Construction method for overall lifting and then split unloading lifting of large-span split type steel corridor
By employing a phased, synchronous lifting construction method, the problems of high-altitude connection accuracy and high-altitude operation risks of large-span steel connecting corridors were solved, achieving optimization of safety, quality, and construction period. The use of hydraulic lifting devices and ground-integrated installation technology reduced the risks of high-altitude operations and construction costs.
Patent Information
- Application Number
- CN202511246254.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-09-02
- Publication Date
- 2025-11-28
AI Technical Summary
In traditional construction techniques, the installation of large-span steel connecting corridors in bulk or in sections at high altitudes presents challenges such as difficulty in controlling the precision of high-altitude connections, high costs of measures, high risks of high-altitude operations, and long construction periods. Furthermore, conventional hydraulic overall synchronous lifting requires a large number of temporary measures, which exacerbates the risks of high-altitude operations.
The construction method adopts a progressive, phased, synchronous lifting approach, which involves "stacked combination → integrated assembly → first-time lifting and docking → subsequent separate unloading → second-time lifting and docking". By integrating and installing pre-set auxiliary structures on the ground, the split steel corridor is lifted as a whole to the design elevation using a hydraulic lifting device, and the load is unloaded and converted in stages.
It achieves comprehensive optimization in terms of safety, quality, and construction period of large-span split steel corridor construction, reduces the amount of high-altitude work, lowers the risks of high-altitude work, and ensures precise positioning and safe stress transfer.
Smart Images

Figure CN121024327A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of building construction technology, specifically to a construction method for lifting and then unloading a large-span, split-type steel corridor as a whole. Background Technology
[0002] As modern architecture develops towards super high-rise buildings, the large-span steel connecting corridors between super high-rise towers, as high-altitude connecting passages, are often erected at heights exceeding 100 meters, facing challenges such as large-tonnage, large-span dismantling, high installation control precision requirements, and prominent safety risks during high-altitude construction.
[0003] In traditional construction techniques, high-altitude bulk or segmented hoisting requires excessive component disassembly due to limitations in lifting equipment, leading to problems such as difficulty in controlling the precision of high-altitude connections, high costs, significant risks associated with high-altitude operations, and long construction periods. While hydraulic synchronous lifting technology for ultra-large components can lift steel corridors as a whole after assembly on the ground, reducing some of the difficulty, for double-layered, split steel corridors (where the upper and lower layers are separate and not part of a system, with large inter-layer heights), conventional hydraulic synchronous lifting requires a large number of temporary measures, such as additional truss supports, between layers to combine the two-layer structure. This results in a large amount of additional measures, increased lifting load, higher requirements for the load-bearing capacity of the assembly site (such as the basement roof slab), and greater difficulty in subsequent dismantling, further exacerbating the risks of high-altitude operations. Summary of the Invention
[0004] To address the aforementioned technical problems, this invention provides a construction method for the overall lifting and subsequent unloading and lifting of a large-span, split-type steel connecting corridor.
[0005] The technical solution of this invention to solve the above-mentioned technical problems is as follows: A construction method for the overall lifting and then separate unloading and lifting of a large-span split steel corridor, comprising the following steps: S1: On the supporting structure directly below the installation location, the lower and upper corridors of the split steel corridor are stacked and combined with temporary connectors to form an overall lifting unit, and the ground integration installation of the preset auxiliary structure is completed during the stacking process. S2: Lifting devices are installed on the tower structures on both sides of the steel connecting corridor, and the lifting devices are connected to the overall lifting unit; S3: The lifting device is used to simultaneously lift the overall lifting unit to the designed docking position of the lower-level connecting corridor, thereby completing the docking and fixing of the lower-level connecting corridor with the tower structure; S4: Remove the temporary connecting parts to unload the load separately, so that the load of the lower corridor can be transferred to the tower structure; S5: The upper-level connecting corridor is lifted individually and synchronously to its designed docking position using the lifting device, thus completing the docking and fixing of the upper-level connecting corridor with the tower structure; S6: Remove the lifting device and other temporary measures to complete the construction of the steel connecting corridor.
