A method and system for regulatory detailed planning review
By establishing a multi-level framework of transmission elements, transmission carriers, and transmission paths, and automated review rules, the problems of strong subjectivity and low efficiency in the review of control detailed plans have been solved, realizing the systematization and precision of planning transmission, and improving the efficiency and accuracy of review.
Patent Information
- Application Number
- CN202511553917.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2025-10-29
- Publication Date
- 2026-02-10
- Estimated Expiration
- 2045-10-29
AI Technical Summary
In territorial spatial planning, the review of regulatory detailed plans lacks an objective, specific, and quantifiable evaluation system, resulting in review results that are highly subjective, inefficient, and lack accuracy.
By establishing a multi-level, refined framework of transmission elements, transmission carriers, and transmission paths, and formulating automated review rules, the systematization and standardization of the transmission process of planning elements are realized. Spatial overlay analysis technology is adopted to design differentiated transmission paths and automated review rules, and the results of the control detailed planning are quantitatively evaluated.
It significantly improves the objectivity and accuracy of planning review, increases review efficiency, solves the technical problems of strong subjectivity and low efficiency in traditional manual review, and realizes the accuracy and applicability of planning transmission.
Smart Images

Figure CN121032437B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the technical field of land spatial planning, and in particular to a method and system for reviewing regulatory detailed plans. Background Technology
[0002] In the national spatial planning system, the national spatial master plan is the basic basis for detailed planning, and the regulatory detailed plan is one type of detailed plan. Therefore, the content of the regulatory detailed plan (referred to as the control plan) cannot exceed the goals, bottom lines, and a series of planning contents such as various facilities set by the master plan. In other words, it should meet the content and rules of the transmission from the master plan to the regulatory detailed plan (referred to as master-detail transmission). Otherwise, the preparation of the regulatory detailed plan will not pass the review and approval of the superior competent department.
[0003] During the review process of detailed control plans, staff typically examine whether the various technical indicators of the control plan meet the requirements of local urban and rural planning management regulations, mainly focusing on aspects such as plot ratio, building height, building density, and green space ratio—elements not strongly correlated with the overall plan. However, regarding whether the control plan conforms to the transmission requirements of the overall plan, the industry currently lacks a comprehensive, objective, specific, and quantifiable evaluation system and standards. Because the content system of the overall plan is quite complex, and the evaluation standards of different review bodies are inconsistent, the review results of the overall-detailed plan transmission contain a significant subjective element. Moreover, manual review is the only option, greatly reducing the efficiency and accuracy of planning review work. Therefore, how to improve the objectivity, efficiency, and accuracy of planning reviews is an extremely important technical problem to be solved. Summary of the Invention
[0004] To address the issues of strong subjectivity, low efficiency, and low accuracy in existing planning reviews, this invention proposes a method and system for reviewing control-based detailed plans, which can improve the objectivity, efficiency, and accuracy of planning reviews.
[0005] To achieve the above-mentioned technical effects, the technical solution of the present invention is as follows:
[0006] A method for reviewing a regulatory detailed plan includes the following steps:
[0007] S1. Obtain the transmission paths of multiple transmission elements used in the process of transmitting from the master plan to the regulatory detailed plan;
[0008] S2. Decompose the transmission elements into multiple detailed planning units to obtain the control base library for each detailed planning unit;
[0009] S3. Based on the transmission path, construct automated review rules, and use the automated review rules to review the completed control detailed planning results to obtain the control detailed planning review results.
[0010] Preferably, obtaining the transmission path for multiple transmission elements in the process of transmitting from the overall plan to the regulatory detailed plan includes:
[0011] S11. Extract multiple transmission elements in the process of transmitting from the master plan to the regulatory detailed plan;
[0012] S12. Divide the conductive carrier under the conductive element;
[0013] S13. Select the conduction path corresponding to the conduction carrier according to the conduction carrier.
[0014] Here, by establishing a multi-level refined transmission framework of transmission elements, transmission carriers, and transmission paths, the systematization and standardization of the transmission process of planning elements are realized. This breaks through the technical bottleneck of relying on manual experience and lacking systematic methods in traditional planning transmission, and effectively avoids the problem of distorted planning information caused by unclear transmission paths.
[0015] Preferably, the transmission elements are those that need to be aligned with and comply with the overall plan when the control detailed plan is prepared. The transmission elements include four categories of transmission elements: target positioning, control bottom line, land use, and special support.
