Mine sump sludge cleaning system

By designing a sludge cleaning system for mining water silt, and using excavation and pumping mechanisms to clean and transport the sludge to the goaf filling area, the problems of high labor intensity, low efficiency and mud pollution in the existing technology are solved, and efficient and environmentally friendly sludge treatment and filling effects are achieved.

CN119754365AInactive Publication Date: 2025-04-04FENY
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411988707.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-31
Publication Date
2025-04-04
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing mining silt cleaning technology has problems such as high labor intensity, low efficiency, mud pollution, and high equipment linkage, complex process and low efficiency.

Method used

A silt cleaning system for mining water silt is designed, including a mining clearance machine, a mining concrete conveying pump and a feeding machine. The silt is cleaned and transported to the gou filling area through the excavation and loading mechanism and the pumping mechanism. The mixing mechanism is mixed with the gelling material and pumped directly to avoid lifting to the surface and the yard.

Benefits of technology

The direct operation of sludge cleaning and filling is realized, avoiding mud stacking and pollution along the way, the process is simple, environmentally friendly, efficient, and the overall cost is low.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119754365A_ABST
    Figure CN119754365A_ABST
Patent Text Reader

Abstract

The invention provides a mine sump sludge cleaning system. The mine sump sludge cleaning system comprises a mine sump cleaning machine, a mine concrete conveying pump and a feeding machine. A digging and loading mechanism and a first pumping mechanism are arranged on the mining clearance machine; an upper stirring mechanism, a second pumping mechanism and a power mechanism are arranged on the mining concrete delivery pump; the power mechanism is in driving connection with the upper stirring mechanism and the second pumping mechanism so as to drive the upper stirring mechanism and the second pumping mechanism to operate. A discharging opening of the feeding machine is communicated with a feeding opening of the upper stirring mechanism so as to provide a cementing material to the upper stirring mechanism; a discharge hole of the upper stirring mechanism is communicated with a feeding hopper of the second pumping mechanism; the first pumping mechanism is communicated with the feeding hole through a material conveying pipeline so as to convey sludge to the upper stirring mechanism; and the second pumping mechanism is communicated with the mined-out filling area through a discharging pipeline. According to the scheme provided by the invention, the water sump sludge can be directly conveyed to the goaf filling area for filling, and the problem that the environment is polluted due to the fact that the sludge is stacked and scattered along the way is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of mining water tank sludge cleaning, and in particular relates to a mining water tank sludge cleaning system. Background Art

[0002] When the silt in the mine water tank reaches a certain amount, it must be cleaned. At present, the commonly used methods for desilting the water tank in mines include: (1) Manual cleaning: Use a shovel to shovel the sludge into a sack or mine car, carry it on your shoulders, push it by hand or use a winch to pull it out of the bin, filter it dry and then transport it to the goaf or lift it to the ground for storage. This method is labor-intensive and inefficient, and the mud is spilled along the way, polluting the environment.

[0003] (2) The use of mechanized excavation such as loaders and scraper conveyors can reduce the labor intensity of workers and speed up the cleaning process. Compared with manual cleaning, the efficiency is greatly improved. However, due to the limited space in the water tank, mechanical excavation is often not able to be carried out, which makes it very inflexible and the excavation effect is average. In addition, there is still the problem of mud spilling along the way and polluting the environment during transportation.

[0004] (3) Use a complete set of equipment for clearing and filtering. After the water jet slurry suction, pipeline pumping out of the bin, and solid-liquid separation in the filter press, the clean water flows back to the water bin, and the dry material is transported to the ground for storage. This method solves the problem of difficulty in dredging sludge and mud spilling along the way to pollute the environment to a certain extent, but it also has the disadvantages of complex procedures, high requirements for equipment linkage, and low efficiency. After the dry material is hoisted and transported to the surface by belt conveyors, mine cars, vertical shafts, etc., it must be transferred to the yard by mine trucks for retention. During the transportation process, it will also cause pollution to the hoisting and transportation lines and the surface environment.

[0005] Based on the technical problems existing in the treatment of the above-mentioned mine sump sedimentation sludge, there is no relevant solution yet; therefore, there is an urgent need to find effective solutions to solve the above-mentioned problems. Summary of the invention

[0006] The purpose of the present invention is to address the deficiencies in the above-mentioned technologies and to propose a mining water tank sludge cleaning system, which aims to solve the problem of existing mining water tank sedimentation sludge treatment.

[0007] The invention provides a silt cleaning system for a mining water tank, which comprises a mining tank cleaning machine, a mining concrete delivery pump and a feeding machine; the mining tank cleaning machine is provided with a digging mechanism and a first pumping mechanism; the digging mechanism is used to clean the silt and transmit it to the first pumping mechanism; the mining concrete delivery pump is provided with an upper stirring mechanism, a second pumping mechanism and a power mechanism; the power mechanism is respectively connected to the upper stirring mechanism and the second pumping mechanism to drive the upper stirring mechanism and the second pumping mechanism to operate; the discharge port of the feeding machine is connected with the feed port of the upper stirring mechanism to provide a cementitious material to the upper stirring mechanism; the discharge port of the upper stirring mechanism is connected with the feed hopper of the second pumping mechanism; the first pumping mechanism is connected with the feed port through a feeding pipeline to transport the silt to the upper stirring mechanism; the second pumping mechanism is connected with a goaf filling area through a discharge pipeline to transport the silt after mixing the cementitious material to the goaf filling area.