[0006] Furthermore, step S1 specifically includes the following steps: S1.1: Support structure preparation: The load-bearing capacity of the support structure directly below the installation location is checked. If it does not meet the requirements, it is reinforced. A temporary support frame is built on the support structure. The frame is arranged with distribution beams and connecting beams are set between the distribution beams to enhance the overall stability and ensure that the frame can stably bear the weight of the steel corridor. S1.2: Lower-level corridor assembly: On the temporary support frame, the lower-level corridor is assembled from the middle to both sides. First, the main beam is installed and firmly welded to the distribution beam, ensuring that the weld height meets the design standard. At the same time, angle steel supports are set on both sides of the main beam to prevent the main beam from tilting during the assembly process. After the main beam is installed, the secondary beams are installed in sequence to ensure the structural integrity of the lower-level corridor. S1.3: Upper-level corridor assembly: After the lower-level corridor is assembled and passes quality inspection, secondary vertical distribution beams are welded to the corresponding positions above the lower-level corridor. The main beam of the upper-level corridor is hoisted to the predetermined position using lifting equipment and welded and fixed to the secondary vertical distribution beams. At the same time, angle steel supports are set on both sides of the main beam of the upper-level corridor, relying on the structure of the lower-level corridor, to ensure the stability of the upper-level corridor during the assembly process. Then, the upper-level beams are installed to complete the basic assembly of the upper-level corridor. S1.4: Temporary connector installation: Select a temporary connector with good rigidity and rigidly connect its two ends to the top of the lower corridor and the bottom of the upper corridor respectively to ensure that the connection is firm and reliable, so that the upper and lower corridors form a stable overall lifting unit. S1.5: Installation of Pre-set Ancillary Structures: During the stacking and assembly of the upper and lower connecting corridors, the ground integration installation of the pre-set ancillary structures is carried out simultaneously. Steel truss floor slabs are laid, and spaces are reserved in advance for areas that will require subsequent patching work. The curtain wall keel and window cleaning machine track at the bottom of the lower connecting corridor are installed to ensure that the installation position is accurate. Fireproof coating is applied to the steel connecting corridor assembly section, and sufficient space is reserved in the node area so that the fireproof coating will not affect the subsequent node connection and welding work.
[0007] Furthermore, step S2 involves installing lifting devices on the tower structures on both sides of the steel connecting corridor, specifically including the following steps: S2.1: Construct a lifting platform: A temporary cantilevered lifting platform is formed by welding steel beams on the side of the tower column. The cantilever length is determined according to construction needs. An operating platform and protective facilities are erected on the platform. S2.2: Install lifting equipment: Fix the hydraulic lifting device on the lifting platform, and use a pressure plate to connect the lifting device to the platform. The pressure plate is welded to the platform and not to the lifting device. S2.3: Configure steel strands: Insert undamaged steel strands into the hoist at left-hand and right-hand intervals, ensuring that the deflection angle of the steel strands and the skew of the upper and lower suspension points meet the requirements. Connect the hoist and the special ground anchor to both ends of the steel strands respectively.
[0008] Furthermore, the connection between the lifting device and the overall lifting unit in step S2 includes the following specific steps: S2.4: Install a special lower lifting device corresponding to the lifting platform on the top of the upper connecting corridor steel beam of the overall lifting unit. Connect the lower lifting device to the ground anchor of the lifting device through steel strands. Leave sufficient length at the end of the steel strands and lock them. S2.5: Install steel strand guide frame to prevent steel strand from tangling, connect the oil pipe between the hydraulic pump station and the hoist, install the sensor and connect it to the control system, and complete the no-load commissioning of the system.
[0009] Furthermore, in step S3, the overall lifting unit is synchronously lifted to the designed docking position of the lower connecting corridor using the lifting device, specifically including the following steps: S3.1: Pre-lifting: Adjust the pressure of the extension cylinder to pre-tension the entire steel strand, so that each steel strand is tensioned in the same way; load in stages according to proportion, and cut the welding points of the temporary support short columns of the lower corridor when the load reaches 20%, 40%, 60%, and 80% in sequence. Continue loading until the overall lifting unit is separated from the assembly jig, and lock it after lifting it 100mm off the ground. Stay for more than 12 hours to check the lifting point structure, load-bearing system and lifting equipment. S3.2: Formal Lifting: Starting from the pre-lifting and adjusted lifting point height, reset the displacement sensor, maintain the horizontal posture of the structure and lift synchronously as a whole. Detect and adjust the height of each lifting point every 5m of lifting. Control the lifting speed at 4-5 meters per hour. Reduce the lifting speed when the structure is about 20cm away from the design position.
[0010] Furthermore, when removing the temporary connectors for disassembly and unloading in step S4, the specific steps include: S4.1: Confirm that all butt welds between the lower-level connecting corridor and the tower structure have been completed and passed inspection, and that the subsequent supplementary members have been installed and temporarily fixed in place; S4.2: Remove the temporary connecting parts between the upper and lower corridors in a symmetrical order from the inside out, so that the load of the upper corridor is gradually transferred to the suspension point and the tower structure on both sides.