[0016] Here, by dividing the elements into four categories, a complete classification system for planning elements is established, which solves the technical problems of chaotic element classification and incomplete coverage in traditional planning review, and provides a clear element framework for automated review.
[0017] Preferably, the transmission carrier is a transmission element divided into different forms of carriers, and the transmission carrier includes indicators, directories, zones, locations and boundaries.
[0018] Here, by defining five specific types of transmission carriers, a precise mapping of abstract planning requirements to specific spatial carriers is achieved, overcoming the technical deficiency of the ambiguous correspondence between requirements and carriers in traditional planning, and providing a precise data docking foundation for subsequent automated review.
[0019] Preferably, the transmission path is the way in which the transmission elements of the overall plan are transmitted to the control detailed plan. The transmission path includes indicator transmission path, directory transmission path, zoning transmission path, actual location transmission path, virtual location transmission path and point location transmission path.
[0020] Here, by designing six targeted transmission paths, a differentiated transmission mechanism for different planning elements was realized, solving the technical problem that the traditional one-size-fits-all transmission method could not adapt to the characteristics of diverse planning elements, and significantly improving the accuracy and applicability of planning transmission.
[0021] Preferably, the step of decomposing the transmission elements into multiple detailed planning units to obtain the control base library for each detailed planning unit includes:
[0022] S21. Obtain detailed planning unit scope data;
[0023] S22. Identify the overall planning database layer corresponding to each of the aforementioned transmission elements, and overlay the overall planning database layer with the detailed planning unit scope data to obtain the overlay result;
[0024] S23. Filter the fitting results according to the name of the detailed planning unit to obtain the overall planning database layer corresponding to the transmission element within the range data of the detailed planning unit, and form the control base library from the overall planning database layer.
[0025] Here, spatial overlay analysis technology was used to accurately locate the overall planning elements to the detailed planning units, solving the technical problem of inaccurate spatial correspondence in the traditional planning decomposition process, and providing an accurate spatial data foundation for subsequent automated review.
[0026] Preferably, the step of constructing automated review rules based on the transmission path includes:
[0027] When the transmission path is a real-location transmission path, for the transmission elements that adopt the real-location transmission path, it is determined whether the specific boundaries and geographical coordinates of the regulatory detailed planning data and the overall planning data are completely overlapping and consistent. If so, the regulatory detailed planning review is approved; otherwise, the regulatory detailed planning review is not approved.
[0028] When the transmission path is a virtual transmission path, for the transmission elements that adopt the virtual transmission path, it is determined whether the area of the control detailed planning data is not less than the area of the overall planning data, and the specific boundaries and geographical coordinates of the control detailed planning data and the overall planning data must partially overlap. If so, the control detailed planning review is approved; otherwise, the control detailed planning review is not approved.
[0029] When the transmission path is a point transmission path, for the transmission elements that adopt the point transmission path, it is determined whether the number and area of the control detailed plan are less than the number and area of the overall plan within the same detailed planning unit. If so, the control detailed plan is approved; otherwise, the control detailed plan is not approved.
[0030] Here, by designing differentiated automated review rules for different transmission paths, a precise quantitative assessment of the planning transmission effect is achieved, breaking through the technical bottleneck that traditional manual review cannot achieve fine-grained comparison, and significantly improving the accuracy and reliability of the review results.
[0031] Preferably, the review of the completed detailed control plan results using the automated review rules includes:
[0032] Determine whether the results of the detailed control plan comply with the automated review rules. If yes, the detailed control plan review result is passed; otherwise, the detailed control plan review result is failed.
[0033] Here, the automated review rule judgment mechanism enables unmanned intervention in the planning review process, completely solving the technical problems of strong subjectivity and low efficiency in traditional methods, and greatly improving the efficiency and standardization of planning review work.
[0034] This invention also proposes a control detailed planning review system, comprising:
[0035] The acquisition module is used to acquire the transmission paths of multiple transmission elements in the process of transmitting from the overall plan to the regulatory detailed plan;
[0036] The decomposition module is used to decompose the transmission elements into multiple detailed planning units to obtain the control base library of each detailed planning unit.
[0037] The review module is used to construct automated review rules based on the transmission path, and to review the completed control detailed planning results using the automated review rules to obtain the control detailed planning review results.
[0038] The present invention also proposes a computer device, comprising: a processor, a memory, a communication interface, and a communication bus, wherein the processor, the memory, and the communication interface communicate with each other through the communication bus;
[0039] The memory is used to store at least one executable instruction that causes the processor to perform operations as described in the control detailed planning review method.
