Fixed pile foundation type offshore photovoltaic running water construction method

By dividing the offshore photovoltaic area into multiple seaside construction areas and adopting a synchronous flow construction strategy, the problems of high difficulty and low efficiency of offshore photovoltaic construction are solved, and construction efficiency and safety are improved.

CN119615864AActive Publication Date: 2025-03-14NORTHWEST ENGINEERING CORPORATION LIMITED
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411867868.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-18
Publication Date
2025-03-14
Estimated Expiration
2044-12-18

AI Technical Summary

Technical Problem

Offshore photovoltaic construction faces the problems of high construction difficulty and low efficiency in marine environments, especially in fixed pile-based offshore photovoltaic construction, the operation and management of ship machines is complex, with construction conflicts and safety hazards.

Method used

The fixed pile-based offshore photovoltaic water flow construction method is adopted to divide the offshore photovoltaic zone into multiple side-by-side and adjacent construction areas. Each area is facing the sea at least on one side. The synchronous water flow construction strategy is adopted. Each construction area is advanced from the center to the surroundings, and the construction directions of adjacent areas are different.

Benefits of technology

By dividing the construction areas and synchronous flow construction, the cross-operation and construction conflicts between the construction teams are reduced, construction efficiency and safety are improved, the complexity of construction organization is simplified, and the management and monitoring efficiency of the construction site is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119615864A_ABST
    Figure CN119615864A_ABST
Patent Text Reader

Abstract

The invention provides a fixed pile foundation type offshore photovoltaic running water construction method, and relates to the field of offshore photovoltaic technologies. The construction method comprises the steps that an offshore photovoltaic area is divided into a plurality of construction areas distributed side by side, at least one side of each construction area is near the sea, and the different construction areas are adjacent to one another; flow construction is synchronously conducted on different construction areas, the construction directions of the construction areas point to the periphery of the construction areas from the centers of the construction areas, and the construction directions of the adjacent construction areas are different. According to the construction method, the construction efficiency can be improved, and the construction difficulty is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the field of offshore photovoltaic technology, and in particular to a fixed pile foundation offshore photovoltaic flowing water construction method. Background Art

[0002] At present, wind power generation is the leading technology in offshore power generation, but with the continuous exploration and deepening of renewable energy utilization, offshore photovoltaics is gradually emerging as a new and promising power generation method. However, it is not easy to apply photovoltaic technology to the marine environment. The influence of the marine environment poses a severe challenge to the construction process, resulting in greater construction difficulty and lower construction efficiency.

[0003] It should be noted that the information disclosed in the above background technology section is only used to enhance the understanding of the background of the present disclosure, and therefore may include information that does not constitute the prior art known to ordinary technicians in the field. Summary of the invention

[0004] The present invention provides a fixed pile foundation offshore photovoltaic flowing water construction method, which can improve construction efficiency and reduce construction difficulty.

[0005] According to one aspect of the present disclosure, a fixed pile foundation offshore photovoltaic flowing water construction method is provided, comprising:

[0006] Divide the offshore photovoltaic area into a plurality of construction areas arranged side by side, each of the construction areas having at least one side facing the sea, and different construction areas being adjacent to each other;

[0007] Different construction areas are simultaneously subjected to flow construction, the construction direction of the construction area is directed from the center of the construction area to the surroundings of the construction area, and the construction directions of adjacent construction areas are different.

[0008] In an exemplary embodiment of the present disclosure, the multiple construction areas include a first construction area, a second construction area and a third construction area, the length of the edge line facing the sea in the first construction area is greater than the length of the edge line not facing the sea in the first construction area; the length of the edge line facing the sea in the second construction area is less than the length of the edge line not facing the sea in the first construction area; the length of the edge line facing the sea in the third construction area is greater than the length of the edge line not facing the sea in the first construction area.

[0009] In an exemplary embodiment of the present disclosure, the area of ​​the first construction zone, the area of ​​the second construction zone, and the area of ​​the third construction zone are different.

[0010] In an exemplary embodiment of the present disclosure, the construction method further includes:

[0011] Assembling photovoltaic support members in a land area to form a photovoltaic support; the land area is connected to the first construction area through a waterway;

[0012] transporting the photovoltaic support to the first construction area through the waterway;

[0013] The photovoltaic support is transported to the third construction area along the edge line of the first construction area facing the sea.

[0014] In an exemplary embodiment of the present disclosure, the edge line of the first construction area facing the sea is located on a side of the first construction area close to the land area.

[0015] In an exemplary embodiment of the present disclosure, the first construction area includes a first inner wire, a second inner wire and a first edge line, the first inner wire is connected to the second inner wire, and the first inner wire and the second inner wire are not colinear, and the first edge line is connected between an end of the first inner wire away from the second inner wire and an end of the second inner wire away from the first inner wire.

