Construction progress real-time display method suitable for foundation pit open cut method construction

By automatically collecting construction conditions and updating the foundation pit model using the GNSS Beidou positioning platform, the problem that the existing technology cannot meet the real-time management and control needs of the construction site is solved, real-time display of construction progress and reduction of labor costs are achieved.

CN119810307APending Publication Date: 2025-04-11SHANGHAI CONSTRUCTION GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411578744.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-07
Publication Date
2025-04-11

AI Technical Summary

Technical Problem

The visual display method at the existing construction site cannot meet the real-time management and control needs, and it consumes a lot of labor and is costly.

Method used

By automatically collecting construction conditions, using GNSS Beidou positioning platform and professional modeling software, the foundation pit model is established and updated to realize real-time display of excavator positioning and construction progress.

Benefits of technology

Real-time display of construction progress is achieved without manual intervention, reducing labor costs and workload, and the construction progress can be displayed in minutes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119810307A_ABST
    Figure CN119810307A_ABST
Patent Text Reader

Abstract

The invention relates to a construction progress real-time display method suitable for foundation pit open cut method construction, and the method comprises the steps: firstly, building a model: 1, preliminarily building the model, and drawing a whole foundation pit model through professional modeling software; 2, real foundation pit three-dimensional coordinate positioning; 3, assigning three-dimensional space information to ensure that the three-dimensional coordinates of points, lines and planes of the model are completely consistent with the three-dimensional coordinates of a real foundation pit; 4, partitioning the model, and dividing the soil body in the whole excavation area into a plurality of cube blocks, cuboid blocks or prismoids; 5, color blocks are designed, and three different color blocks are used for distinguishing; then, obtaining positioning information: 1, constructing a positioning platform, constructing a GNSS Beidou positioning platform, importing a foundation pit model, and determining the position of the model according to coordinates; 2, equipment installation; 3, positioning information is received, and space coordinates of the excavator are obtained based on a positioning platform; and finally, three-dimensional display of the construction progress: 1, excavator positioning information display, and 2, instant display of the construction progress.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of intelligent management of construction sites, and in particular relates to a real-time display method of construction progress applicable to open excavation construction of foundation pits. Background Art

[0002] Currently, there are two ways to visualize the construction site: one is to establish a BIM model for model display, and the other is to use drones to shoot videos from high altitude. However, there are the following problems:

[0003] 1) Not real-time enough. The BIM model requires manual modification of the model to display the working conditions and progress, which will cause a certain amount of time delay. The drone project progress display requires a second flight and a lot of post-processing of the video data, which also takes 1-2 days of work. It cannot meet the needs of real-time on-site control.

[0004] 2) High labor consumption. The construction schedule requires the arrangement of special personnel to handle project models or conduct drone flights every day, which has high labor costs and heavy workload.

[0005] Therefore, how to provide a real-time display method for construction progress suitable for open excavation construction is a technical problem that technical personnel in this field urgently need to solve. Summary of the invention

[0006] The present invention provides a real-time display method for construction progress applicable to open excavation construction of foundation pits, which automatically collects on-site construction conditions and automatically corrects excavation models without manual intervention, accurately reflecting on-site excavation conditions.

[0007] In order to solve the above technical problems, the present invention includes the following technical solutions:

[0008] A real-time display method for construction accuracy of open-cut foundation pit excavation, comprising the following steps:

[0009] Step S1, model establishment: 1. Preliminary model establishment, according to the foundation pit drawings of the design institute, the entire foundation pit model is drawn through professional modeling software; 2. Real foundation pit three-dimensional coordinate positioning; 3. Three-dimensional space information assignment, assigning three-dimensional space information to the model, ensuring that the three-dimensional coordinates of the model points, lines and surfaces are completely consistent with the three-dimensional coordinates of the real foundation pit; 4. Model zoning, dividing the entire excavation area soil into multiple cube blocks, rectangular blocks or prisms; 5. Color block design, setting each block to three states: unexcavated, excavated, and excavated, distinguished by three different color block colors;

[0010] Step S2, obtaining positioning information: 1. Building a positioning platform, building a GNSS Beidou positioning platform, importing a foundation pit model, and determining the model position based on the coordinates; 2. Equipment installation, installing Beidou positioning equipment on the cab and the lower swing arm of the excavator, and building a positioning platform in the background to obtain the three-dimensional spatial coordinates of the excavator body and the excavation point in real time. The positioning label of the cab is marked as A, and the label on the swing arm is marked as B; 3. Receiving positioning information, obtaining the spatial coordinates of the excavator based on the positioning platform;

[0011] Step S3, three-dimensional display of construction progress: 1. Display of excavator positioning information, based on displaying the excavator in label mode on the foundation pit model, the label position is the three-dimensional space coordinate position of the excavator positioning device A; 2. Real-time display of construction progress.

[0012] Furthermore, the ratio of the foundation pit model in step S1 to the actual project is 1:1.