[0040] Compared with the prior art, the beneficial effects of the technical solution of the present invention are:
[0041] This invention proposes a method and system for reviewing regulatory detailed plans. First, it obtains the transmission paths of multiple transmission elements used in the process of transferring data from the master plan to the regulatory detailed plan. The aim is to establish a unified transmission mechanism and clarify the specific transmission paths of each transmission element in the process of transferring data from the master plan to the regulatory detailed plan. Second, it decomposes the transmission elements into multiple detailed planning units, obtaining a control base library for each detailed planning unit. Then, it constructs automated review rules based on the transmission paths and uses these automated review rules to review the completed regulatory detailed plan results. This achieves a fundamental shift from relying on human experience-based judgment to digitally assisted review based on clearly defined automated review rules. It effectively overcomes the shortcomings of strong subjectivity, low efficiency, and insufficient accuracy in planning reviews, significantly improving the objectivity, efficiency, and accuracy of planning reviews. Attached Figure Description
[0042] Figure 1 This is a flowchart illustrating a method for reviewing control detailed planning proposed in an embodiment of the present invention.
[0043] Figure 2 This is another flowchart illustrating a method for reviewing control detailed planning proposed in an embodiment of the present invention;
[0044] Figure 3 This diagram illustrates the real-position conduction path proposed in this embodiment of the invention.
[0045] Figure 4 This is a schematic diagram of the virtual position conduction path proposed in the embodiments of the present invention;
[0046] Figure 5 This is a schematic diagram of the point transmission path proposed in the embodiments of the present invention;
[0047] Figure 6 This diagram illustrates the structural block diagram of a control detailed planning review system proposed in an embodiment of the present invention.
[0048] Figure 7 This is a schematic diagram of the structure of a computer device proposed in an embodiment of the present invention.
[0049] 71. Processor; 72. Memory; 73. Communication interface; 74. Communication bus; 75. Executable instructions. Detailed Implementation
[0050] The accompanying drawings are for illustrative purposes only and should not be construed as limiting the invention.
[0051] It is understandable to those skilled in the art that some well-known details may be omitted from the accompanying drawings;
[0052] The technical solution of the present invention will be further described below with reference to the accompanying drawings and embodiments.
[0053] Example 1
[0054] like Figure 1 and Figure 2 As shown, this embodiment proposes a method for reviewing regulatory detailed plans. The aim is to provide an evaluation system and quantitative standards for reviewing regulatory detailed plans from the perspective of overall-to-detailed planning transmission. Simultaneously, it translates the rules of overall-to-detailed planning transmission into automated review rules that can be executed on a computer, thereby improving the work efficiency of regulatory plan review personnel. The method includes the following steps:
[0055] S1. Obtain the transmission paths of multiple transmission elements used in the process of transmitting from the master plan to the regulatory detailed plan;
[0056] In S1, this step mainly clarifies the elements and carriers of planning transmission between the overall plan and the regulatory detailed plan, and proposes the transmission paths of each transmission element. Obtaining the transmission paths of multiple transmission elements used in the transmission process from the overall plan to the regulatory detailed plan includes:
[0057] S11. Extract multiple transmission elements in the process of transmitting from the master plan to the regulatory detailed plan;
[0058] S12. Divide the conductive carrier under the conductive element;
[0059] S13. Select the conduction path corresponding to the conduction carrier according to the conduction carrier.
[0060] Here, by establishing a multi-level refined transmission framework of transmission elements, transmission carriers, and transmission paths, the systematization and standardization of the transmission process of planning elements are realized. This breaks through the technical bottleneck of relying on manual experience and lacking systematic methods in traditional planning transmission, and effectively avoids the problem of distorted planning information caused by unclear transmission paths.
[0061] The transmission elements mentioned are those that must be closely aligned with and comply with the overall plan during the preparation of the detailed control plan. These transmission elements include four main categories: target positioning, control bottom line, land use, and special support (see Table 1). Based on these four categories, 26 transmission elements for the overall plan are extracted and further categorized into binding and guiding elements according to control requirements. Binding elements refer to mandatory requirements, while guiding elements are provided for reference and should be selected based on local needs for refined management. The definitions of the four categories of transmission elements—target positioning, control bottom line, land use, and special support—are as follows:
[0062] Target positioning: including two guiding elements: the dominant function of the unit and population size;
[0063] Control bottom line: including 10 binding elements such as permanent basic farmland, ecological protection red line, urban development boundary, urban "four lines", and historical and cultural protection line;
[0064] Land use: This includes one guiding element: the maximum building area for residential, industrial, and commercial land.