[0016] In an exemplary embodiment of the present disclosure, the second construction area includes a third inner wire, a fourth inner wire, a fifth inner wire, a sixth inner wire and a second edge line which are connected end to end in sequence, the third inner wire is distributed in parallel with and adjacent to the first inner wire, and a first channel is formed between the first inner wire and the third inner wire; the fourth inner wire is distributed in parallel with and adjacent to the second inner wire, and a second channel is formed between the fourth inner wire and the second inner wire.

[0017] In an exemplary embodiment of the present disclosure, the third construction area includes a third edge line and a seventh inner line, an eighth inner line, and a ninth inner line connected in sequence, the seventh inner line is parallel to and adjacent to the sixth inner line, and a third channel is between the seventh inner line and the sixth inner line; the eighth inner line is parallel to and adjacent to the fifth inner line, and a fourth channel is between the fifth inner line and the eighth inner line; the ninth inner line is colinearly arranged with the fourth inner line, and the ninth inner line is parallel to and adjacent to the second inner line, and a fifth channel is between the second inner line and the ninth inner line; the third edge line is connected between the seventh inner line and the ninth inner line.

[0018] In an exemplary embodiment of the present disclosure, the flow construction at least includes equipment installation, photovoltaic bracket installation, cable laying and photovoltaic panel installation.

[0019] In an exemplary embodiment of the present disclosure, the different construction areas are simultaneously subjected to flow construction, including:

[0020] Installing the equipment in the first construction area, including setting up a substation and laying a collector line;

[0021] transporting the photovoltaic panel to the second construction area, and inspecting the performance parameters of the photovoltaic panel at the second construction area;

[0022] Installing the photovoltaic support and laying the cables in the third construction area;

[0023] And after the photovoltaic bracket and the cables in the third construction area are laid, the photovoltaic panels are installed on the photovoltaic bracket.

[0024] The fixed pile foundation offshore photovoltaic flow construction method disclosed in the present invention subdivides the photovoltaic area into a plurality of parallel and adjacent construction areas, each of which is at least one side facing the sea, which can facilitate material transportation and reduce the difficulty of material handling. At the same time, the construction area is clearly divided, which is convenient for efficient management and monitoring. A synchronous flow construction strategy is adopted, and each construction area advances from the center to the surrounding areas, and the construction directions of adjacent construction areas are different, which not only reduces the cross-operation between construction teams and avoids construction conflicts (for example, ship-machine collisions), but also improves construction efficiency and reduces safety risks. At the same time, zoning construction makes large-scale projects easy to manage, and each area can independently plan the construction process, reducing the complexity of construction organization. In addition, since each construction area is at least one side facing the sea, a natural logistics channel is provided for the entry and exit of large equipment and materials. The seaside layout also facilitates rapid response and evacuation in emergency situations, further enhancing the safety of the construction site.

[0025] In addition, the synchronous construction strategy ensures that all areas are advanced simultaneously, avoiding overall progress lags caused by local delays. Construction strategies in different directions promote flexible scheduling and optimal allocation of resources, and personnel and machinery can be efficiently transferred between different areas, avoiding idle resources.

[0026] It is to be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the present disclosure. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] The accompanying drawings herein are incorporated into the specification and constitute a part of the specification, illustrate embodiments consistent with the present disclosure, and together with the specification are used to explain the principles of the present disclosure. Obviously, the accompanying drawings described below are only some embodiments of the present disclosure, and for ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without creative work.

[0028] Figure 1 The present invention is a flow chart of a fixed pile foundation offshore photovoltaic flow construction method according to an embodiment of the present invention.

[0029] Figure 2 Schematic diagram of the photovoltaic area in the embodiment of the present disclosure.

[0030] Figure 3 FIG. 1 is a flow chart of step S120 in the present embodiment.

[0031] Figure 4 This is a flow chart of a fixed pile foundation offshore photovoltaic flow construction method in another embodiment of the present disclosure.

[0032] In the figure: 100, photovoltaic area; 1, first construction area; 11, first internal connection; 12, second internal connection; 13, first edge line; 2, second construction area; 21, third internal connection; 22, fourth internal connection; 23, fifth internal connection; 24, sixth internal connection; 25, second edge line; 3, third construction area; 31, seventh internal connection; 32, eighth internal connection; 33, ninth internal connection; 34, third edge line; 4, waterway; 5, land area; 10, first channel; 20, second channel; 30, third channel; 40, fourth channel; 50, fifth channel. DETAILED DESCRIPTION

[0033] Example embodiments will now be described more fully with reference to the accompanying drawings. However, example embodiments can be implemented in a variety of forms and should not be construed as limited to the embodiments set forth herein; rather, these embodiments are provided so that this disclosure will be comprehensive and complete and will fully convey the concepts of the example embodiments to those skilled in the art. The same reference numerals in the figures represent the same or similar structures, and thus their detailed description will be omitted.