[0013] Furthermore, in step S1, a GNSS Beidou measurement device is used to measure the spatial three-dimensional coordinates of each corner of the actual foundation pit to achieve three-dimensional spatial positioning of the foundation pit excavation surface.

[0014] Furthermore, in step S1, the central part of the foundation pit is divided into cubic blocks with a side length of 2 to 3 meters, and the edges of the foundation pit are divided into rectangular blocks or prismatic blocks.

[0015] Furthermore, in step S3, the design algorithm used for the construction progress display includes:

[0016] 1. All blocks are initially unexcavated;

[0017] 2. When positioning tag B is located in a certain block, this block is automatically set to positive excavation;

[0018] 3. When the positioning tag A is located in a certain block, this block is automatically set to be excavated;

[0019] 4. Once a block is automatically set to excavation, it cannot be adjusted back to non-excavation unless manually modified;

[0020] 5. When a block is automatically set to excavated, no automatic status modification is allowed except for manual modification;

[0021] 6. When a block is in active excavation for more than two weeks, the platform will remind the management personnel whether there is a machine failure;

[0022] 7. When the surrounding blocks have been in the excavation stage for more than two weeks, if this block is still in the unexcavated stage, remind the management personnel to come to the site for inspection.

[0023] Compared with the prior art, the present invention has the following advantages and beneficial effects:

[0024] The present invention provides a real-time display method for construction accuracy of open-cut foundation pit excavation, comprising the following steps: first, model establishment: 1. Preliminary model establishment, according to the foundation pit drawings of the design institute, the entire foundation pit model is drawn by professional modeling software; 2. Real foundation pit three-dimensional coordinate positioning; 3. 3D spatial information assignment, assigning the three-dimensional spatial information to the model, ensuring that the three-dimensional coordinates of the model points, lines and surfaces are completely consistent with the three-dimensional coordinates of the real foundation pit; 4. Model zoning, dividing the soil in the entire excavation area into a plurality of cube blocks, rectangular blocks or prisms; 5. Color block design, setting each block to three states: unexcavated, excavated, and excavated, distinguished by three different color block colors; then, determining Acquisition of positioning information: 1. Construction of the positioning platform: Build a GNSS Beidou positioning platform, import the foundation pit model, and determine the model position according to the coordinates; 2. Equipment installation: Install Beidou positioning equipment on the cab and the lower swing arm of the excavator, and build a positioning platform in the background to obtain the three-dimensional spatial coordinates of the excavator body and excavation points in real time. The positioning label of the cab is marked as A, and the label on the swing arm is B; 3. Receiving positioning information: Obtain the spatial coordinates of the excavator based on the positioning platform; Finally, three-dimensional display of construction progress: 1. Display of excavator positioning information: Display the excavator in label mode on the foundation pit model, and the label position is the three-dimensional spatial coordinate position of the excavator positioning device A; 2. Real-time display of construction progress.

[0025] The real-time display method of construction accuracy applicable to open-cut foundation pit excavation provided by the present invention can display the construction progress unmanned without manual intervention. The platform automatically adjusts the color blocks of the model based on the algorithm according to the positioning of the excavator equipment and the excavation points, so as to realize the real visualization display of the construction progress and working conditions. Moreover, the method can realize real-time display, automatically receiving the positioning data every 20-30 seconds, so the construction progress can be displayed in minutes. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 A schematic diagram of the installation position of the excavator positioning tag in a method for real-time display of construction accuracy for open-cut foundation pit excavation according to an embodiment of the present invention;

[0027] Figure 2 This is a schematic diagram of GNSS measurement points and foundation pit partitioning in a real-time display method of construction accuracy for open-cut foundation pit excavation according to an embodiment of the present invention. DETAILED DESCRIPTION

[0028] The following is a further detailed description of a method for real-time display of construction progress applicable to open excavation construction provided by the present invention in conjunction with specific embodiments and drawings. The advantages and features of the present invention will become more apparent from the following description.

[0029] Embodiment 1: A method for real-time display of construction accuracy applicable to open-cut foundation pit excavation, comprising the following steps:

[0030] Step S1, model establishment: 1. Preliminary model establishment, according to the foundation pit drawings of the design institute, the entire foundation pit model is drawn through professional modeling software; 2. Real foundation pit three-dimensional coordinate positioning; 3. Three-dimensional space information assignment, assigning three-dimensional space information to the model, ensuring that the three-dimensional coordinates of the model points, lines and surfaces are completely consistent with the three-dimensional coordinates of the real foundation pit; 4. Model zoning, dividing the entire excavation area soil into multiple cube blocks, rectangular blocks or prisms; 5. Color block design, setting each block to three states: unexcavated, excavated, and excavated, distinguished by three different color block colors;

[0031] Step S2, obtaining positioning information: 1. Building a positioning platform, building a GNSS Beidou positioning platform, importing a foundation pit model, and determining the model position based on the coordinates; 2. Equipment installation, installing Beidou positioning equipment on the cab and the lower swing arm of the excavator, and building a positioning platform in the background to obtain the three-dimensional spatial coordinates of the excavator body and the excavation point in real time. The positioning label of the cab is marked as A, and the label on the swing arm is marked as B; 3. Receiving positioning information, obtaining the spatial coordinates of the excavator based on the positioning platform;

[0032] Step S3, three-dimensional display of construction progress: 1. Display of excavator positioning information, based on displaying the excavator in label mode on the foundation pit model, the label position is the three-dimensional space coordinate position of the excavator positioning device A; 2. Real-time display of construction progress.

