The design method according to claim 2, characterized in that: The step of determining the maximum length of the pipeline integrated unit according to the transport path includes: Acquire the action type of the pipeline integration unit within the transportation path; The maximum length of the pipeline integration unit is determined in combination with the action type of the pipeline integration unit and the transportation path.

4. The design method according to claim 3, characterized in that: The action type of obtaining the pipeline within the transportation path, wherein: The action type includes at least one of translation, horizontal rotation, vertical flip and horizontal turn.

5. The design method according to claim 1, characterized in that: The step of dividing the pipes in the room to be divided according to the maximum size to form at least one pipe integration unit comprises: Determine the order of dividing the pipelines according to the structure of the room to be divided; Divide the pipes in the room to be divided according to the division order and the maximum size; The divided pipelines are integrated with corresponding pipeline accessories to form at least one pipeline integrated unit.

6. The design method according to claim 5, characterized in that: The step of determining the order of dividing the pipelines according to the structure of the room to be divided includes: If the room to be divided is a non-annular room, the order of dividing the pipes is determined to be wall-ceiling-floor according to the surfaces of the room to be divided; In each surface of the room to be divided, the order of pipe division is determined as integrated layout area - parallel pipe sections - scattered pipe sections.

7. The design method according to claim 5, characterized in that: The step of determining the order of dividing the pipelines according to the structure of the room to be divided includes: If the room to be divided is a ring-shaped room, the room to be divided is divided into a plurality of sectors; In each sector of the room to be divided, the pipeline division order is determined to be radial-normal.

8. The design method according to claim 6 or 7, characterized in that: The step of determining the order of dividing the pipelines according to the structure of the room to be divided further comprises: According to the diameter of the pipeline, the pipeline is divided into large-diameter pipeline and small-diameter pipeline.

9. A design system for a portable pipeline integrated unit, characterized in that: The invention comprises a memory, a processor and a computer program stored in the memory, wherein the processor executes the computer program to implement the steps of the method for designing a portable pipeline integrated unit as described in any one of claims 1 to 8.

10. A storage medium, characterized in that: Used to store non-transitory computer instructions, when the non-transitory computer instructions are executed, the steps of the design method of the portable pipeline integrated unit as described in any one of claims 1-8 are executed.

11. A computer program product, comprising a computer program, characterized in that When the computer program is executed by a processor, the steps of the method for designing a portable pipeline integrated unit as described in any one of claims 1 to 8 are implemented.

Citation Information

Patent Citations

  • Discrete prefabricated distributed construction method for high-density refrigerating machine room

    CN113293998A

  • Pipeline installation method in nuclear power construction

    CN114251514A

  • Pipeline module division method for electromechanical installation stage

    CN114969919A

  • Visual nuclear power pipeline division method and system

    CN115810085A

  • Room planning system and method

    US20190171779A1