By designing the plant energy regulation system, using meteorological and operation and maintenance data to adjust the operating power of air-conditioning equipment, the problem of difficult to adjust the power consumption of refrigeration equipment under high temperature power limit is solved, and energy consumption management under power limit conditions and reasonable control of office area temperature is achieved.
Patent Information
- Application Number
- CN202510376515.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-28
- Publication Date
- 2025-04-25
- Estimated Expiration
- 2045-03-28
AI Technical Summary
It is difficult for existing energy regulation systems to reasonably regulate and control the power consumption of a large number of refrigeration equipment in the factory under extreme electricity consumption requirements, especially when power is limited by high temperatures.
A factory energy regulation system is designed, and meteorological data and operation and maintenance data are obtained through the calculation module. The adjustment module adjusts the operating power of the air conditioner main unit and air conditioner sub-machine based on the refrigeration level and population inlet and outflow of the office area, and reasonably adjusts the actual temperature of the office area.
Energy consumption regulation management is realized while meeting the power limit requirements. Through priority classification and flow adjustment, the power consumption of refrigeration equipment is effectively reduced and the normal operation of the office area is ensured.
Smart Images

Figure CN119879356A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of plant energy management, and in particular to a plant energy regulation system. Background Art
[0002] High-temperature power rationing in industrial plants is a common energy regulation method that can effectively control the load of urban circuits. After obtaining the power rationing quota, the plant will effectively allocate it to ensure the normal operation of the plant's production lines and office areas as much as possible. In hot weather, the cooling demand will consume a large proportion of the plant's energy consumption, but the plant's cooling energy consumption management or regulation methods are based on the situation when there is no power rationing, and are not targeted at the special power consumption scenario of high-temperature power rationing. Therefore, there is an urgent need for a plant power regulation system for the special power consumption scenario of high-temperature power rationing, so that it can reasonably adjust and control the power consumption of a large number of refrigeration equipment in the plant under extreme power requirements. Summary of the invention
[0003] The purpose of the present invention is to provide a plant energy regulation system to solve the problem that the current energy regulation system lacks the ability to reasonably regulate and control the power consumption of a large number of refrigeration equipment in the plant under extreme power requirements.
[0004] In order to achieve the above objectives, the present application provides the following technical solutions: On the one hand, an embodiment of the present application provides a plant energy regulation system, the system comprising: a calculation module, the calculation module comprising a meteorological data acquisition unit and a first calculation unit, wherein the meteorological data acquisition unit is connected to an external meteorological network for obtaining current temperature data; a regulation module, the regulation module comprising a data retrieval unit and a regulation unit, wherein the data retrieval unit is connected to an operation and maintenance database of the plant, for retrieving preset temperatures of multiple office areas in the plant from the operation and maintenance data, the regulation unit is connected to multiple refrigeration links, office area temperature sensors and key channel temperature sensors, the refrigeration link comprising an air-conditioning main unit and multiple air-conditioning sub-units cooperating with the air-conditioning main unit; wherein the regulation unit is used to adjust the operating power of multiple air-conditioning main units and air-conditioning sub-units matched with the air-conditioning main unit based on the refrigeration levels and population in and out of multiple office areas in the case of power restriction in the plant, thereby reasonably adjusting the actual temperatures of multiple office areas; Among them, the method of adjusting the actual temperature of multiple office areas is: The current temperature data and the target temperature of each office area in the factory are obtained, and based on the current temperature data and the target temperature, the first cooling power consumption corresponding to each office area and the key channel per square is retrieved from the operation and maintenance database, and the total cooling power consumption corresponding to multiple office areas and multiple key channels is calculated based on the first cooling power consumption, the area of the office area and the area of the key channel; Obtain the current power-limiting data and retrieve the cooling power consumption quota in the power-limiting data. If the total cooling power consumption is greater than 115% of the cooling power consumption quota, adjust the operating power of multiple air-conditioning hosts and the air-conditioning sub-units matched with the air-conditioning hosts based on the cooling levels and population inflows and outflows of multiple office areas, and then reasonably adjust the actual temperatures of multiple office areas.