[0033] In this embodiment, more preferably, the ratio of the foundation pit model in step S1 to the actual project is 1:1.

[0034] In this embodiment, more preferably, in step S1, a GNSS Beidou measurement device is used to measure the spatial three-dimensional coordinates of each corner of the actual foundation pit to achieve three-dimensional spatial positioning of the foundation pit excavation surface.

[0035] In this embodiment, more preferably, in step S1, considering the aesthetics, the central part of the foundation pit is divided into cubic blocks with a side length of 2 to 3 meters, and the edges of the foundation pit are divided into rectangular blocks or prismatic blocks.

[0036] In this embodiment, more preferably, in step S3, the design algorithm used for the construction progress display includes:

[0037] 1. All blocks are initially unexcavated;

[0038] 2. When positioning tag B is located in a certain block, this block is automatically set to positive excavation;

[0039] 3. When the positioning tag A is located in a certain block, this block is automatically set to be excavated;

[0040] 4. Once a block is automatically set to excavation, it cannot be adjusted back to non-excavation unless manually modified;

[0041] 5. When a block is automatically set to excavated, no automatic status modification is allowed except for manual modification;

[0042] 6. When a block is in active excavation for more than two weeks, the platform will remind the management personnel whether there is a machine failure;

[0043] 7. When the surrounding blocks have been in the excavation stage for more than two weeks, if this block is still in the unexcavated stage, remind the management personnel to come to the site for inspection.

[0044] The above examples are preferred embodiments of the present invention, but the embodiments of the present invention are not limited to the above embodiments. The above embodiments only express several embodiments of the present invention, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the invention patent. It should be pointed out that, for those of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.

Claims

1. A real-time display method for construction accuracy of open-cut foundation pit excavation, characterized in that: The steps include: Step S1, model establishment:

1. Preliminary model establishment, according to the foundation pit drawings of the design institute, the entire foundation pit model is drawn through professional modeling software; 2. Real foundation pit three-dimensional coordinate positioning; 3. Three-dimensional space information assignment, assigning three-dimensional space information to the model, ensuring that the three-dimensional coordinates of the model points, lines and surfaces are completely consistent with the three-dimensional coordinates of the real foundation pit; 4. Model zoning, dividing the entire excavation area soil into multiple cube blocks, rectangular blocks or prisms; 5. Color block design, setting each block to three states: unexcavated, excavated, and excavated, distinguished by three different color block colors; Step S2, obtaining positioning information:

1. Building a positioning platform, building a GNSS Beidou positioning platform, importing the foundation pit model, and determining the model position according to the coordinates; 2. Equipment installation, installing Beidou positioning equipment on the cab and the lower swing arm of the excavator, and building a positioning platform in the background to obtain the three-dimensional spatial coordinates of the excavator body and the excavation point in real time. The positioning label of the cab is marked as A, and the label on the swing arm is B; 3. Receiving positioning information, obtaining the spatial coordinates of the excavator based on the positioning platform; Step S3, three-dimensional display of construction progress:

1. Display of excavator positioning information, based on displaying the excavator in label mode on the foundation pit model, the label position is the three-dimensional space coordinate position of the excavator positioning device A; 2. Real-time display of construction progress.

2. The method according to claim 1, characterized in that The ratio of the foundation pit model in step S1 to the actual project is 1:

1.

3. The method according to claim 1, characterized in that In step S1, a GNSS Beidou measurement device is used to measure the spatial three-dimensional coordinates of each corner of the actual foundation pit to achieve three-dimensional spatial positioning of the foundation pit excavation surface.

4. The method according to claim 1, characterized in that In step S1, the central part of the foundation pit is divided into cube blocks with a side length of 2 to 3 meters, and the edges of the foundation pit are divided into rectangular blocks or prism blocks.

5. The method according to claim 1, characterized in that In step S3, the design algorithm used for construction progress display includes:

1. All blocks are initially unexcavated; 2. When positioning tag B is located in a certain block, this block is automatically set to positive excavation; 3. When the positioning tag A is located in a certain block, this block is automatically set to be excavated; 4. Once a block is automatically set to excavation, it cannot be adjusted back to non-excavation unless manually modified; 5. When a block is automatically set to excavated, no automatic status modification is allowed except for manual modification; 6. When a block is in active excavation for more than two weeks, the platform will remind the management personnel whether there is a machine failure; 7. When the surrounding blocks have been in the excavation stage for more than two weeks, if this block is still in the unexcavated stage, remind the management personnel to come to the site for inspection.