A module sliding installation structure and usage method for offshore suspended cable photovoltaic

Through the module slip installation structure, the trolley is installed using the slip cable pillars, the slip cables and the slip, combined with the power lifting device and the electric bolt fastener, the automatic installation of the offshore photovoltaic module is realized, solving the problems of low installation efficiency, poor safety and high cost in the existing technology, and achieving a fast, safe and economical installation effect.

CN119276207BActive Publication Date: 2025-06-20POWERCHINA HUADONG ENG CORP LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310826046.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-07-06
Publication Date
2025-06-20
Estimated Expiration
2043-07-06

AI Technical Summary

Technical Problem

The existing offshore photovoltaic power generation installation technology is inefficient and has poor safety, high installation costs, and difficult transportation ships to operate at sea, resulting in low installation efficiency.

Method used

The module slip installation structure is adopted, including slip cable pillars, slip cables and slip installation trolleys. The automatic installation of the photovoltaic module is achieved through power lifting devices and electric bolt fasteners to avoid manual operation.

Benefits of technology

It realizes rapid, safe and economical photovoltaic module installation, improves installation efficiency, reduces installation costs, and avoids the difficulty of transport ships shifting at sea.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119276207B_ABST
    Figure CN119276207B_ABST
Patent Text Reader

Abstract

The present invention provides a module sliding installation structure for offshore suspended cable photovoltaic power generation, which includes sliding cable struts, sliding cables and sliding installation trolleys. The sliding cable struts are detachably connected to the pile head structures on the tops of pile foundations. The sliding cable struts are distributed around the photovoltaic module components to enclose an overall operation area. The sliding cables are connected between the sliding cable struts along the direction of the load-bearing cables. The sliding installation trolleys are arranged on the sliding cables, and power lifting devices that can be connected to the photovoltaic brackets on the photovoltaic module components are arranged inside the trolleys. By arranging the sliding cables above the load-bearing cables and using the lifting devices of the sliding installation trolleys to lift the photovoltaic module components, the two are combined to form a combined body and move along the sliding cables together. Therefore, the horizontal transportation of the photovoltaic module components does not require the displacement of a transport ship, and rapid and efficient transportation can be achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of offshore photovoltaic power generation, and particularly to a module sliding installation structure and a usage method for offshore suspension photovoltaic. Background Art

[0002] As more and more coastal provinces in China turn their attention to the ocean in the photovoltaic power generation market, offshore photovoltaic power generation, as a new field, has a broad market. How to achieve safe, economical and reliable installation of offshore photovoltaic structures has become one of the key technologies restricting the development of offshore photovoltaics.

[0003] The existing technologies close to the present invention are the manual installation technology of flexible support components and the construction cable hoisting installation technology of offshore suspension photovoltaics. The manual installation technology of flexible support components is to manually transport individual photovoltaic modules to the cable structure. The installation workers simultaneously rise to the installation position with the help of scaffolding or a scissor lift, and then manually install and fix the module to the cable structure. The construction cable hoisting installation technology of offshore suspension photovoltaics is to set a cable crane on the construction cable, transport the module to the lower part of the installation position by ship, the cable crane hoists the module to the installation position, the installation workers reach the installation position by means of a pedestrian cable, and then manually install and fix the module to the cable structure. The traditional installation technologies have the following defects:

[0004] (1) Whether it is the manual installation technology of flexible support components or the construction cable hoisting installation technology of offshore suspension photovoltaics, the installation workers need to reach the installation position and then manually install and fix the module to the cable structure. The manual installation method has low efficiency, poor safety and high installation costs.