[0005] Optionally, adjusting the actual working temperatures of the multiple office areas based on the cooling levels and population inflows and outflows of the multiple office areas includes: Obtain target temperatures, office area areas, and weather data corresponding to multiple first-level office areas, and find the second cooling power consumption corresponding to each first-level office area per square in the operation and maintenance database based on the target temperature and weather data corresponding to each first-level office area, and calculate the corresponding first-level cooling power consumption based on the second cooling power consumption corresponding to each first-level office area and the office area, and then calculate the first operation and maintenance power corresponding to the multiple first-level office areas; Acquire current power-limiting data, and calculate a second operation and maintenance power threshold based on a difference between a cooling power consumption quota in the power-limiting data and the first operation and maintenance power; Obtain monitoring images corresponding to multiple secondary office areas and monitoring images of multiple key channels within the first time period, and identify the number of office workers corresponding to each secondary office area and the number of people passing through each key channel within the first time period in turn, and eliminate multiple invalid key channels and secondary office areas based on a preset number threshold, thereby screening out multiple valid secondary office areas and valid key channels; Retrieve the maximum operating temperature thresholds corresponding to multiple valid secondary office areas and valid key channels, and correct the maximum operating temperature thresholds corresponding to the valid secondary office areas based on the total lengths of the moving trajectories corresponding to multiple moving targets in the valid secondary office areas, and calculate the second operation and maintenance powers corresponding to the multiple valid secondary office areas and valid key channels based on the maximum operating temperature thresholds; If the second operation and maintenance power is less than the second operation and maintenance power threshold, corresponding operation instructions for the air-conditioning host and the air-conditioning sub-unit are generated based on the maximum operating temperature thresholds corresponding to multiple valid secondary office areas and valid key channels.
[0006] Optionally, after calculating the second operation and maintenance powers corresponding to the plurality of valid secondary office areas and the valid key channels based on the maximum operating temperature threshold, the method further includes: If the second operation and maintenance power is greater than or equal to the second operation and maintenance power threshold, based on the difference between the second operation and maintenance power threshold and the second operation and maintenance power, the maximum operating temperature threshold corresponding to the effective critical channel in the non-direct sunlight orientation is increased or the operation of the air-conditioning host corresponding to the effective critical channel is stopped, thereby reducing the second operation and maintenance power until it is lower than the second operation and maintenance power threshold.
[0007] Optionally, when the second operation and maintenance power is greater than or equal to the second operation and maintenance power threshold, based on the difference between the second operation and maintenance power threshold and the second operation and maintenance power, increasing the maximum operating temperature threshold corresponding to the valid key channel in the non-direct sunlight orientation or stopping the operation of the air conditioner host and the air conditioner sub-unit corresponding to the valid key channel, including: Get the current time node, and retrieve the corresponding lighting parameters and the three-dimensional virtual model of the factory area, and then obtain at least one first wall surface that is not directly exposed to sunlight, and construct a first radiation zone based on the first wall surface. The width of the first radiation zone is set based on the current temperature, and query whether there is a valid key channel in the first radiation zone. If the proportion of the valid key channel in the first radiation zone is greater than 55%, it is determined to be a second key channel; The operating power consumption of the air conditioner sub-unit and / or the air conditioner main unit corresponding to the second key channel is reduced or even turned off until the adjusted second operation and maintenance power is less than the second operation and maintenance power threshold.
[0008] Optionally, the correcting the maximum operating temperature threshold corresponding to the effective secondary office area based on the total length of the movement tracks corresponding to the multiple moving targets in the effective secondary office area includes: In an effective secondary office area, multiple surveillance videos from different angles are dispatched, and the human targets in each surveillance video are identified based on the shape-based image feature extraction algorithm. The repeated human targets in multiple surveillance videos are eliminated based on the scene coordinates and target human features, and the number of human targets in the effective secondary office area is obtained. Based on the road distribution in the effective secondary office area, multiple mobile point monitoring coordinates are constructed, and when the human target in the monitoring video moves to the corresponding mobile point monitoring coordinates, the moving path corresponding to the human target is marked as the first effective path; Acquire multiple first valid paths collected in a first time period, and remove first valid paths whose lengths are less than a minimum threshold, thereby obtaining multiple second valid paths; Based on the end vector direction of each second valid path and the coordinates of the doorway of the valid secondary office area, the second valid paths used to represent the paths that have left the valid secondary office area within the first time period are eliminated, thereby obtaining a plurality of third valid paths; An average activity path length corresponding to an average effective secondary office area is calculated based on the number of third effective paths and the total length of multiple third effective paths; Based on the fluctuation of the number of target people in the effective secondary office area in the first time period, the average total number of people in the effective secondary office area in the first time period is calculated; The first activity of the effective secondary office area is calculated by a weighted algorithm based on the ratio between the number of the third effective paths and the average total number of people and the average activity path length; The maximum operating temperature threshold corresponding to the effective secondary office area is corrected based on the first activity level.