[0011] Furthermore, step S4 also includes load transfer monitoring: during the dismantling of temporary connecting parts, the monitoring system of the lifting device monitors the stress changes of each lifting point in real time to ensure that the load transfer is smooth. If any abnormality occurs, the operation is suspended and adjusted. After the dismantling is completed, it is confirmed that the load of the lower corridor has been completely transferred to the tower structure.
[0012] Furthermore, in step S5, the upper connecting corridor is individually and synchronously lifted to its designed docking position using a lifting device, specifically including the following steps: S5.1: Pre-lift inspection: Confirm that the temporary connectors have been removed and the load of the lower corridor has been completely transferred to the tower. Check the condition of the lifting device and steel strands to ensure there are no abnormalities. S5.2 Synchronous Lifting: Start the lifting device and gradually lift the upper corridor based on the principles of balanced hydraulic pressure at the lifting points, structural posture adjustment, and synchronous displacement control. During the process, the height of each lifting point is checked regularly and the horizontal posture is adjusted. When approaching the design position, the lifting speed is reduced.
[0013] Furthermore, step S5, which completes the connection and fixation between the upper corridor and the tower structure, includes the following steps: using the fine-tuning function of the lifting device to make the upper corridor accurately aligned, using temporary fixing measures to fix the non-post-replacement section, installing and temporarily fixing the post-replacement section members, performing butt welding and testing, and locking the lifting device after passing the test.
[0014] This invention offers the following advantages: The method for constructing a large-span, split-type steel corridor by lifting and then unloading it in stages employs a progressive, phased, synchronous lifting construction technique: "stacked assembly → integrated assembly → primary lifting and docking → secondary unloading → secondary lifting and docking." This achieves comprehensive optimization of safety, quality, cost, and construction period in the construction of large-span, split-type steel corridors. By stacking the upper and lower steel corridor structures on the basement roof slab, using short columns for temporary connections to form the overall structure, and then using a hydraulic synchronous lifting device installed on the tower columns, the structure is progressively lifted to the design elevation in stages. The construction process incorporates several key technologies, including simulation, graded synchronous control, and unloading conversion, to achieve precise positioning and safe stress conversion. Simultaneous ground-based integrated installation is adopted, completing auxiliary work such as floor decking, fireproof coating, and curtain wall framing during the steel corridor assembly stage, reducing the amount of high-altitude work, lowering the risks of high-altitude operations, and achieving inherent safety. Attached Figure Description
[0015] Figure 1 This is a flowchart of the construction method in this invention; Figure 2 This is a detailed flowchart of the construction method in this invention; Figure 3 This is a schematic diagram illustrating the construction method of the present invention. Detailed Implementation
[0016] The principles and features of the present invention are described below with reference to the accompanying drawings. The examples given are only for explaining the present invention and are not intended to limit the scope of the present invention.
[0017] like Figures 1 to 2As shown, a construction method for the overall lifting and subsequent separate unloading and lifting of a large-span, split-type steel corridor includes the following steps: S1: On the supporting structure directly below the installation location, the lower and upper corridors of the split steel corridor are stacked and combined with temporary connectors to form an overall lifting unit, and the ground integration installation of the preset auxiliary structure is completed during the stacking process. Specifically, the following steps are included: S1.1: Support Structure Preparation: The load-bearing capacity of the support structure directly below the installation location is checked. If it does not meet the requirements, reinforcement is carried out. A temporary support frame is erected on the support structure, using distribution beams. Connecting beams are installed between the distribution beams to enhance overall stability and ensure that the frame can stably support the weight of the steel connecting corridor. The temporary support structure consists of distribution beams with specifications of HM488*300 or HM700*300. Six distribution beams are arranged at the bottom, aligning with the two sides of the three rows of transverse beams of the steel connecting corridor. Connecting beams are installed between the distribution beams to increase stability and prevent uneven settlement. Six primary vertical distribution beams are welded onto each row of distribution beams, raising the steel connecting corridor to 1500mm. The primary vertical distribution beams support the six lower main beams of the steel connecting corridor. After the lower main beams are installed, six secondary vertical distribution beams with a height of 700mm are welded onto the main beams to support the upper main beams of the steel connecting corridor.