[0005] (2) The manual installation technology requires manual transportation of components, which is difficult, costly and has a high safety risk in offshore operations and is not feasible; although the construction cable hoisting installation technology can use a cable crane for hoisting, the transport ship needs to reach the lower part of the installation position. In this way, the transport ship needs to be continuously displaced during the installation process, and the displacement of the transport ship needs to be achieved by winching the anchor. However, there are many piles and the pile positions are dense in the offshore photovoltaic field area, and the displacement operation of the transport ship is difficult and time-consuming, resulting in low installation efficiency. Summary of the Invention

[0006] The first object of the present invention is to provide a module sliding installation structure that can be automatically, quickly and safely installed without manual operation when connecting the block and the cable. For this purpose, the present invention adopts the following technical solutions:

[0007] A module sliding installation structure for offshore suspended cable photovoltaic power generation, comprising sliding cable supports, sliding cables, and sliding installation trolleys. The sliding cable supports are detachably connected to the pile head structure on the top of the pile foundation piles. The sliding cable supports are distributed around the photovoltaic module to enclose an overall working area. The sliding cables are connected between the sliding cable supports along the direction of the load-bearing cable. The sliding installation trolleys are arranged on the sliding cables, and a power lifting device that can be connected to the photovoltaic brackets on the photovoltaic modules is arranged inside. A groove is formed at the bottom of the sliding installation trolley, and the opening direction of the groove corresponds to the load-bearing cable. An electric bolt fastener that can cooperate with the bolts on the photovoltaic brackets is arranged in the groove. A cavity is arranged on the side wall of the groove, and an upper pressing block that can be automatically moved out is received in the cavity. The upper pressing block can also be connected and cooperated with the bolts, so that the photovoltaic module is firmly connected to the load-bearing cable through the upper pressing block.

[0008] Furthermore: The sliding installation trolleys are independently arranged on each sliding cable, and steel beams are connected between adjacent sliding installation trolleys to form an overall sliding structure.

[0009] Furthermore: A receiving body is arranged at the bottom of the sliding installation trolley, and the groove is accommodated inside the receiving body. A power wheel is arranged below the sliding installation trolley, and the power wheel is arranged in a staggered manner with the receiving body. At the same time, the power wheel is connected to the sliding cable, so that the sliding installation trolley moves along the cable direction on the sliding cable.

[0010] Furthermore: A spring is connected and arranged on the inner side wall of the cavity. The spring is located between the inner side wall of the cavity and the upper pressing block, and an electric door is arranged at the outlet position of the cavity.

[0011] Furthermore: A telescopic motor is arranged in the groove, and the telescopic motor is connected to the electric bolt fastener. The bolt is arranged on the photovoltaic bracket, and a connection hole for the bolt to pass through is formed through the upper pressing block. The electric bolt fastener can cooperate with the bolt, so that the upper pressing block is fixed through the bolt when connected to the photovoltaic bracket.

[0012] Furthermore: The power lifting device includes a cable and a winch. The winch is installed in the sliding installation trolley. One end of the cable is connected to the winch, and the other end extends out of the sliding installation trolley and is connected to the photovoltaic bracket.

[0013] Furthermore: The pile head structure includes a hanging plate arranged on the top of the pile foundation pile and a pin column. The pin column is connected to the hanging plate, and an upper pin column is arranged on the part of the pin column extending above the hanging plate. The sliding cable support is sleeved on the upper pin column.

[0014] Further: a pillar hanging plate is arranged on the outer surface of the sliding cable pillar, and the pillar hanging plate is connected to the sliding cable.

[0015] Further: the distance between adjacent sliding cables is greater than the distance between adjacent load-bearing cables, so as to facilitate the operation of the photovoltaic module.

