By standardizing the monitoring data of the simulated debugging equipment, combining the status change information and target status change information, efficient debugging of the energy storage power station monitoring system is achieved, solving the problems of long debugging cycle and low efficiency.

CN119891311APending Publication Date: 2025-04-25新源智储能源发展(北京)有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411801444.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-09
Publication Date
2025-04-25

AI Technical Summary

Technical Problem

The debugging cycle of the energy storage power station monitoring system is long and the debugging efficiency is low, resulting in delays in the delivery date of the power station connected to the grid.

Method used

Through the pre-constructed standard device point table, the monitoring data simulated by the simulation debugging equipment is standardized and analyzed, the functional debugging results of the monitoring system are determined, and debugged according to the status change information and the target state change information.

Benefits of technology

It realizes independent and efficient debugging of the monitoring system function of the energy storage power station, shortens the debugging cycle and improves the debugging efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119891311A_ABST
    Figure CN119891311A_ABST
Patent Text Reader

Abstract

The invention relates to a debugging method and device for an energy storage power station monitoring system and electronic equipment, and the method comprises the steps: carrying out the standardization processing of first monitoring data simulated by simulation debugging equipment, obtaining standard monitoring data, and transmitting the standard monitoring data to a monitoring system; analyzing standard monitoring data received by the monitoring system according to the standard device point table to obtain second monitoring data, and determining a first function debugging result of the monitoring system according to the first monitoring data and the second monitoring data; the simulation debugging equipment is controlled to execute a control instruction sent by the monitoring system, state change information of the simulation debugging equipment is obtained, and the state change information is sent to the monitoring system; determining a second function debugging result of the monitoring system according to the state change information and the target state change information; according to the first function debugging result and the second function debugging result, the debugging result of the monitoring system is determined, and the debugging efficiency of the energy storage power station monitoring system is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the technical field of energy storage power stations, and in particular to a debugging method, device and electronic equipment for an energy storage power station monitoring system. Background Art

[0002] Energy storage technology is an important supporting technology for building a new power system, achieving high-quality energy development, and realizing dual carbon goals.

[0003] The number of battery cells and energy storage units in electrochemical energy storage power stations has also increased significantly, increasing the difficulty of debugging, especially the debugging of the monitoring system of electrochemical energy storage power stations. Due to the unique equipment such as the power conversion system (PCS) and the battery management system (BMS) in the electrochemical energy storage power station, the amount of information uploaded to the monitoring system during the communication process is huge, and there is a lack of effective debugging tools during the debugging process. The debugging process is relatively complicated, and even the grid-connected delivery date of the power station is delayed due to the long debugging cycle. On the other hand, since the main function of the monitoring system of the electrochemical energy storage power station is to interact with the power station information with the electrical equipment and control protection devices in the station, so as to realize the panoramic monitoring and comprehensive automation management of the electrochemical energy storage power station, due to the involvement of multiple equipment, a large amount of debugging work is difficult to be carried out independently in advance, resulting in a significant increase in the difficulty of joint debugging and prolonging the debugging time. Therefore, how to shorten the debugging cycle of the monitoring system of the energy storage power station to improve the debugging efficiency of the monitoring system of the energy storage power station has become an urgent problem to be solved. Summary of the invention

[0004] The present disclosure provides a debugging method, device and electronic equipment for an energy storage power station monitoring system, so as to at least solve the problems of long debugging period and low debugging efficiency of the energy storage power station monitoring system in the related art.

[0005] The technical solution of the present disclosure is as follows:

[0006] According to a first aspect of an embodiment of the present disclosure, a debugging method for an energy storage power station monitoring system is provided, the method comprising: performing standard processing on first monitoring data simulated by a simulation debugging device according to a pre-constructed standard device point table to obtain standard monitoring data, and sending the standard monitoring data to a monitoring system, wherein the simulation debugging device is used to simulate an energy storage power station interval layer device; parsing the standard monitoring data received by the monitoring system according to the standard device point table to obtain second monitoring data, and determining a first functional debugging result of the monitoring system according to the first monitoring data and the second monitoring data; controlling the simulation debugging device to execute a control instruction sent by the monitoring system to obtain state change information of the simulation debugging device, and sending the state change information to the monitoring system, wherein the control instruction is used to indicate target state change information of the simulation debugging device; determining a second functional debugging result of the monitoring system according to the state change information and the target state change information; and determining a debugging result of the monitoring system according to the first functional debugging result and the second functional debugging result.