[0018] S1.2: Lower-level corridor assembly: On the temporary support frame, the lower-level corridor is assembled from the middle to both sides. First, the main beam is installed and firmly welded to the distribution beam, ensuring that the weld height meets the design standard. At the same time, angle steel supports are set on both sides of the main beam to prevent the main beam from tilting during the assembly process. After the main beam is installed, the secondary beams are installed in sequence to ensure the structural integrity of the lower-level corridor. S1.3: Upper-level corridor assembly: After the lower-level corridor is assembled and passes quality inspection, secondary vertical distribution beams are welded to the corresponding positions above the lower-level corridor. The main beam of the upper-level corridor is hoisted to the predetermined position using lifting equipment and welded and fixed to the secondary vertical distribution beams. At the same time, angle steel supports are set on both sides of the main beam of the upper-level corridor, relying on the structure of the lower-level corridor, to ensure the stability of the upper-level corridor during the assembly process. Then, the upper-level beams are installed to complete the basic assembly of the upper-level corridor. S1.4: Temporary Connector Installation: Rigid temporary connectors (short steel columns) are selected, and their two ends are rigidly connected to the top of the lower-level corridor and the bottom of the upper-level corridor, respectively, to ensure a firm and reliable connection, forming a stable overall lifting unit for the upper and lower corridors. Based on lifting simulation analysis, the pre-installed and lifting sections of the steel corridor structure are reinforced. The specifications of the short steel columns are H600×600×25×25 and HW300×300×10×15, both made of Q355B material. The short steel columns are connected to the original structure using full penetration welding, with a weld grade of Class I.
[0019] S1.5: Installation of Pre-set Ancillary Structures: During the stacking and assembly of the upper and lower connecting corridors, the ground integration installation of the pre-set ancillary structures is carried out simultaneously. Steel truss floor slabs are laid, and spaces are reserved in advance for areas that will require subsequent patching work. The curtain wall keel and window cleaning machine track at the bottom of the lower connecting corridor are installed to ensure that the installation position is accurate. Fireproof coating is applied to the steel connecting corridor assembly section, and sufficient space is reserved in the node area so that the fireproof coating will not affect the subsequent node connection and welding work.
[0020] S2: Lifting devices are installed on the tower structures on both sides of the steel connecting corridor, and the lifting devices are connected to the overall lifting unit.
[0021] Specifically, lifting devices are installed on the tower structures on both sides of the steel connecting corridor, including the following steps: S2.1: Construct a lifting platform: A temporary cantilevered lifting platform is formed by welding steel beams on the side of the tower column. The cantilever length is determined according to construction needs. An operating platform and protective facilities are erected on the platform. S2.2: Install lifting equipment: Fix the hydraulic lifting device on the lifting platform, and use a pressure plate to connect the lifting device to the platform. The pressure plate is welded to the platform and not to the lifting device. S2.3: Steel Strand Configuration: Thread undamaged steel strands into the lifting device at left-hand and right-hand intervals, ensuring the deflection angle and skew of the upper and lower lifting points meet requirements. Connect both ends of the steel strand to the lifting device and a dedicated ground anchor. Before fixing the steel strand ground anchor, conduct a no-load lifting operation check to confirm that the hydraulic lifting system is operating normally. After confirming the system is functioning correctly, fix the steel strand ground anchor in the lower lifting device. Another purpose of the no-load operation is to lift any excessively long steel strands to a suitable height, cut off the excess portion, and leave a length of ≥10cm from the ground anchor at the lower end of the steel strand.
[0022] The connection between the lifting device and the overall lifting unit includes the following specific steps: S2.4: Install a special lower lifting device corresponding to the lifting platform on the top of the upper connecting corridor steel beam of the overall lifting unit. Connect the lower lifting device to the ground anchor of the lifting device through steel strands. Leave sufficient length at the end of the steel strands and lock them. S2.5: Install the steel strand guide frame to prevent the steel strand from tangling, connect the hydraulic pump station and the hoist's oil pipes, install the sensors and connect them to the control system, and complete the system's no-load commissioning. The steel strand guide frame is used to guide the steel strand during hoisting and prevent it from tangling. The guide frame's exit direction is based on the principle of facilitating the installation and removal of oil pipes and sensors and not affecting the free fall of the steel strand. The guide frame crossbeam is approximately 1.5 to 2 meters above the safety anchor. After the steel strand is exited, bundle it to prevent it from becoming scattered.