[0008] In some embodiments, a mining clearing machine includes a frame chassis, a traveling mechanism is provided at the bottom of the frame chassis, a digging and loading mechanism is provided at one end of the frame chassis, and a first pumping mechanism is provided at the other end of the frame chassis; an electromagnetic starter, a drive motor, an oil pump group, an operating table, a radiator and a plurality of control valves are also provided on the frame chassis; the electromagnetic starter is electrically connected to the drive motor, and the drive motor is connected to a plurality of control valves; and the plurality of control valves are respectively connected to the traveling mechanism, the digging and loading mechanism, the first pumping mechanism, the operating table and the radiator.

[0009] In some embodiments, the digging and loading mechanism includes a digging and loading frame and a conveying device, a spiral material collecting device is provided at one end of the digging and loading frame, and a driving assembly is provided at the other end of the digging and loading frame; the driving assembly is transmission-connected to one end of the conveying device to drive the conveying device to operate in the digging and loading frame; the other end of the conveying device is transmission-connected to the spiral material collecting device to drive the spiral material collecting device to operate.

[0010] In some embodiments, the spiral aggregate device is provided with a driven sprocket shaft, which is rotatably arranged in the spiral aggregate device, and the driven sprocket shaft is provided with a driven sprocket, a left spiral blade and a right spiral blade; the driving assembly includes a driving sprocket shaft and a first hydraulic motor, and the driving sprocket shaft is provided with a driving sprocket; the first hydraulic motor is transmission-connected to the driving sprocket shaft to drive the driving sprocket shaft to rotate; the conveying device is a scraper conveying device, and the scraper conveying device includes a chain, and a plurality of scrapers are provided on the chain; one end of the chain is sleeved on the driving sprocket, and one end of the chain is sleeved on the driven sprocket, and can run synchronously with the driving sprocket and the driven sprocket, thereby driving the scraper to transport the sludge in the spiral aggregate device to the feed hopper of the first pumping mechanism.

[0011] In some embodiments, the first pumping mechanism includes a feed hopper, a first swinging cylinder, a first S valve and a first piston delivery cylinder; the first S valve is arranged in the feed hopper; the first piston delivery cylinder is arranged on one side of the feed hopper and is connected to the first S valve; the first swinging cylinder is arranged on the feed hopper and is connected to the control end of the first S valve; a first pressure outlet is also provided on the side wall of the feed hopper, one end of the first pressure outlet is connected to the first S valve; the other end of the first pressure outlet is connected to one end of the delivery pipeline; the first S valve is also connected to one outlet of the first piston delivery cylinder, and the other outlet of the first piston delivery cylinder is connected to the feed hopper.

[0012] In some embodiments, the upper stirring mechanism includes a casing, a stirring shaft and a driving box; the feed port is arranged at one end of the casing, the discharge port is arranged at the other end of the casing, and a water supply pipeline is arranged on the side of the feed port; the driving box is arranged at one end of the casing; the stirring shaft is rotatably arranged in the casing, and a plurality of stirring blades are arranged on the stirring shaft; one end of the stirring shaft is transmission-connected to the driving box, and the other end of the stirring shaft is rotatably arranged at the other end of the casing through a bearing seat; a first hydraulic motor is arranged on the driving shaft of the driving box; an electromagnetic flowmeter and an electric regulating valve are arranged on the water supply pipeline, and the electromagnetic flowmeter and the electric regulating valve are electrically connected to the control console respectively.

[0013] In some embodiments, the second pumping mechanism includes a second swinging cylinder, a second S valve, a second hydraulic motor and a second piston delivery cylinder; the second S valve is arranged in the feed hopper; the second piston delivery cylinder is arranged on one side of the feed hopper and is connected to the second S valve; the second swinging cylinder is arranged on the outside of the feed hopper and is connected to the control end of the second S valve; a stirring shaft is provided in the feed hopper; the second hydraulic motor is arranged on the outside of the feed hopper and is transmission-connected to the stirring shaft; a second pressure outlet is also provided on the side wall of the feed hopper, one end of the second pressure outlet is connected to the second S valve, and the other end of the second pressure outlet is connected to one end of the discharge pipeline; the second S valve is also connected to one outlet of the second piston delivery cylinder, and the other outlet of the second piston delivery cylinder is connected to the feed hopper.

[0014] In some embodiments, the power mechanism includes a power frame and an electromagnetic starter, a drive motor and an oil pump group are provided on the power frame, the electromagnetic starter is arranged on one side of the power frame and is electrically connected to the drive motor; the drive motor is connected to the oil pump group, the oil pump group is connected to a plurality of control valves through hydraulic pipelines, and the plurality of control valves are respectively connected to the main cylinder of the second piston delivery cylinder, the first hydraulic motor on the upper stirring mechanism, the second swing cylinder, and the second hydraulic motor.

[0015] In some embodiments, the loader is a spiral loader; the spiral loader includes a spiral tube, a spiral shaft, a variable frequency motor and an electric control box; a feed port is provided at one end of the spiral tube, and a discharge port is provided at the other end of the spiral tube; a spiral blade is fixedly provided on the spiral shaft; the variable frequency motor is provided on the spiral tube and is transmission-connected to the spiral shaft; a speed sensor is also provided on the spiral shaft; the electric control box is electrically connected to the variable frequency motor to control the operation of the variable frequency motor; the speed sensor and the electric control box are electrically connected to the control console respectively.