[0007] According to a second aspect of an embodiment of the present disclosure, a debugging device for an energy storage power station monitoring system is provided, comprising: a first processing module, for performing standard processing on first monitoring data simulated by a simulation debugging device according to a pre-constructed standard device point table to obtain standard monitoring data, and sending the standard monitoring data to a monitoring system, wherein the simulation debugging device is used to simulate an energy storage power station interval layer device; a first debugging module, for parsing the standard monitoring data received by the monitoring system according to the standard device point table to obtain second monitoring data, and determining a first functional debugging result of the monitoring system according to the first monitoring data and the second monitoring data; a second processing module, for controlling the simulation debugging device to execute a control instruction sent by the monitoring system, to obtain state change information of the simulation debugging device, and sending the state change information to the monitoring system, wherein the control instruction is used to indicate target state change information of the simulation debugging device; a second debugging module, for determining a second functional debugging result of the monitoring system according to the state change information and the target state change information; and a determination module, for determining a debugging result of the monitoring system according to the first functional debugging result and the second functional debugging result.

[0008] According to a third aspect of an embodiment of the present disclosure, an electronic device is provided, comprising: a processor; and a memory for storing executable instructions of the processor; wherein the processor is configured to execute the instructions to implement the debugging method of the energy storage power station monitoring system as described in the first aspect of the embodiment of the present disclosure.

[0009] According to the fourth aspect of an embodiment of the present disclosure, a computer-readable storage medium is provided. When the instructions in the computer-readable storage medium are executed by a processor of an electronic device, the electronic device can execute the debugging method of the energy storage power station monitoring system as described in the first aspect of the embodiment of the present disclosure.

[0010] The technical solution provided by the embodiments of the present disclosure brings at least the following beneficial effects:

[0011] In an embodiment of the present disclosure, first monitoring data simulated by a simulation debugging device is standardized according to a pre-constructed standard device point table to obtain standard monitoring data, and the standard monitoring data is sent to a monitoring system, wherein the simulation debugging device is used to simulate the interval layer device of an energy storage power station, and the standard monitoring data received by the monitoring system is parsed according to the standard device point table to obtain second monitoring data, and a first functional debugging result of the monitoring system is determined according to the first monitoring data and the second monitoring data, and the simulation debugging device is controlled to execute a control instruction sent by the monitoring system to obtain state change information of the simulation debugging device, and the state change information is sent to the monitoring system, wherein the control instruction is used to indicate target state change information of the simulation debugging device, and a second functional debugging result of the monitoring system is determined according to the state change information and the target state change information, and a debugging result of the monitoring system is determined according to the first functional debugging result and the second functional debugging result. Therefore, the present disclosure can autonomously and efficiently realize the functional debugging of the monitoring system of the energy storage power station, shorten the debugging cycle of the monitoring system of the energy storage power station, and improve the debugging efficiency of the monitoring system of the energy storage power station.

[0012] It is to be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the present disclosure. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] The drawings herein are incorporated into and constitute a part of the specification, illustrate embodiments consistent with the present disclosure, and together with the description are used to explain the principles of the present disclosure, and do not constitute improper limitations on the present disclosure.

[0014] Figure 1 The present invention is a flowchart of a debugging method of an energy storage power station monitoring system according to an exemplary embodiment.

[0015] Figure 2 The present invention is a flowchart of a debugging method of an energy storage power station monitoring system according to another exemplary embodiment.

[0016] Figure 3 The figure is a structural diagram of a monitoring network of an electrochemical energy storage power station according to an exemplary embodiment.

[0017] Figure 4It is a block diagram of a debugging device of an energy storage power station monitoring system according to an exemplary embodiment.