[0023] S3: The entire lifting unit is simultaneously lifted to the designed docking position of the lower-level connecting corridor using the lifting device, thus completing the docking and fixing of the lower-level connecting corridor with the tower structure; Specifically, in step S3, the entire lifting unit is synchronously lifted to the designed docking position of the lower connecting corridor using a lifting device, which includes the following steps: S3.1: Pre-lifting: Adjust the cylinder pressure to pre-tension the entire steel strand, ensuring each strand is tensioned uniformly. Load the steel strands in stages, reaching 20%, 40%, 60%, and 80% load respectively. Cut the welding points of the temporary support columns of the lower-level connecting corridor at these stages. Continue loading until the entire lifting unit detaches from the assembly frame. After lifting 100mm off the ground, lock the unit and hold it for at least 12 hours to inspect the lifting point structure, load-bearing system, and lifting equipment. Specifically, based on the reaction force values of each lifting point calculated by the computer simulation of the steel connecting corridor, perform staged loading (trial lifting) on the steel connecting corridor structure. The cylinder pressure of the hydraulic lifting system at each lifting point should be increased slowly in stages, at 20%, 40%, 60%, and 80% respectively. When 80% is reached, cut and unload the welding points of the temporary support columns of the lower-level connecting corridor. Use a symmetrical cutting and unloading method from the inside out to separate the steel connecting corridor to be lifted from the support columns. Once it is confirmed that there are no abnormalities in any part, loading can continue to 90%, 95%, and 100% until the truss is completely detached from the assembly jig and unloaded. During the staged loading process, after each stage of loading is completed, it should be paused and checked (such as the deformation of the upper and lower lifting points, the truss structure, etc. before and after loading, as well as the stability of the surrounding civil structures). If everything is normal, continue to the next stage of loading.
[0024] When the structure is about to leave the assembly jig during the staged loading process, different points may not lift off the ground simultaneously. In this case, the lifting speed should be reduced, and the lifting status of each point should be closely observed. If necessary, "single-point movement" lifting should be performed to ensure that the truss lifts off the ground smoothly and synchronously at all points.
[0025] S3.2: Formal Lifting: Starting from the pre-lifting and adjusted lifting point height, reset the displacement sensor, maintain the horizontal posture of the structure and lift synchronously as a whole. Detect and adjust the height of each lifting point every 5m of lifting. Control the lifting speed at 4-5 meters per hour. Reduce the lifting speed when the structure is about 20cm away from the design position.
[0026] Specifically, in this step, to ensure the smooth and safe lifting process of the steel corridor structure, based on the characteristics of the structure, a synchronous lifting and unloading control strategy of "balanced hydraulic pressure at lifting points, structural posture adjustment, synchronous displacement control, and staged unloading and positioning" is proposed. After all pre-lifting checks are normal and error-free, the formal lifting will proceed. Measuring instruments will be used to detect the distance from the ground at each lifting point, and the relative height difference between each lifting point will be calculated. The height of each lifting point will be adjusted using the hydraulic lifting system to achieve a horizontal posture. The adjusted height of each lifting point will be used as the new starting position, and the displacement sensors will be reset. During the overall lifting process, this posture will be maintained until the structure is lifted to near the design elevation. During the overall lifting construction, the main factors affecting the lifting speed of the components are the length of the hydraulic oil pipes and the number of pump stations. According to the equipment configuration in this plan, the overall lifting speed is approximately 4-5 meters per hour. During the lifting and lowering process, fine-tuning of the height is required due to aerial posture adjustments and member alignment. Before fine-tuning begins, the computer synchronous control system will be switched from automatic mode to manual mode. As needed, the hydraulic lifters at each lifting point in the entire hydraulic lifting system can be synchronously micro-moved (raised or lowered), or individual hydraulic lifters can be micro-adjusted. The micro-movement, or jogging adjustment, can achieve millimeter-level precision, fully meeting the accuracy requirements for truss steel structure installation.
[0027] S4: Remove the temporary connecting parts to unload the load separately, so that the load of the lower corridor can be transferred to the tower structure; When removing the temporary connectors for disassembly in step S4, the specific steps include: S4.1: Confirm that all butt welds between the lower-level connecting corridor and the tower structure have been completed and passed inspection, and that the subsequent supplementary members have been installed and temporarily fixed in place; S4.2: Remove the temporary connecting parts between the upper and lower corridors in a symmetrical order from the inside out, so that the load of the upper corridor is gradually transferred to the suspension point and the tower structure on both sides.
[0028] In addition, step S4 also includes load transfer monitoring: during the dismantling of temporary connecting parts, the monitoring system of the lifting device monitors the stress changes of each lifting point in real time to ensure that the load transfer is smooth. If any abnormality occurs, the operation is suspended and adjusted. After the dismantling is completed, it is confirmed that the load of the lower corridor has been completely transferred to the tower structure.