[0009] Optionally, correcting the maximum operating temperature threshold corresponding to the effective secondary office area based on the activity level includes: Retrieving the activity threshold corresponding to the current valid secondary office area from the operation and maintenance database, where the activity threshold is determined based on the employee position table; If the first activity level is greater than the activity level threshold, the maximum operating temperature threshold corresponding to the effective secondary office area is reduced based on the difference between the first activity level and the activity level threshold.
[0010] In a second aspect, an embodiment of the present application provides a plant energy regulation device, which includes a memory and a processor.
[0011] The memory is used to store computer programs; the processor is used to implement the steps of adjusting the actual temperatures of multiple office areas by the above-mentioned plant energy regulation system when executing the computer program.
[0012] In a third aspect, an embodiment of the present application provides a medium having a computer program stored thereon, and when the computer program is executed by a processor, the above-mentioned steps of adjusting the actual temperatures of multiple office areas are implemented.
[0013] The beneficial effects of the present invention are: The plant energy regulation system provided by the present invention prioritizes the cooling demands of plant sites. For some office areas with higher priorities, such as biological laboratories, the preset temperatures are not changed, and then the corresponding power consumption is adjusted in sequence according to the levels. For office areas with lower priorities, the operating power of refrigeration equipment is appropriately reduced based on the flow of people, or even the operation of the corresponding refrigeration equipment is shut down, thereby realizing energy consumption regulation management while meeting the power limitation requirements.
[0014] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or be understood by practicing the embodiments of the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures particularly pointed out in the written description, claims, and drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.
[0016] Figure 1 It is a schematic diagram of the structure of a plant energy regulation system described in an embodiment of the present invention; Figure 2 is a schematic diagram of the plant refrigeration system architecture described in an embodiment of the present invention; Figure 3 It is a schematic diagram of the structure of a plant energy regulation device described in an embodiment of the present invention. DETAILED DESCRIPTION
[0017] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all of the embodiments. The components of the embodiments of the present invention generally described and shown in the drawings here can be arranged and designed in various different configurations. Therefore, the following detailed description of the embodiments of the present invention provided in the drawings is not intended to limit the scope of the claimed invention, but merely represents selected embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0018] It should be noted that similar reference numerals or letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings. At the same time, in the description of the present invention, the terms "first", "second", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance.
[0019] Embodiment 1: Before explaining the plant energy regulation system, it is necessary to briefly explain the existing plant refrigeration system, such as Figure 2 As shown, a common factory refrigeration system includes multiple refrigeration links. Each refrigeration link includes at least one water tower, an air-conditioning main unit and multiple air-conditioning sub-units matched with the air-conditioning main unit. The air-conditioning main unit and the multiple air-conditioning sub-units are connected through multiple ventilation ducts. The water tower is used to dissipate heat for the air-conditioning main unit, thereby ensuring the refrigeration efficiency of the air-conditioning main unit.
[0020] like Figure 1 As shown, this embodiment provides a plant energy regulation system, the system comprising: A calculation module, the calculation module includes a meteorological data acquisition unit and a first calculation unit, wherein the meteorological data acquisition unit is connected to an external meteorological network and is used to obtain current temperature data. The temperature data will affect the cooling effect of the refrigeration equipment in the factory area, and is therefore an important basis for energy regulation; A regulating module, the regulating module comprising a data retrieval unit and a regulating unit, wherein the data retrieval unit is connected to the operation and maintenance database of the plant area and is used to retrieve the preset temperatures of multiple office areas in the plant area from the operation and maintenance data, the regulating unit is connected to multiple refrigeration links, office area temperature sensors and key channel temperature sensors, the refrigeration link comprises an air-conditioning host and multiple air-conditioning sub-units cooperating with the air-conditioning host, and the temperature control of a specific office area is achieved by controlling the switches of the multiple air-conditioning sub-units; Among them, the adjustment unit is used to adjust the operating power of multiple air-conditioning main units and air-conditioning sub-units matched with the air-conditioning main units based on the cooling level and population in and out of multiple office areas when the factory is power-limited, thereby reasonably adjusting the actual temperature of multiple office areas.