[0018] Figure 5 It is a block diagram of an electronic device according to an exemplary embodiment. DETAILED DESCRIPTION

[0019] In order to enable ordinary persons in the art to better understand the technical solutions of the present disclosure, the technical solutions in the embodiments of the present disclosure will be clearly and completely described below in conjunction with the accompanying drawings.

[0020] It should be noted that the terms "first", "second", etc. in the specification and claims of the present disclosure and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present disclosure described herein can be implemented in an order other than those illustrated or described herein. The embodiments described in the following exemplary embodiments do not represent all embodiments consistent with the present disclosure. Instead, they are merely examples of devices and methods consistent with some aspects of the present disclosure as detailed in the appended claims.

[0021] The debugging method, device and electronic equipment of the energy storage power station monitoring system proposed in the present disclosure are described in detail using embodiments.

[0022] Figure 1 A flowchart of a debugging method for an energy storage power station monitoring system provided in an embodiment of the present disclosure.

[0023] like Figure 1 As shown, the debugging method of the energy storage power station monitoring system proposed in this embodiment includes the following steps:

[0024] S101, based on a pre-constructed standard device point table, standardize the first monitoring data simulated by the simulation debugging equipment to obtain standard monitoring data, and send the standard monitoring data to the monitoring system, wherein the simulation debugging equipment is used to simulate the energy storage power station interval layer equipment.

[0025] In the disclosed embodiment, the energy storage power station bay layer equipment may be simulated to obtain a simulation debugging device, and the simulation debugging device is used to simulate the energy storage power station bay layer equipment to communicate with the monitoring system.

[0026] It should be noted that the energy storage power station isolation layer equipment includes but is not limited to the measurement and control equipment of the primary equipment of the energy storage power station, relay protection equipment, comprehensive measurement and control equipment of the auxiliary system of the energy storage power station, and energy storage equipment.

[0027] Among them, primary equipment includes but is not limited to transformers, circuit breakers, current transformers, voltage transformer disconnectors, auxiliary control systems include but are not limited to fire protection systems, air conditioning systems, heating auxiliary equipment, environmental monitoring systems and AC and DC power supply systems, energy storage equipment includes but is not limited to battery packs, control systems and PCS converters.

[0028] In the disclosed embodiment, the equipment information data of the energy storage power station can be determined, and based on the equipment information data, a standard device point table of the interaction between the energy storage power station bay layer equipment and the monitoring system can be constructed.

[0029] In the disclosed embodiment, the first monitoring data can be simulated by a simulation debugging device, and the first monitoring data simulated by the simulation debugging device can be standardized according to a pre-constructed standard device point table to obtain standard monitoring data, and the standard monitoring data can be sent to the monitoring system.

[0030] S102, parsing the standard monitoring data received by the monitoring system according to the standard device point table to obtain second monitoring data, and determining a first function debugging result of the monitoring system according to the first monitoring data and the second monitoring data.

[0031] In the embodiment of the present disclosure, after the standard monitoring data is sent to the monitoring system, the monitoring system receives the standard monitoring data accordingly and can parse the standard monitoring data received by the monitoring system according to the standard device point table to obtain second monitoring data.

[0032] Optionally, the first monitoring data and the second monitoring data may be compared, and the first function debugging result of the monitoring system may be determined according to the comparison result.

[0033] For example, in response to the first monitoring data and the second monitoring data being the same, it is determined that the first function debugging result of the monitoring system is normal; in response to the first monitoring data and the second monitoring data being different, it is determined that the first function debugging result of the monitoring system is abnormal.

[0034] S103, controlling the simulation debugging device to execute the control instruction sent by the monitoring system, obtaining the state change information of the simulation debugging device, and sending the state change information to the monitoring system, wherein the control instruction is used to indicate the target state change information of the simulation debugging device.

[0035] In the disclosed embodiment, the monitoring system may send control instructions to the simulation debugging device. Accordingly, the simulation debugging device receives the control instructions, performs actions according to the control instructions, obtains state change information of the simulation debugging device, and sends the state change information to the monitoring system.