[0065] Specialized support includes 13 binding elements across 5 areas: transportation, green space, public services, municipal services, and comprehensive disaster prevention.
[0066] Here, by dividing the elements into four categories, a complete classification system for planning elements is established, which solves the technical problems of chaotic element classification and incomplete coverage in traditional planning review, and provides a clear element framework for automated review.
[0067] The transmission carriers are transmission elements categorized into different forms, including indicators, directories, zones, locations, and boundaries; among them, "locations" and "boundaries" carry relatively specific spatial attributes. The definitions of various transmission carriers are as follows:
[0068] Indicators: These are quantitative control requirements that the overall plan requires detailed planning to strictly implement. They do not have spatial attributes and are mainly expressed in terms of quantity, such as population size.
[0069] Lists: These are lists that are presented in a catalog format, do not have spatial attributes, and require detailed planning and coordination for implementation, such as lists of cultural relics protection units.
[0070] Zoning: refers to the qualitative control requirements of the overall plan or various land space policy zoning, which generally designates a specific area, such as the dominant function of a unit or the geological disaster risk zoning.
[0071] Location: This refers to the general layout proposed in the overall plan, where the number or area of locations is clear, but the specific land use scope is not yet clear. Detailed planning is needed to determine the specific site selection and delineate specific boundaries and geographical coordinates, such as community-level public service facilities.
[0072] Boundary: refers to the specific control area defined in the overall plan, and specifies the control requirements such as the use attributes of the space within the area. It has spatial attributes such as area and coordinates, such as the three control lines and various planning facilities.
[0073] Here, by defining five specific types of transmission carriers, a precise mapping of abstract planning requirements to specific spatial carriers is achieved, overcoming the technical deficiency of the ambiguous correspondence between requirements and carriers in traditional planning, and providing a precise data docking foundation for subsequent automated review.
[0074] The transmission path refers to the method by which transmission elements of the overall plan are transmitted to the regulatory detailed plan, that is, clarifying the question of "how to transmit." The transmission path includes indicator transmission paths, directory transmission paths, zoning transmission paths, actual location transmission paths, virtual location transmission paths, and point location transmission paths. This invention selects the transmission path corresponding to the transmission carrier based on the transmission carrier. The definitions of various transmission paths are as follows:
[0075] Indicator transmission path: For quantitative control requirements within a specific area (which can be a detailed planning unit or a policy zone) as defined in the overall plan, the requirements are transmitted according to the "indicators", requiring that the control detailed plan must not exceed the corresponding scope.
[0076] The list transmission path mainly targets the names of historical and cultural resource points that appear in the relevant appendices of the overall plan, but whose specific locations or boundaries have not yet been clarified. The transmission is carried out according to the "list", requiring the control detailed plan to further verify the specific locations and determine the protection scope.
[0077] Zoning Transmission Path: The control zones determined by the overall plan are transmitted according to the "zone". The detailed control plan should comply with the control requirements associated with the zone. The control requirements may be indicators or specific control provisions.
[0078] Real-position conduction path: The conduction elements that adopt the "real-position conduction path" are described in the following section. Figure 3 Guided by the principle of "implementation," the regulatory detailed plans must strictly adhere to the planning content determined by the overall plan or the latest data filed with the Ministry of Natural Resources. In principle, no adjustments should be made, and the regulatory detailed plans cannot alter the specific boundaries and geographical coordinates determined by the overall plan, reflecting a rigid control approach. For example, the three control lines fall into this category.
[0079] Virtual conduction path: The conduction elements that adopt the "virtual conduction path" are described in the following section. Figure 4 Guided by the principle of "deepening," the regulatory detailed plan requires further decomposition and refinement of the overall plan's content. Specifically, while adhering to the principle of maintaining the basic location and area defined in the overall plan, the regulatory detailed plan allows for optimization of the specific boundaries and shapes of elements, and clarifies their geographical coordinates. This is specifically divided into three types: ① Changes in the scope of element patches, with unchanged area and basically unchanged location; ② Changes in the scope of element patches, with increased area and basically unchanged location; ③ Changes in the scope and area of element patches, with minor adjustments to their location. This reflects a control approach that combines rigidity and flexibility; for example, municipal and district-level public service facilities and urban fourth-tier cities fall into this category.