[0021] In this embodiment, the plant energy regulation system prioritizes the cooling needs of the plant sites. For some office areas with higher priorities, such as biological laboratories, the preset temperatures are not changed, and then the corresponding power consumption is adjusted in sequence according to the levels. For office areas with lower priorities, the operating power of the refrigeration equipment is appropriately reduced based on the flow of people, or even the corresponding refrigeration equipment is shut down, thereby achieving energy consumption regulation management while meeting the power limit requirements.
[0022] Secondly, there are significant differences in the spatial layout of factory areas and traditional office buildings. Therefore, it is not possible to uniformly schedule and adjust by simply raising the preset ambient temperature threshold. It is necessary to prioritize each area. For example, important production resource storage areas, important experimental areas, etc., are all areas that have rigid requirements on ambient temperature. Therefore, it is necessary to prioritize the stability of their temperature. Such places are classified as primary office areas in this embodiment, followed by conventional office areas, which are areas that can be appropriately adjusted.
[0023] Secondly, the activity patterns of personnel are quite different from those in traditional office buildings. Personnel are more active, that is, they move around a lot. Therefore, it is necessary to adjust the working temperature of the corresponding office area based on the activity level of personnel in the area.
[0024] Secondly, the above method for adjusting the actual temperature of multiple office areas includes step S100 and step S200.
[0025] Step S100, obtaining the current temperature data through the meteorological data acquisition unit and retrieving the target temperature of each office area in the factory through the data retrieval unit, and retrieving the first cooling power consumption corresponding to each office area and key channel per square in the operation and maintenance database based on the current temperature data and the target temperature, and calculating the total cooling power consumption corresponding to multiple office areas and multiple key channels based on the first cooling power consumption, the area of the office area and the area of the key channel; It should be noted that due to the architectural structure characteristics of the factory, there are large differences in the cooling power consumption per unit square corresponding to different office areas. For example, multi-story buildings and single-story buildings, the floor area of the building, the location of the office area in the building, etc. will lead to certain differences in the cooling demand of the office areas under the same temperature conditions. It is necessary to conduct power consumption tests on each office area at different temperatures in advance, or to collect power consumption data of refrigeration equipment corresponding to each office area and key channels, and then obtain statistics on the cooling power consumption per unit square of each office area and key channel at different temperatures, and record them in the factory's operation and maintenance database.
[0026] Step S200, obtain the current power limit data, and retrieve the cooling power consumption quota in the power limit data. If the total cooling power consumption is greater than 115% of the cooling power consumption quota, adjust the operating power of multiple air-conditioning hosts and air-conditioning sub-units matched with the air-conditioning hosts based on the cooling levels and population in and out of multiple office areas, and then reasonably adjust the actual temperatures of multiple office areas. It should be noted that, in the case of no power limit, each office area in the factory is set with a target temperature and corresponding opening and closing time periods, so that the office areas and key channels are kept within a certain temperature range. However, the power consumption limitation caused by high temperature power limit will make it impossible to meet the cooling needs under normal circumstances. Therefore, it is necessary to meet them in turn according to the priority of the office areas, and eliminate some office areas and key channels with fewer people.