[0036] S104, determining a second function debugging result of the monitoring system according to the state change information and the target state change information.

[0037] Optionally, the state change information and the target state change information may be compared, and the second function debugging result of the monitoring system may be determined according to the comparison result.

[0038] For example, in response to the state change information and the target state change information being the same, the second function debugging result of the monitoring system is determined to be normal; in response to the state change information and the target state change information being different, the second function debugging result of the monitoring system is determined to be abnormal.

[0039] S105, determining a debugging result of the monitoring system according to the first function debugging result and the second function debugging result.

[0040] In an embodiment of the present disclosure, in response to the first function debugging result and the second function debugging result being both normal, it is determined that the debugging result of the monitoring system is normal.

[0041] In summary, the debugging method of the energy storage power station monitoring system provided by the embodiment of the present disclosure performs standard processing on the first monitoring data simulated by the simulation debugging device according to the pre-constructed standard device point table to obtain standard monitoring data, and sends the standard monitoring data to the monitoring system, wherein the simulation debugging device is used to simulate the energy storage power station interval layer device, and parses the standard monitoring data received by the monitoring system according to the standard device point table to obtain second monitoring data, and determines the first function debugging result of the monitoring system according to the first monitoring data and the second monitoring data, and controls the simulation debugging device to execute the control instruction sent by the monitoring system to obtain the state change information of the simulation debugging device, and sends the state change information to the monitoring system, wherein the control instruction is used to indicate the target state change information of the simulation debugging device, and determines the second function debugging result of the monitoring system according to the state change information and the target state change information, and determines the debugging result of the monitoring system according to the first function debugging result and the second function debugging result. Therefore, the present disclosure can autonomously and efficiently realize the functional debugging of the monitoring system of the energy storage power station, shorten the debugging cycle of the energy storage power station monitoring system, and improve the debugging efficiency of the energy storage power station monitoring system.

[0042] The following is an explanation of the process of a debugging method for an energy storage power station monitoring system provided by an embodiment of the present disclosure.

[0043] For example, the first monitoring data includes the first telesignaling data and the first telemetering data, the second monitoring data includes the second telesignaling data and the second telemetering data, the first function debugging result includes the telesignaling function debugging result and the telemetering function debugging result, the control instruction includes the remote control instruction and the remote adjustment instruction, the state change information includes the first state change information obtained by the simulation debugging device executing the remote control instruction and the second state change information obtained by executing the remote adjustment instruction, the remote control instruction is used to indicate the first target state change information of the simulation debugging device, the remote adjustment instruction is used to indicate the second target state change information of the simulation debugging device, and the second function debugging result includes the remote control function debugging result and the remote adjustment function debugging result. Figure 2 As shown, the debugging method of the energy storage power station monitoring system proposed in this embodiment includes the following steps:

[0044] S201, standardize the first telesignaling data and the first telemetry data simulated by the simulation debugging equipment according to the pre-constructed standard device point table, obtain standard telesignaling data and standard telemetry data, and send the standard telesignaling data and the standard telemetry data to the monitoring system.

[0045] It should be noted that the first telesignaling data includes protection telesignaling, status telesignaling, etc., and the first telemetering data includes current telemetering and voltage telemetering, etc.

[0046] It should be noted that the protection telesignaling includes but is not limited to protection action, protection logic, protection setting, protection action value, protection process status word, etc. The status of the current simulation debugging equipment can be determined based on the protection telesignaling.

[0047] For example, for the protection remote signal of PCS converter, PCS converter mainly includes bridge circuit, insulated gate bipolar transistor (Insulated Gate Bipolar Transistor (IGBT) driver, DC voltage conversion, unit controller, DC capacitor, bypass switch, etc. Possible faults include: leakage current protection, low-side overload, bypass switch and its detection circuit fault, unit controller fault, control circuit protection system hardware fault and protection strategy fault. Corresponding protection configuration information is set according to the above possible fault conditions. For example, for system current protection, the amount of protection information includes quick-break protection, overcurrent protection and overload alarm; for system voltage protection, the amount of protection information includes undervoltage protection and overvoltage protection; for commutation chain redundancy protection, the amount of protection information includes link redundancy protection; for current protection, the amount of protection information includes overcurrent protection, overcurrent protection stage I, and overcurrent protection stage II; for circuit breaker protection, the amount of protection information includes circuit breaker failure protection and circuit breaker tripping protection; for system voltage protection, the amount of protection information includes working voltage overvoltage / undervoltage; for communication protection, the amount of protection information includes loss of connection of working measurement and control device, loss of connection of control protection device, internal communication fault of board and air conditioner communication fault.