[0016] The second object of the present invention is to provide a use method with fast and efficient, good safety and low installation cost. For this purpose, the present invention adopts the following technical solutions:

[0017] A use method of a module sliding installation structure for offshore suspension photovoltaic includes the following steps:

[0018] S1: The required photovoltaic module is processed and manufactured in an onshore factory, transported to the installation sea area by a transport ship, and is close to one side of the pile foundation;

[0019] S2: Install the required sliding cable pillar on the pile head structure at the top of the photovoltaic pile foundation, and carry out fastening connection, and install the sliding cable on the pillar hanging plate of the sliding cable pillar;

[0020] S3: The sliding installation trolley is installed on the sliding cable and connected by the steel beam to keep the relative positions of the two sliding installation trolleys unchanged;

[0021] S4: The photovoltaic module located on the transport ship is connected to the sliding installation trolley through the cable, and the upper pressing block is placed in the cavity on the side wall of the groove under the sliding installation trolley, and the electric door is closed;

[0022] S5: Start the winch to lift the photovoltaic module to a certain height, remotely control the driving wheel of the sliding installation trolley to move along the direction of the sliding cable to the installation position, and brake the driving wheel;

[0023] S6: Recover the cable to pull the photovoltaic module, align the position of the bolt with the electric bolt tightening device, open the electric door to eject the upper pressing block by the spring, make it pass through the bolt and fall on the photovoltaic bracket, and realize automatic installation of the block cable through the coordinated work of the telescopic motor and the electric bolt tightening device;

[0024] S7: Repeat the installation layout to successively install the remaining photovoltaic modules to the target installation positions on the load-bearing cable, and remove the upper operation structure after the installation of the photovoltaic modules is completed.

[0025] Compared with the prior art, the present invention has the following beneficial effects:

[0026] In the present invention, a sliding cable is arranged above the load-bearing cable, and a sliding installation trolley lifts a photovoltaic module through a lifting device, so that the two are combined to form a composition body and move along the sliding cable together. Therefore, the horizontal transportation of the photovoltaic module does not require the displacement of a transport ship, and rapid and efficient transportation can be achieved. Moreover, the electric bolt fastener at the bottom of the sliding installation trolley corresponds to the cable connection position of the block, and automatic installation can be carried out after the sliding installation trolley carries the photovoltaic module to the installation position, and rapid, safe and economical module installation can be realized without manual operation. At the same time, the overall structure of the present invention is not fixed and can be reused, and the installation cost can be shared and saved. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is an elevation view of the sliding installation of the photovoltaic module of the present invention;

[0028] Figure 2 It is a plan view of the sliding installation of the photovoltaic module of the present invention;

[0029] Figure 3 It is a plan view of the combination of the sliding installation trolley and the module of the present invention;

[0030] Figure 4 It is a front elevation view before the installation of the combination of the sliding installation trolley and the module of the present invention is completed;

[0031] Figure 5 It is a front elevation view after the installation of the combination of the sliding installation trolley and the module of the present invention is completed;

[0032] Figure 6 It is a side elevation view of the combination of the sliding installation trolley and the module of the present invention;

[0033] Figure 7 It is a plan view of the photovoltaic module of the present invention;

[0034] Figure 8 It is a front elevation view of the photovoltaic module of the present invention;

[0035] Figure 9 It is a plan view of the pressing plate type block cable connection structure of the present invention;

[0036] Figure 10 It is an elevation view of the pressing plate type block cable connection structure of the present invention;

[0037] Figure 11 It is a detailed view of the block cable guiding structure of the present invention;

[0038] Figure 12 It is a front elevation view of the sliding installation trolley of the present invention;

[0039] Figure 13 It is a side elevation view of the sliding installation trolley of the present invention;

[0040] Figure 14 Plan view of the sliding cable and the sliding cable support pillar of the present invention;

[0041] Figure 15 Front elevation view of the sliding cable and the sliding cable support pillar of the present invention;

[0042] Figure 16 Side elevation view of the sliding cable and the sliding cable support pillar of the present invention:

[0043] Figure 17 Detail drawing of the pile head structure of the present invention.

