Combined structure overhanging steel corbel joint and construction method

By designing the outer steel bare nodes of the combined structure, the fixed installation problem of steel crane beams in specific structures is solved, stable connections are achieved and bearing capacity is improved, and new design and construction plans are opened up.

CN119491553APending Publication Date: 2025-02-21CHINA ENERGY CONSTR GRP SHAANXI ELECTRIC POWER DESIGN INST CO LTD
View PDF 0 Cites 3 Cited by

Patent Information

Application Number
CN202411992897.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-31
Publication Date
2025-02-21

AI Technical Summary

Technical Problem

The prior art does not clearly define the design of the outer steel bull leg node when the steel crane beams arranged on steel concrete columns, steel pipe concrete columns, and steel concrete beams when fixed installation.

Method used

A combined structure with external steel beef leg nodes is designed, including a combined structure with built-in steel frames and a steel beef leg installed on the steel frame to support the crane beams. Reinforcement components are provided on the steel frames to reinforce the connecting nodes.

Benefits of technology

The stable connection of steel crane beams on steel concrete columns, steel pipe concrete columns, and steel concrete beams has been realized, which has improved the bearing capacity and stability of the nodes, and has opened up new design concepts and construction plans.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119491553A_ABST
    Figure CN119491553A_ABST
Patent Text Reader

Abstract

The invention discloses a composite structure overhanging steel corbel joint and a construction method, the composite structure overhanging steel corbel joint comprises a composite structure with a built-in steel framework and a steel corbel arranged on the steel framework and used for supporting a crane beam, and the steel framework is provided with a reinforcing assembly used for reinforcing the connecting joint of the steel corbel and the steel framework; the reinforcing assembly comprises a plurality of first reinforcing pieces and a plurality of second reinforcing pieces, and the first reinforcing pieces are arranged at the joints of the tops of the corresponding steel corbels of the steel framework and extend towards the sides away from the steel corbels. According to the invention, the steel crane beam is arranged on the combined structural member formed by combining the steel reinforced concrete column, the concrete filled steel tubular column and the steel reinforced concrete beam, a node method of arranging the steel crane beam on the steel reinforced concrete column, the concrete filled steel tubular column and the steel reinforced concrete beam is defined, and a new design concept and a new construction scheme are developed; reference is provided for similar engineering design and construction, and the method has great application and popularization prospects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a composite structure cantilevered steel corbel node and a construction method. Background Art

[0002] The statements herein merely provide background information related to the present invention and do not necessarily constitute prior art.

[0003] With the rapid development of my country's construction industry, steel and concrete composite structures have been widely used, and a lot of engineering experience and research results have been accumulated. Composite structure is an independent structural form composed of steel and concrete. Since the load-bearing section is not only reinforced concrete, but also the steel section works in a trinity with steel bars and concrete with its inherent strength and ductility, the composite structure has the advantages of greater bearing capacity, greater rigidity, and better seismic performance than traditional reinforced concrete structures; and compared with steel structures, it has the advantages of good fire resistance, good local and overall structural stability, and saving steel. Targeted promotion and application of such structures is of great significance to promoting the development of high-rise and multi-story buildings in my country, improving the overall seismic performance of the structure, and increasing the use space of the structure.

[0004] The crane beam is a beam structure that supports the operation of the bridge crane. There are crane tracks on the beam, and the crane travels back and forth on the crane beam through the tracks. At present, the current national standard drawings for reference in the design of crane beams are: "Steel Crane Beam (6m~9m)" G520-1~2, "Crane Track Connection and Car Stop" 05G525. The installation nodes in the drawings only specify the connection between the steel crane beam and the steel column and concrete column respectively, but do not specify the external steel bracket node sample when the steel crane beam is fixedly installed on the steel concrete column, steel tube concrete column, and steel concrete beam. Therefore, it is very necessary to study the installation sample of the external steel bracket node. Summary of the invention

[0005] The purpose of the present invention is to address the above-mentioned deficiencies and provide a composite structure cantilevered steel corbel node and construction method to solve the connection problem of steel crane beams arranged on steel concrete columns, steel tube concrete columns, and steel concrete beams.