[0048] S202, analyzing the standard telesignaling data and the simulated telemetry data according to the standard device point table to obtain the second telesignaling data and the second telemetry data.

[0049] S203, comparing the first telesignaling data with the second telesignaling data, and in response to the first telesignaling data and the second telesignaling data being the same, determining that the telesignaling function debugging result of the monitoring system is normal.

[0050] In an embodiment of the present disclosure, in response to the first telesignaling data and the second telesignaling data being different, it is determined that the telesignaling function debugging result of the monitoring system is abnormal.

[0051] S204: Compare the first telemetry data with the second telemetry data, and in response to the first telemetry data and the second telemetry data being the same, determine that the telemetry function debugging result of the monitoring system is normal.

[0052] In an embodiment of the present disclosure, in response to the first telemetry data and the second telemetry data being different, it is determined that the telemetry function debugging result of the monitoring system is abnormal.

[0053] S205, controlling the simulation debugging device to execute the remote control instruction and the remote adjustment instruction sent by the monitoring system, obtaining first state change information and second state change information of the simulation debugging device, and sending the first state change information and the second state change information to the monitoring system.

[0054] The first state change information is obtained by executing a remote control instruction through the simulation debugging device, and the second state change information is obtained by executing a remote adjustment instruction through the simulation debugging device.

[0055] S206: Compare the first state change information with the first target state change information, and in response to the first state change information and the first target state change information being the same, determine that the remote control function debugging result of the monitoring system is normal.

[0056] In an embodiment of the present disclosure, in response to the first state change information and the first target state change information being different, it is determined that the remote control function debugging result of the monitoring system is abnormal.

[0057] S207, comparing the second state change information with the second target state change information, and in response to the second state change information and the second target state change information being the same, determining that the remote adjustment function debugging result of the monitoring system is normal.

[0058] In the embodiment of the present disclosure, in response to the second state change information and the second target state change information being different, it is determined that the remote adjustment function debugging result of the monitoring system is abnormal.

[0059] Furthermore, in response to any function debugging result of the monitoring system being abnormal, abnormal prompt information is generated.

[0060] S208, in response to the remote signaling function debugging result, the telemetry function debugging result, the remote control function debugging result and the remote adjustment function debugging result being normal, determining that the debugging result of the monitoring system is normal.

[0061] In the embodiment of the present disclosure, after the debugging result of the monitoring system is obtained, a debugging report of the monitoring system can be generated based on the debugging result of the monitoring system.

[0062] For example, Figure 3 The electrochemical energy storage power station monitoring network structure diagram shown in the figure completes the automation function debugging of the station control layer equipment (operator station host, operator station backup machine, main coordination controller, backup coordination controller, main server, backup server, main remote motor and backup remote motor) of the monitoring system by simulating the energy storage power station interval layer equipment (PCS, batteries, conventional protection devices and conventional measurement and control devices). The energy storage power station interval layer equipment and station control layer equipment communicate through the monitoring A network switch and the monitoring B network switch.