[0029] S5: The upper-level connecting corridor is lifted individually and synchronously to its designed docking position using a lifting device, thus completing the docking and fixing of the upper-level connecting corridor with the tower structure; Specifically, in step S5, the upper connecting corridor is individually and synchronously lifted to its designed docking position using a lifting device, which includes the following steps: S5.1: Pre-lift inspection: Confirm that the temporary connectors have been removed and the load of the lower corridor has been completely transferred to the tower. Check the condition of the lifting device and steel strands to ensure there are no abnormalities. S5.2 Synchronous Lifting: Start the lifting device and gradually lift the upper corridor based on the principles of balanced hydraulic pressure at the lifting points, structural posture adjustment, and synchronous displacement control. During the process, the height of each lifting point is checked regularly and the horizontal posture is adjusted. When approaching the design position, the lifting speed is reduced.
[0030] Step S5 involves the following steps to complete the connection and fixation between the upper-level corridor and the tower structure: the upper-level corridor is precisely aligned using the fine-tuning function of the lifting device; temporary fixing measures are used to fix the non-post-replacement section; the post-replacement section members are installed and temporarily fixed; butt welding and testing are performed; and the lifting device is locked after passing the test.
[0031] Specifically, after the upper-level connecting corridor structural members are installed and all butt welds are completed and inspected, the hydraulic system is operated to unload synchronously, transferring the truss to the permanent structure. Then, the hydraulic system is unloaded in stages at 10%, 30%, 60%, 80%, 90%, and 100% according to the following proportions, until the steel strands are completely relaxed and the entire load of the upper-level connecting corridor is transferred to the main structure. During unloading, based on the calculated lifting load, all lifting points are lowered simultaneously by 10%. During this process, load transfer may occur, meaning that points with faster unloading speeds transfer the load to points with slower unloading speeds, potentially causing overloading at some points. Therefore, the pump station frequency needs to be adjusted, the descent speed slowed, and the pressure and displacement values in the computer control system closely monitored. If the load at any lifting point exceeds 10% of the pre-unloading load, or if the displacement of the lifting points is asynchronous by 10mm, unloading at other points is immediately stopped, and these abnormal points are unloaded separately. This process is repeated until the steel strands are completely relaxed. After unloading, sensors, data cables and other vulnerable parts should be manually removed and properly placed in a timely manner. Steel strands, hoists and pump stations should be dismantled using tower cranes. When cutting steel strands with flames, the distance from the bottom of the hoist should not be too close to avoid the flames damaging the hoist base.
[0032] S6: Dismantle the lifting device and other temporary measures to complete the steel connecting corridor construction. Specifically, using the reserved space between the main tower and the steel tower, the tower crane is used to lower the steel strands and lifting devices. During the lowering process, preliminary coiling is carried out simultaneously. 12mm thick temporary lifting lugs are welded onto the components to be dismantled, and the tower crane is used for the dismantling and hoisting of the components. During the dismantling of the lifting frame, the tower crane applies slight lifting force to the components to be dismantled, keeping the hoisting wire rope taut. A hanging basket or large hanging basket is used in conjunction to cut and separate the lifting frame, employing flame cutting for separation. During separation, ropes are used for traction to prevent component instability. The temporary horizontal reinforcement members are dismantled, and subsequent steel pipe supports are installed and welded, and the reserved floor decking is laid.
[0033] Figure 3 As shown, (a)-(g) are schematic diagrams of the specific construction process in this invention, wherein, Figure 3(a) indicates that the steel connecting corridor is assembled into a whole on the basement roof slab directly below the installation location, temporary lifting measures are set up, and hydraulic synchronous lifting system equipment, including hydraulic pump source system, lifting device, sensors, etc., is installed. Special bottom anchors and special steel strands are installed between the upper and lower lifting points, and the hydraulic lifting system is debugged. Figure 3 (b) indicates: After confirming that there are no errors, load the material in sequence at 20%, 40%, 60%, 80%, and 100% until the structure is about 10cm off the ground. If necessary, make "single-point" fine adjustments and stay for 12 hours. Figure 3 (c) indicates: After re-inspecting the steel structure lifting unit and confirming that there are no abnormalities, the hydraulic lifting system is debugged and the entire connecting corridor structure is lifted. Figure 3 (d) indicates: The connecting corridor structure is raised to the designed height of about 200mm, the lifting speed is slowed down, the posture of the lifting unit is finely adjusted, and the lower connecting corridor structure is accurately positioned and welded together. Figure 3 (e) indicates that after the butt welding is completed and the inspection is passed, the temporary connection between the upper and lower corridors will be cut off. Figure 3 (f) indicates: Continue to lift the upper corridor structure until it is precisely in place, carry out the butt weld work between the upper corridor structure and the main structure, the structure forms an overall load-bearing structure, the hydraulic lift is unloaded, the lifting equipment and temporary reinforcement rods are removed, and the installation of the corridor structure is completed. Figure 3 (g) indicates: Continue to lift the upper corridor structure until it is precisely in place, carry out the butt weld work between the upper corridor structure and the main structure, the structure forms an integral force, the hydraulic lift is unloaded, the lifting equipment and temporary reinforcement rods are removed, and the installation of the corridor structure is completed.