[0044] The reference signs in the drawings are: 2 - pile foundation, 3 - load-bearing cable, 4 - photovoltaic module, 41 - photovoltaic panel, 42 - photovoltaic support, 5 - power lifting device, 51 - cable, 52 - winch, 6 - power wheel, 7 - sliding installation trolley, 8 - spring, 9 - electric bolt fastener, 91 - telescopic motor, 10 - pressing plate type cable connection structure, 101 - lower pressing block, 102 - upper pressing block, 103 - bolt, 11 - electric door, 12 - transport ship, 13 - sliding cable, 14 - steel beam, 15 - nut, 16 - pile head structure, 161 - pile head hanging plate, 162 - upper pin column, 163 - lower pin column, 17 - sliding cable support pillar, 171 - support pillar hanging plate, 18 - bolt and nut. Detailed implementation manners

[0045] The present invention will be further described below in conjunction with the drawings and embodiments, but it shall not be used as a basis for limiting the present invention.

[0046] As Figure 1-17 shown, a module sliding installation structure for offshore suspended cable photovoltaic includes a sliding cable support pillar 17, a sliding cable 13 and a sliding installation trolley 7. The sliding cable support pillar 17 is detachably connected to a pile head structure 16 on the top of a pile foundation 2. The sliding cable support pillars 17 are distributed around the photovoltaic module 4 to enclose an overall working area. The sliding cable 13 is connected between the sliding cable support pillars 17 along the direction of the load-bearing cable 3. The sliding installation trolley 7 is arranged on the sliding cable 13, and a power lifting device 5 that can be connected to the photovoltaic support 42 on the photovoltaic module 4 is arranged therein. A groove is formed at the bottom of the sliding installation trolley 7, and the opening direction of the groove corresponds to the load-bearing cable 3. An electric bolt fastener 9 that can cooperate with a bolt 103 on the photovoltaic support 42 is arranged in the groove. A cavity is arranged on the side wall of the groove, and an upper pressing block 102 that can be automatically moved out is received in the cavity. The upper pressing block 102 can also be connected and cooperated with the bolt 103, so that the photovoltaic module 4 is tightly connected to the load-bearing cable 3 through the upper pressing block 102.

[0047] As Figure 1-13As shown, specifically, the sliding installation trolley 7 is independently arranged on each sliding cable 13. Thus, the overall structure is equipped with two sliding installation trolleys 7, and a steel beam 14 is connected between adjacent sliding installation trolleys 7 to form an overall sliding structure. The two sliding installation trolleys 7 are connected by the steel beam 14 to keep their relative positions unchanged.

[0048] Among them, a receiving body is arranged at the bottom of the sliding installation trolley 7, and a groove is arranged inside the receiving body; a driving wheel 6 is arranged below the sliding installation trolley 7, and the driving wheel 6 is arranged in a staggered manner with the receiving body to avoid the driving wheel 6 affecting the installation control of the photovoltaic module 4. At the same time, two sets of driving wheels 6 are equipped below each sliding installation trolley 7, and the driving wheels 6 are connected to the sliding cable 13 so that the sliding installation trolley 7 can move stably along the cable direction on the sliding cable 13 through remote control.

[0049] Among them, a spring 8 is connected to the inner side wall of the cavity. The spring 8 is located between the inner side wall of the cavity and the upper pressing block 102, and an electric door 11 is arranged at the outlet of the cavity so that the upper pressing block 102 is received in the cavity when the electric door 11 is closed, and can be ejected from the cavity under the elastic force of the spring 8 after the electric door 11 is opened.

[0050] Among them, a telescopic motor 91 is arranged in the groove. The telescopic motor 91 is connected to the electric bolt fastener 9, and a nut 15 that can cooperate with the bolt 103 is pre-installed in the electric bolt fastener 9 so that the upper pressing block 102 is integrally fixed when connected to the photovoltaic support 42.

[0051] Specifically, the power lifting device 5 includes a cable 51 and a winch 52. The winch 52 is installed in the sliding installation trolley 7. One end of the cable 51 is connected to the winch 52, and the other end extends out of the sliding installation trolley 7 and is connected to the photovoltaic support 42, so that the object below the sliding installation trolley 7 can be freely lifted.

[0052] In this embodiment, the sliding cable support 17, the sliding cable 13, and the sliding installation trolley 7 are not fixed and can be reused, which can maximize the sharing and saving of installation costs and reduce the construction cost.