[0080] Point-to-point transmission: Transmission elements employing a "point-to-point transmission path," see [link / reference]. Figure 5Guided by the principle of "optimization," the regulatory detailed plan allows for relatively flexible adjustments to the content of the overall plan. Generally, this is based on the principle of not exceeding the unit area where the site is located and ensuring that the facilities meet the service radius requirements. Under the premise that the number of elements and the area (if any) are not reduced, the regulatory detailed plan can optimize and adjust the location of elements, and determine specific boundaries and geographical coordinates. Specifically, there are three types: ① The overall plan only specifies the location without area requirements, allowing the regulatory detailed plan to determine the map area within the unit where the site is located, specifying the area; ② The overall plan has both location and area requirements, and the regulatory detailed plan determines the map area within the unit where the site is located, with an increased area, which is considered positive optimization; ③ The overall plan has both location and area requirements, and the regulatory detailed plan determines the map area within the unit where the site is located, while keeping the area unchanged. This reflects a flexible and guiding management approach. For example, community-level public service facilities with jurisdiction at the district level or below fall into this category.
[0081] Here, by designing six targeted transmission paths, a differentiated transmission mechanism for different planning elements was realized, solving the technical problem that the traditional one-size-fits-all transmission method could not adapt to the characteristics of diverse planning elements, and significantly improving the accuracy and applicability of planning transmission.
[0082] Where the transmission carrier is a zone, the transmission path shall be the zone transmission path; where the transmission carrier is an indicator, the transmission path shall be the indicator transmission path; where the transmission carrier is a directory, the transmission path shall be the directory transmission path; for transmission carriers with spatial attributes such as locations and boundaries, which are mainly some facility-related planning contents, this application proposes to adopt differentiated transmission methods of real location transmission path, virtual location transmission path, or point location transmission path based on the planning status, type, and level of the element; where the transmission carrier is a boundary, one or more of the above-mentioned real location transmission, virtual location transmission, and point location transmission methods shall be adopted as needed.
[0083] Table 1. Overall-Detailed Transmission Element System
[0084]
[0085] S2. Decompose the transmission elements into multiple detailed planning units to obtain the control base library for each detailed planning unit;
[0086] In S2, the overall plan serves as the superior basis for the preparation of detailed plans. In accordance with the relevant requirements of the Ministry of Natural Resources, each region will divide into several detailed planning units before preparing the control detailed plan. The planning scope of the control plan is the scope of the detailed planning unit. Therefore, the control detailed planning unit is an important spatial carrier for transmitting and implementing the relevant requirements of the overall plan, and it is the basic unit for carrying out the preparation, management and implementation supervision of detailed plans.
[0087] Referring to Table 2, for transmission elements that can be fully reviewed by machines, on the nationally used "One Map" implementation supervision information system platform for territorial spatial planning, these transmission elements are decomposed into multiple detailed planning units, resulting in the control base library for each detailed planning unit, including:
[0088] S21. Obtain detailed planning unit scope data;
[0089] S22. Identify the overall planning database layer corresponding to each of the aforementioned transmission elements, and overlay the overall planning database layer with the detailed planning unit scope data to obtain the overlay result;
[0090] S23. Filter the fitting results according to the name of the detailed planning unit to obtain the overall planning database layer corresponding to the transmission element within the range data of the detailed planning unit, and form the control base library from the overall planning database layer.
[0091] In S23, spatial overlay analysis technology is used to accurately locate the overall planning elements to the detailed planning units, solving the technical problem of inaccurate spatial correspondence in the traditional planning decomposition process, and providing an accurate spatial data foundation for subsequent automated review. In S23, the overall planning database layers corresponding to each transmission element are exported separately using the control detailed planning unit as the organizational unit, forming a control base library for the control detailed planning unit. The control base library has two main functions: first, in the process of compiling detailed plans for different units, the corresponding map features are implemented or further deepened and optimized based on the base library and transmission requirements; second, during the review, the layers are directly called for review according to the review rules.
[0092] The control base database is stored in an ArcGIS file geodatabase (.gdb) format. The database is divided into multiple feature datasets according to different types, and the layers corresponding to each transmitted feature are stored under the corresponding feature dataset.
[0093] Table 2. Corresponding Layers of the Overall Planning Database for Transmission Elements
[0094]
[0095] S3. Based on the transmission path, construct automated review rules, and use the automated review rules to review the completed control detailed planning results to obtain the control detailed planning review results.