[0006] In order to solve the above technical problems, the present invention adopts the following technical solutions: a composite structure cantilevered steel corbel node, comprising a composite structure with a built-in steel frame and a steel corbel installed on the steel frame and used to support the crane beam, wherein the steel frame is provided with a reinforcing component for reinforcing the connection node between the steel corbel and the steel frame;

[0007] The reinforcement assembly includes multiple first reinforcement members and multiple second reinforcement members, each of the first reinforcement members is arranged at the top connection of the corresponding steel corbel of the steel frame and extends to the side away from the steel corbel, and each of the second reinforcement members is arranged at the bottom connection of the corresponding steel corbel of the steel frame and extends to the side away from the steel corbel.

[0008] Furthermore, the steel corbel includes an upper steel corbel flange, a lower steel corbel flange and a steel corbel web connecting the upper steel corbel flange and the lower steel corbel flange, and a plurality of first stiffening ribs connected to the steel corbel web are also arranged between the upper steel corbel flange and the lower steel corbel flange.

[0009] Furthermore, the composite structure is a steel-concrete column, which is composed of a steel column, steel-concrete column longitudinal reinforcement and steel-concrete column stirrups as a skeleton, and is cast with concrete outside, and the corresponding steel bracket is welded to one of the flanges of the steel column;

[0010] The reinforcement component includes a plurality of outer transverse partitions arranged between two flanges of the steel column and arranged in an upper and lower arrangement. At least one second stiffening rib connected to the web of the steel column is arranged between two upper and lower adjacent outer transverse partitions.

[0011] Furthermore, a steel sleeve for connecting to the longitudinal reinforcement of the steel concrete column is arranged on the upper flange of the steel corbel of the corresponding steel concrete column, and a connecting steel plate for connecting to the longitudinal reinforcement of the steel concrete column is arranged at the bottom of the lower flange of the steel corbel of the corresponding steel concrete column.

[0012] Furthermore, connecting steel bars for connecting to the stirrups of the steel concrete column are provided between the first stiffening rib of the corresponding steel concrete column and the flange of the steel column.

[0013] Furthermore, the combined structure is a steel tube concrete column, which uses a steel tube as a skeleton and concrete is poured into the steel tube. The reinforcement component also includes a plurality of inner transverse partitions arranged in the steel tube and a curved welded steel plate for connecting the steel tube to the upper flange of the steel corbel and the lower flange of the steel corbel. Concrete pouring holes are opened on the inner transverse partitions.

[0014] Furthermore, the composite structure is a steel-concrete beam, which is composed of a steel beam, steel beam longitudinal reinforcement, steel beam stirrups, steel beam waist reinforcement and fixed steel bars as a skeleton, and is cast with concrete on the outside, and the corresponding steel bracket is welded to the web of the steel beam;

[0015] The thickness and width of the upper flange of the steel beam are greater than those of the lower flange, and a short square steel tube column which is not penetrated by the longitudinal reinforcement of the steel beam is arranged on the upper flange of the steel beam;

[0016] The reinforcement assembly also includes a third stiffening rib arranged on a side of the web of the steel beam away from the corresponding steel corbel and a plurality of fourth stiffening ribs arranged on the third stiffening rib and perpendicular to the third stiffening rib.

[0017] A construction method for a composite structure cantilevered steel corbel node, comprising any one of the composite structure cantilevered steel corbel nodes, the method being as follows:

[0018] S1. Weld the steel bracket to the steel column, and after the welding of the steel bracket is completed, weld the outer diaphragm, the second stiffening rib, the steel sleeve and the connecting steel plate to the installation point in sequence;

[0019] Weld the steel bracket to the steel pipe, and after the welding of the steel bracket is completed, weld the inner diaphragm and the curved welded steel plate to the installation point;

[0020] Weld the steel bracket to the steel beam, and after the welding of the steel bracket is completed, weld the third stiffening rib and the fourth stiffening rib to the installation point in sequence;

[0021] S2, transporting the steel frame welded in step S1 to the construction site;

[0022] S3. After the steel frame is transported to the place, it is fixed and installed, and the node components are installed;

[0023] S4. Tie the steel-concrete column longitudinal reinforcement, steel-concrete column stirrups and connecting steel bars to the installed steel columns in sequence, and tie the steel beam longitudinal reinforcement, steel beam stirrups, steel beam waist reinforcement and fixed steel bars to the installed steel beams in sequence;

[0024] S5. Casting concrete in steel-concrete columns, steel tube concrete columns and steel-concrete beams;

[0025] S6. Cast the steel corbel surface layer.