[0053] Such as Figure 9-11As shown in the figure, in this embodiment, a pressing plate type block-cable connection structure is provided to connect the photovoltaic module 4 to the load-bearing cable 3. The pressing plate type block-cable connection structure 10 includes a lower pressing block 101 pre-fixed at the end of the photovoltaic bracket 42, and a separate upper pressing block 102. Groove parts that can cooperate with the load-bearing cable 3 are respectively arranged on the mating surfaces of the upper pressing block 102 and the lower pressing block 101, so that after the upper pressing block 102 and the lower pressing block 101 are mated, they can be fixed to the load-bearing cable 3 accordingly. Bolts 103 are arranged on both sides of the lower pressing block 101 relative to its inner groove part, and connection holes for the bolts 103 to pass through are arranged through the upper pressing block 102, so that the upper pressing block 102 can pass through the bolts 103 to be attached to the lower pressing block 101 for subsequent connection.

[0054] As Figure 14-17 shown, in this embodiment, a photovoltaic module with double-span and double-row is taken as an example for the offshore photovoltaic support structure (not limited to this), and corresponding installation processing is carried out in cooperation with the module sliding installation structure.

[0055] Specifically, the pile head structure 16 includes a hanging plate 61 arranged at the top of the pile foundation 2 and a pin column. The pin column is connected to the hanging plate 61, and an upper pin column 162 is arranged on the part of the pin column extending above the hanging plate 61; the sliding cable support column 17 is sleeved on the upper pin column 162. Among them, the load-bearing cable 3 is connected to the hanging plate 61 so that the photovoltaic module 4 can be installed on the load-bearing cable 3 in this operation area.

[0056] Specifically, a support column hanging plate 171 is arranged on the outer surface of the sliding cable support column 17, and the support column hanging plate 171 is connected to the sliding cable 13. And, in this operation area, the distance between adjacent sliding cables 13 is greater than the distance between adjacent load-bearing cables 3 to facilitate the installation operation of the photovoltaic module 4.

[0057] Among them, the pin column is provided with a lower inserted pin column 163 and an upper pin column 162 according to the different positions extended inside the hanging plate 61; at the top of the pile foundation 2, the lower inserted pin column 163 of the pile head structure 16 is inserted into the pile foundation 2 and grouted for connection. The sliding cable support column 17 is sleeved outside the upper pin column 162 of the pile head structure 16 and is fixedly connected to the pile head structure 16 through bolts and nuts 18.

[0058] Please refer to Figure 1-17 , when the module sliding installation structure is installed offshore, the specific installation steps are as follows:

[0059] S1: The required photovoltaic module 4 is processed and manufactured in a land factory, transported to the installation sea area by the transport ship 12, and close to one side of the pile foundation 2;

[0060] S2: The required photovoltaic pile foundation 2 has completed the piling operation, the pile head structure 16 has been completed for installation, and the load-bearing cable 3 has been installed on the pile head hanging plate 161 of the pile head structure 16;

[0061] S3: Insert the slip cable support column 17 outside the upper pin column 162 of the pile head structure 16 and tightly connect it to the pile head structure 16 with bolts and nuts 18;

[0062] S4: Install the slip cable 13 on the support plate 171 of the slip cable support column 17;

[0063] S5: Install two slip installation trolleys 7 on the slip cable 13. The two slip installation trolleys 7 are connected by a steel beam 14 to keep their relative positions unchanged;

[0064] S6: The photovoltaic module 4 located on the transport ship 12 is connected to the slip installation trolley 7 through the cable 51 in the power lifting device 5. Place the upper pressing block 102 into the cavity on the side wall of the groove under the slip installation trolley 7 and close the electric door 11;

