Method and system for regulating and controlling three-phase imbalance of low-voltage transformer area
By constructing a day-ahead optimization model and combining it with real-time monitoring, the low-voltage distribution area equipment is adaptively controlled, solving the problem of three-phase unbalanced load adjustment in the low-voltage distribution area and improving operational reliability and equipment utilization efficiency.
Patent Information
- Application Number
- CN202511409367.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-09-29
- Publication Date
- 2025-12-19
AI Technical Summary
Existing technologies for handling three-phase unbalanced load adjustment in low-voltage distribution areas suffer from problems such as difficulty in achieving dynamic tracking and balancing, high costs, insufficient real-time performance, and frequent equipment operation affecting reliability, resulting in poor operational reliability of low-voltage distribution areas.
By acquiring the grid structure data of the low-voltage distribution area and the basic parameters of the controllable equipment, a day-ahead optimization model is constructed. A preset genetic algorithm is used to solve and generate a day-ahead control plan for three-phase imbalance. Combined with real-time monitoring of the three-phase imbalance degree and load rate, the equipment is adaptively controlled to achieve optimization of the three-phase imbalance in the low-voltage distribution area.
It improves the optimization effect of three-phase unbalanced load adjustment in low-voltage distribution areas, enhances the operational reliability and equipment utilization efficiency of low-voltage distribution areas, and reduces the risk of equipment overload.
Smart Images

Figure CN121172802A_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the field of low-voltage area three-phase imbalance load regulation, and in particular to a low-voltage area three-phase imbalance regulation method and system. BACKGROUND
[0002] The current domestic low-voltage power distribution network power supply mode is mainly three-phase four-wire system, and the user power consumption is mainly single-phase. With the continuous increase of power grid industry expansion in recent years, and the rapid change of load characteristics, the three-phase imbalance problem becomes more and more common and serious.
[0003] At present, the existing technology mainly adopts passive element compensation method, active element compensation method, artificial meter balancing method and automatic phase change balancing method to solve the problem of low-voltage area three-phase imbalance load regulation. Among them, the passive element compensation method is to realize the transfer and adjustment of inter-phase load by connecting inductance and capacitance elements in series or parallel between phases. The compensation principle of this method is simple, but it is difficult to realize dynamic tracking and balancing. The active element compensation method is to connect static reactive power compensation device and other power quality dynamic management equipment, which can realize continuous and smooth compensation adjustment. However, the use cost of active filter and other devices is high, and it is mainly used in high voltage level system at present. The artificial meter balancing method relies on the combination adjustment of electric energy meter by operation and maintenance personnel to improve the load distribution in the area and to relieve the three-phase imbalance problem. However, due to the significant randomness and volatility of new type of area load and new energy output, it is difficult for artificial meter to match the changes in real time, and its effectiveness and real-time performance are insufficient. The automatic phase change balancing method relies on intelligent phase change device to realize automatic phase change switching, has online monitoring capability of area, and can realize real-time adjustment. However, with the gradual increase of distributed photovoltaic and other new energy equipment in new type of low-voltage area, the power strong randomness and strong volatility of the equipment aggravate the change degree of area operation state. The traditional automatic phase change balancing method based on phase change switch will lead to frequent action of phase change switch, affecting the service life of the switch. Therefore, the existing technology has the problem of low-voltage area three-phase imbalance regulation under the random fluctuation of distributed source and load power, resulting in poor operation reliability of low-voltage area. SUMMARY
[0004] In order to solve the above problems, the present application provides a low-voltage area three-phase imbalance regulation method and system, which realizes the optimization of low-voltage area three-phase imbalance load regulation and improves the operation reliability of low-voltage area.
[0005] To achieve the above object, the embodiment of the present application provides a low-voltage area three-phase imbalance regulation method, comprising: obtaining target low-voltage area network structure data and target low-voltage area adjustable equipment basic parameters; constructing a day-ahead optimization model based on the target low-voltage area network structure data and the target low-voltage area adjustable equipment basic parameters; solving the day-ahead optimization model based on a preset genetic algorithm to obtain a three-phase imbalance day-ahead regulation plan and perform day-ahead three-phase imbalance regulation on the target low-voltage area; and monitoring the three-phase imbalance degree and load rate of the target low-voltage area in real time, and performing real-time three-phase imbalance regulation on the target low-voltage area adjustable equipment according to the three-phase imbalance degree and the load rate.
[0006] The embodiment of the present application provides a low-voltage area three-phase imbalance regulation method, obtains target low-voltage area network structure data and target low-voltage area adjustable equipment basic parameters and constructs a day-ahead optimization model, uses a preset genetic algorithm to solve the day-ahead optimization model to generate a corresponding three-phase imbalance day-ahead regulation plan to perform day-ahead three-phase imbalance regulation on the target low-voltage area, and simultaneously monitors the three-phase imbalance degree and the load rate of the target low-voltage area in real time to ensure that the three-phase imbalance degree and the load rate are always within a safe range. Thus, through the coordinated control of day-ahead optimization and real-time monitoring, the target low-voltage area adjustable equipment is adaptively regulated, the three-phase imbalance load of the low-voltage area is optimized, and the operation reliability of the low-voltage area is improved.
[0007] Further, the day-ahead optimization model is constructed based on the target low-voltage area network structure data and the target low-voltage area adjustable equipment basic parameters, comprising: based on a preset regulation period, calculating a first cost and a second cost in the preset regulation period according to the target low-voltage area adjustable equipment basic parameters; constructing a target function based on the first cost and the second cost; constructing a plurality of three-phase imbalance regulation constraint conditions based on the target low-voltage area network structure data and the target low-voltage area adjustable equipment basic parameters; and constructing the day-ahead optimization model based on the target function and the plurality of three-phase imbalance regulation constraint conditions.
[0008] In the above scheme, the first cost and the second cost are calculated in the preset regulation period to construct the target function, and then the target function is constrained according to the target low-voltage area network structure data and the target low-voltage area adjustable equipment basic parameters to obtain the day-ahead optimization model. Thus, the target low-voltage area adjustable equipment is optimized through the construction of the day-ahead optimization model, and the target low-voltage area adjustable equipment is adaptively regulated through the coordinated control of subsequent real-time monitoring to optimize the three-phase imbalance load of the low-voltage area and improve the operation reliability of the low-voltage area.
[0009] Further, the three-phase imbalance day-ahead regulation plan is obtained by solving the day-ahead optimization model based on the preset genetic algorithm, and the target low-voltage transformer area is regulated in three-phase imbalance day-ahead, including: based on the preset genetic algorithm, a plurality of three-phase imbalance regulation plans are binary coded into a plurality of chromosomes to obtain an initial population; based on the preset penalty factor and the day-ahead optimization model, an fitness model is constructed; the model solving process is executed: a plurality of first chromosomes are randomly selected from the initial population, the fitness of each first chromosome is calculated based on the fitness model, the first chromosome whose fitness meets the preset first iteration requirement is taken as the parent chromosome of the next generation, and a plurality of child chromosomes are generated according to the parent chromosome; if the current evolution generation meets the preset catastrophe requirement, the child chromosomes and the parent chromosomes are merged to obtain the merged chromosomes; the fitness of the merged chromosomes is calculated based on the fitness model, the merged chromosomes that meet the preset second iteration requirement are selected to construct an optimized population, and the model solving process is ended; based on the optimized population, the model solving process is repeatedly executed until the current evolution generation meets the preset target evolution requirement, a target population is obtained, the fitness of each second chromosome in the target population is calculated, the second chromosome whose fitness meets the preset third iteration requirement is selected as the target chromosome, the binary coding of the target chromosome is obtained, and the corresponding three-phase imbalance regulation plan is obtained; based on the three-phase imbalance regulation plan, the target low-voltage transformer area is regulated in three-phase imbalance day-ahead.