[0026] The beneficial effects of the present invention are embodied in:

[0027] The present invention proposes to arrange the steel crane beam on a composite structural member composed of a steel-concrete column, a steel tube concrete column and a steel-concrete beam, clarifies the node method of the cantilevered steel bracket arranged on the steel-concrete column, the steel tube concrete column and the steel-concrete beam, opens up a new design concept and construction plan, provides a reference for similar engineering design and construction, and has great prospects for promotion and application. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a plan view of the crane beam of the present invention;

[0029] Figure 2 It is the AA cross-sectional view of the present invention;

[0030] Figure 3 It is a CC cross-sectional view of the present invention;

[0031] Figure 4 It is a schematic diagram of the connection between the steel concrete column and the steel corbel of the present invention;

[0032] Figure 5 It is the BB cross-sectional view of the present invention;

[0033] Figure 6 It is the DD cross-sectional view of the present invention;

[0034] Figure 7 It is a schematic diagram of the connection between a steel tube concrete column and a steel corbel in one embodiment of the present invention;

[0035] Figure 8 It is a schematic diagram of the installation of the inner diaphragm of the present invention;

[0036] Fig. 9 It is a schematic diagram of the connection between a steel tube concrete column and a steel corbel in another embodiment of the present invention;

[0037] Fig.10 It is a cross-sectional view of EE of the present invention;

[0038] Fig.11 FF is a cross-sectional view of the present invention;

[0039] Fig.12 It is a schematic diagram of the connection between the steel concrete beam and the steel corbel of the present invention;

[0040] Fig.13 It is a schematic diagram of the installation of the third stiffening rib and the fourth stiffening rib of the present invention.

[0041] In the figure:

[0042] 1. Steel-concrete column; 11. Steel column; 12. Longitudinal reinforcement of steel-concrete column; 13. Stirrup reinforcement of steel-concrete column;

[0043] 2. Steel tube concrete column;

[0044] 3. Steel concrete beam; 31. Steel beam; 32. Longitudinal reinforcement of steel beam; 33. Stirrups of steel beam; 34. Waist reinforcement of steel beam; 35. Fixed reinforcement; 36. Square steel tube short column;

[0045] 4. Steel corbel; 41. Steel corbel upper flange; 42. Steel corbel lower flange; 43. Steel corbel web; 44. First stiffening rib;

[0046] 5. Strengthening assembly; 51. External transverse diaphragm; 52. Second stiffening rib; 53. Internal transverse diaphragm; 54. Curved welded steel plate; 55. Third stiffening rib; 56. Fourth stiffening rib;

[0047] 6. Connect steel plates; 7. Connect steel bars. DETAILED DESCRIPTION

[0048] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. In the absence of conflict, the embodiments in this application and the features in the embodiments can be combined with each other. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0049] See also Figure 1-13 The present invention discloses a composite structure cantilevered steel corbel node, comprising a composite structure with a built-in steel frame and a steel corbel 4 installed on the steel frame and used to support a crane beam, and a reinforcing component 5 is provided on the steel frame for reinforcing a connection node between the steel corbel 4 and the steel frame;

[0050] The reinforcement assembly 5 includes multiple first reinforcement members and multiple second reinforcement members. Each first reinforcement member is arranged at the top connection of the corresponding steel corbel 4 of the steel frame and extends to the side away from the steel corbel 4. Each second reinforcement member is arranged at the bottom connection of the corresponding steel corbel 4 of the steel frame and extends to the side away from the steel corbel 4.

[0051] The present invention proposes to arrange the steel crane beam on the combined structure, clarifies the node method of the cantilevered steel bracket 4 of the steel crane beam on the combined structure, opens up a new design concept and construction plan, provides a reference for similar engineering design and construction, and has great prospects for promotion and application.

[0052] It should be noted that the spacing between steel-concrete columns 1 and steel tube concrete columns 2 is 6 to 9 meters, and the setting of crane beams must meet the design and installation requirements of current specifications and drawings for steel crane beams.

[0053] In one embodiment, the steel corbel 4 includes a steel corbel upper flange 41, a steel corbel lower flange 42 and a steel corbel web 43 connecting the steel corbel upper flange 41 and the steel corbel lower flange 42, and a plurality of first stiffening ribs 44 connected to the steel corbel web 43 are also arranged between the steel corbel upper flange 41 and the steel corbel lower flange 42.

[0054] With this design, the first stiffening rib 44 strengthens the space between the upper flange 41 of the steel corbel and the lower flange 42 of the steel corbel, thereby improving the supporting effect on the crane beam.