[0063] In summary, the debugging method of the energy storage power station monitoring system provided by the embodiment of the present disclosure performs standard processing on the first telesignaling data and the first telemetering data simulated by the simulation debugging equipment according to a pre-constructed standard device point table to obtain standard telesignaling data and standard telemetering data, sends the standard telesignaling data and the standard telemetering data to the monitoring system, parses the standard telesignaling data and the simulation telemetering data according to the standard device point table to obtain the second telesignaling data and the second telemetering data, compares the first telesignaling data and the second telemetering data, and determines that the debugging result of the telesignaling function of the monitoring system is normal in response to the first telesignaling data and the second telemetering data being the same, compares the first telemetering data and the second telemetering data, and determines that the debugging result of the telemetering function of the monitoring system is normal in response to the first telemetering data and the second telemetering data being the same, controls the simulation debugging equipment to execute the remote control command and the remote adjustment command sent by the monitoring system, obtains the first state change information and the second state change information of the simulation debugging equipment, sends the first state change information and the second state change information to the monitoring system, and the first state change The information is compared with the first target state change information, and in response to the first state change information and the first target state change information being the same, it is determined that the remote control function debugging result of the monitoring system is normal, the second state change information and the second target state change information are compared, and in response to the second state change information and the second target state change information being the same, it is determined that the remote adjustment function debugging result of the monitoring system is normal, and in response to the remote signaling function debugging result, the telemetry function debugging result, the remote control function debugging result and the remote adjustment function debugging result are all normal, it is determined that the debugging result of the monitoring system is normal. Therefore, the present disclosure determines the first function debugging result of the monitoring system by comparing the first monitoring data and the second monitoring data, and compares the state change information with the target state change information to determine the second function debugging result of the monitoring system, which significantly improves the debugging efficiency of the energy storage power station monitoring system, shortens the debugging period before and after the energy storage power station is connected to the grid, reduces the debugging cost of the energy storage power station, and generates a debugging report of the monitoring system based on the debugging result, which provides a strong guarantee for the safe and continuous operation of the energy storage power station.

[0064] Figure 4 FIG. 1 is a block diagram of a debugging device for an energy storage power station monitoring system according to an exemplary embodiment. Figure 4 As shown, the debugging device 400 of the energy storage power station monitoring system of the embodiment of the present disclosure may specifically include: a first processing module 401 , a first debugging module 402 , a second processing module 403 , a second debugging module 404 and a determination module 405 .

[0065] The first processing module 401 is used to perform standard processing on the first monitoring data simulated by the simulation debugging device according to a pre-constructed standard device point table to obtain standard monitoring data, and send the standard monitoring data to the monitoring system, wherein the simulation debugging device is used to simulate the energy storage power station interval layer device;

[0066] A first debugging module 402 is used to parse the standard monitoring data received by the monitoring system according to the standard device point table to obtain second monitoring data, and determine a first function debugging result of the monitoring system according to the first monitoring data and the second monitoring data;

[0067] The second processing module 403 is used to control the simulation debugging device to execute the control instruction sent by the monitoring system, obtain the state change information of the simulation debugging device, and send the state change information to the monitoring system, wherein the control instruction is used to indicate the target state change information of the simulation debugging device;

[0068] A second debugging module 404, configured to determine a second function debugging result of the monitoring system according to the state change information and the target state change information;

[0069] The determination module 405 is used to determine the debugging result of the monitoring system according to the first function debugging result and the second function debugging result.

[0070] In one embodiment of the present disclosure, the first monitoring data includes at least first telesignaling data and first telemetry data, the second monitoring data includes at least second telesignaling data and second telemetry data, and the first function debugging result includes at least telesignaling function debugging result and telemetry function debugging result.

[0071] In one embodiment of the present disclosure, the first debugging module 402 is further used to: compare the first telesignaling data with the second telesignaling data, and in response to the first telesignaling data and the second telesignaling data being the same, determine that the debugging result of the telesignaling function of the monitoring system is normal; compare the first telemetry data with the second telemetry data, and in response to the first telemetry data and the second telemetry data being the same, determine that the debugging result of the telemetry function of the monitoring system is normal.

[0072] In one embodiment of the present disclosure, the control instruction includes at least a remote control instruction and a remote adjustment instruction, the state change information includes at least a first state change information obtained by the simulation debugging device executing the remote control instruction and a second state change information obtained by executing the remote adjustment instruction, the remote control instruction is used to indicate the first target state change information of the simulation debugging device, the remote adjustment instruction is used to indicate the second target state change information of the simulation debugging device, and the second function debugging result includes at least a remote control function debugging result and a remote adjustment function debugging result.