[0010] In the above scheme, the genetic algorithm is used to introduce catastrophe mechanism and elite strategy to solve the day-ahead optimization model, and generate a three-phase imbalance regulation plan to regulate the target low-voltage transformer area in three-phase imbalance day-ahead. Therefore, the genetic algorithm with catastrophe mechanism and elite strategy is used to solve the day-ahead optimization model, which can avoid the model from falling into local optimum, improve the reliability of the three-phase imbalance regulation plan, and facilitate subsequent collaborative control combined with real-time monitoring to adaptively regulate the adjustable equipment of the target low-voltage transformer area, optimize the three-phase imbalance load of the low-voltage transformer area, and improve the operation reliability of the low-voltage transformer area.
[0011] Further, the three-phase imbalance degree and the load rate of the target low-voltage transformer area are monitored in real time, and the adjustable equipment of the target low-voltage transformer area is regulated in real-time three-phase imbalance according to the three-phase imbalance degree and the load rate, including: the three-phase imbalance degree and the load rate of the target low-voltage transformer area are monitored in real time; if the three-phase imbalance degree and the load rate of the target low-voltage transformer area meet the first regulation condition, a first regulation strategy is generated, and the adjustable equipment of the target low-voltage transformer area is regulated in three-phase imbalance according to the first regulation strategy; if the three-phase imbalance degree and the load rate of the target low-voltage transformer area meet the second regulation condition, a second regulation strategy is generated, and the adjustable equipment of the target low-voltage transformer area is regulated in three-phase imbalance according to the second regulation strategy; if the three-phase imbalance degree and the load rate of the target low-voltage transformer area meet the third regulation condition, a third regulation strategy is generated, and the adjustable equipment of the target low-voltage transformer area is regulated in three-phase imbalance according to the third regulation strategy.
[0012] In the above scheme, the three-phase imbalance degree and the load rate of the target low-voltage area are monitored in real time, and corresponding control strategies are generated according to different control conditions met by the three-phase imbalance degree and the load rate, so as to control the controllable equipment of the target low-voltage area in real time. Thus, through the coordinated control of day-ahead optimization and real-time monitoring, the controllable equipment of the target low-voltage area is adaptively controlled, and the three-phase imbalance load of the low-voltage area is optimized, thereby improving the operation reliability of the low-voltage area.
[0013] Further, if the three-phase imbalance degree and the load rate of the target low-voltage area meet the first control condition, a first control strategy is generated, and the three-phase imbalance control is performed on the controllable equipment of the target low-voltage area according to the first control strategy, including: if the three-phase imbalance degree of the target low-voltage area meets the preset risk monitoring requirement and the load rate of the target low-voltage area meets the preset risk monitoring requirement, the three-phase imbalance degree and the load rate of the target low-voltage area meet the first control condition; a charging strategy is generated according to the rated power of the controllable equipment of the target low-voltage area and a preset charging power coefficient; and the controllable equipment of the target low-voltage area is uniformly charged according to the charging strategy until the power reaches a preset margin range or the control period reaches a preset termination time, and the three-phase imbalance control is ended.
[0014] In the above scheme, if the three-phase imbalance degree of the target low-voltage area meets the preset risk monitoring requirement and the load rate of the target low-voltage area meets the preset risk monitoring requirement, the energy storage charging is fully utilized in the low valley period of the power grid or the large generation period of new energy, the power reserve of the controllable equipment of the target low-voltage area is improved, the uniform charging strategy provides greater adjustment margin for the controllable equipment of the target low-voltage area, and this helps to optimize the three-phase imbalance load of the low-voltage area and improve the operation reliability of the low-voltage area.
[0015] Further, if the three-phase imbalance degree and the load rate of the target low-voltage area meet the second control condition, a second control strategy is generated, and the three-phase imbalance control is performed on the controllable equipment of the target low-voltage area according to the second control strategy, including: if the three-phase imbalance degree of the target low-voltage area does not meet the preset risk monitoring requirement and the load rate of the target low-voltage area meets the preset risk monitoring requirement, the three-phase imbalance degree and the load rate of the target low-voltage area meet the second control condition; the load current of each controllable equipment of the target low-voltage area is calculated, the controllable equipment of the target low-voltage area whose load current meets the preset adjustment requirement is obtained, and the grid-connected voltage and the adjustment current of the controllable equipment of the target low-voltage area are used to generate the second control strategy; and the controllable equipment of the target low-voltage area is discharged and shared according to the second control strategy until the three-phase imbalance degree of the target low-voltage area meets the preset risk monitoring requirement, and the three-phase imbalance control is ended.
[0016] In the above scheme, if the three-phase imbalance degree of the target low-voltage area does not meet the preset risk monitoring requirement and the load rate of the target low-voltage area meets the preset risk monitoring requirement, the target low-voltage area with a load current meeting the preset adjustment requirement is intelligently selected to discharge energy to control the equipment, to quickly suppress the difference between three-phase currents, reduce the imbalance degree, and adopt a discharge sharing control strategy to avoid overloading of a single device, which helps to optimize the three-phase imbalance load control of the low-voltage area and improve the operation reliability of the low-voltage area.
[0017] Further, if the three-phase imbalance degree and the load rate of the target low-voltage area meet the third control condition, a third control strategy is generated, and the three-phase imbalance of the target low-voltage area is controlled according to the third control strategy, including: if the three-phase imbalance degree of the target low-voltage area meets the preset risk monitoring requirement and the load rate of the target low-voltage area does not meet the preset risk monitoring requirement, the three-phase imbalance degree and the load rate of the target low-voltage area meet the third control condition; the load current of each target low-voltage area controllable equipment is calculated, the target low-voltage area controllable equipment with a load current meeting the preset adjustment requirement is obtained, the grid-connected voltage and the adjustment current of the target low-voltage area controllable equipment are obtained, the third control strategy is generated; and the target low-voltage area controllable equipment is discharged according to the third control strategy, until the load rate of the target low-voltage area meets the preset risk monitoring requirement, and the three-phase imbalance control is ended.
[0018] In the above scheme, if the three-phase imbalance degree of the target low-voltage area meets the preset risk monitoring requirement and the load rate of the target low-voltage area does not meet the preset risk monitoring requirement, the target low-voltage area with a load current meeting the preset adjustment requirement is intelligently selected to discharge energy to control the equipment, to quickly suppress the difference between three-phase currents, reduce the imbalance degree, and adopt a discharge sharing control strategy to avoid overloading of a single device, which helps to optimize the three-phase imbalance load control of the low-voltage area and improve the operation reliability of the low-voltage area.