[0096] In S3, the control detailed planning review method based on the overall-detailed transmission is translated into rules that can be analyzed by computers. This makes it easier for qualified localities to develop functional modules on the "one map" implementation supervision information system of territorial spatial planning to achieve automated review. Among them, the three transmission methods of zoning, indicators, and lists are mainly reviewed manually, while the three transmission methods of actual location, virtual location, and point location are based on automated review rules.
[0097] Referring to Table 3, the automated review rules built on the computer based on the real-position transmission path, the virtual-position transmission path, and the point-position transmission path include:
[0098] When the transmission path is a real-location transmission path, for the transmission elements that adopt the real-location transmission path, it is determined whether the specific boundaries and geographical coordinates of the regulatory detailed planning data and the overall planning data are completely overlapping and consistent. If so, the regulatory detailed planning review is approved; otherwise, the regulatory detailed planning review is not approved.
[0099] When the transmission path is a virtual transmission path, for the transmission elements that adopt the virtual transmission path, it is determined whether the area of the control detailed planning data is not less than the area of the overall planning data, and the specific boundaries and geographical coordinates of the control detailed planning data and the overall planning data must partially overlap, that is, the positions remain basically unchanged. If so, the control detailed planning review is approved; if not, the control detailed planning review is not approved.
[0100] When the transmission path is a point transmission path, for the transmission elements that adopt the point transmission path, it is determined whether the number and area of the control detailed plan are less than the number and area of the overall plan within the same detailed planning unit. If so, the control detailed plan is approved; otherwise, the control detailed plan is not approved.
[0101] Here, by designing differentiated automated review rules for different transmission paths, a precise quantitative assessment of the planning transmission effect is achieved, breaking through the technical bottleneck that traditional manual review cannot achieve fine-grained comparison, and significantly improving the accuracy and reliability of the review results.
[0102] Based on the database standards of the Ministry of Natural Resources regarding the overall land use planning and detailed planning, for transmission elements that adopt real-location transmission paths, virtual-location transmission paths, and point-location transmission paths, the layers involved in each review rule are identified, and the corresponding land use patches are selected to facilitate comparative analysis according to the requirements of the automated review rules.
[0103] Table 3 Automated Review Rules for General-to-Detail Transmission Elements
[0104]
[0105] The process of reviewing the completed regulatory detailed planning results using the automated review rules in visual formats such as reports, tables, and data includes:
[0106] First, automated quality inspection is carried out by importing the control detailed planning result package with one click. The quality inspection results can be viewed and exported as follows:
[0107] The system determines whether the results of the detailed control plan comply with the automated review rules. If yes, the detailed control plan review result is passed; otherwise, the detailed control plan review result is failed. For detailed control plan data that does not comply with the automated review rules, functions such as error location viewing and error description viewing are provided to assist the planning unit in modifying the detailed control plan results. For situations where modification is not possible due to special circumstances, the planning unit is supported in filling in explanations and marking exceptions.
[0108] Here, the automated review rule judgment mechanism enables unmanned intervention in the planning review process, completely solving the technical problems of strong subjectivity and low efficiency in traditional methods, and greatly improving the efficiency and standardization of planning review work.
[0109] Specifically, the review of the completed control detailed planning results using the aforementioned automated review rules is achieved through a platform integration. More specifically, the review of the completed control detailed planning results using the aforementioned automated review rules will be integrated into the existing "one map" detailed planning subsystem on the nationally used "one map" land and space planning implementation supervision information system. This will expand the subsystem's functions of bottom-line control review and overall plan compliance review, ensuring the standardization of the results and improving review efficiency.
[0110] The review of the completed regulatory detailed planning results includes three parts: first, obtaining the completed regulatory detailed planning results; second, obtaining the management and control base library of the overall plan decomposed into each regulatory detailed planning unit; and third, comparing the results of the regulatory detailed planning and the contents of the management and control base library through code execution based on the aforementioned automated review rules.
[0111] The control detailed planning review method proposed in this embodiment also adopts a regular monitoring approach. If the overall planning data on the "one map" implementation supervision information system platform of the national spatial planning is dynamically updated, the basic database for detailed planning unit control will be updated simultaneously to ensure the accuracy of the review results.