[0016] In some embodiments, an electromagnetic flowmeter and an online slurry density meter are provided on the material delivery pipeline; the electromagnetic flowmeter and the online slurry density meter are electrically connected to a control console, respectively; a PLC programmable controller and a liquid crystal touch screen are provided on the control console; the controller controls the real-time water supply by acquiring the signal data detected by the electromagnetic flowmeter and adjusting the valve opening through an electric regulating valve controller.

[0017] The present invention provides a mining water tank sludge cleaning system, which does not need to lift the water tank sludge to the surface, nor does it need to set up a yard on the surface. The water tank sludge can be directly transported to the goaf filling area for filling, solving the problem of mud stacking and spilling along the way to pollute the environment. It has the advantages of simple process, green environmental protection, high efficiency and low comprehensive cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0019] The present invention will be further described below in conjunction with the accompanying drawings: Figure 1 This is an overall schematic diagram of a mining water tank sludge cleaning system of the present invention; Figure 2 It is a structural schematic diagram of the mine cleaning machine of the present invention; Figure 3 It is a structural schematic diagram of the excavation and loading mechanism of the present invention; Figure 4 It is a structural schematic diagram of the first pumping mechanism of the present invention; Figure 5 It is a structural schematic diagram of a mining concrete delivery pump with an upper stirring mechanism according to the present invention; Figure 6 It is a structural schematic diagram of the stirring mechanism of the present invention; Figure 7 is a schematic structural diagram of the second pumping mechanism of the present invention; Figure 8 It is a structural schematic diagram of the spiral feeder of the present invention.

[0020] In the figure: 1. Mining warehouse cleaning machine; 2. Mining concrete pump; 3. Screw feeder; 4. Electromagnetic flowmeter; 5. Slurry online density meter; 6. Control panel; 7. Frame chassis; 8. Crawler travel mechanism; 9. Digging and loading mechanism; 10. Digging and loading frame; 11. Screw collecting device; 12. Driven sprocket shaft; 13. Driven sprocket; 14. Left spiral blade; 15. Right spiral blade; 16. Scraper conveying device; 17. Driving sprocket shaft; 18. Driving sprocket; 19. Chain; 20. Scraper; 21. First hydraulic motor ; 22, lifting cylinder; 23, first pumping mechanism; 24, feed hopper; 25, first cylinder; 26, first master cylinder; 27, first delivery piston; 28, first master cylinder piston rod; 29, first water tank; 30, first swing cylinder; 31, first S valve; 32, first pressure outlet; 33, vacuum electromagnetic starter; 34, first drive motor; 35, first oil pump group; 36, operating table; 37, radiator; 38, work Frame; 39, upper stirring mechanism; 40, casing; 41, stirring shaft; 42, stirring blade; 43, driving box; 44, first hydraulic motor; 45, bearing seat; 46, feed port; 47, water supply pipeline; 48, discharge port; 49, second pumping mechanism; 50, feed hopper; 51, second material cylinder; 52, second main oil cylinder; 53, second delivery piston; 54, second main oil cylinder piston rod; 55, second water tank; 56, second swing Oil cylinder; 57, second S valve; 58, stirring shaft; 59, second pressure outlet; 60, power chassis; 61, second drive motor; 62, second oil pump group; 63, electromagnetic starter; 64, second hydraulic motor; 65, spiral tube; 66, feed inlet; 67, discharge outlet; 68, spiral shaft; 69, spiral blade; 70, variable frequency motor; 71, electric control box; 72, speed sensor; 73, feed pipeline; 74, discharge pipeline. DETAILED DESCRIPTION

[0021] In order to make the technical problems, technical solutions and beneficial effects to be solved by the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0022] It should be noted that when an element is referred to as being "fixed to" or "disposed on" another element, it can be directly on the other element or indirectly on the other element. When an element is referred to as being "connected to" another element, it can be directly connected to the other element or indirectly connected to the other element.

[0023] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "multiple" is two or more, unless otherwise clearly and specifically defined. The meaning of "several" is one or more, unless otherwise clearly and specifically defined.

[0024] In the description of the present invention, it is necessary to understand that the directions or positional relationships indicated by the terms "up", "down", "front", "back", "left", "right", etc. are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.

[0025] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0026] As shown in Figure 1 to Figure 8As shown, the present invention provides a mining water tank sludge cleaning system, which includes a mining tank cleaning machine 1, a mining concrete delivery pump 2 and a feeder. The mining tank cleaning machine 1 is provided with a digging mechanism 9 and a first pumping mechanism 23; the digging mechanism 9 is used to clean the sludge and transfer it to the first pumping mechanism 23; the mining concrete delivery pump 2 is provided with an upper stirring mechanism 39, a second pumping mechanism 49 and a power mechanism. The upper stirring mechanism 39 is integrated with the working frame 38, or can be split. The power mechanism is respectively connected to the upper stirring mechanism 39 and the second pumping mechanism 49 to drive the upper stirring mechanism 39 and the second pumping mechanism 49 to operate. The discharge port 67 of the feeder is connected to the feed port 46 of the upper stirring mechanism 39 to provide cementitious material to the upper stirring mechanism 39. The discharge port 48 of the upper stirring mechanism 39 is connected to the feed hopper 50 of the second pumping mechanism 49; the first pumping mechanism 23 is connected to the feed port 46 through the feeding pipeline 73 to transport sludge to the upper stirring mechanism 39; the second pumping mechanism 49 is connected to the goaf filling area through the discharge pipeline 74 to transport the sludge after mixing the cementitious material to the goaf filling area. The cementitious material includes cement, quicklime and other cementitious solidifying materials, which can change the gap structure between the sludge particles, increase the strength and stability of the sludge, and thus meet the requirements of filling the goaf filling area.