[0019] The embodiment of the present application also provides a low-voltage area three-phase imbalance control system, which comprises: a data acquisition module, a day-ahead optimization model construction module, a day-ahead three-phase imbalance control module and a real-time three-phase imbalance control module; the data acquisition module is used to acquire target low-voltage area network structure data and target low-voltage area controllable equipment basic parameters; the day-ahead optimization model construction module is used to construct a day-ahead optimization model based on the target low-voltage area network structure data and the target low-voltage area controllable equipment basic parameters; the day-ahead three-phase imbalance control module is used to solve the day-ahead optimization model based on a preset genetic algorithm, obtain a three-phase imbalance day-ahead control plan and perform day-ahead three-phase imbalance control on the target low-voltage area; and the real-time three-phase imbalance control module is used to monitor the three-phase imbalance degree and the load rate of the target low-voltage area in real time, and perform real-time three-phase imbalance control on the target low-voltage area controllable equipment according to the three-phase imbalance degree and the load rate.
[0020] The embodiment of the present application provides a low-voltage area three-phase imbalance regulation system, obtains target low-voltage area network structure data and target low-voltage area adjustable equipment basic parameters and constructs a day-ahead optimization model, solves the day-ahead optimization model by using a preset genetic algorithm to generate a corresponding three-phase imbalance day-ahead regulation plan to perform day-ahead three-phase imbalance regulation on the target low-voltage area, and simultaneously combines real-time monitoring of the three-phase imbalance degree and the load rate of the target low-voltage area to ensure that the three-phase imbalance degree and the load rate are always within a safe range. Therefore, through the cooperative control of day-ahead optimization and real-time monitoring, the target low-voltage area adjustable equipment is adaptively regulated, three-phase imbalance load of the low-voltage area is optimized, and the operation reliability of the low-voltage area is improved.
[0021] Further, the day-ahead optimization model construction module is used for constructing a day-ahead optimization model based on the target low-voltage area network structure data and the target low-voltage area adjustable equipment basic parameters, and includes a regulation data acquisition unit, a target function construction unit, a constraint condition construction unit and a model construction unit. The regulation data acquisition unit is used for calculating a first cost and a second cost in a preset regulation period according to the target low-voltage area adjustable equipment basic parameters based on the preset regulation period. The target function construction unit is used for constructing a target function based on the first cost and the second cost. The constraint condition construction unit is used for constructing a plurality of three-phase imbalance regulation constraint conditions based on the target low-voltage area network structure data and the target low-voltage area adjustable equipment basic parameters. The model construction unit is used for constructing the day-ahead optimization model based on the target function and the plurality of three-phase imbalance regulation constraint conditions.
[0022] In the above scheme, the first cost and the second cost are calculated in the preset regulation period, the target function is constructed based on the first cost and the second cost, and the target function is constrained according to the target low-voltage area network structure data and the target low-voltage area adjustable equipment basic parameters to obtain the day-ahead optimization model. Therefore, the target low-voltage area adjustable equipment is day-ahead optimized by constructing the day-ahead optimization model, the target low-voltage area adjustable equipment is adaptively regulated through the cooperative control of subsequent real-time monitoring, three-phase imbalance load of the low-voltage area is optimized, and the operation reliability of the low-voltage area is improved.
[0023] Further, the real-time three-phase imbalance regulation module is used for monitoring the three-phase imbalance degree and load rate of the target low-voltage transformer area in real time, and regulating the controllable equipment of the target low-voltage transformer area in real time according to the three-phase imbalance degree and load rate, comprising a real-time data monitoring unit, a first regulation unit, a second regulation unit and a third regulation unit; the real-time data monitoring unit is used for monitoring the three-phase imbalance degree and load rate of the target low-voltage transformer area in real time; the first regulation unit is used for generating a first regulation strategy if the three-phase imbalance degree and load rate of the target low-voltage transformer area meet a first regulation condition, and regulating the controllable equipment of the target low-voltage transformer area according to the first regulation strategy; the second regulation unit is used for generating a second regulation strategy if the three-phase imbalance degree and load rate of the target low-voltage transformer area meet a second regulation condition, and regulating the controllable equipment of the target low-voltage transformer area according to the second regulation strategy; the third regulation unit is used for generating a third regulation strategy if the three-phase imbalance degree and load rate of the target low-voltage transformer area meet a third regulation condition, and regulating the controllable equipment of the target low-voltage transformer area according to the third regulation strategy.
[0024] In the above scheme, the three-phase imbalance degree and load rate of the target low-voltage transformer area are monitored in real time, and corresponding regulation strategies are generated according to different regulation conditions met by the three-phase imbalance degree and load rate, so as to regulate the controllable equipment of the target low-voltage transformer area in real time. Thus, through the coordinated control of day-ahead optimization and real-time monitoring, the controllable equipment of the target low-voltage transformer area is adaptively regulated, and the three-phase imbalance load of the low-voltage transformer area is optimized, thereby improving the operation reliability of the low-voltage transformer area. BRIEF DESCRIPTION OF DRAWINGS
[0025] Figure 1 A step flowchart of a low-voltage transformer area three-phase imbalance regulation method provided for an embodiment of the present application is shown in the figure;
[0026] Figure 2 A real-time regulation flowchart of a low-voltage transformer area three-phase imbalance regulation method provided for an embodiment of the present application is shown in the figure;
[0027] Figure 3 A module structure diagram of a low-voltage transformer area three-phase imbalance regulation system provided for an embodiment of the present application is shown in the figure. DETAILED DESCRIPTION
[0028] The technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by those of ordinary skill in the art without creative labor fall within the scope of protection of the present application.
[0029] Embodiment 1
[0030] Referring to Figure 1 , Figure 1 A step flowchart of a low-voltage area three-phase imbalance regulation method provided for an embodiment of the present application; as Figure 1 shown, the embodiment of the present application proposes a low-voltage area three-phase imbalance regulation method, which comprises steps 101 to 104, and each step is as follows:
[0031] Step 101, obtaining target low-voltage area network structure data and target low-voltage area adjustable equipment basic parameters;
[0032] Step 102, constructing a day-ahead optimization model based on the target low-voltage area network structure data and the target low-voltage area adjustable equipment basic parameters;
[0033] Step 103, solving the day-ahead optimization model based on a preset genetic algorithm, obtaining a three-phase imbalance day-ahead regulation plan, and performing day-ahead three-phase imbalance regulation on the target low-voltage area;
[0034] Step 104, real-time monitoring of the three-phase imbalance degree and load rate of the target low-voltage area, and real-time three-phase imbalance regulation of the target low-voltage area adjustable equipment according to the three-phase imbalance degree and load rate.