[0112] This embodiment proposes a method for reviewing regulatory detailed plans. The method outlines the transmission system for implementing the overall planning requirements within the regulatory detailed plan, distilling the complex overall planning content into review priorities comprised of 4 major categories and 26 elements, and clarifying the transmission paths of each transmission element and carrier. Building upon this, this embodiment also proposes a grid-based decomposition method using regulatory detailed planning units as basic units to decompose the overall planning content, laying a data foundation for the overall-detailed transmission review of regulatory detailed plans. Simultaneously, the transmission paths are translated into automated review rules that conform to nationally applicable technical specifications for territorial spatial planning and can be executed on computers. A method is proposed to output specific problem patches and error descriptions on the system for further verification and modification by case handlers. This method also helps maintain the authority of the overall territorial spatial planning, reduces the workload and errors associated with manual review, enables batch review, improves the efficiency of regulatory plan review, and provides a concrete method for accelerating the digital transformation of planning preparation and implementation management.
[0113] Example 2
[0114] See Figure 6 This embodiment proposes a control detailed planning review system, including:
[0115] The acquisition module is used to acquire the transmission paths of multiple transmission elements in the process of transmission from the master plan to the regulatory detailed plan;
[0116] The decomposition module is used to decompose the transmission elements into multiple detailed planning units to obtain the control base library of each detailed planning unit.
[0117] The review module is used to construct automated review rules based on the transmission path, and to review the completed control detailed planning results using the automated review rules to obtain the control detailed planning review results.
[0118] In this embodiment, firstly, the transmission paths of multiple transmission elements used in the process of transmitting from the overall plan to the regulatory detailed plan are obtained. The purpose is to formulate a unified transmission mechanism and clarify the specific transmission paths of each transmission element in the process of transmitting from the overall plan to the regulatory detailed plan. Secondly, the transmission elements are decomposed into multiple detailed planning units to obtain the control base library of each detailed planning unit. Then, automated review rules are constructed according to the transmission paths. The completed regulatory detailed plan results are reviewed using the automated review rules. This realizes a fundamental shift from relying on human experience judgment to digitally assisted review based on clear automated review rules. It effectively overcomes the defects of strong subjectivity, low efficiency and insufficient accuracy in planning review, and significantly improves the objectivity, efficiency and accuracy of planning review.
[0119] Example 3
[0120] See Figure 7 This embodiment also proposes a computer device, see [link to relevant documentation]. Figure 7 It includes: a processor 71, a memory 72, a communication interface 73, and a communication bus 74, wherein the processor 71, the memory 72, and the communication interface 73 communicate with each other through the communication bus 74;
[0121] The processor 71, memory 72, and communication interface 73 communicate with each other via a communication bus 74. The communication interface 73 is used for network communication with other devices, such as clients or other servers. The processor 71 executes executable instructions 75, specifically performing the operations of the control detailed planning review method described above. Specifically, the executable instructions 75 may include program code. The processor 71 may be a central processing unit (CPU), an application-specific integrated circuit (ASIC), or one or more integrated circuits configured to implement embodiments of the present invention. The computer device includes one or more processors, which may be processors of the same type, such as one or more CPUs; or processors of different types, such as one or more CPUs and one or more ASICs.
[0122] Memory 72 is used to store executable instructions 75. Memory 72 may include high-speed RAM memory, and may also include non-volatile memory, such as at least one disk storage device.
[0123] Executable instruction 75 can be invoked by processor 71 to cause the computer device to perform the following operations:
[0124] S1. Obtain the transmission paths of multiple transmission elements used in the process of transmitting from the master plan to the regulatory detailed plan;
[0125] S2. Decompose the transmission elements into multiple detailed planning units to obtain the control base library for each detailed planning unit;
[0126] S3. Based on the transmission path, construct automated review rules, and use the automated review rules to review the completed control detailed planning results to obtain the control detailed planning review results.
[0127] In this embodiment, firstly, the transmission paths of multiple transmission elements used in the process of transmitting from the overall plan to the regulatory detailed plan are obtained. The purpose is to formulate a unified transmission mechanism and clarify the specific transmission paths of each transmission element in the process of transmitting from the overall plan to the regulatory detailed plan. Secondly, the transmission elements are decomposed into multiple detailed planning units to obtain the control base library of each detailed planning unit. Then, automated review rules are constructed according to the transmission paths. The completed regulatory detailed plan results are reviewed using the automated review rules. This realizes a fundamental shift from relying on human experience judgment to digitally assisted review based on clear automated review rules. It effectively overcomes the defects of strong subjectivity, low efficiency and insufficient accuracy in planning review, and significantly improves the objectivity, efficiency and accuracy of planning review.