[0027] Secondly, the specific implementation method of adjusting the actual working temperature of multiple office areas based on the cooling levels and population inflow and outflow of multiple office areas in step S200 is: Step S210: acquiring target temperatures, office area areas, and weather data corresponding to multiple first-level office areas, and finding the second cooling power consumption corresponding to each first-level office area per square meter in the operation and maintenance database based on the target temperature and weather data corresponding to each first-level office area, and calculating the corresponding first-level cooling power consumption based on the second cooling power consumption corresponding to each first-level office area and the office area, and then calculating the first operation and maintenance power corresponding to the multiple first-level office areas; Step S220: obtaining current power-limiting data, and calculating a second operation and maintenance power threshold based on a difference between a cooling power consumption quota in the power-limiting data and the first operation and maintenance power; Step S230: acquiring monitoring images corresponding to a plurality of secondary office areas and monitoring images of a plurality of key channels in the first time period, and sequentially identifying the number of office workers corresponding to each secondary office area and the number of people passing through each key channel in the first time period, and eliminating a plurality of invalid key channels and secondary office areas based on a preset number threshold, thereby screening out a plurality of valid secondary office areas and valid key channels; Step S240, retrieve the maximum operating temperature thresholds corresponding to multiple valid secondary office areas and valid key channels, correct the maximum operating temperature thresholds corresponding to the valid secondary office areas based on the total lengths of the moving trajectories corresponding to multiple moving targets in the valid secondary office areas, and calculate the second operation and maintenance powers corresponding to the multiple valid secondary office areas and valid key channels based on the maximum operating temperature thresholds; It should be noted that the maximum working temperature threshold is the preset maximum working environment temperature and is written to the operation and maintenance server in advance. At the same time, the maximum working temperature threshold should be appropriately lowered for office areas with high human activity to improve the office experience.
[0028] Step S250: If the second operation and maintenance power is less than the second operation and maintenance power threshold, the corresponding operation instructions for the air conditioner host and the air conditioner slave are generated based on the maximum operating temperature thresholds corresponding to the multiple valid secondary office areas and the valid key channels.
[0029] Step S260: If the second operation and maintenance power is greater than or equal to the second operation and maintenance power threshold, based on the difference between the second operation and maintenance power threshold and the second operation and maintenance power, the maximum operating temperature threshold corresponding to the effective key channel in the non-direct sunlight orientation is increased or the operation of the air-conditioning host corresponding to the effective key channel is stopped, thereby reducing the second operation and maintenance power until it is lower than the second operation and maintenance power threshold.
[0030] Secondly, the specific implementation method of increasing the maximum operating temperature threshold corresponding to the effective key channel in the non-direct sunlight orientation or stopping the operation of the air conditioner host and the air conditioner slave corresponding to the effective key channel based on the difference between the second operation and maintenance power threshold and the second operation and maintenance power in step S260 is: Step S261, obtaining the current time node, and calling the corresponding lighting parameters and the three-dimensional virtual model of the factory area, thereby obtaining at least one first wall surface that is not directly exposed to sunlight, constructing a first radiation zone based on the first wall surface, wherein the width of the first radiation zone is set based on the current temperature, and querying whether there is a valid key channel in the first radiation zone. If the proportion of the valid key channel in the first radiation zone is greater than 55%, it is determined to be a second key channel; Step S262: reduce or even shut down the operating power consumption of the air conditioner slave and / or the air conditioner host corresponding to the second key channel until the adjusted second operation and maintenance power is less than the second operation and maintenance power threshold.
[0031] Secondly, the specific implementation method of correcting the maximum operating temperature threshold corresponding to the effective secondary office area based on the total length of the movement tracks corresponding to the multiple moving targets in the effective secondary office area in step S240 is: Step S241: dispatch multiple surveillance videos from different angles in an effective secondary office area, identify the human targets in each surveillance video based on the shape-based image feature extraction algorithm, and eliminate repeated human targets in multiple surveillance videos based on scene coordinates and target human features, thereby obtaining the number of human targets in the effective secondary office area; Step S242: construct multiple moving point monitoring coordinates based on the road distribution in the valid secondary office area, and when the person target in the monitoring video moves to the corresponding moving point monitoring coordinates, mark the moving path corresponding to the person target as the first valid path; Step S243, obtaining multiple first valid paths collected in the first time period, and eliminating first valid paths whose lengths are less than a minimum threshold, thereby obtaining multiple second valid paths; Step S244: based on the end vector direction of each second valid path and the coordinates of the doorway of the valid secondary office area, eliminate the second valid paths used to indicate that the paths have left the valid secondary office area within the first time period, thereby obtaining a plurality of third valid paths; Step S245: Calculate the average activity path length corresponding to the average effective secondary office area based on the number of third effective paths and the total length of multiple third effective paths; Step S246: based on the fluctuation of the number of target people in the effective secondary office area in the first time period, calculate the average total number of people in the effective secondary office area in the first time period; Step S247: Calculate the first activity level of the effective secondary office area through a weighted algorithm based on the ratio between the number of the third effective paths and the average total number of people and the average activity path length; Step S248: Correct the maximum operating temperature threshold corresponding to the valid secondary office area based on the first activity level.