[0035] A specific implementation manner, collecting the network structure data of the target low-voltage area, wherein the network structure data comprises the connection relationship between the conventional load, photovoltaic, energy storage, phase change switch and low-voltage phase line and the rated carrying capacity of the low-voltage phase line and collecting the basic parameters of the target low-voltage area adjustable equipment, including the unit action loss cost γ of the phase change switch, the rated capacity S essN , the rated power P essN of the energy storage, the charging efficiency η c of the energy storage, the discharging efficiency η d of the energy storage, the maintenance cost coefficient C omb of the energy storage, the depreciation cost coefficient η dep of the energy storage, the number of recyclable charging and discharging times N of the energy storage, the unit power installation cost C P of the energy storage, and the unit capacity installation cost C S;It is worth mentioning that the target low-voltage area is a three-phase four-wire network, and the low-voltage phase line refers to a certain phase of a certain low-voltage branch in the target low-voltage area; after obtaining the target low-voltage area network structure data and the basic parameters of the target low-voltage area controllable equipment, a target function is constructed according to the basic parameters of the target low-voltage area controllable equipment, and a constraint condition is set according to the target low-voltage area network structure data and the basic parameters of the target low-voltage area controllable equipment, so that the day-ahead optimization model is constructed by the target function and the constraint condition; the day-ahead optimization model constructed above is solved by using a catastrophe genetic algorithm, and in this embodiment, the preset genetic algorithm is characterized by the catastrophe genetic algorithm; in the catastrophe genetic algorithm solving process, firstly, the chromosome is initialized, a number of three-phase imbalance day-ahead regulation plans are compiled into binary codes to form an initial population, and a penalty term is introduced to expand the objective function on the basis of the objective function of the day-ahead optimization model to generate a new objective function, and then the new objective function is solved by using a tournament selection mechanism and an elite strategy until the new objective function converges, and finally a three-phase imbalance day-ahead regulation plan is obtained, and the target low-voltage area is regulated in three-phase imbalance in day-ahead by using the three-phase imbalance day-ahead regulation plan; in addition to performing three-phase imbalance day-ahead regulation, the embodiment of the present application also proposes to monitor the target low-voltage area in real time, obtain the three-phase imbalance of the distribution transformer low-voltage bus and the load rate of the low-voltage outgoing line, and execute different regulation strategies on the target low-voltage area according to whether the three-phase imbalance of the distribution transformer low-voltage bus and the load rate of the low-voltage outgoing line are out of limit, so as to regulate the target low-voltage area controllable equipment in real time three-phase imbalance.
[0036] The embodiment of the present application proposes a low-voltage area three-phase imbalance regulation method, obtains the target low-voltage area network structure data and the basic parameters of the target low-voltage area controllable equipment and constructs a day-ahead optimization model, solves the day-ahead optimization model by using a preset genetic algorithm to generate a corresponding three-phase imbalance day-ahead regulation plan to regulate the target low-voltage area in day-ahead three-phase imbalance, and at the same time, real-time monitoring of the three-phase imbalance and load rate of the target low-voltage area is combined to ensure that the three-phase imbalance and load rate are always within a safe range. Therefore, through the coordinated control of day-ahead optimization combined with real-time monitoring, the target low-voltage area controllable equipment is adaptively regulated, the three-phase imbalance load of the low-voltage area is optimized, and the operation reliability of the low-voltage area is improved.
[0037] A preferred scheme, the execution step 102 comprises: based on the preset regulation period, calculating the first cost and the second cost in the preset regulation period according to the basic parameters of the target low-voltage area controllable equipment; based on the first cost and the second cost, constructing a target function; based on the target low-voltage area network structure data and the basic parameters of the target low-voltage area controllable equipment, constructing a number of three-phase imbalance regulation constraints; based on the target function and the number of three-phase imbalance regulation constraints, constructing a day-ahead optimization model.
[0038] One preferred implementation involves constructing an objective function based on the basic parameters of the controllable equipment in the target low-voltage distribution area, and setting constraints based on the network structure data and basic parameters of the controllable equipment in the target low-voltage distribution area. The objective function and constraints are then used to construct a day-ahead optimization model. Specifically, in this embodiment, within a preset control period, the first cost is represented as the commutation switch loss cost C within the control period. loss The second cost is characterized by the charging and discharging loss cost C of energy storage during the regulation cycle. ess The preset control period is set according to the actual application and is not limited here. The commutation switch loss cost C within the control period is... loss The calculation formula is as follows:
[0039]
[0040] In the formula, γ is the unit operating loss cost of the commutation switch; T is the control cycle duration; N ps This represents the total number of commutation switches; Let j be the switching position of the j-th commutator switch at time t; Let j be the switching position of the j-th commutator switch at time t+1; This is the gear switching identifier for the j-th commutator switch at time t.
[0041] The charging and discharging loss cost of energy storage during the regulation cycle, C ess The calculation formula is as follows:
[0042]
[0043] In the formula, C omb Energy storage maintenance cost coefficient (unit: yuan / kWh); These represent the charging power and discharging power of the energy storage device at time t, respectively; Δt is the scheduling time interval in hours. C represents the discharge state at time t and the previous time (t-1), respectively; dep The depreciation cost of the energy storage device (unit: yuan) is C. dep The calculation formula is as follows:
[0044]
[0045] In the formula, S essN P represents the rated capacity of the energy storage. essN Rated energy storage capacity; η dep C is the energy storage depreciation cost factor. P Installation cost per unit power of energy storage (unit: yuan / kWh); C Sis the installation cost of the energy storage unit per capacity (unit: yuan / kWh); N is the number of cycles of the energy storage, in this embodiment, N is represented as N(t), N(t) is the number of cycles of the energy storage device at the current time t, which is related to the depth of discharge DOD(t) at the current time t, and the number of cycles of the energy storage N(t) is calculated according to the following formula:
[0046]
[0047] In the formula, is the remaining power of the energy storage device at the current time t; b1-b5 are known parameters provided by the manufacturer;
[0048] Finally, the switching loss cost C loss and the charge-discharge loss cost C ess of the energy storage in the regulation period are constructed to form the objective function minF, as follows:
[0049] minF=C loss +C ess ;
[0050] After obtaining the objective function, constraint conditions are set according to the target low-voltage substation grid structure data and the basic parameters of the adjustable equipment of the target low-voltage substation, including state variable constraints and control variable inequality constraints. The state variable constraints include bus three-phase imbalance constraints and low-voltage phase line load rate constraints, and the bus three-phase imbalance constraints are specifically expressed as follows:
[0051]
[0052] Among them:
[0053]
[0054] In the formula, δ is the bus three-phase imbalance degree; and are the currents of the bus A phase, B phase and C phase of the target low-voltage substation at time t after regulation, respectively; β1 is the safety threshold of the bus three-phase imbalance degree; and are the currents of the bus A phase, B phase and C phase of the target low-voltage substation at time t before regulation, respectively; and are the currents at time t after the switching of the phase switch from A phase to B phase, A phase to C phase, B phase to A phase, B phase to C phase, C phase to A phase and C phase to B phase, respectively; and are the A phase charging power and A phase discharging power of the i-th energy storage at time t, respectively; and These are the charging power of phase B and the discharging power of phase B at the i-th energy storage time t, respectively. and These are the C-phase charging power and C-phase discharging power at time t of the i-th energy storage event;
[0055] The specific expression for the low-voltage phase line load rate constraint is as follows:
[0056]
[0057] In the formula, For the first time Low-voltage phase line load rate at time t; For the first time The current before adjustment of the low-voltage phase line at time t; For the first time The current after adjustment of the low-voltage phase line at time t; For the first time The rated current value of the low-voltage phase line; β2 is the safe threshold for the load rate of the low-voltage phase line.