[0034] Although relative terms such as "upper" and "lower" are used in this specification to describe the relative relationship of one component of the illustration to another component, these terms are used in this specification only for convenience, such as according to the orientation of the examples described in the drawings. It is understood that if the device of the illustration is turned upside down, the component described as "upper" will become the component "lower". When a structure is "on" other structures, it may mean that the structure is formed integrally on the other structure, or that the structure is "directly" disposed on the other structure, or that the structure is "indirectly" disposed on the other structure through another structure.

[0035] The terms "a", "an", "the" and "said" are used to indicate the presence of one or more elements / components / etc.; the terms "including" and "having" are used to indicate an open-ended inclusive meaning and mean that there may be additional elements / components / etc. in addition to the listed elements / components / etc. The terms "first", "second" ... "ninth" are used only as labels and are not intended to limit the quantity of their objects.

[0036] Due to its unique marine environment, offshore photovoltaic projects have extremely high requirements for construction. How to carry out construction efficiently and safely has become a key issue that needs to be solved urgently. Especially in the construction process of fixed pile-based offshore photovoltaics (i.e., photovoltaic panels are supported above the sea surface by pile foundations and photovoltaic brackets), the operation management of ship engines is particularly important, and safety hazards such as collisions must be avoided. In view of the complexity and challenges of offshore photovoltaic construction, we urgently need a new construction method to ensure a smooth construction process.

[0037] Based on this, the present disclosure provides a fixed pile foundation offshore photovoltaic water flow construction method, such as Figure 1 As shown, the construction method includes steps S11 to S120, wherein:

[0038] Step S110, dividing the offshore photovoltaic area into a plurality of construction areas distributed side by side, each of the construction areas having at least one side facing the sea, and different construction areas being adjacent to each other;

[0039] Step S120, different construction areas are synchronously subjected to flow construction, the construction direction of the construction area is directed from the center of the construction area to the periphery of the construction area, and the construction directions of adjacent construction areas are different.

[0040] like Figure 2 As shown, the multiple construction areas include a first construction area 1, a second construction area 2, and a third construction area 3. The length of the edge line of the first construction area 1 facing the sea is greater than the length of the edge line of the first construction area 1 not facing the sea; the length of the edge line of the second construction area 2 facing the sea is less than the length of the edge line of the first construction area 1 not facing the sea; the length of the edge line of the third construction area 3 facing the sea is greater than the length of the edge line of the first construction area 1 not facing the sea. The area of ​​the first construction area 1, the area of ​​the second construction area 2, and the area of ​​the third construction area 3 are different.

[0041] In some embodiments of the present disclosure, the flow construction method of the present disclosure may further include:

[0042] Step S130, assembling photovoltaic support members in the land area 5 to form a photovoltaic support; the land area 5 is connected to the first construction area 1 through the waterway 4;

[0043] Step S140, transporting the photovoltaic support to the first construction area 1 through the waterway 4;

[0044] Step S150: transporting the photovoltaic support to the third construction area 3 along the edge line of the first construction area 1 facing the sea.

[0045] The edge line of the first construction area 1 facing the sea is located on a side of the first construction area 1 close to the land area 5 .

[0046] The fixed pile foundation offshore photovoltaic flow construction method disclosed in the present invention divides the photovoltaic area 100 into a plurality of parallel and adjacent construction areas (including the first construction area 1, the second construction area 2 and the third construction area 3), and ensures that at least one side of each construction area is close to the sea, which can facilitate material transportation, reduce the difficulty of material handling, and facilitate rapid response and evacuation in emergency situations, and the construction safety is high; at the same time, the boundaries of the construction area are clear, which is convenient for efficient management and monitoring. At the same time, the first construction area 1 has a long seaward edge line, which is convenient for connection with the land area 5 through the waterway 4, providing convenience for the transportation of photovoltaic brackets.

[0047] By adopting a synchronous flow construction strategy, each construction area advances in an orderly manner from the center to the surrounding areas, and the construction directions of adjacent construction areas are different, which can reduce cross-operation between construction teams and fundamentally avoid construction conflicts, such as ship-machine collision and other safety hazards, thereby improving construction efficiency and reducing safety risks.