[0073] In one embodiment of the present disclosure, the second debugging module 404 is further used to: compare the first state change information with the first target state change information, and in response to the first state change information and the first target state change information being the same, determine that the remote control function debugging result of the monitoring system is normal; compare the second state change information with the second target state change information, and in response to the second state change information and the second target state change information being the same, determine that the remote adjustment function debugging result of the monitoring system is normal.

[0074] In one embodiment of the present disclosure, the device 400 is further used to: generate abnormal prompt information in response to any function debugging result of the monitoring system being abnormal.

[0075] In one embodiment of the present disclosure, the determination module 405 is further used to: in response to both the first function debugging result and the second function debugging result being normal, determine that the debugging result of the monitoring system is normal.

[0076] In one embodiment of the present disclosure, after determining the debugging result of the monitoring system, the device 400 generates a debugging report of the monitoring system based on the debugging result of the monitoring system.

[0077] In the embodiment of the present disclosure, the specific manner in which each module in the debugging device of the energy storage power station monitoring system of the above embodiment performs operations has been described in detail in the embodiment of the debugging method of the energy storage power station monitoring system, and will not be repeated here.

[0078] In summary, the debugging device of the energy storage power station monitoring system provided by the embodiment of the present disclosure performs standard processing on the first monitoring data simulated by the simulation debugging device according to the pre-constructed standard device point table to obtain standard monitoring data, and sends the standard monitoring data to the monitoring system, wherein the simulation debugging device is used to simulate the energy storage power station interval layer device, and parses the standard monitoring data received by the monitoring system according to the standard device point table to obtain second monitoring data, and determines the first function debugging result of the monitoring system according to the first monitoring data and the second monitoring data, and controls the simulation debugging device to execute the control instruction sent by the monitoring system to obtain the state change information of the simulation debugging device, and sends the state change information to the monitoring system, wherein the control instruction is used to indicate the target state change information of the simulation debugging device, and determines the second function debugging result of the monitoring system according to the state change information and the target state change information, and determines the debugging result of the monitoring system according to the first function debugging result and the second function debugging result. Therefore, the present disclosure can autonomously and efficiently realize the functional debugging of the monitoring system of the energy storage power station, shorten the debugging cycle of the energy storage power station monitoring system, and improve the debugging efficiency of the energy storage power station monitoring system.

[0079] In order to implement the above embodiment, Figure 5 As shown, the present disclosure also proposes an electronic device 1000, the device includes a memory 110, a processor 120, and a computer program stored in the memory and executable on the processor 120, when the processor 120 executes the program instructions, the execution is realized Figures 1 to 3 An embodiment of a debugging method for an energy storage power station monitoring system.

[0080] In order to implement the above embodiments, the present disclosure also proposes a computer-readable storage medium.

[0081] When the instructions in the computer-readable storage medium are executed by the processor of the electronic device, the electronic device can execute the debugging method of the energy storage power station monitoring system as described above. Optionally, the computer-readable storage medium can be a ROM, a random access memory (RAM), a CD-ROM, a magnetic tape, a floppy disk, an optical data storage device, etc.

[0082] Those skilled in the art will readily appreciate other embodiments of the present disclosure after considering the specification and practicing the invention disclosed herein. The present disclosure is intended to cover any variations, uses or adaptations of the present disclosure that follow the general principles of the present disclosure and include common knowledge or customary techniques in the art that are not disclosed in the present disclosure. The description and examples are to be considered exemplary only, and the true scope and spirit of the present disclosure are indicated by the following claims.

[0083] It should be understood that the present disclosure is not limited to the exact structures that have been described above and shown in the drawings, and that various modifications and changes may be made without departing from the scope thereof. The scope of the present disclosure is limited only by the appended claims.