[0058] The control variable inequality constraints include: P of the energy storage device ess Upper and lower limit constraints, SOC upper and lower limit constraints of energy storage devices, and charge and discharge balance constraints of energy storage devices, P of energy storage devices ess The specific expressions for the upper and lower limit constraints are as follows:
[0059] P essi,min ≤P essi ≤P essi,max ,i∈Ω ess ;
[0060] In the formula, Ω ess For the set of energy storage grid-connected nodes; P essi P represents the active power output of the i-th energy storage unit. essi,max and P essi,min These are the upper and lower limits of the active power output of the i-th energy storage unit, respectively;
[0061] The specific expressions for the upper and lower limits of the SOC constraint of the energy storage device are as follows:
[0062] SOC i,min +ε essi ≤SOC i ≤SOC i,max -ε essi ;
[0063] In the formula, SOC i,max and SOC i,min ε represents the upper and lower limits of the state of charge (SOC) of the i-th energy storage unit, respectively; essi The reserved capacity margin factor is the ratio of reserved capacity to the rated energy storage capacity.
[0064] In the embodiments of the present application, by combining the upper and lower limits of the SOC of the energy storage device, the P ess The upper and lower limit constraints are converted into:
[0065]
[0066] In the formula, and are the upper and lower limits of the active power at the i th energy storage time t; is the remaining power of the i th energy storage device at the previous time (t-1); η ci and η di are the charging efficiency and discharging efficiency of the i th energy storage device, respectively; wherein the remaining power of the energy storage device at the current time t can be calculated from the remaining power at the previous time (t-1) and the current charging and discharging power, and the specific calculation formula is:
[0067]
[0068] In the formula, and are the charging power and discharging power of the i th energy storage device at time t; and are the charging state and discharging state of the i th energy storage device at time t; S lossi is the static energy loss of the i th energy storage device;
[0069] Finally, the charging and discharging balance constraint of the energy storage device, i.e., the remaining power at the starting time of the scheduling period should be equal to the remaining power at the end time of the scheduling period, and the specific expression is as follows:
[0070]
[0071] In the formula, is the remaining power of the i th energy storage device at the end time of the scheduling period; is the remaining power of the i th energy storage device at the starting time of the scheduling period; ΔS essi is the charging and discharging balance allowable deviation, which can be set to 0 in specific solution, and the charging and discharging balance deviation of the energy storage is determined by the real-time control condition, so that ΔS essi ≤S essNi ×ε essi Therefore, the reserved capacity margin coefficient can be valued according to the charging and discharging balance allowable deviation.
[0072] Finally, according to the objective function and the constraint conditions, the day-ahead optimization model is constructed.
[0073] In the above scheme, the first cost and the second cost are calculated in a preset regulation period, thereby constructing a target function, and the target function is constrained according to the target low-voltage transformer area network structure data and the target low-voltage transformer area adjustable device basic parameters, thereby obtaining a day-ahead optimization model. Thus, the day-ahead optimization model is constructed to perform day-ahead optimization on the adjustable devices in the target low-voltage transformer area, and the adjustable devices in the target low-voltage transformer area are adaptively regulated and controlled in combination with subsequent real-time monitoring and cooperative control, thereby optimizing the three-phase imbalance load in the low-voltage transformer area and improving the operation reliability of the low-voltage transformer area.
[0074] In a preferred scheme, the step 103 comprises: based on a preset genetic algorithm, encoding a plurality of three-phase imbalance regulation plans into a plurality of chromosomes to obtain an initial population; based on a preset penalty factor and the day-ahead optimization model, constructing a fitness model; performing a model solving process: randomly selecting a plurality of first chromosomes from the initial population, calculating the fitness of each first chromosome based on the fitness model, selecting the first chromosome satisfying a preset first iteration requirement as a parent chromosome of the next generation, and generating a plurality of child chromosomes according to the parent chromosome; if the current evolution generation satisfies a preset catastrophe requirement, merging the child chromosomes and the parent chromosomes to obtain a merged chromosome; calculating the fitness of the merged chromosome based on the fitness model, selecting the merged chromosome satisfying a preset second iteration requirement to construct an optimized population, and ending the model solving process; based on the optimized population, repeatedly performing the model solving process until the current evolution generation satisfies a preset target evolution requirement, obtaining a target population, calculating the fitness of each second chromosome in the target population, selecting the second chromosome satisfying a preset third iteration requirement as a target chromosome, obtaining the binary code of the target chromosome, and obtaining the corresponding three-phase imbalance regulation plan; based on the three-phase imbalance regulation plan, performing day-ahead three-phase imbalance regulation on the target low-voltage transformer area.
[0075] In an implementation manner of the preferred scheme, the catastrophe genetic algorithm is used to solve the constructed day-ahead optimization model, in the embodiment, the preset genetic algorithm is characterized as the catastrophe genetic algorithm; in the solving process of the catastrophe genetic algorithm, firstly, the chromosome is initialized, a plurality of three-phase unbalance day-ahead regulation plans are compiled into binary codes to form an initial population, a penalty term is introduced into the objective function of the day-ahead optimization model to expand the objective function, a fitness model is generated, the tournament selection mechanism and the elite strategy are used to solve the new objective function, until the new objective function converges, finally, the three-phase unbalance day-ahead regulation plan is obtained, and the target low-voltage area is subjected to the day-ahead three-phase unbalance regulation by using the three-phase unbalance day-ahead regulation plan. Specifically, firstly, the plurality of three-phase unbalance day-ahead regulation plans are compiled into binary codes to initialize the chromosome, the three-phase unbalance day-ahead regulation plan is set as the configuration of the phase-changing switch in the embodiment, 0 represents that the corresponding phase-changing switch is removed, and 1 represents that the corresponding phase-changing switch is put into, the total evolution generation number of the population is set as gen; secondly, the state variable constraint is added into the objective function as the penalty term to facilitate searching the feasible solution, and the second objective function is obtained after expansion as follows:
[0076] min F' = C loss + C ess + λ L P Llim + λ η P ηlim ;
[0077] In the formula, λ L and λ η are penalty factors, generally, are normal numbers with large values; P Llim is the three-phase unbalance degree out-of-limit risk punishment index; P ηlim is the line overload risk punishment index.
[0078] The three-phase unbalance degree out-of-limit risk punishment index P Llim is specifically expressed as follows:
[0079]
[0080] The line overload risk punishment index P ηlim is specifically expressed as follows:
[0081]
[0082] After the new objective function, that is, the fitness model is obtained, the catastrophe genetic algorithm uses the tournament selection mechanism: firstly, s first chromosomes are randomly selected in the population, the fitness of each first chromosome is calculated and compared by using the fitness model, and the first chromosome with the highest fitness will be selected as the parent chromosome P t of the next generation, and the parent chromosome P tQ is obtained by crossover and mutation of the sub-chromosomes Q t If the current evolution generation is an integer multiple of the preset catastrophe interval generation, catastrophe is implemented.
[0083] The elite strategy is further adopted to combine the parent chromosomes P t and the sub-chromosomes Q t to obtain a combined chromosome R t , the fitness of the combined chromosome R t is calculated, the first function value is calculated by the second objective function, and the first M chromosomes are selected as a new parent population P t+1 ; when the fitness model meets the convergence condition t>gen, the target population is output, the fitness of each second chromosome in the target population is calculated by the fitness model, the second chromosome with the highest fitness is selected as a target chromosome, the binary code of the target chromosome is obtained, the corresponding three-phase imbalance regulation plan is obtained after decoding, and the target low-voltage transformer area is regulated in advance according to the obtained three-phase imbalance regulation plan. In this embodiment, the preset first iteration requirement represents the first chromosome with the highest fitness; the preset catastrophe requirement represents the preset catastrophe interval generation, which can generally be set to 50 generations; the preset second iteration requirement represents the selection of the first M chromosomes; the preset target evolution requirement represents the convergence condition t>gen; and the preset third iteration requirement represents the second chromosome with the highest fitness.