[0048] At the same time, the zoning construction strategy makes large-scale photovoltaic projects easy to manage. Each area can independently plan the construction process according to the actual situation, which can simplify the complexity of construction organization. In addition, the synchronous construction strategy ensures that all construction areas can be advanced synchronously, effectively avoiding the overall progress lag caused by local delays. The construction strategy in different directions of adjacent areas promotes the flexible scheduling and optimal allocation of construction resources, allowing personnel, machinery, etc. to flow efficiently between different areas, avoiding idleness and waste of resources, and further improving construction efficiency and economic benefits.

[0049] The following is a detailed description of the various steps and specific details of the fixed pile foundation offshore photovoltaic flow water construction method in the embodiment of the present disclosure:

[0050] like Figure 1 As shown, in step S110, the offshore photovoltaic area 100 is divided into a plurality of construction areas distributed side by side, each construction area is adjacent to the sea on at least one side, and different construction areas are adjacent to each other.

[0051] The offshore photovoltaic area 100 can be determined according to the geographical features of the sea area, water depth, tidal conditions, wind and wave conditions, and the layout requirements of the photovoltaic array. The photovoltaic area 100 can be rectangular, polygonal, or irregular in shape, and is not specifically limited here. The area of ​​the photovoltaic area 100 can be 5km 2 ~8km 2 There is no special limitation on the area of ​​the photovoltaic area 100. The photovoltaic area 100 can be 2.0 km away from the coast at its shortest distance and 6.5 km away from the coast at its farthest distance. The water depth of the photovoltaic area 100 is about 8m to 12m.

[0052] Please continue to see Figure 2As shown, the photovoltaic area 100 can be divided into a plurality of construction areas arranged side by side, and each construction area is at least one side facing the sea. With such a design, the ocean can be used as a natural logistics channel to facilitate the transportation and installation of large equipment (such as crane ships or pile-driving ships, etc.), materials, and photovoltaic brackets, and can also effectively reduce the cost and risk of land transportation. The construction area on the sea side often serves as the logistics hub of the entire project, and undertakes the important tasks of docking with the land area 5 and the distribution of materials; at the same time, it can also ensure that the ship and machinery can be smoothly withdrawn after the construction is completed.

[0053] In an exemplary embodiment of the present disclosure, different construction areas are adjacent to each other to ensure that each construction area can work independently and cooperate with each other. Buffer zones or shared channels can be set between adjacent construction areas to facilitate the flexible transfer of construction teams, equipment, and materials between different areas, while avoiding construction conflicts and resource competition. This not only helps to improve construction efficiency, but also enhances the overall coordination and controllability of the project.

[0054] In an exemplary embodiment of the present disclosure, please continue to refer to Figure 2 As shown, the multiple construction areas may include a first construction area 1, a second construction area 2 and a third construction area 3, wherein:

[0055] The first construction area 1 can serve as the logistics hub and starting point of the entire offshore photovoltaic system. Its edge line facing the sea is relatively long. For example, the length of the edge line facing the sea in the first construction area 1 is greater than the length of the edge line not facing the sea in the first construction area 1, so that large equipment, photovoltaic brackets and construction materials can be smoothly transported directly to the construction site by sea. At the same time, the long edge line facing the sea provides a wide working space for the construction team, which is convenient for the rapid development and efficient advancement of construction activities.

[0056] Please continue to see Figure 2 As shown, compared with the first construction area 1, the length of the seaward edge line of the second construction area 2 is relatively small. For example, the length of the seaward edge line in the second construction area 2 is smaller than the length of the non-seaward edge line in the first construction area 1, and the seaward edge line in the second construction area 2 is connected to the seaward edge line in the first construction area 1. The second construction area 2 is mainly used in the finishing stage of the project construction. Its smaller seaward edge line reduces direct contact with the outside world and reduces external interference during the construction process, which is conducive to the construction team to concentrate on completing the final finishing work (for example, photovoltaic panel installation). At the same time, the non-seaward edge line provides a relatively closed working environment for the construction team, which helps to improve construction efficiency and safety.

[0057] Please continue to see Figure 2As shown, the third construction area 3 adjacent to the second construction area 2 also has a long seaward edge line. For example, the length of the seaward edge line in the third construction area 3 is greater than the length of the non-seaward edge line in the first construction area 1. Moreover, the seaward edge line in the third construction area 3 is connected to the seaward edge line in the first construction area 1 and the seaward edge line in the second construction area 2. This layout not only maintains the continuity of the logistics channel, allowing materials to flow quickly between the two construction areas, but also further enhances the flexibility and coordination of construction activities in the third construction area 3.