[0027] The mining water tank sludge cleaning system provided by the present invention does not send the sludge to the well after the water tank is cleaned. Instead, the sludge is directly pumped to the goaf filling area by adding a certain proportion of cementitious materials and stirring and mixing. This method does not require the sludge to be lifted to the surface, nor does it require a yard to be set up on the surface, which solves the problem of mud stacking and spilling along the way to pollute the environment, while taking into account the filling of the goaf, and has the advantages of simple process, green environmental protection, high efficiency and low comprehensive cost.

[0028] As shown in Figure 1 to Figure 8As shown, in some embodiments, the mine clearing machine 1 includes a frame chassis 7, and a traveling mechanism is provided at the bottom of the frame chassis 7, and the traveling mechanism is preferably a crawler traveling mechanism 8 or a tire-type or rail-wheel traveling mechanism. The digging and loading mechanism 9 is arranged at one end of the frame chassis 7, and the first pumping mechanism 23 is arranged at the other end of the frame chassis 7; the frame chassis 7 is also provided with an electromagnetic starter 33, a first drive motor 34, an oil pump group 35, an operating table 36, a radiator 37 and a plurality of control valves. The radiator 37 is an air-cooled radiator, which functions to cool the hydraulic oil, and is specifically installed in the oil return path from the control valve to the hydraulic oil tank. The electromagnetic starter 33 is electrically connected to the first drive motor 34, and the first drive motor 34 is connected to a plurality of control valves; the plurality of control valves are respectively connected to the traveling mechanism, the digging and loading mechanism 9, the first pumping mechanism 23, the operating table 36, and the radiator 37 to realize drive control. Specifically, the oil pump group 35 includes a main oil pump and multiple auxiliary oil pumps. The pressure oil generated by the auxiliary oil pump drives the first hydraulic motor 21 of the digging and loading mechanism 9 to operate, drives the scraper 20 in the digging and loading mechanism 9 to work, and at the same time drives the left spiral blade 14 and the right spiral blade 15 of the spiral collecting device 11 to work, collects the sludge, and transports it to the feed hopper 24 by the scraper 20; the pressure oil generated by the main oil pump drives the first piston rods 28 of the two first main oil cylinders 26 to move, drives the first delivery pistons 27 in the first material cylinders 25 of the two delivery cylinders to produce alternating reciprocating motion; the pressure oil generated by the auxiliary oil pump drives the first swinging cylinder 30 to move, drives the first S valve 31 to swing back and forth, and connects the piston delivery cylinder with the first pressure outlet 32; at the same time, the auxiliary oil pump also drives the travel motor of the crawler travel mechanism 8 to drive the entire mining cleaning machine 1 to move. Due to the coordinated actions among the crawler-type walking mechanism 8, the digging and loading mechanism 9 and the first pumping mechanism 23, the sludge is continuously transported from the water tank through the pipeline to the feed port 46 of the mining concrete delivery pump 2 with the upper mixing mechanism.

[0029] As shown in Figure 1 to Figure 8 As shown, in some embodiments, the digging and loading mechanism 9 includes a digging and loading frame 10 and a conveying device, and the conveying device is a scraper conveying device 16 or a chain bucket conveying device. A spiral collecting device 11 is provided at one end of the digging and loading frame 10, and a driving assembly is provided at the other end of the digging and loading frame 10; the driving assembly is connected to one end of the conveying device to drive the conveying device to operate in the digging and loading frame 10; the other end of the conveying device is connected to the spiral collecting device 11 to drive the spiral collecting device 11 to operate. A lifting cylinder 22 is provided at the lower part of the digging and loading frame 10, and the other end of the lifting cylinder 22 is connected to the frame chassis 7 to realize the lifting function. Specifically, when the mine cleaning machine 1 is empty, the digging and loading mechanism 9 is lifted off the ground by the lifting cylinder 22 to reduce friction resistance; during the digging and loading work, if the silt is accumulated too high, it is easy to collapse and cause an accident when cleaning from the bottom layer. At this time, the digging and loading mechanism 9 can be lifted to a suitable height by the lifting cylinder 22, and the silt on the upper layer is cleaned first, and then the silt on the lower layer is cleaned.

[0030] As shown in Figure 1 to Figure 8 As shown, in some embodiments, the spiral material collecting device 11 is provided with a driven sprocket shaft 12, which is rotatably arranged in the spiral material collecting device 11, and the driven sprocket shaft 12 is provided with a driven sprocket 13, a left spiral blade 14 and a right spiral blade 15. The driving assembly includes a driving sprocket shaft 17 and a first hydraulic motor 21, and the driving sprocket shaft 17 is provided with a driving sprocket 18; the first hydraulic motor 21 is transmission-connected with the driving sprocket shaft 17 to drive the driving sprocket shaft 17 to rotate. The conveying device is a scraper conveying device 16, and the scraper conveying device 16 includes a chain 19, and a plurality of scrapers 20 are provided on the chain 19; one end of the chain 19 is sleeved on the driving sprocket 18, and one end of the chain 19 is sleeved on the driven sprocket 13, and can run synchronously with the driving sprocket 18 and the driven sprocket 13, thereby driving the scraper 20 to transport the sludge in the spiral material collecting device 11 to the feed hopper 24 of the first pumping mechanism 23.