[0065] S7: Start the winch 52 to lift the photovoltaic module 4 and the photovoltaic panel 41 carried thereon to a certain height. Remotely control the driving wheels 6 of the slip installation trolley 7 to move along the slip cable 13 in the cable direction to the installation position, and brake the driving wheels 6 of the slip installation trolley 7 to realize the slip transportation of the photovoltaic module 4, avoiding the movement of the transport ship 12 between the pile foundations 2;

[0066] S8: The power lifting device 5 lifts the photovoltaic module 4 by retracting the cable 51 to align the position of the lower pressing block 101 and the electric bolt fastener 9. Open the electric door 11, and the upper pressing block 102 is ejected by the spring 8, passes through the bolt 103 and lands above the lower pressing block 101. Through the coordinated work of the telescopic motor 91 and the electric bolt fastener 9, the bolt 103 is tightened to the set torque value. After tightening, release the power lifting device 5, and the photovoltaic module 4 is separated from the slip installation trolley 7 to realize the automatic installation of the block cable;

[0067] S9: Repeat the content in steps S6 - S8 to successively install the remaining photovoltaic modules 4 to the installation positions of the load-bearing cable 3 to complete the module installation of the offshore suspension photovoltaic;

[0068] S10: Remove the slip cable support column 17, the slip cable 13 and the slip installation trolley 7, and the transport ship 12 withdraws from the operation. The removed structures can be recycled and reused.

[0069] The above embodiments are only a relatively optimal technical solution of the present invention. Those skilled in the art should understand that without departing from the principles and essence of the present invention, modifications or replacements can be made to the technical solutions or parameters in the embodiments, and all should be covered within the protection scope of the present invention.

Claims

1. A module sliding installation structure for offshore suspended PV, characterized in that: It includes a sliding cable support (17), a sliding cable (13), and a sliding installation trolley (7). The sliding cable support (17) is detachably connected to a pile head structure (16) at the top of a pile foundation (2). The sliding cable supports (17) are distributed around the photovoltaic module (4) to enclose an overall working area. The sliding cable (13) is connected between the sliding cable supports (17) along the direction of the load-bearing cable (3). The sliding installation trolley (7) is arranged on the sliding cable (13). A power lifting device (5) that can be connected to a photovoltaic bracket (42) on the photovoltaic module (4) is arranged inside it. A groove is formed at the bottom of the sliding installation trolley (7), and the opening direction of the groove corresponds to the load-bearing cable (3). An electric bolt tightener (9) that can cooperate with a bolt (103) on the photovoltaic bracket (42) is arranged in the groove. A cavity is arranged on the side wall of the groove, and an upper pressing block (102) that can automatically move out is accommodated in the cavity. The upper pressing block (102) can also be connected and cooperated with the bolt (103) so that the photovoltaic module (4) is tightly connected to the load-bearing cable (3) through the upper pressing block (102). It includes a lower pressing block pre-fixed at the end of the photovoltaic bracket and a separately arranged upper pressing block. Groove parts that can cooperate with the load-bearing cable are respectively arranged on the mutually contacting surfaces of the upper pressing block and the lower pressing block, so that they can be fixed to the load-bearing cable after the upper pressing block and the lower pressing block are in contact with each other. Bolts are arranged on both sides of the lower pressing block relative to its inner groove part, and a connecting hole for the bolt to pass through is arranged through the upper pressing block, so that the upper pressing block passes through the bolt to be in contact with the lower pressing block for subsequent connection.

2. The module sliding installation structure for offshore suspended PV according to claim 1, characterized in that: The sliding installation trolleys (7) are independently arranged on each sliding cable (13), and a steel beam (14) is connected between adjacent sliding installation trolleys (7) to form an overall sliding structure.

3. The module sliding installation structure for offshore suspended PV according to claim 1, characterized in that: A receiving body is arranged at the bottom of the sliding installation trolley (7), and the groove is accommodated inside the receiving body. A power wheel (6) is arranged below the sliding installation trolley (7). The power wheel (6) is arranged in a staggered manner with the receiving body, and at the same time, the power wheel (6) is connected to the sliding cable (13) so that the sliding installation trolley (7) moves along the cable direction on the sliding cable (13).