[0055] In one embodiment, the composite structure is a steel-concrete column 1, which is composed of a steel column 11, steel-concrete column longitudinal reinforcement 12 and steel-concrete column stirrups 13 as a skeleton, and is poured with concrete. The corresponding steel bracket 4 is welded to one of the flanges of the steel column 11;

[0056] The reinforcement assembly 5 includes a plurality of outer transverse diaphragms 51 arranged between two flanges of the steel column 11 and arranged in an upper and lower arrangement. At least one second stiffening rib 52 connected to the web of the steel column 11 is arranged between two upper and lower adjacent outer transverse diaphragms 51 .

[0057] In this design, a plurality of outer transverse partitions 51 and second stiffening ribs 52 are arranged at the connection node between the steel corbel 4 and the steel column 11, thereby improving the bearing capacity and stability of the node area.

[0058] In one embodiment, a steel sleeve for connecting to the longitudinal reinforcement 12 of the steel concrete column is provided on the upper flange 41 of the steel corbel of the corresponding steel concrete column 1, and a connecting steel plate 6 for connecting to the longitudinal reinforcement 12 of the steel concrete column is provided at the bottom of the lower flange 42 of the steel corbel of the corresponding steel concrete column 1.

[0059] In this design, the steel sleeve is connected to the upper flange, and the connecting steel plate 6 is used to connect the longitudinal reinforcement 12 of the steel concrete column to the lower flange 42 of the steel corbel. The provision of the connecting steel plate 6 can avoid the use of the steel sleeve to connect to the lower flange 42 of the steel corbel, solve the limitation of the oblique cutting connection of the steel sleeve, and meet the requirements of the standard drawing set on the connection between the longitudinal reinforcement 12 of the steel concrete column and the steel beam.

[0060] In the specific implementation, the steel bracket 4 is pre-welded to the steel concrete column 1, the steel tube concrete column 2 and the steel concrete beam 3 in the factory, and the longitudinal reinforcement 12 of the steel concrete column is connected with the upper flange 41 of the steel bracket by a steel sleeve, which can effectively reduce the welding and weld quality inspection work at the construction site, prevent large discreteness of weld quality during on-site welding, ensure construction quality, improve construction efficiency, shorten construction period, save engineering construction costs, and have obvious social benefits.

[0061] In one embodiment, a connecting steel bar 7 for connecting to the steel concrete column stirrup 13 is provided between the first stiffening rib 44 of the corresponding steel concrete column 1 and the flange of the steel column 11 .

[0062] Such a design enables the steel-concrete column stirrups 13 to be installed in the blocking area of ​​the steel corbel 4 through the connecting steel bars 7, ensuring that the steel-concrete column stirrups 13 can be normally arranged there.

[0063] In one embodiment, the combined structure is a steel tube concrete column 2, which uses a steel tube as a skeleton and is formed by pouring concrete into the steel tube. When the diameter of the steel tube is greater than 700 mm and is within 2 m of the steel tube to be spliced, the reinforcement component 5 also includes a plurality of inner transverse partitions 53 arranged in the steel tube and a curved welded steel plate 54 for connecting the steel tube to the upper flange 41 of the steel corbel and the lower flange 42 of the steel corbel, and a concrete pouring hole is opened on the inner transverse partition 53.

[0064] By designing in this way, the curved welded steel plate 54 and the inner transverse partition 53 are arranged at the connection node between the steel corbel 4 and the steel tube concrete column 2, so as to improve the bearing capacity and stability of the node area.

[0065] In another embodiment, when the diameter of the steel pipe is less than 700 mm, since neither the human body nor the welding equipment can enter the steel pipe, the inner cross partition 53 cannot be welded inside the steel pipe. Therefore, the curved welded steel plate 54 is set as a complete circular steel plate, which facilitates welding while achieving the purpose of enhancing the bearing capacity and stability of the node area.

[0066] In one embodiment, the composite structure is a steel concrete beam 3, which is composed of a steel beam 31, steel beam longitudinal reinforcement 32, steel beam stirrups 33, steel beam waist reinforcement 34 and fixed steel bars 35 as a skeleton, and is cast with concrete on the outside, and the corresponding steel bracket 4 is welded to the web of the steel beam 31;

[0067] The thickness and width of the upper flange of the steel beam 31 are greater than those of the lower flange. A short square steel tube column 36 which is not penetrated by the longitudinal reinforcement 32 of the steel beam is arranged on the upper flange of the steel beam 31.