[0031] As shown in Figure 1 to Figure 8 As shown, in some embodiments, the first pumping mechanism 23 includes a feed hopper 24, a first swing oil cylinder 30, a first S valve 31 and a first piston delivery cylinder; wherein the first S valve 31 is arranged in the feed hopper 24; the first piston delivery cylinder is arranged on one side of the feed hopper 24 and is connected to the first S valve 31; the first swing oil cylinder 30 is arranged on the feed hopper 24 and is connected to the control end of the first S valve 31; a first pressure outlet 32 ​​is also arranged on the side wall of the feed hopper 24, one end of the first pressure outlet 32 ​​is connected to the first S valve 31; the other end of the first pressure outlet 32 ​​is connected to one end of the material delivery pipeline 73; the first S valve 31 is also connected to an outlet of the first piston delivery cylinder to realize sludge pumping; the other outlet of the first piston delivery cylinder is connected to the feed hopper 24 to realize sludge delivery. The first piston delivery cylinder is used to provide pumping pressure. Specifically, the first piston delivery cylinder includes two first material cylinders 25 arranged in parallel, the other end of the first material cylinder 25 is connected to the first master cylinder 26, a first delivery piston 27 is arranged in the first material cylinder 25, a first master cylinder piston rod 28 is arranged in the first master cylinder 26, and the first master cylinder piston rod 28 is connected to the first delivery piston 27. A first water tank 29 is arranged between the first material cylinder 25 and the first master cylinder 26, and the first water tank 29 connects the first material cylinder 25 and the first master cylinder 26, cools the first material cylinder 25, the first delivery piston 27 and the first master cylinder piston rod 28, and flushes the inner wall of the first material cylinder 25.

[0032] As shown in Figure 1 to Figure 8As shown, in some embodiments, the upper stirring mechanism 39 includes a housing 40, a stirring shaft 41 and a driving box 43; a feed port 46 is arranged at one end of the housing 40, a discharge port 48 is arranged at the other end of the housing 40, and a water supply pipeline 47 is arranged on the side of the feed port 46. The driving box 43 is arranged at one end of the housing 40; the stirring shaft 41 is rotatably arranged in the housing 40, and a plurality of stirring blades 42 are arranged on the stirring shaft 41; one end of the stirring shaft 41 is transmission-connected with the driving box 43, and the other end of the stirring shaft 41 is rotatably arranged at the other end of the housing 40 through a bearing seat 45; a first hydraulic motor 44 is arranged on the driving shaft of the driving box 43; and an electromagnetic flowmeter and an electric regulating valve are arranged on the water supply pipeline 47, and the electromagnetic flowmeter and the electric regulating valve are respectively electrically connected to the control console 6, so that the water supply can be monitored and adjusted in real time. Specifically, the control console 6 includes a PLC programmable controller and a liquid crystal touch screen, so as to obtain the signal data detected by the electromagnetic flowmeter 4 and the slurry online density meter 5 in real time, calculate the concentration and flow rate of the real-time transported sludge, and determine the mass of the cementitious material to be added according to the filling strength requirements of the goaf and the material formula determined in advance through the strength test; obtain the data of the speed sensor of the spiral feeder in real time, adjust the speed of the frequency conversion motor 70 in real time through the frequency conversion controller, and control the amount of cementitious material transported; obtain the signal data detected by the electromagnetic flowmeter on the water supply pipeline, adjust the valve opening through the electric regulating valve controller, and control the real-time water supply.

[0033] As shown in Figure 1 to Figure 8As shown, in some embodiments, the second pumping mechanism 49 includes a second swing oil cylinder 56, a second S valve 57, a second hydraulic motor 64 and a second piston delivery cylinder; the second S valve 57 is arranged in the feed hopper 50; the second piston delivery cylinder is arranged on one side of the feed hopper 50 and is connected to the second S valve 57; the second swing oil cylinder 56 is arranged on the outside of the feed hopper 50 and is connected to the control end of the second S valve 57; a stirring shaft 58 is arranged in the feed hopper 50; the second hydraulic motor 64 is arranged on the outside of the feed hopper 50 and is transmission-connected to the stirring shaft 58; a second pressure outlet 59 is also arranged on the side wall of the feed hopper 50, one end of the second pressure outlet 59 is connected to the second S valve 57, and the other end of the second pressure outlet 59 is connected to one end of the discharge pipeline 74; the second S valve 57 is also connected to an outlet of the second piston delivery cylinder to realize sludge pumping; the other outlet of the second piston delivery cylinder is connected to the feed hopper 50. The second piston delivery cylinder is used to provide pumping pressure. Specifically, the second piston delivery cylinder is located in the middle of the working frame 38, and the second piston delivery cylinder includes two second material cylinders 51 arranged in parallel, and the other end of the second material cylinder 51 is connected to the second master cylinder 52, and the second material cylinder 51 is provided with a second delivery piston 53, and the second master cylinder 52 is provided with a second master cylinder piston rod 54, and the second master cylinder piston rod 54 is connected to the second delivery piston 53. A second water tank 55 is provided between the second material cylinder 51 and the second master cylinder 52; the second water tank 55 connects the second material cylinder 51 and the second master cylinder 52, cools the second material cylinder 51, the second delivery piston 53 and the second master cylinder piston rod 54, and flushes the inner wall of the second material cylinder 51.