[0032] Effective activity tracks within the office area should meet the following requirements: 1. The moving distance within a certain period of time must reach the preset distance value to prevent misjudgment of activity due to small-scale activities at the workstation; 2. If you leave the office area during this period, it will be considered an invalid trajectory, that is, the activity trajectory of the person leaving will not be counted as an evaluation parameter for the activity of the office area.
[0033] Secondly, the implementation method of correcting the maximum operating temperature threshold corresponding to the effective secondary office area based on the activity level in step S248 is: Step S2481, retrieve the activity threshold corresponding to the current valid secondary office area from the operation and maintenance database, the activity threshold is determined based on the employee position table, and the employee position table can be used to determine the number of long-term residents corresponding to each office area, and then determine different numbers of people (activity thresholds corresponding to different office areas); Step S2482: If the first activity level is greater than the activity level threshold, the maximum operating temperature threshold corresponding to the effective secondary office area is lowered based on the difference between the first activity level and the activity level threshold.
[0034] Embodiment 2: Corresponding to the above method embodiment, the embodiment of the present disclosure further provides a plant energy regulation device 800. The plant energy regulation device 800 described below and the method of regulating the actual temperature of multiple office areas described above can be referenced to each other.
[0035] Figure 3 FIG. 8 is a block diagram of a plant energy regulation device 800 according to an exemplary embodiment. Figure 3 As shown, the plant energy conditioning device 800 may include: a processor 801 and a memory 802. The plant energy conditioning device 800 may also include one or more of a multimedia component 803, an I / O interface 804, and a communication component 805.
[0036] The processor 801 is used to control the overall operation of the plant energy regulation device 800 to complete all or part of the steps in the above-mentioned plant energy regulation method. The memory 802 is used to store various types of data to support the operation of the plant energy regulation device 800, and these data may include, for example, instructions for any application or method operating on the plant energy regulation device 800, and application-related data, such as contact data, sent and received messages, pictures, audio, video, etc. The memory 802 can be implemented by any type of volatile or non-volatile storage device or a combination thereof, such as static random access memory (SRAM), electrically erasable programmable read-only memory (EEPROM), erasable programmable read-only memory (EPROM), programmable read-only memory (PROM), read-only memory (ROM), magnetic memory, flash memory, disk or optical disk. The multimedia component 803 may include a screen and an audio component. The screen may be, for example, a touch screen, and the audio component is used to output and / or input audio signals. For example, the audio component may include a microphone for receiving external audio signals. The received audio signal may be further stored in the memory 802 or sent via the communication component 805. The audio component also includes at least one speaker for outputting audio signals. The I / O interface 804 provides an interface between the processor 801 and other interface modules, and the above-mentioned other interface modules can be keyboards, mice, buttons, etc. These buttons can be virtual buttons or physical buttons. The communication component 805 is used for wired or wireless communication between the plant energy regulation device 800 and other devices. Wireless communication, such as Wi-Fi, Bluetooth, Near Field Communication (NFC), 2G, 3G or 4G, or a combination of one or more of them, so the corresponding communication component 805 can include: Wi-Fi module, Bluetooth module, NFC module.
[0037] In an exemplary embodiment, the plant energy regulation device 800 can be implemented by one or more application specific integrated circuits (ASIC), digital signal processors (DSP), digital signal processing devices (DSPD), programmable logic devices (PLD), field programmable gate arrays (FPGA), controllers, microcontrollers, microprocessors or other electronic components to execute the above-mentioned plant energy regulation method.