[0034] Additionally, it should be noted that components not described in detail in this article are existing technologies.
[0035] The above are merely preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A construction method for the overall lifting and subsequent separate unloading and lifting of a large-span, split-type steel connecting corridor, characterized in that: Includes the following steps: S1: On the supporting structure directly below the installation location, the lower and upper corridors of the split steel corridor are stacked and combined with temporary connectors to form an overall lifting unit, and the ground integration installation of the preset auxiliary structure is completed during the stacking process. S2: Lifting devices are installed on the tower structures on both sides of the steel connecting corridor, and the lifting devices are connected to the overall lifting unit; S3: The lifting device is used to simultaneously lift the overall lifting unit to the designed docking position of the lower-level connecting corridor, thereby completing the docking and fixing of the lower-level connecting corridor with the tower structure; S4: Remove the temporary connecting parts to unload the load separately, so that the load of the lower corridor can be transferred to the tower structure; S5: The upper-level connecting corridor is lifted individually and synchronously to its designed docking position using the lifting device, thus completing the docking and fixing of the upper-level connecting corridor with the tower structure; S6: Remove the lifting device and other temporary measures to complete the construction of the steel connecting corridor.
2. The construction method for the overall lifting and subsequent unloading and lifting of a large-span split steel corridor according to claim 1, characterized in that, Step S1 specifically includes the following steps: S1.1: Support structure preparation: The load-bearing capacity of the support structure directly below the installation location is checked. If it does not meet the requirements, it is reinforced. A temporary support frame is built on the support structure. The frame is arranged with distribution beams and connecting beams are set between the distribution beams to enhance the overall stability and ensure that the frame can stably bear the weight of the steel corridor. S1.2: Lower-level corridor assembly: On the temporary support frame, the lower-level corridor is assembled from the middle to both sides. First, the main beam is installed and firmly welded to the distribution beam, ensuring that the weld height meets the design standard. At the same time, angle steel supports are set on both sides of the main beam to prevent the main beam from tilting during the assembly process. After the main beam is installed, the secondary beams are installed in sequence to ensure the structural integrity of the lower-level corridor. S1.3: Upper-level corridor assembly: After the lower-level corridor is assembled and passes quality inspection, secondary vertical distribution beams are welded to the corresponding positions above the lower-level corridor. The main beam of the upper-level corridor is hoisted to the predetermined position using lifting equipment and welded and fixed to the secondary vertical distribution beams. At the same time, angle steel supports are set on both sides of the main beam of the upper-level corridor, relying on the structure of the lower-level corridor, to ensure the stability of the upper-level corridor during the assembly process. Then, the upper-level beams are installed to complete the basic assembly of the upper-level corridor. S1.4: Temporary connector installation: Select a temporary connector with good rigidity and rigidly connect its two ends to the top of the lower corridor and the bottom of the upper corridor respectively to ensure that the connection is firm and reliable, so that the upper and lower corridors form a stable overall lifting unit. S1.5: Installation of Pre-set Ancillary Structures: During the stacking and assembly of the upper and lower connecting corridors, the ground integration installation of the pre-set ancillary structures is carried out simultaneously. Steel truss floor slabs are laid, and spaces are reserved in advance for areas that will require subsequent patching work. The curtain wall keel and window cleaning machine track at the bottom of the lower connecting corridor are installed to ensure that the installation position is accurate. Fireproof coating is applied to the steel connecting corridor assembly section, and sufficient space is reserved in the node area so that the fireproof coating will not affect the subsequent node connection and welding work.