[0068] The reinforcement assembly 5 further includes a third stiffening rib 55 disposed on a side of the web of the steel beam 31 away from the corresponding steel corbel 4 and a plurality of fourth stiffening ribs 56 disposed on the third stiffening rib 55 and perpendicular to the third stiffening rib 55 .

[0069] Such a design facilitates the installation and fixation of the top of the crane beam by welding the square steel tube short column 36 to the upper flange of the steel beam 31. Since the upper flange of the steel beam 31 is reinforced compared with the lower flange, the area of ​​the steel beam longitudinal reinforcement 32 in the compression zone of the steel concrete beam 3 is reduced, and the steel beam longitudinal reinforcement 32 is prevented from passing through the square steel tube short column 36, thereby reducing the weakening of the square steel tube short column 36 and improving the local stability of the square steel tube short column 36. This improves the overall bearing capacity of the steel concrete beam 3 and the overall stability of the connection node, thereby having obvious social benefits.

[0070] It should be noted that after the crane beam is installed, a 50 mm thick concrete protective layer needs to be poured on the steel bracket 4 to meet the overall appearance requirements of the steel-concrete composite structural member.

[0071] A construction method for a composite structure cantilevered steel corbel node, comprising any one of the composite structure cantilevered steel corbel nodes, the method is as follows:

[0072] S1, welding the steel bracket 4 to the steel column 11, and after the welding of the steel bracket 4 is completed, sequentially welding the outer diaphragm 51, the second stiffening rib 52, the steel sleeve and the connecting steel plate 6 to the installation point;

[0073] Weld the steel bracket 4 onto the steel pipe, and after the welding of the steel bracket 4 is completed, weld the inner diaphragm 53 and the curved welded steel plate 54 to the installation point;

[0074] Weld the steel bracket 4 onto the steel beam 31, and after the welding of the steel bracket 4 is completed, weld the third stiffening rib 55 and the fourth stiffening rib 56 to the installation point in sequence;

[0075] S2, transporting the steel frame welded in step S1 to the construction site;

[0076] S3. After the steel frame is transported to the place, it is fixed and installed, and the node components are installed;

[0077] S4, sequentially tying the steel-concrete column longitudinal reinforcement 12, steel-concrete column stirrups 13 and connecting steel bars 7 to the installed steel column 11, and sequentially tying the steel beam longitudinal reinforcement 32, steel beam stirrups 33, steel beam waist reinforcement 34 and fixing steel bars 35 to the installed steel beam 31;

[0078] S5, pouring concrete in steel concrete column 1, steel tube concrete column 2, and steel concrete beam 3;

[0079] S6. Cast the 4th surface layer of steel corbel.

[0080] It should be noted that if the embodiments of the present invention involve directional indications (such as up, down, left, right, front, back, etc.), the directional indications are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.

[0081] In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the present invention, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or suggesting their relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in the field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the present invention.

[0082] In addition, "plurality" means two or more.

[0083] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A composite structure cantilevered steel bracket node, characterized in that: It comprises a combined structure of a built-in steel frame and a steel bracket (4) installed on the steel frame and used to support the crane beam, wherein the steel frame is provided with a reinforcing component (5) for reinforcing the connection node between the steel bracket (4) and the steel frame; The reinforcement assembly (5) includes a plurality of first reinforcement members and a plurality of second reinforcement members, each of the first reinforcement members is arranged at the top connection of the corresponding steel corbel (4) of the steel frame and extends to a side away from the steel corbel (4), and each of the second reinforcement members is arranged at the bottom connection of the corresponding steel corbel (4) of the steel frame and extends to a side away from the steel corbel (4).

2. According to claim 1, a composite structure cantilevered steel corbel node is characterized in that: The steel corbel (4) comprises a steel corbel upper flange (41), a steel corbel lower flange (42) and a steel corbel web (43) connecting the steel corbel upper flange (41) and the steel corbel lower flange (42); a plurality of first stiffening ribs (44) connected to the steel corbel web (43) are further arranged between the steel corbel upper flange (41) and the steel corbel lower flange (42).