[0128] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the implementation of the present invention. Those skilled in the art can make other variations or modifications based on the above description. It is neither necessary nor possible to exhaustively describe all embodiments here. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the scope of protection of the claims of the present invention.
Claims
1. A method for reviewing regulatory detailed planning, characterized in that, Includes the following steps: S1. Obtain the transmission paths for multiple transmission elements used in the process of transmitting from the master plan to the regulatory detailed plan, including: S11. Extract multiple transmission elements in the process of transmitting from the master plan to the regulatory detailed plan; S12. Divide the conductive carrier under the conductive element; S13. Select the conduction path corresponding to the conduction carrier according to the conduction carrier; The transmission path refers to the way in which the transmission elements of the overall plan are transmitted to the regulatory detailed plan. The transmission path includes indicator transmission path, list transmission path, zoning transmission path, actual location transmission path, virtual location transmission path, and point location transmission path. S2. Decompose the transmission elements into multiple detailed planning units to obtain the control base library for each detailed planning unit; S3. Based on the transmission path, construct automated review rules, and use the automated review rules to review the completed control detailed planning results to obtain the control detailed planning review results; The construction of automated review rules based on the transmission path includes: When the transmission path is a real-location transmission path, for the transmission elements that adopt the real-location transmission path, it is determined whether the specific boundaries and geographical coordinates of the regulatory detailed planning data and the overall planning data are completely overlapping and consistent. If so, the regulatory detailed planning review is approved; otherwise, the regulatory detailed planning review is not approved. When the transmission path is a virtual transmission path, for the transmission elements that adopt the virtual transmission path, it is determined whether the area of the control detailed planning data is not less than the area of the overall planning data, and the specific boundaries and geographical coordinates of the control detailed planning data and the overall planning data must partially overlap. If so, the control detailed planning review is approved; otherwise, the control detailed planning review is not approved. When the transmission path is a point transmission path, for the transmission elements that adopt the point transmission path, it is determined whether the number and area of the control detailed plan are less than the number and area of the overall plan within the same detailed planning unit. If so, the control detailed plan is approved; otherwise, the control detailed plan is not approved.
2. The method for reviewing regulatory detailed planning according to claim 1, characterized in that, The transmission elements are those that must be aligned with and comply with the overall plan when preparing the control detailed plan. The transmission elements include four major categories: target positioning, control bottom line, land use, and special support.
3. The method for reviewing regulatory detailed planning according to claim 1, characterized in that, The transmission carrier is a transmission element divided into different forms of carriers, including indicators, directories, zones, locations, and boundaries.
4. The method for reviewing regulatory detailed planning according to claim 1, characterized in that, The process of decomposing the transmission elements into multiple detailed planning units to obtain the control base library for each detailed planning unit includes: S21. Obtain detailed planning unit scope data; S22. Identify the overall planning database layer corresponding to each of the aforementioned transmission elements, and overlay the overall planning database layer with the detailed planning unit scope data to obtain the overlay result; S23. Filter the fitting results according to the name of the detailed planning unit to obtain the overall planning database layer corresponding to the transmission element within the range data of the detailed planning unit, and form the control base library from the overall planning database layer.
5. The method for reviewing regulatory detailed planning according to claim 1, characterized in that, The review of the completed detailed control plan results using the automated review rules includes: Determine whether the results of the detailed control plan comply with the automated review rules. If yes, the detailed control plan review result is passed; otherwise, the detailed control plan review result is failed.
6. A regulatory detailed planning review system, said system being implemented based on the regulatory detailed planning review method according to any one of claims 1-5, characterized in that, include: The acquisition module is used to acquire the transmission paths of multiple transmission elements in the process of transmitting from the overall plan to the regulatory detailed plan; The decomposition module is used to decompose the transmission elements into multiple detailed planning units to obtain the control base library of each detailed planning unit. The review module is used to construct automated review rules based on the transmission path, and to review the completed control detailed planning results using the automated review rules to obtain the control detailed planning review results.
7. A computer device, characterized in that, include: The processor, memory, communication interface, and communication bus are provided, wherein the processor, memory, and communication interface communicate with each other via the communication bus. The memory is used to store at least one executable instruction that causes the processor to perform the operation of the control detailed planning review method as described in any one of claims 1-5.
Citation Information
Patent Citations
Control rule examination system and method based on multi-rule translation
CN117291530A
Examination method and system for territorial space control detailed planning result
CN120746472A