[0058] In some embodiments of the present disclosure, the area of ​​the first construction area 1, the area of ​​the second construction area 2, and the area of ​​the third construction area 3 can be set according to different operation requirements, that is, when the first construction area 1, the second construction area 2, and the third construction area 3 respectively carry different operation tasks, the areas of the first construction area 1, the second construction area 2, and the third construction area 3 are different. For example, the first construction area 1 can be used to set up a substation and lay a collector line; the second construction area 2 can be used to transport photovoltaic panels and perform performance parameter testing on photovoltaic panels; the third construction area 3 can be used to install photovoltaic brackets and lay cables.

[0059] In an exemplary embodiment of the present disclosure, please continue to refer to Figure 2 As shown, the first construction area 1 includes a first inner line 11, a second inner line 12 and a first edge line 13. The first inner line 11 and the second inner line 12 can both be straight lines. One end of the first inner line 11 is connected to one end of the second inner line 12, and the first inner line 11 and the second inner line 12 are not colinear; for example, the first inner line 11 and the second inner line 12 can be perpendicular to each other. The first edge line 13 can be a broken line, and the first edge line 13 is connected between the end of the first inner line 11 away from the second inner line 12 and the end of the second inner line 12 away from the first inner line 11. The first inner line 11, the second inner line 12 and the first edge line 13 together enclose the first construction area 1, wherein the first edge line 13 is distributed near the sea, and some areas of the first inner line 11 and the second inner line 12 are adjacent to the second construction area 2. In some embodiments of the present disclosure, the angle between the first inner line 11 and the second inner line 12 can be defined as an inner angle, and the first edge line 13 is connected to the side away from the inner angle.

[0060] Please continue to see Figure 2As shown, the second construction area 2 is composed of the third inner line 21, the fourth inner line 22, the fifth inner line 23, the sixth inner line 24 and the second edge line 25 connected end to end in sequence. The third inner line 21, the fourth inner line 22, the fifth inner line 23, the sixth inner line 24 and the second edge line 25 can all be straight lines, and no two adjacent lines are collinear. The third inner line 21 and the first inner line 11 are parallel and adjacently arranged, and the space formed between them is the first channel 10, which can be used for logistics transportation or personnel passage during the construction process; the fourth inner line 22 and the second inner line 12 can also be parallel and adjacently arranged, and the length of the fourth inner line 22 can be less than the length of the second inner line 12. The interval between the fourth inner line 22 and the second inner line 12 constitutes the second channel 20, which can also be used for logistics transportation or personnel passage within the construction area.

[0061] In an exemplary embodiment of the present disclosure, when the first inner line 11 is perpendicular to the second inner line 12, the third inner line 21 may also be perpendicular to the fourth inner line 22. At the same time, the fifth inner line 23 may be perpendicular to the fourth inner line 22, and the fifth inner line 23 is located on the side of the fourth inner line 22 away from the second inner line 12. The sixth inner line 24 may be perpendicular to the fifth inner line 23, that is, the sixth inner line 24 may be distributed parallel to the fourth inner line 22. The second edge line 25 is connected between the third inner line 21 and the sixth inner line 24, and the second edge line 25 is distributed near the sea. At the same time, the third inner line 21 and the fourth inner line 22 are both adjacent to the first construction area 1, and the fifth inner line 23 and the sixth inner line 24 are both adjacent to the third construction area 3.

[0062] The second edge line 25 serves as the closed boundary of the entire second construction area 2. It can be a straight line, a broken line or a curve, as long as it can adapt to the topography and work requirements of the construction site. The second edge line 25 is connected between the end of the sixth inner line 24 away from the fifth inner line 23 and the end of the third inner line 21 away from the fourth inner line 22, thereby enclosing a complete and functionally clear second construction area 2 together with the remaining inner lines.

[0063] In some embodiments of the present disclosure, in order to optimize construction efficiency and management, the width, position of the first channel 10 and the second channel 20 and the protective measures on both sides of the channels can be adjusted according to the actual needs of the construction activities. For example, safety isolation fences, signs or lighting facilities can be added to ensure traffic safety and smooth operations in the construction area.

[0064] Please continue to see Figure 2As shown, the third construction area 3 includes a third edge line 34 and the seventh inner line 31, the eighth inner line 32, and the ninth inner line 33 connected in sequence, that is, the third edge line 34 and the closely connected seventh inner line 31, the eighth inner line 32, and the ninth inner line 33 together enclose the third construction area 3. Among them, the seventh inner line 31 is parallel to and adjacent to the sixth inner line 24, and the third channel 30 is between the seventh inner line 31 and the sixth inner line 24; the third channel 30 can be used for material transportation and personnel flow during construction, ensuring efficient logistics and safe passage of personnel. The width of the third channel 30 can be matched with the needs of construction activities, and the width of the third channel 30 is not specifically limited here. The eighth inner line 32 is parallel to and adjacent to the fifth inner line 23, and the fourth channel 40 is between the fifth inner line 23 and the eighth inner line 32; the fourth channel 40 also bears the function of traffic diversion in the construction area, which can be convenient for alleviating traffic pressure that may occur during construction. In order to further improve the safety and efficiency of the channel, necessary traffic signs, safety fences and lighting systems can be installed on both sides of the channel to ensure smooth construction activities.