Claims

1. A debugging method for an energy storage power station monitoring system, characterized in that: The method comprises: According to a pre-constructed standard device point table, the first monitoring data simulated by the simulation debugging device is standardized to obtain standard monitoring data, and the standard monitoring data is sent to the monitoring system, wherein the simulation debugging device is used to simulate the energy storage power station interval layer device; parsing the standard monitoring data received by the monitoring system according to the standard device point table to obtain second monitoring data, and determining a first function debugging result of the monitoring system according to the first monitoring data and the second monitoring data; Controlling the simulation debugging device to execute the control instruction sent by the monitoring system, obtaining the state change information of the simulation debugging device, and sending the state change information to the monitoring system, wherein the control instruction is used to indicate the target state change information of the simulation debugging device; Determining a second function debugging result of the monitoring system according to the state change information and the target state change information; The debugging result of the monitoring system is determined according to the first function debugging result and the second function debugging result.

2. The method according to claim 1, characterized in that The first monitoring data at least includes first telesignaling data and first telemetry data, the second monitoring data at least includes second telesignaling data and second telemetry data, and the first function debugging result at least includes a telesignaling function debugging result and a telemetry function debugging result.

3. The method according to claim 2, characterized in that Determining a first function debugging result of the monitoring system according to the first monitoring data and the second monitoring data includes: comparing the first remote signaling data with the second remote signaling data, and in response to the first remote signaling data and the second remote signaling data being the same, determining that the remote signaling function debugging result of the monitoring system is normal; The first telemetry data and the second telemetry data are compared, and in response to the first telemetry data and the second telemetry data being the same, it is determined that the telemetry function debugging result of the monitoring system is normal.

4. The method according to claim 1, characterized in that: The control instruction includes at least a remote control instruction and a remote adjustment instruction, the state change information includes at least first state change information obtained by the simulation debugging device executing the remote control instruction and second state change information obtained by executing the remote adjustment instruction, the remote control instruction is used to indicate first target state change information of the simulation debugging device, the remote adjustment instruction is used to indicate second target state change information of the simulation debugging device, and the second function debugging result includes at least a remote control function debugging result and a remote adjustment function debugging result.

5. The method according to claim 4, characterized in that The determining, according to the state change information and the target state change information, a second function debugging result of the monitoring system includes: comparing the first state change information with the first target state change information, and in response to the first state change information and the first target state change information being the same, determining that a remote control function debugging result of the monitoring system is normal; The second state change information is compared with the second target state change information, and in response to the second state change information being the same as the second target state change information, it is determined that the remote adjustment function debugging result of the monitoring system is normal.

6. The method according to any one of claims 2 to 5, characterized in that: The method further comprises: In response to any function debugging result of the monitoring system being abnormal, abnormal prompt information is generated.

7. The method according to any one of claims 2 to 5, characterized in that: Determining the debugging result of the monitoring system according to the first function debugging result and the second function debugging result includes: In response to the first function debugging result and the second function debugging result being both normal, it is determined that the debugging result of the monitoring system is normal.

8. The method according to claim 1, characterized in that: After determining the debugging result of the monitoring system, the method further comprises: Based on the debugging result of the monitoring system, a debugging report of the monitoring system is generated.

9. A debugging device for an energy storage power station monitoring system, characterized in that: The device comprises: A first processing module is used to perform standardization processing on the first monitoring data simulated by the simulation debugging device according to a pre-constructed standard device point table to obtain standard monitoring data, and send the standard monitoring data to the monitoring system, wherein the simulation debugging device is used to simulate the energy storage power station interval layer device; A first debugging module, configured to parse the standard monitoring data received by the monitoring system according to the standard device point table to obtain second monitoring data, and determine a first function debugging result of the monitoring system according to the first monitoring data and the second monitoring data; A second processing module is used to control the simulation debugging device to execute the control instruction sent by the monitoring system, obtain the state change information of the simulation debugging device, and send the state change information to the monitoring system, wherein the control instruction is used to indicate the target state change information of the simulation debugging device; A second debugging module, used to determine a second function debugging result of the monitoring system according to the state change information and the target state change information; A determination module is used to determine the debugging result of the monitoring system according to the first function debugging result and the second function debugging result.

10. An electronic device, characterized in that: include: processor; a memory for storing executable instructions for the processor; The processor is configured to execute the instructions to implement the debugging method of the energy storage power station monitoring system according to any one of claims 1 to 8.