3. According to claim 2, a composite structure cantilevered steel corbel node is characterized in that: The combined structure is a steel-concrete column (1), which is composed of a steel column (11), steel-concrete column longitudinal reinforcement (12) and steel-concrete column stirrups (13) as a skeleton, and is cast with concrete on the outside, and the corresponding steel bracket (4) is welded to one of the flanges of the steel column (11); The reinforcing assembly (5) comprises a plurality of outer transverse diaphragms (51) arranged between two flanges of the steel column (11) and arranged in an up-and-down arrangement, and at least one second stiffening rib (52) connected to the web of the steel column (11) is arranged between two upper and lower adjacent outer transverse diaphragms (51).

4. According to claim 3, a composite structure cantilevered steel corbel node is characterized in that: A steel sleeve for connecting to the longitudinal reinforcement (12) of the steel concrete column is arranged on the upper flange (41) of the steel corbel of the corresponding steel concrete column (1), and a connecting steel plate (6) for connecting to the longitudinal reinforcement (12) of the steel concrete column is arranged at the bottom of the lower flange (42) of the steel corbel of the corresponding steel concrete column (1).

5. According to claim 3, a composite structure cantilevered steel corbel node is characterized in that: A connecting steel bar (7) for connecting to the steel concrete column stirrup (13) is provided between the first stiffening rib (44) of the corresponding steel concrete column (1) and the flange of the steel column (11).

6. According to claim 2, a composite structure cantilevered steel corbel node is characterized in that: The combined structure is a steel tube concrete column (2), wherein the steel tube concrete column (2) is formed by pouring concrete into the steel tube using a steel tube as a skeleton, and the reinforcement component (5) further comprises a plurality of inner transverse partitions (53) arranged in the steel tube and a curved welded steel plate (54) for connecting the steel tube with the upper flange (41) of the steel corbel and the lower flange (42) of the steel corbel, and the inner transverse partitions (53) are provided with concrete pouring holes.

7. According to claim 1, a composite structure cantilevered steel corbel node is characterized by: The composite structure is a steel-concrete beam (3), which is composed of a steel beam (31), steel beam longitudinal reinforcement (32), steel beam stirrups (33), steel beam waist reinforcement (34) and fixed steel bars (35) as a skeleton, and is cast with concrete on the outside, and the corresponding steel bracket (4) is welded to the web of the steel beam (31); The thickness and width of the upper flange of the steel beam (31) are greater than the thickness and width of the lower flange, and a square steel tube short column (36) which is not penetrated by the steel beam longitudinal reinforcement (32) is arranged on the upper flange of the steel beam (31); The reinforcement assembly (5) further comprises a third stiffening rib (55) arranged on the side of the web of the steel beam (31) away from the corresponding steel corbel (4), and a plurality of fourth stiffening ribs (56) arranged on the third stiffening rib (55) and perpendicular to the third stiffening rib (55).

8. A construction method for a composite structure cantilevered steel bracket node, characterized in that: The method comprises a composite structure cantilevered steel corbel node as claimed in any one of claims 1 to 7, wherein: S1, welding a steel bracket (4) to the profiled steel column (11), and after the welding of the steel bracket (4) is completed, sequentially welding the outer transverse diaphragm (51), the second stiffening rib (52), the steel sleeve and the connecting steel plate (6) to the installation point; Welding a steel bracket (4) onto the steel pipe, and after the welding of the steel bracket (4) is completed, welding the inner diaphragm (53) and the curved welded steel plate (54) to the installation point; Welding a steel bracket (4) onto the steel beam (31), and after the welding of the steel bracket (4) is completed, sequentially welding the third stiffening rib (55) and the fourth stiffening rib (56) to the installation point; S2, transporting the steel frame welded in step S1 to the construction site; S3. After the steel frame is transported to the place, it is fixed and installed, and the node components are installed; S4, sequentially tying the steel-concrete column longitudinal reinforcement (12), steel-concrete column stirrups (13) and connecting steel bars (7) to the installed steel column (11), and sequentially tying the steel beam longitudinal reinforcement (32), steel beam stirrups (33), steel beam waist reinforcement (34) and fixing steel bars (35) to the installed steel beam (31); S5, pouring concrete in the steel concrete column (1), the steel tube concrete column (2), and the steel concrete beam (3); S6. Cast the surface layer of the steel corbel (4).

Citation Information

Cited By

  • Connecting joint of steel reinforced concrete column and prestressed reinforced concrete beam

    CN120119717A

  • T-shaped joint structure of steel reinforced concrete column and beam

    CN121556605A

  • A t-shaped joint structure of a steel reinforced concrete column and a beam

    CN121556605B