[0065] The ninth inner wire 33 is arranged in the same line as the fourth inner wire 22 to improve space utilization. The ninth inner wire 33 can be arranged parallel to and adjacent to the second inner wire 12, and the fifth channel 50 is between the second inner wire 12 and the ninth inner wire 33; the establishment of the fifth channel 50 provides another important path for horizontal communication within the construction area, thereby enhancing the connectivity and flexibility within the construction area.

[0066] The third edge line 34 is distributed along the sea. The third edge line 34 serves as the outer boundary of the third construction area 3. Its shape can be flexibly adjusted according to the specific terrain, geological conditions and construction requirements of the construction site. Whether it is a straight line, a broken line or a curve shape, it is intended to ensure the safe closure and efficient management of the construction area. The third edge line 34 is connected between the seventh inner line 31 and the ninth inner line 33 (for example, the third edge line 34 is connected between the end of the seventh inner line 31 away from the eighth inner line 32 and the end of the ninth inner line 33 away from the eighth inner line 32), and cooperates with each inner line to enclose the third construction area 3.

[0067] In addition, in order to further optimize the construction process and improve management efficiency, the width, location and protection measures of the passages in the third construction area 3 can be dynamically adjusted according to the construction progress and actual conditions. For example, temporary roads can be added in the third construction area 3, the layout of the passages can be adjusted, and safety protection measures can be strengthened to ensure that construction activities are carried out smoothly in a safe and efficient environment.

[0068] It should be noted that the first edge line 13 (i.e., the edge line facing the sea in the first construction area 1), the second edge line 25 (i.e., the edge line facing the sea in the second construction area 2) and the third edge line 34 (i.e., the edge line facing the sea in the third construction area 3) can jointly enclose the photovoltaic area 100 disclosed herein.

[0069] like Figure 1 As shown, in step S120, different construction areas are synchronously subjected to flow construction, the construction direction of the construction area is from the center of the construction area to the surroundings of the construction area, and the construction directions of adjacent construction areas are different.

[0070] Flow construction can be carried out simultaneously in different construction areas. For example, flow construction can be carried out simultaneously in the first construction area 1, the second construction area 2 and the third construction area 3. During this process, each construction area can be advanced from the center to the surrounding areas. Since the construction directions of adjacent construction areas are different, it not only reduces the cross-operation between construction teams and avoids construction conflicts (for example, ship-machine collision), but also improves construction efficiency and reduces safety risks. At the same time, zoning construction makes large-scale projects easier to manage. Each area can plan the construction process independently, reducing the complexity of construction organization. In addition, the synchronous construction strategy ensures that all areas are advanced synchronously, avoiding overall progress lags due to local delays. Construction strategies in different directions promote flexible scheduling and optimal allocation of resources. Personnel and machinery can flow efficiently between different areas, avoiding idle resources.

[0071] In some embodiments of the present disclosure, the flow construction may include at least equipment installation, photovoltaic bracket installation, cable laying, photovoltaic panel installation, etc. The simultaneous flow construction in different construction areas (i.e., step S120) may include steps S210 to S240, such as Figure 3 As shown, where:

[0072] Step S210, installing the equipment in the first construction area, wherein the equipment installation includes setting up a substation and laying a collector line.

[0073] The substation infrastructure components can be transported to the predetermined location. Due to the special offshore environment, floating cranes or offshore cranes are required for precise lifting, and divers are required to fix and inspect the underwater infrastructure components. After the substation infrastructure components are stabilized, the main equipment of the substation is installed. The main equipment may include transformers, switchgear, control systems, etc. It should be noted that these equipment must be treated with anti-corrosion to adapt to the marine environment.

[0074] The collection line can be laid using ships and professional offshore cable laying equipment. The line needs to be laid along a preset seabed or sea surface path, and buoys or seabed markers are set to mark the line direction. Cable traction and fixing devices can be used during the laying process to ensure the stability and safety of the cable in the marine environment.

[0075] Step S220, transporting the photovoltaic panels to the second construction area, and inspecting performance parameters of the photovoltaic panels in the second construction area.