3. The construction method for the overall lifting and subsequent split unloading and lifting of a large-span split steel corridor according to claim 2, characterized in that, Step S2 involves installing lifting devices on the tower structures on both sides of the steel connecting corridor, specifically including the following steps: S2.1: Construct a lifting platform: A temporary cantilevered lifting platform is formed by welding steel beams on the side of the tower column. The cantilever length is determined according to construction needs. An operating platform and protective facilities are erected on the platform. S2.2: Install lifting equipment: Fix the hydraulic lifting device on the lifting platform, and use a pressure plate to connect the lifting device to the platform. The pressure plate is welded to the platform and not to the lifting device. S2.3: Configure steel strands: Insert undamaged steel strands into the hoist at left-hand and right-hand intervals, ensuring that the deflection angle of the steel strands and the skew of the upper and lower suspension points meet the requirements. Connect the hoist and the special ground anchor to both ends of the steel strands respectively.
4. The construction method for the overall lifting and subsequent unloading and lifting of a large-span split steel corridor according to claim 3, characterized in that, The connection between the lifting device and the overall lifting unit in step S2 includes the following specific steps: S2.4: Install a special lower lifting device corresponding to the lifting platform on the top of the upper connecting corridor steel beam of the overall lifting unit. Connect the lower lifting device to the ground anchor of the lifting device through steel strands. Leave sufficient length at the end of the steel strands and lock them. S2.5: Install steel strand guide frame to prevent steel strand from tangling, connect the oil pipe between the hydraulic pump station and the hoist, install the sensor and connect it to the control system, and complete the no-load commissioning of the system.
5. The construction method for the overall lifting and subsequent split unloading and lifting of a large-span split steel corridor according to claim 1, characterized in that, Step S3 involves simultaneously lifting the entire lifting unit to the designed docking position of the lower connecting corridor using the lifting device, specifically including the following steps: S3.1: Pre-lifting: Adjust the pressure of the extension cylinder to pre-tension the entire steel strand, so that each steel strand is tensioned in the same way; load in stages according to proportion, and cut the welding points of the temporary support short columns of the lower corridor when the load reaches 20%, 40%, 60%, and 80% in sequence. Continue loading until the overall lifting unit is separated from the assembly jig, and lock it after lifting it 100mm off the ground. Stay for more than 12 hours to check the lifting point structure, load-bearing system and lifting equipment. S3.2: Formal Lifting: Starting from the pre-lifting and adjusted lifting point height, reset the displacement sensor, maintain the horizontal posture of the structure and lift synchronously as a whole. Detect and adjust the height of each lifting point every 5m of lifting. Control the lifting speed at 4-5 meters per hour. Reduce the lifting speed when the structure is about 20cm away from the design position.
6. The construction method for the overall lifting and subsequent split unloading and lifting of a large-span split steel corridor according to claim 1, characterized in that, When removing the temporary connectors for disassembly in step S4, the specific steps include: S4.1: Confirm that all butt welds between the lower-level connecting corridor and the tower structure have been completed and passed inspection, and that the subsequent supplementary members have been installed and temporarily fixed in place; S4.2: Remove the temporary connecting parts between the upper and lower corridors in a symmetrical order from the inside out, so that the load of the upper corridor is gradually transferred to the suspension point and the tower structure on both sides.
7. The construction method for the overall lifting and subsequent unloading and lifting of a large-span split steel corridor according to claim 6, characterized in that, Step S4 also includes load transfer monitoring: during the removal of temporary connectors, the monitoring system of the lifting device monitors the stress changes of each lifting point in real time to ensure smooth load transfer. If any abnormality occurs, the operation is paused and adjustments are made. After the demolition was completed, it was confirmed that the load of the lower-level connecting corridor had been completely transferred to the tower structure.
8. The construction method for the overall lifting and subsequent split unloading and lifting of a large-span split steel corridor according to claim 1, characterized in that, Step S5 involves using a lifting device to individually and synchronously lift the upper connecting corridor to its designed docking position, specifically including the following steps: S5.1: Pre-lift inspection: Confirm that the temporary connectors have been removed and the load of the lower corridor has been completely transferred to the tower. Check the condition of the lifting device and steel strands to ensure there are no abnormalities. S5.2 Synchronous Lifting: Start the lifting device and gradually lift the upper corridor based on the principles of balanced hydraulic pressure at the lifting points, structural posture adjustment, and synchronous displacement control. During the process, the height of each lifting point is checked regularly and the horizontal posture is adjusted. When approaching the design position, the lifting speed is reduced.
9. The construction method for the overall lifting and subsequent split unloading and lifting of a large-span split steel corridor according to claim 8, characterized in that, Step S5 involves the following steps to complete the connection and fixation between the upper-level corridor and the tower structure: the upper-level corridor is precisely aligned using the fine-tuning function of the lifting device; temporary fixing measures are used to fix the non-post-replacement section; the post-replacement section members are installed and temporarily fixed; butt welding and testing are performed; and the lifting device is locked after passing the test.