[0038] In another exemplary embodiment, a computer-readable storage medium including program instructions is also provided, and when the program instructions are executed by a processor, the steps of the above-mentioned plant energy regulation method are implemented. For example, the computer-readable storage medium can be the above-mentioned memory 802 including program instructions, and the above-mentioned program instructions can be executed by the processor 801 of the plant energy regulation device 800 to complete the above-mentioned plant energy regulation method.
[0039] Embodiment 3: Corresponding to the above method embodiment, the embodiment of the present disclosure further provides a readable storage medium. The readable storage medium described below and the method for adjusting the actual temperature of multiple office areas described above can refer to each other.
[0040] A readable storage medium stores a computer program, which, when executed by a processor, implements the steps of the plant area energy regulation method of the above method embodiment.
[0041] The readable storage medium may specifically be a U disk, a mobile hard disk, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk, or other readable storage medium that can store program codes.
[0042] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A plant energy regulation system, characterized in that: The system comprises: A calculation module, wherein the calculation module includes a meteorological data acquisition unit, wherein the meteorological data acquisition unit is connected to an external meteorological network to obtain current temperature data; A regulating module, the regulating module comprising a data retrieval unit and a regulating unit, wherein the data retrieval unit is connected to an operation and maintenance database of the plant area, the regulating unit is connected to a plurality of refrigeration links and temperature sensors, the refrigeration links comprising an air-conditioning host and a plurality of air-conditioning sub-units cooperating with the air-conditioning host; The regulating unit is used to regulate the operating power of multiple air-conditioning main units and air-conditioning sub-units matched with the air-conditioning main units based on the cooling levels and population inflow and outflow of multiple office areas in the case of power restriction in the factory area, thereby reasonably regulating the actual temperature of multiple office areas; Among them, the method of adjusting the actual temperature of multiple office areas is: The current temperature data and the target temperature of each office area in the factory are obtained, and based on the current temperature data and the target temperature, the first cooling power consumption corresponding to each office area and the key channel per square is retrieved from the operation and maintenance database, and the total cooling power consumption corresponding to multiple office areas and multiple key channels is calculated based on the first cooling power consumption, the area of the office area and the area of the key channel; Obtain the current power-limiting data and retrieve the cooling power consumption quota in the power-limiting data. If the total cooling power consumption is greater than 115% of the cooling power consumption quota, adjust the operating power of multiple air-conditioning hosts and the air-conditioning sub-units matched with the air-conditioning hosts based on the cooling levels and population inflows and outflows of multiple office areas, and then reasonably adjust the actual temperatures of multiple office areas.
2. The plant energy regulation system according to claim 1, characterized in that: The method of adjusting the actual working temperature of the multiple office areas based on the cooling levels and the population inflow and outflow of the multiple office areas includes: Obtain target temperatures, office area areas, and weather data corresponding to multiple first-level office areas, and find the second cooling power consumption corresponding to each first-level office area per square in the operation and maintenance database based on the target temperature and weather data corresponding to each first-level office area, and calculate the corresponding first-level cooling power consumption based on the second cooling power consumption corresponding to each first-level office area and the office area, and then calculate the first operation and maintenance power corresponding to the multiple first-level office areas; Acquire current power-limiting data, and calculate a second operation and maintenance power threshold based on a difference between a cooling power consumption quota in the power-limiting data and the first operation and maintenance power; Obtain monitoring images corresponding to multiple secondary office areas and monitoring images of multiple key channels within the first time period, and identify the number of office workers corresponding to each secondary office area and the number of people passing through each key channel within the first time period in turn, and eliminate multiple invalid key channels and secondary office areas based on a preset number threshold, thereby screening out multiple valid secondary office areas and valid key channels; Retrieve the maximum operating temperature thresholds corresponding to multiple valid secondary office areas and valid key channels, and correct the maximum operating temperature thresholds corresponding to the valid secondary office areas based on the total lengths of the moving trajectories corresponding to multiple moving targets in the valid secondary office areas, and calculate the second operation and maintenance powers corresponding to the multiple valid secondary office areas and valid key channels based on the maximum operating temperature thresholds; If the second operation and maintenance power is less than the second operation and maintenance power threshold, corresponding operation instructions for the air-conditioning host and the air-conditioning sub-unit are generated based on the maximum operating temperature thresholds corresponding to multiple valid secondary office areas and valid key channels.