[0034] In the present application, the designed S valve is specifically the first S valve and the second S valve. The specific working principle is: the S valve is connected to the piston delivery cylinder and the pressure outlet respectively. During normal pumping operation, the S valve is connected to an outlet of a piston delivery cylinder, and the delivery piston moves forward to pressurize the sludge and pump it out through the S valve. At the same time, the outlet of the other piston delivery cylinder is connected to the feed hopper (or feed inlet), and the delivery piston retreats to suck the sludge in the feed hopper (or feed inlet) into the piston delivery cylinder; through the control of the hydraulic reversing valve, the main oil cylinder piston is reversed, and a signal is sent to the swing oil cylinder to push the S valve to swing to the outlet of the other piston delivery cylinder and connect, so as to achieve cyclic reciprocating continuous pumping. When a short-term pipe blockage occurs, the reverse pump method can be used to clear the pipe blockage. Through the control valve reverse pump operation, the piston delivery cylinder in the suction stroke is connected to the S valve, and the piston delivery cylinder in the push stroke is connected to the feed hopper, so that the sludge in the delivery pipeline is drawn back to the feed hopper.

[0035] As shown in Figure 1 to Figure 8As shown, in some embodiments, the power mechanism includes a power frame 60 and an electromagnetic starter 63, and the electromagnetic starter 63 is a vacuum electromagnetic starter; a second drive motor 61 and an oil pump group 62 are provided on the power frame 60, and the electromagnetic starter 63 is arranged on one side of the power frame 60 and is electrically connected to the second drive motor 61; the second drive motor 61 is connected to the oil pump group 62, and the oil pump group 62 is connected to a plurality of control valves through hydraulic pipelines, and the plurality of control valves are respectively connected to the main cylinder 52 of the second piston delivery cylinder, the first hydraulic motor 44 on the upper stirring mechanism 39, the second swing cylinder 56, and the second hydraulic motor 64. The power supply provided by the electromagnetic starter 63 controls the second drive motor 61 to drive the second oil pump group 62 to work. The second oil pump group 62 includes a main oil pump and multiple auxiliary oil pumps. The pressure oil generated by the auxiliary oil pump drives the first hydraulic motor 44 of the upper stirring mechanism 39 to operate, driving the stirring shaft 41 in the upper stirring mechanism 39 to rotate, mixing the water tank sludge, cementitious materials, water and other materials added from the feed port 46, and then transporting them through the discharge port 48 to the lower hopper 50 for further mixing; the pressure oil generated by the main oil pump drives the second piston rods 54 of the two second main oil cylinders 52 to move, driving the second delivery pistons 53 in the second material cylinders 51 of the two delivery cylinders to produce alternating reciprocating motion; the pressure oil generated by the auxiliary oil pump drives the second swing cylinder 56 to move, driving the second S valve 57 to swing back and forth, connecting the piston delivery cylinder and the second pressure outlet 59. Through the coordinated action of the upper stirring mechanism 39 and the second pumping mechanism 49, the mixed slurry is transported to the goaf filling area through the pipeline.

[0036] As shown in Figure 1 to Figure 8 As shown, in some embodiments, the feeder is a spiral feeder 3. The spiral feeder 3 includes a spiral tube 65, a spiral shaft 68, a variable frequency motor 70 and an electric control box 71; one end of the spiral tube 65 is provided with a feed port 66, and a discharge port 67 is provided at the other end of the spiral tube 65; a spiral blade 69 is fixedly provided on the spiral shaft 68; the variable frequency motor 70 is provided on the spiral tube 65 and is transmission-connected with the spiral shaft 68; a speed sensor 72 is also provided on the spiral shaft 68; the electric control box 71 is electrically connected to the variable frequency motor 70 to control the operation of the variable frequency motor 70; the speed sensor 72 and the electric control box 71 are electrically connected to the control console 6 respectively, and can monitor and adjust the spiral shaft speed and the cementitious material delivery amount in real time.

[0037] As shown in Figure 1 to Figure 8As shown, in some embodiments, an electromagnetic flowmeter 4 and an online slurry density meter 5 are provided on the material delivery pipeline 73; the electromagnetic flowmeter 4 and the online slurry density meter 5 are electrically connected to the control console 6 respectively. A PLC programmable controller and a liquid crystal touch screen are provided on the control console 6; the controller controls the real-time water supply by acquiring the signal data detected by the electromagnetic flowmeter 4 and adjusting the valve opening through the electric regulating valve controller. The control console 6 includes a PLC programmable controller and a liquid crystal touch screen, which can acquire the signal data detected by the electromagnetic flowmeter 4 and the online slurry density meter 5 in real time, calculate the concentration and flow rate of the real-time sludge conveyed, and determine the mass of the cementitious material to be added according to the filling strength requirements of the goaf and the material formula determined in advance through the strength test; acquire the data of the speed sensor 72 on the spiral feeder 3 in real time, adjust the speed of the variable frequency motor 70 in real time through the variable frequency controller, and then control the speed of the spiral blade 69 and the delivery amount of the cementitious material; acquire the signal data detected by the electromagnetic flowmeter on the water supply pipeline 47, and adjust the valve opening through the electric regulating valve controller to control the real-time water supply, so as to realize the water supply regulation.