[0076] The photovoltaic panels can be transported from the land area 5 or the warehouse to the second construction area 2 by a transport ship. Subsequently, the staff can be organized to check the performance parameters of the photovoltaic panels and record the test results. The performance parameters may include the power, voltage, current, efficiency, and waterproof performance of the photovoltaic panels. Photovoltaic panels that do not meet the requirements must be marked and isolated in time to avoid flowing into the subsequent installation links.

[0077] Step S230, installing the photovoltaic support in the third construction area and laying the cable.

[0078] The installation location and layout of the photovoltaic bracket can be determined according to the design drawings and actual site conditions. During the installation process, professional offshore construction equipment and tools, such as offshore cranes, screwdrivers, wrenches, etc., must be used, and strict installation specifications and operating procedures must be followed. After the photovoltaic bracket is installed, a stability check is required to ensure that the photovoltaic bracket can withstand the weight of the photovoltaic panel and the test of the marine environment.

[0079] After the photovoltaic bracket is installed, you can start laying cables. The cables need to be laid along the bracket or the preset path and fixed with cable clamps or fixing devices. During the laying process, cable joints and junction boxes need to be set up, and the insulation and conductivity of the cables need to be ensured to be good.

[0080] Step S240, installing the photovoltaic panel on the photovoltaic bracket after the photovoltaic bracket and the cable are laid in the third construction area.

[0081] After the photovoltaic brackets and cables are laid, the photovoltaic panel installation phase begins. For example, the installation order and location of the photovoltaic panels can be determined based on the design drawings and the performance parameters of the photovoltaic panels. Then, the photovoltaic panels are hoisted one by one onto the photovoltaic brackets using offshore cranes or lifting equipment, and fixed using tools such as screwdrivers and wrenches. During the installation process, it is necessary to ensure that the connection between the photovoltaic panel and the photovoltaic bracket is firm and reliable, and adjust the angle and orientation of the photovoltaic panel to maximize the use of solar energy.

[0082] After the photovoltaic panels are installed, electrical connections and commissioning are required. For example, the photovoltaic panels can be connected to cables and necessary protection devices and monitoring systems can be set up. Finally, the entire photovoltaic system is fully inspected and tested to ensure that the system can operate normally and meet the design requirements.

[0083] In an exemplary embodiment of the present disclosure, Figure 4 As shown, the fixed pile foundation offshore photovoltaic flowing water construction method disclosed in the present invention may also include steps S130 to S150, wherein:

[0084] Step S130, assembling photovoltaic support members in a land area to form a photovoltaic support; the land area is connected to the first construction area through a waterway.

[0085] A land area 5 close to the photovoltaic area 100 and with convenient transportation can be selected on the coast as an assembly site. The area has a flat terrain and no obstructions, which is convenient for the entry and exit and operation of large equipment and materials. Considering the convenience of subsequent transportation, the site of the land area 5 can be selected as close to the entrance of the waterway 4 as possible.

[0086] Photovoltaic supports (e.g., support grids, support beams, support rods, fixings and connectors, etc.) can be assembled in the land area 5 to form a photovoltaic support for supporting photovoltaic panels. The land area 5 can be planned with clear logistics channels, assembly areas, storage areas and temporary facilities areas to ensure that the functional areas do not interfere with each other and the process is smooth. The materials such as the support grids, support beams, support rods, fixings and connectors required for the photovoltaic supports can be transported to the land area 5 in advance and stored in categories as needed. The support grids, support beams, support rods, fixings and connectors are assembled according to the design drawings to form a photovoltaic support.

[0087] It should be noted that the process of assembling photovoltaic support members in the land area 5 can be carried out simultaneously with the flow construction process in the first construction area 1, the second construction area 2 and the third construction area 3, thus realizing efficient use of construction resources and rapid advancement of construction progress. The land area 5 and each construction area can ensure smooth construction and timely resolution of problems through effective communication and coordination mechanisms.

[0088] Step S140: transport the photovoltaic support to the first construction area through the waterway.

[0089] The edge line of the first construction area 1 facing the sea (i.e., the first edge line 13) is located on the side of the first construction area 1 close to the land area 5, that is, the first edge line 13 is close to the boundary of the ocean, and the assembled photovoltaic brackets in the land area 5 can be transported to the first edge line 13 of the first construction area 1 through the waterway 4. The waterway 4 can be a straight waterway 4, which can shorten the transportation distance to the maximum extent and improve the logistics speed; and the straight design helps to simplify the navigation route, reduce the difficulty of navigation, and thus improve the safety of transportation.

[0090] Step S150: transporting the photovoltaic support to the third construction area along the edge line of the first construction area facing the sea.