3. The plant energy regulation system according to claim 2, characterized in that: After calculating the second operation and maintenance power corresponding to multiple valid secondary office areas and valid key channels based on the maximum operating temperature threshold, it also includes: If the second operation and maintenance power is greater than or equal to the second operation and maintenance power threshold, based on the difference between the second operation and maintenance power threshold and the second operation and maintenance power, the maximum operating temperature threshold corresponding to the effective critical channel in the non-direct sunlight orientation is increased or the operation of the air-conditioning host corresponding to the effective critical channel is stopped, thereby reducing the second operation and maintenance power until it is lower than the second operation and maintenance power threshold.
4. The plant energy regulation system according to claim 3, characterized in that: When the second operation and maintenance power is greater than or equal to the second operation and maintenance power threshold, based on the difference between the second operation and maintenance power threshold and the second operation and maintenance power, increasing the maximum operating temperature threshold corresponding to the effective key channel in the non-direct sunlight orientation or stopping the operation of the air conditioner host and the air conditioner sub-unit corresponding to the effective key channel, including: Get the current time node, and retrieve the corresponding lighting parameters and the three-dimensional virtual model of the factory area, and then obtain at least one first wall surface that is not directly exposed to sunlight, and construct a first radiation zone based on the first wall surface. The width of the first radiation zone is set based on the current temperature, and query whether there is a valid key channel in the first radiation zone. If the proportion of the valid key channel in the first radiation zone is greater than 55%, it is determined to be a second key channel; The operating power consumption of the air conditioner sub-unit and / or the air conditioner main unit corresponding to the second key channel is reduced or even turned off until the adjusted second operation and maintenance power is less than the second operation and maintenance power threshold.
5. The plant energy regulation system according to claim 2, characterized in that: The method of correcting the maximum operating temperature threshold corresponding to the effective secondary office area based on the total length of the moving tracks corresponding to the multiple moving targets in the effective secondary office area includes: In an effective secondary office area, multiple surveillance videos from different angles are dispatched, and the human targets in each surveillance video are identified based on the shape-based image feature extraction algorithm. The repeated human targets in multiple surveillance videos are eliminated based on the scene coordinates and target human features, and the number of human targets in the effective secondary office area is obtained. Based on the road distribution in the effective secondary office area, multiple mobile point monitoring coordinates are constructed, and when the human target in the monitoring video moves to the corresponding mobile point monitoring coordinates, the moving path corresponding to the human target is marked as the first effective path; Acquire multiple first valid paths collected in a first time period, and remove first valid paths whose lengths are less than a minimum threshold, thereby obtaining multiple second valid paths; Based on the end vector direction of each second valid path and the coordinates of the doorway of the valid secondary office area, the second valid paths used to represent the paths that have left the valid secondary office area within the first time period are eliminated, thereby obtaining a plurality of third valid paths; An average activity path length corresponding to an average effective secondary office area is calculated based on the number of third effective paths and the total length of multiple third effective paths; Based on the fluctuation of the number of target people in the effective secondary office area in the first time period, the average total number of people in the effective secondary office area in the first time period is calculated; The first activity of the effective secondary office area is calculated by a weighted algorithm based on the ratio between the number of the third effective paths and the average total number of people and the average activity path length; The maximum operating temperature threshold corresponding to the effective secondary office area is corrected based on the first activity level.
6. The plant energy regulation system according to claim 5, characterized in that: Modifying the maximum operating temperature threshold corresponding to the effective secondary office area based on the activity level includes: Retrieving the activity threshold corresponding to the current valid secondary office area from the operation and maintenance database, where the activity threshold is determined based on the employee position table; If the first activity level is greater than the activity level threshold, the maximum operating temperature threshold corresponding to the effective secondary office area is reduced based on the difference between the first activity level and the activity level threshold.
Citation Information
Patent Citations
Digital integrated intelligent control system of central air conditioner and adjusting method thereof
CN102147146A
Energy-saving control method and device for central air-conditioning system and central air-conditioning system
CN113739359A
Air conditioner energy-saving control method, system and equipment and storage medium
CN116221911A
Air conditioner control method and device, electronic equipment and storage medium
CN116294088A
Air conditioner load adjusting method and device, electronic equipment and storage medium
CN117366794A