[0038] As shown in Figure 1 to Figure 8 As shown, the present invention provides a mining water tank sludge cleaning system. When working, the mining tank cleaning machine 1 enters the water tank, and the hydraulic system controls the coordinated actions of the crawler walking mechanism 8, the digging mechanism 9, and the first pumping mechanism 23 to transport the sludge to the feed port 46 of the mining concrete delivery pump 2 with the upper stirring mechanism; the PLC programmable controller of the control console 6 obtains the signal data detected by the electromagnetic flowmeter 4 and the slurry online density meter 5, calculates the real-time sludge concentration and flow rate, and determines the mass of the cementitious material to be added according to the filling strength requirements of the goaf and the material formula determined in advance by the strength test; the cementitious material is added to the feed port 66 of the spiral feeder 3, The PLC programmable controller obtains the signal data of the speed sensor 72 in real time, adjusts the speed of the variable frequency motor 70 in real time through the variable frequency controller, and drives the spiral blade 69 to rotate, so as to deliver the cementitious material to the feed port 46 of the mining concrete delivery pump 2 according to the demand; the upper stirring mechanism 39 of the mining concrete delivery pump 2 mixes the added silt and cementitious material, and then delivers them to the feed hopper 50 of the mining concrete delivery pump 2; the upper stirring mechanism 39 and the second pumping mechanism 49 are controlled by the hydraulic system to coordinate the action, and the mixed slurry is delivered to the goaf filling area. Among them, the concentration of the mixed slurry can be adjusted by adding water during stirring according to the filling requirements. The PLC programmable controller obtains the signal data detected by the electromagnetic flowmeter on the water supply pipeline, adjusts the valve opening through the electric regulating valve controller, and controls the real-time water supply.

[0039] The present invention provides a mining water tank sludge cleaning system, which does not need to lift the water tank sludge to the surface, nor does it need to set up a yard on the surface. The water tank sludge can be directly transported to the goaf filling area for filling, solving the problem of mud stacking and spilling along the way to pollute the environment. It has the advantages of simple process, green environmental protection, high efficiency and low comprehensive cost.

[0040] The above is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any technician familiar with the art can make many possible changes and modifications to the technical solution of the present invention by using the above-mentioned technical content without departing from the scope of the technical solution of the present invention, or modify it into an equivalent embodiment of equivalent changes. Therefore, any changes, modifications, equivalent changes and modifications made to the above embodiments based on the technology of the present invention without departing from the content of the technical solution of the present invention belong to the protection scope of the present technical solution.

Claims

1. A mining water tank sludge cleaning system, characterized in that: The cleaning system comprises a mine cleaning machine (1), a mine concrete delivery pump (2) and a feeder; the mine cleaning machine (1) is provided with a digging mechanism (9) and a first pumping mechanism (23); the digging mechanism (9) is used to clean sludge and transfer it to the first pumping mechanism (23); the mine concrete delivery pump (2) is provided with an upper stirring mechanism (39), a second pumping mechanism (49) and a power mechanism; the power mechanism is respectively connected to the upper stirring mechanism (39) and the second pumping mechanism (49) to drive the upper stirring mechanism (39) and the second pumping mechanism (49) to operate The discharge port (67) of the feeder is connected to the feed port (46) of the upper stirring mechanism (39) to provide the upper stirring mechanism (39) with a cementitious material; the discharge port (48) of the upper stirring mechanism (39) is connected to the feed hopper (50) of the second pumping mechanism (49); the first pumping mechanism (23) is connected to the feed port (46) via a feed pipeline (73) to transport sludge to the upper stirring mechanism (39); the second pumping mechanism (49) is connected to the void filling area via a discharge pipeline (74) to transport the sludge mixed with the cementitious material to the void filling area.

2. The mining water tank sludge cleaning system according to claim 1 is characterized in that: The mining bin clearing machine (1) comprises a chassis (7), a traveling mechanism is provided at the bottom of the chassis (7), the excavating mechanism (9) is arranged at one end of the chassis (7), and the first pumping mechanism (23) is arranged at the other end of the chassis (7); the chassis (7) is also provided with an electromagnetic starter (33), a first drive motor (34), an oil pump group (35), an operating table (36), a radiator (37) and a plurality of control valves; the electromagnetic starter (33) is electrically connected to the first drive motor (34), and the first drive motor (34) is connected to the plurality of control valves; the plurality of control valves are respectively connected to the traveling mechanism, the excavating mechanism (9), the first pumping mechanism (23), the operating table (36) and the radiator (37).

3. The mining water tank sludge cleaning system according to claim 1 is characterized in that: The digging and loading mechanism (9) comprises a digging and loading frame (10) and a conveying device; one end of the digging and loading frame (10) is provided with a spiral material collecting device (11), and the other end of the digging and loading frame (10) is provided with a driving assembly; the driving assembly is transmission-connected to one end of the conveying device to drive the conveying device to operate in the digging and loading frame (10); the other end of the conveying device is transmission-connected to the spiral material collecting device (11) to drive the spiral material collecting device (11) to operate.

4. The mining water tank sludge cleaning system according to claim 3 is characterized in that: The spiral material collecting device (11) is provided with a driven sprocket shaft (12), the driven sprocket shaft (12) is rotatably arranged in the spiral material collecting device (11), and the driven sprocket shaft (12) is provided with a driven sprocket (13), a left spiral blade (14), and a right spiral blade (15); the driving component comprises a driving sprocket shaft (17) and a first hydraulic motor (21), the driving sprocket shaft (17) is provided with a driving sprocket (18); the first hydraulic motor (21) is in transmission connection with the driving sprocket shaft (17) to drive the driving sprocket shaft (17) The conveying device is a scraper conveying device (16), and the scraper conveying device (16) includes a chain (19), and a plurality of scrapers (20) are provided on the chain (19); one end of the chain (19) is sleeved on the driving sprocket (18), and one end of the chain (19) is sleeved on the driven sprocket (13), and can run synchronously with the driving sprocket (18) and the driven sprocket (13), thereby driving the scraper (20) to transport the sludge in the spiral collecting device (11) to the feed hopper (24) of the first pumping mechanism (23).