[0091] After arriving at the first construction area 1 , the photovoltaic support can be transported to the third construction area 3 along the first edge line 13 .

[0092] Those skilled in the art will readily appreciate other embodiments of the present disclosure after considering the specification and practicing the invention disclosed herein. This application is intended to cover any modification, use or adaptation of the present disclosure, which follows the general principles of the present disclosure and includes common knowledge or customary techniques in the art that are not disclosed in the present disclosure. The specification and examples are intended to be exemplary only, and the true scope and spirit of the present disclosure are indicated by the appended claims.

Claims

1. A fixed pile foundation offshore photovoltaic water flow construction method, characterized in that: include: Divide the offshore photovoltaic area into a plurality of construction areas arranged side by side, each of the construction areas having at least one side facing the sea, and different construction areas being adjacent to each other; Different construction areas are simultaneously subjected to flow construction, the construction direction of the construction area is directed from the center of the construction area to the surroundings of the construction area, and the construction directions of adjacent construction areas are different.

2. The construction method according to claim 1, characterized in that: The multiple construction areas include a first construction area, a second construction area and a third construction area. The length of the edge line facing the sea in the first construction area is greater than the length of the edge line not facing the sea in the first construction area; the length of the edge line facing the sea in the second construction area is less than the length of the edge line not facing the sea in the first construction area; the length of the edge line facing the sea in the third construction area is greater than the length of the edge line not facing the sea in the first construction area.

3. The construction method according to claim 2, characterized in that: The area of ​​the first construction zone, the area of ​​the second construction zone, and the area of ​​the third construction zone are different.

4. The construction method according to claim 2, characterized in that: The construction method also includes: Assembling photovoltaic support members in a land area to form a photovoltaic support; the land area is connected to the first construction area through a waterway; transporting the photovoltaic support to the first construction area through the waterway; The photovoltaic support is transported to the third construction area along the edge line of the first construction area facing the sea.

5. The construction method according to claim 4, characterized in that: The seaward edge line of the first construction area is located on a side of the first construction area close to the land area.

6. The construction method according to any one of claims 2 to 4, characterized in that: The first construction area includes a first inner line, a second inner line and a first edge line, the first inner line is connected to the second inner line, and the first inner line and the second inner line are not colinear, and the first edge line is connected between an end of the first inner line away from the second inner line and an end of the second inner line away from the first inner line.

7. The construction method according to claim 6, characterized in that: The second construction area includes a third inner wire, a fourth inner wire, a fifth inner wire, a sixth inner wire and a second edge line which are connected end to end in sequence, the third inner wire is parallel to and adjacent to the first inner wire, and a first channel is between the first inner wire and the third inner wire; the fourth inner wire is parallel to and adjacent to the second inner wire, and a second channel is between the fourth inner wire and the second inner wire.

8. The construction method according to claim 7, characterized in that: The third construction area includes a third edge line and a seventh internal wiring line, an eighth internal wiring line, and a ninth internal wiring line connected in sequence. The seventh internal wiring line is parallel to and adjacent to the sixth internal wiring line, and a third channel is formed between the seventh internal wiring line and the sixth internal wiring line; the eighth internal wiring line is parallel to and adjacent to the fifth internal wiring line, and a fourth channel is formed between the fifth internal wiring line and the eighth internal wiring line; the ninth internal wiring line is collinearly arranged with the fourth internal wiring line, and the ninth internal wiring line is parallel to and adjacent to the second internal wiring line, and a fifth channel is formed between the second internal wiring line and the ninth internal wiring line; the third edge line is connected between the seventh internal wiring line and the ninth internal wiring line.

9. The construction method according to claim 2, characterized in that: The flow construction at least includes equipment installation, photovoltaic bracket installation, cable laying and photovoltaic panel installation.

10. The construction method according to claim 9, characterized in that: The different construction areas are simultaneously carrying out flow construction, including: Installing the equipment in the first construction area, including setting up a substation and laying a collector line; transporting the photovoltaic panel to the second construction area, and inspecting the performance parameters of the photovoltaic panel at the second construction area; Installing the photovoltaic support and laying the cables in the third construction area; After the photovoltaic support and the cables in the third construction area are laid, the photovoltaic panels are installed on the photovoltaic support.

Citation Information

Patent Citations

  • Offshore mud flat fixed pipe pile photovoltaic multifunctional construction equipment and construction method

    CN116556397A

  • Offshore photovoltaic device and offshore photovoltaic construction operation method

    CN117155220A

  • Construction method of offshore photovoltaic platform

    CN118422657A

  • Offshore floating type photovoltaic power generation primary system design method

    CN119010778A

  • Method and Device for virtual construction

    KR102389872B1