[0084] In the above scheme, the genetic algorithm is adopted to introduce the catastrophe mechanism and the elite strategy to solve the day-ahead optimization model, generate a three-phase imbalance regulation plan, and regulate the target low-voltage transformer area in advance. Therefore, the genetic algorithm with the catastrophe mechanism and the elite strategy is used to solve the day-ahead optimization model, which can avoid the situation that the model falls into a local optimum, improve the reliability of the three-phase imbalance regulation plan, and be beneficial to subsequent collaborative control combined with real-time monitoring, self-adaptive regulation of the target low-voltage transformer area, optimization of the three-phase imbalance load of the low-voltage transformer area, and improvement of the operation reliability of the low-voltage transformer area.
[0085] In an optimal scheme, step 104 includes: monitoring the three-phase imbalance degree and the load rate of the target low-voltage transformer area in real time; if the three-phase imbalance degree and the load rate of the target low-voltage transformer area meet the first regulation condition, a first regulation strategy is generated, and the three-phase imbalance of the target low-voltage transformer area is regulated according to the first regulation strategy; if the three-phase imbalance degree and the load rate of the target low-voltage transformer area meet the second regulation condition, a second regulation strategy is generated, and the three-phase imbalance of the target low-voltage transformer area is regulated according to the second regulation strategy; and if the three-phase imbalance degree and the load rate of the target low-voltage transformer area meet the third regulation condition, a third regulation strategy is generated, and the three-phase imbalance of the target low-voltage transformer area is regulated according to the third regulation strategy.
[0086] In an implementation of the preferred solution, the three-phase imbalance degree of the low-voltage bus and the load rate of the low-voltage outgoing line are monitored in real time, and according to the regulation and control conditions met by the three-phase imbalance degree of the low-voltage bus and the load rate of the low-voltage outgoing line, a corresponding regulation and control strategy is generated to adaptively regulate and control the charging and discharging power of the energy storage. Specifically, refer to Figure 2 , Figure 2 A real-time regulation and control process schematic diagram of a low-voltage area three-phase imbalance regulation and control method is provided for a certain embodiment of the present application; as shown in Figure 2 When the first regulation and control condition is met, i.e., the three-phase imbalance degree and the load rate are both not out of limit, the energy storage is charged under the premise of not causing out-of-limit, and the energy storage power is ensured to return to the margin range; when the second regulation and control condition is met, i.e., the three-phase imbalance degree is out of limit and the load rate is not out of limit, the energy storage in the phase with the maximum load current is discharged, and the discharge strategy is that all the energy storages in the phase are discharged equally, and if the margin range has been exceeded, emergency discharge is enabled; if all the energy storages have no capacity, an alarm is started; when the third regulation and control condition is met, i.e., the three-phase imbalance degree is not out of limit and the load rate is out of limit, the energy storage in the phase with the maximum load current of the low-voltage outgoing line is discharged, and the discharge strategy is that all the energy storages in the phase are discharged equally.
[0087] In the above solution, the three-phase imbalance degree and the load rate of the target low-voltage area are monitored in real time, and according to different regulation and control conditions met by the three-phase imbalance degree and the load rate, a corresponding regulation and control strategy is generated to regulate and control the target low-voltage area controllable equipment in real time. Thus, through the coordinated control of day-ahead optimization and real-time monitoring, the target low-voltage area controllable equipment is adaptively regulated and controlled, the three-phase imbalance load of the low-voltage area is optimized, and the operation reliability of the low-voltage area is improved.
[0088] In an implementation of the preferred solution, in step 104, if the three-phase imbalance degree and the load rate of the target low-voltage area meet the first regulation and control condition, a first regulation and control strategy is generated, and the target low-voltage area controllable equipment is regulated and controlled according to the first regulation and control strategy, including: if the three-phase imbalance degree of the target low-voltage area meets the preset risk monitoring requirement and the load rate of the target low-voltage area meets the preset risk monitoring requirement, the three-phase imbalance degree and the load rate of the target low-voltage area meet the first regulation and control condition; a charging strategy is generated according to the rated power of the target low-voltage area controllable equipment and a preset charging power coefficient; the target low-voltage area controllable equipment is uniformly charged according to the charging strategy until the power reaches the preset margin range or the regulation and control period reaches the preset termination time, and the three-phase imbalance regulation and control is ended.
[0089] An implementable manner of a preferred scheme is that when the first regulation condition, i.e. the three-phase imbalance degree and the load rate, is not out of limit, the energy storage is charged without causing out of limit, and the energy storage power is ensured to return to the margin range. Specifically, when the three-phase imbalance degree of the distribution transformer low-voltage bus and the low-voltage phase line load rate of the target low-voltage area are not out of limit, the charging strategy is executed on each energy storage according to the rated power of the adjustable equipment of the target low-voltage area and the preset charging power coefficient. The charging strategy is to uniformly charge at the rated power multiplied by the coefficient until the end of the regulation period or the power reaches the margin range. The charging strategy is specifically represented as:
[0090] P c,i =λ×P essNi ;
[0091]
[0092] In the formula, P c,i is the charging power of the i th energy storage; P essNi is the rated power of the energy storage; λ is the charging power coefficient; is the number of energy storages of the regulated phase; V i is the grid-connected voltage of the i th energy storage; is the current required to be regulated by the maximum phase of the load current.
[0093] The phase current is calculated by the charging strategy, and the three-phase imbalance degree δ and the load rate η are calculated. If it is out of limit, the value of λ is reduced. Thus, the target low-voltage area adjustable equipment is uniformly charged by the charging strategy until the power reaches the preset margin range or the regulation period reaches the preset termination time, and the three-phase imbalance regulation is ended. In this embodiment, the preset risk monitoring requirement is represented as whether the three-phase imbalance degree and the load rate are out of limit, the preset charging power coefficient is represented as λ, the preset margin range is represented as the quotient value of the remaining energy storage power and the rated energy storage power, and the preset termination time is represented as the end of the regulation period.
[0094] In the above scheme, if the three-phase imbalance degree of the target low-voltage area meets the preset risk monitoring requirement and the load rate of the target low-voltage area meets the preset risk monitoring requirement, the energy storage is charged during the grid valley period or the new energy high generation period, the power reserve of the target low-voltage area adjustable equipment is improved, the uniform charging strategy provides greater regulation margin for the target low-voltage area adjustable equipment, which helps to optimize the three-phase imbalance load regulation of the low-voltage area and improve the operation reliability of the low-voltage area.