4. The module sliding installation structure for offshore suspended PV according to claim 1, characterized in that: A spring (8) is connected and arranged on the inner side wall of the cavity. The spring (8) is located between the inner side wall of the cavity and the upper pressing block (102), and an electric door (11) is arranged at the outlet position of the cavity.

5. The module sliding installation structure for offshore suspended PV according to claim 1 or 4, characterized in that: A telescopic motor (91) is arranged in the groove. The telescopic motor (91) is connected to the electric bolt tightener (9). At the same time, a connecting hole for the bolt (103) to pass through is arranged through the upper pressing block (102).

6. The module sliding installation structure for offshore suspended PV according to claim 1, characterized in that: The power lifting device (5) comprises a cable (51) and a winch (52), wherein the winch (52) is installed in the sliding installation trolley (7), one end of the cable (51) is connected to the winch (52), and the other end extends out of the sliding installation trolley (7) and is connected to the photovoltaic support (42).

7. The module sliding installation structure for offshore suspended PV according to claim 1, characterized in that: The pile head structure (16) comprises a hanging plate (61) arranged on the top of the pile foundation (2), and a pin column, wherein the pin column is connected to the hanging plate (61), and an upper pin column (162) is arranged on the upper part of the pin column extending from the hanging plate (61); the sliding rope support (17) is sleeved on the upper pin column (162).

8. The module sliding installation structure for offshore suspended PV according to claim 1 or 7, characterized in that: A support plate (171) is provided on the outer surface of the sliding cable support (17), and the support plate (171) is connected to the sliding cable (13).

9. The module sliding installation structure for offshore suspended PV according to claim 1, characterized in that: The spacing between adjacent sliding cables (13) is greater than the spacing between adjacent supporting cables (3), so as to facilitate the operation of the photovoltaic assembly module (4).

10. A method for using the module sliding installation structure for offshore suspended PV, characterized in that: The module sliding installation structure for offshore cable photovoltaic is installed and used according to any one of claims 1 to 9, and the specific steps are as follows: S1: The required photovoltaic assembly modules (4) are processed and manufactured in a land factory and transported by a transport ship (12) to the installation sea area, close to one side of the pile foundation (2); S2: installing the required sliding cable support (17) on the pile head structure (16) at the top of the photovoltaic pile foundation (2) to achieve a fastening connection, and installing the sliding cable (13) on the support plate (171) of the sliding cable support (17); S3: The sliding installation trolley (7) is installed on the sliding cable (13) and connected via a steel beam (14), so that the relative positions of the sliding installation trolleys (7) on both sides remain unchanged; S4: The photovoltaic assembly module (4) located on the transport ship (12) is connected to the sliding installation trolley (7) via a cable (51), and the upper pressing block (102) is placed in the cavity of the side wall of the groove below the sliding installation trolley (7), and the electric door (11) is closed; S5: starting the winch (52) to lift the photovoltaic assembly module (4) to a certain height, remotely controlling the power wheel (6) of the sliding installation trolley (7) to move along the direction of the sliding rope (13) to the installation position, and braking the power wheel (6); S6: The photovoltaic assembly module (4) is lifted by retrieving the cable (51), and the position of the bolt (103) and the electric bolt fastener (9) are aligned, and the electric door (11) is opened so that the upper pressing block (102) is ejected by the spring (8) so that it passes through the bolt (103) and falls onto the photovoltaic support (42), and the block cable is automatically installed by the cooperation of the telescopic motor (91) and the electric bolt fastener (9); S7: Repeat the installation steps to successively install the remaining photovoltaic assembly modules (4) to the target installation positions on the load-bearing cable (3), and remove the upper working structure after the installation of the photovoltaic assembly modules (4) is completed.

Citation Information

Patent Citations

  • Photovoltaic module

    CN105610392A

  • Offshore photovoltaic panel support with steering function

    CN216625661U