5. The mining water tank sludge cleaning system according to claim 1 is characterized in that: The first pumping mechanism (23) comprises a feed hopper (24), a first swinging oil cylinder (30), a first S valve (31) and a first piston delivery cylinder; the first S valve (31) is arranged in the feed hopper (24); the first piston delivery cylinder is arranged on one side of the feed hopper (24) and is in communication with the first S valve (31); the first swinging oil cylinder (30) is arranged on the feed hopper (24) and is in communication with the control end of the first S valve (31); a first pressure outlet (32) is also arranged on the side wall of the feed hopper (24); one end of the first pressure outlet (32) is in communication with the first S valve (31); the other end of the first pressure outlet (32) is in communication with one end of the material delivery pipeline (73); the first S valve (31) is also in communication with one outlet of the first piston delivery cylinder, and the other outlet of the first piston delivery cylinder is in communication with the feed hopper (24).

6. The mining water tank sludge cleaning system according to claim 1, characterized in that: The upper stirring mechanism (39) comprises a casing (40), a stirring shaft (41) and a driving box (43); the feed port (46) is arranged at one end of the casing (40), the discharge port (48) is arranged at the other end of the casing (40), and a water supply pipeline (47) is arranged on the side of the feed port (46); the driving box (43) is arranged at one end of the casing (40); the stirring shaft (41) is rotatably arranged in the casing (40), and the stirring shaft (41) is rotatably arranged in the casing (40). (41) is provided with a plurality of stirring blades (42); one end of the stirring shaft (41) is transmission-connected to the driving box (43), and the other end of the stirring shaft (41) is rotatably arranged on the other end of the casing (40) through a bearing seat (45); a first hydraulic motor (44) is provided on the driving shaft of the driving box (43); an electromagnetic flowmeter and an electric regulating valve are provided on the water supply pipeline (47), and the electromagnetic flowmeter and the electric regulating valve are respectively electrically connected to the control console (6).

7. The mining water tank sludge cleaning system according to claim 1, characterized in that: The second pumping mechanism (49) comprises a second swinging oil cylinder (56), a second S valve (57), a second hydraulic motor (64) and a second piston delivery cylinder; the second S valve (57) is arranged in the feed hopper (50); the second piston delivery cylinder is arranged on one side of the feed hopper (50) and is communicated with the second S valve (57); the second swinging oil cylinder (56) is arranged on the outside of the feed hopper (50) and is communicated with the control end of the second S valve (57); a stirring shaft (58) is arranged in the feed hopper (50); A second hydraulic motor (64) is arranged on the outside of the feed hopper (50) and is transmission-connected to the stirring shaft (58); a second pressure outlet (59) is also provided on the side wall of the feed hopper (50); one end of the second pressure outlet (59) is connected to the second S-valve (57), and the other end of the second pressure outlet (59) is connected to one end of the discharge pipeline (74); the second S-valve (57) is also connected to an outlet of the second piston delivery cylinder, and the other outlet of the second piston delivery cylinder is connected to the feed hopper (50).

8. The mining water tank sludge cleaning system according to claim 7, characterized in that: The power mechanism comprises a power frame (60) and an electromagnetic starter (63); a second drive motor (61) and an oil pump group (62) are provided on the power frame (60); the electromagnetic starter (63) is arranged on one side of the power frame (60) and is electrically connected to the second drive motor (61); the second drive motor (61) is connected to the oil pump group (62); the oil pump group (62) is connected to a plurality of control valves via hydraulic pipelines; the plurality of control valves are respectively connected to a main oil cylinder (52) of the second piston delivery cylinder, a first hydraulic motor (44) on the upper stirring mechanism (39), the second swing oil cylinder (56), and the second hydraulic motor (64).

9. The mining water tank sludge cleaning system according to claim 1, characterized in that: The feeder is a spiral feeder (3); the spiral feeder (3) comprises a spiral tube (65), a spiral shaft (68), a variable frequency motor (70) and an electric control box (71); a feed port (66) is provided at one end of the spiral tube (65), and a discharge port (67) is provided at the other end of the spiral tube (65); a spiral blade (69) is fixedly provided on the spiral shaft (68); the variable frequency motor (70) is provided on the spiral tube (65) and is transmission-connected to the spiral shaft (68); a speed sensor (72) is also provided on the spiral shaft (68); the electric control box (71) is electrically connected to the variable frequency motor (70) to control the operation of the variable frequency motor (70); the speed sensor (72) and the electric control box (71) are respectively electrically connected to a control console (6).

10. The mining water tank sludge cleaning system according to claim 1, characterized in that: The material delivery pipeline (73) is provided with an electromagnetic flowmeter (4) and an online slurry density meter (5); the electromagnetic flowmeter (4) and the online slurry density meter (5) are respectively electrically connected to a control panel (6); the control panel (6) is provided with a PLC programmable controller and a liquid crystal touch screen; the controller controls the real-time water supply by acquiring the signal data detected by the electromagnetic flowmeter (4) and adjusting the valve opening through an electric regulating valve controller.

Citation Information

Patent Citations

  • Phosphogypsum cementing and post-filling mining method and pulping technology thereof

    CN101008316A

  • Coal mining and filling method

    CN116498376A

  • Sticky material conveyor

    CN205172857U

  • A type of underground water tank cleaning robot

    CN215165917U

  • Swing mechanism and concrete pumping equipment

    CN216241139U