[0095] In step 104, if the three-phase imbalance degree and the load rate of the target low-voltage area meet the second regulation condition, a second regulation strategy is generated, and the three-phase imbalance regulation is performed on the target low-voltage area according to the second regulation strategy, including: if the three-phase imbalance degree of the target low-voltage area does not meet the preset risk monitoring requirement and the load rate of the target low-voltage area meets the preset risk monitoring requirement, the three-phase imbalance degree and the load rate of the target low-voltage area meet the second regulation condition; the load current of each target low-voltage area controllable equipment is calculated, the target low-voltage area controllable equipment whose load current meets the preset adjustment requirement is obtained, the grid-connected voltage and the adjustment current of the target low-voltage area controllable equipment are adjusted, the second regulation strategy is generated; and the discharge is shared according to the second regulation strategy, until the three-phase imbalance degree of the target low-voltage area meets the preset risk monitoring requirement, and the three-phase imbalance regulation is ended.
[0096] In an embodiment of the preferred scheme, when the second regulation condition is met, that is, the three-phase imbalance degree is out of limit and the load rate is not out of limit, the energy storage in the phase with the maximum load current is discharged, and the discharge strategy is that all the energy storages in the phase are discharged and shared, and if the margin range is exceeded, emergency discharge is enabled; if all the energy storages have no capacity, an alarm is started. Specifically, when the three-phase imbalance degree of the distribution low-voltage bus is out of limit and the load rate of the low-voltage phase line is not out of limit, the phase line with the maximum load current is obtained, and the discharge strategy is used to discharge and share all the energy storages in the phase line, and the discharge strategy expression is as follows:
[0097]
[0098] In the formula, P d,i is the discharge power of the i th energy storage; is the number of energy storages in the adjusted phase; V i is the grid-connected voltage of the i th energy storage; is the current required to be adjusted in the phase with the maximum load current;
[0099] The target low-voltage area controllable equipment is discharged and shared in this way, until the discharge capacity is within the margin range and the three-phase imbalance degree returns to the limit range, and the three-phase imbalance regulation is ended. If the discharge capacity exceeds the margin range, it is judged whether all the energy storages have capacity, if not, an alarm is started, and if yes, emergency discharge is started. The calculation expression of the margin range exceeding is as follows:
[0100]
[0101] In the formula, is the residual capacity of the i th energy storage at time t; S essNi is the rated capacity of the i th energy storage; ε essi is the reserved capacity coefficient.
[0102] In the above scheme, if the three-phase imbalance degree of the target low-voltage transformer area does not meet the preset risk monitoring requirement and the load rate of the target low-voltage transformer area meets the preset risk monitoring requirement, the target low-voltage transformer area with a load current meeting the preset adjustment requirement is intelligently selected to control the equipment to discharge energy, quickly suppress the difference between three-phase currents, reduce the imbalance degree, and adopt a discharge sharing control strategy to avoid overload of a single device, which helps to optimize the three-phase imbalance load control of the low-voltage transformer area and improve the operation reliability of the low-voltage transformer area.
[0103] In a preferred scheme, in step 104, if the three-phase imbalance degree and the load rate of the target low-voltage transformer area meet the third control condition, a third control strategy is generated, and the target low-voltage transformer area is controlled according to the third control strategy, including: if the three-phase imbalance degree of the target low-voltage transformer area meets the preset risk monitoring requirement and the load rate of the target low-voltage transformer area does not meet the preset risk monitoring requirement, the three-phase imbalance degree and the load rate of the target low-voltage transformer area meet the third control condition; the load current of each target low-voltage transformer area controllable equipment is calculated, the target low-voltage transformer area controllable equipment with a load current meeting the preset adjustment requirement is obtained, the grid-connected voltage and the adjustment current of the target low-voltage transformer area controllable equipment are adjusted, the third control strategy is generated; and the target low-voltage transformer area controllable equipment is discharged according to the third control strategy, until the load rate of the target low-voltage transformer area meets the preset risk monitoring requirement, and the three-phase imbalance control is ended.
[0104] In an implementation manner of a preferred scheme, when the third control condition is met, i.e., the three-phase imbalance degree is not out of limit and the load rate is out of limit, the energy of the low-voltage outgoing line with the maximum load current is adjusted to discharge, and the discharge strategy is to discharge all the energy of the phase. Specifically, when the three-phase imbalance degree of the transformer low-voltage bus is not out of limit and the load rate of the low-voltage phase line is out of limit, the phase line with the maximum load current is obtained, and the discharge strategy of discharging all the energy of the phase is adopted for the phase line. The discharge strategy expression is as follows:
[0105]
[0106] In the formula, P d,i is the discharge power of the i th energy; is the number of energy of the adjusted phase; V i is the grid-connected voltage of the i th energy; is the current required to be adjusted by the phase with the maximum load current;
[0107] The target low-voltage transformer area controllable equipment is discharged in this way until the discharge capacity is within the margin range and the load rate returns to the limit range, and the three-phase imbalance control is ended.
[0108] In the above scheme, if the three-phase imbalance degree of the target low-voltage transformer area meets the preset risk monitoring requirement and the load rate of the target low-voltage transformer area does not meet the preset risk monitoring requirement, the target low-voltage transformer area with a load current meeting the preset adjustment requirement is intelligently selected to control the equipment to discharge energy storage, quickly suppress the three-phase current difference, reduce the imbalance degree, and adopt the discharge sharing control strategy to relieve the line pressure, which helps to optimize the three-phase imbalance load of the low-voltage transformer area and improve the operation reliability of the low-voltage transformer area.
[0109] Embodiment 2
[0110] Referring to Figure 3 , Figure 3 A module structure schematic diagram of a low-voltage transformer area three-phase imbalance control system provided by an embodiment of the present application is shown in the figure. Figure 3 As shown in the figure, the low-voltage transformer area three-phase imbalance control system provided by the embodiment of the present application comprises a data acquisition module 201, a day-ahead optimization model construction module 202, a day-ahead three-phase imbalance control module 203, and a real-time three-phase imbalance control module 204. The data acquisition module 201 is used to acquire the target low-voltage transformer area grid structure data and the target low-voltage transformer area controllable equipment basic parameters. The day-ahead optimization model construction module 202 is used to construct a day-ahead optimization model based on the target low-voltage transformer area grid structure data and the target low-voltage transformer area controllable equipment basic parameters. The day-ahead three-phase imbalance control module 203 is used to solve the day-ahead optimization model based on a preset genetic algorithm, obtain a three-phase imbalance day-ahead control plan, and perform day-ahead three-phase imbalance control on the target low-voltage transformer area. The real-time three-phase imbalance control module 204 is used to monitor the three-phase imbalance degree and the load rate of the target low-voltage transformer area in real time, and perform real-time three-phase imbalance control on the target low-voltage transformer area controllable equipment according to the three-phase imbalance degree and the load rate.
[0111] The low-voltage transformer area three-phase imbalance control system provided by the embodiment of the present application acquires the target low-voltage transformer area grid structure data and the target low-voltage transformer area controllable equipment basic parameters, constructs a day-ahead optimization model, solves the day-ahead optimization model by using a preset genetic algorithm to generate a corresponding three-phase imbalance day-ahead control plan for performing day-ahead three-phase imbalance control on the target low-voltage transformer area, and simultaneously monitors the three-phase imbalance degree and the load rate of the target low-voltage transformer area in real time to ensure that the three-phase imbalance degree and the load rate are always within a safe range. In this way, through the cooperative control of day-ahead optimization and real-time monitoring, the target low-voltage transformer area controllable equipment is adaptively controlled, the three-phase imbalance load of the low-voltage transformer area is optimized, and the operation reliability of the low-voltage transformer area is improved.
[0112] In an embodiment, the day-ahead optimization model construction module 202 is configured to construct a day-ahead optimization model based on the target low-voltage transformer area network architecture data and the target low-voltage transformer area adjustable device basic parameters. The day-ahead optimization model construction module 202 includes a regulation data acquisition unit 301, a target function construction unit 302, a constraint condition construction unit 303, and a model construction unit 304. The regulation data acquisition unit 301 is configured to calculate a first cost and a second cost within a preset regulation period according to the target low-voltage transformer area adjustable device basic parameters based on the preset regulation period. The target function construction unit 302 is configured to construct a target function based on the first cost and the second cost. The constraint condition construction unit 303 is configured to construct a plurality of three-phase imbalance regulation constraints based on the target low-voltage transformer area network architecture data and the target low-voltage transformer area adjustable device basic parameters. The model construction unit 304 is configured to construct the day-ahead optimization model based on the target function and the plurality of three-phase imbalance regulation constraints.
[0113] In the above scheme, the first cost and the second cost are calculated within the preset regulation period to construct the target function. Then, the target function is constrained based on the target low-voltage transformer area network architecture data and the target low-voltage transformer area adjustable device basic parameters to obtain the day-ahead optimization model. Thus, the day-ahead optimization model is constructed to optimize the target low-voltage transformer area adjustable device in advance. In combination with subsequent real-time monitoring and cooperative control, the target low-voltage transformer area adjustable device is adaptively regulated to optimize the three-phase imbalance load of the low-voltage transformer area and improve the operation reliability of the low-voltage transformer area.
[0114] In an embodiment, the real-time three-phase imbalance regulation module 204 is configured to monitor the three-phase imbalance degree and the load rate of the target low-voltage transformer area in real time and regulate the target low-voltage transformer area adjustable device based on the three-phase imbalance degree and the load rate. The real-time three-phase imbalance regulation module 204 includes a real-time data monitoring unit 401, a first regulation unit 402, a second regulation unit 403, and a third regulation unit 404. The real-time data monitoring unit 401 is configured to execute a three-phase imbalance regulation plan and monitor the three-phase imbalance degree and the load rate of the target low-voltage transformer area in real time. The first regulation unit 402 is configured to generate a first regulation strategy if the three-phase imbalance degree and the load rate of the target low-voltage transformer area meet a first regulation condition and regulate the target low-voltage transformer area adjustable device based on the first regulation strategy. The second regulation unit 403 is configured to generate a second regulation strategy if the three-phase imbalance degree and the load rate of the target low-voltage transformer area meet a second regulation condition and regulate the target low-voltage transformer area adjustable device based on the second regulation strategy. The third regulation unit 404 is configured to generate a third regulation strategy if the three-phase imbalance degree and the load rate of the target low-voltage transformer area meet a third regulation condition and regulate the target low-voltage transformer area adjustable device based on the third regulation strategy.
[0115] In the above scheme, the three-phase imbalance degree and the load rate of the target low-voltage transformer area are monitored in real time, and corresponding control strategies are generated according to different control conditions met by the three-phase imbalance degree and the load rate, so as to control the adjustable equipment of the target low-voltage transformer area in real time. Thus, through the coordinated control of day-ahead optimization and real-time monitoring, the adjustable equipment of the target low-voltage transformer area is adaptively controlled, the three-phase imbalance load of the low-voltage transformer area is optimized, and the operation reliability of the low-voltage transformer area is improved.
[0116] The above is only the preferred embodiment of the present application, and it should be pointed out that for ordinary skilled in the art, without departing from the technical principles of the present application, a number of improvements and modifications can be made, and these improvements and modifications should be considered as the protection scope of the present application.
[0117] In the description of the present specification, the description of the terms "one embodiment", "some embodiments", "an example", "a specific example" or "some examples" means that the specific features, structures, materials or characteristics described in connection with the embodiment or example are included in at least one embodiment or example of the present application. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner. In addition, the person skilled in the art can combine and combine the different embodiments or examples described in the present specification and the features of the different embodiments or examples without contradiction.
[0118] In addition, the terms "first", "second" are only for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of indicated technical features. Therefore, the features defined with "first", "second" can explicitly or implicitly include at least one of the features. In the description of the present application, the meaning of "a plurality of" is two or more, unless otherwise specifically limited.
Claims
1. A method for controlling three-phase imbalance in a low-voltage distribution area, characterized in that, include: Acquire the grid structure data of the target low-voltage distribution area and the basic parameters of the adjustable equipment in the target low-voltage distribution area; A day-ahead optimization model is constructed based on the target low-voltage distribution area grid structure data and the basic parameters of the adjustable equipment in the target low-voltage distribution area. Based on the preset genetic algorithm, the daytime optimization model is solved to obtain the three-phase imbalance daytime control plan and the daytime three-phase imbalance control is carried out on the target low-voltage area. The three-phase imbalance and load rate of the target low-voltage distribution area are monitored in real time, and the three-phase imbalance of the adjustable equipment in the target low-voltage distribution area is adjusted in real time according to the three-phase imbalance and the load rate.
2. The method for controlling three-phase imbalance in a low-voltage distribution area as described in claim 1, characterized in that, Based on the target low-voltage distribution area's grid structure data and the basic parameters of the target low-voltage distribution area's adjustable equipment, a day-ahead optimization model is constructed, including: Based on a preset control cycle, calculate the first cost and the second cost within the preset control cycle according to the basic parameters of the controllable equipment in the target low-voltage area. Based on the first cost and the second cost, construct an objective function; Based on the target low-voltage distribution area grid structure data and the basic parameters of the target low-voltage distribution area adjustable equipment, several three-phase imbalance control constraints are constructed. A day-ahead optimization model is constructed based on the objective function and several of the three-phase imbalance control constraints.
3. The method for controlling three-phase imbalance in a low-voltage distribution area as described in claim 2, characterized in that, Based on a preset genetic algorithm, the daytime optimization model is solved to obtain a three-phase imbalance daytime control plan and to perform daytime three-phase imbalance control on the target low-pressure area, including: Based on a pre-defined genetic algorithm, several three-phase imbalance control plans are binary-coded into several chromosomes to obtain an initial population. A fitness model is constructed based on a preset penalty factor and the day-ahead optimization model. The model solving process is as follows: Randomly select several first chromosomes from the initial population; calculate the fitness of each first chromosome based on the fitness model; use the first chromosome whose fitness meets the preset first iteration requirement as the parent chromosome for the next generation; and generate several child chromosomes based on the parent chromosomes; if the current generation meets the preset catastrophe requirement, merge the child chromosomes and the parent chromosomes to obtain a merged chromosome; calculate the fitness of the merged chromosome based on the fitness model; select the merged chromosome that meets the preset second iteration requirement to construct an optimized population, and end the model solving process. Based on the optimized population, the model solution process is repeated until the current generation meets the preset target evolutionary requirements to obtain the target population. The fitness of each second chromosome in the target population is calculated, and the second chromosome whose fitness meets the preset third iteration requirements is selected as the target chromosome. The binary code of the target chromosome is obtained to obtain the corresponding three-phase imbalance control plan. Based on the aforementioned three-phase imbalance control plan, daytime three-phase imbalance control is carried out on the target low-voltage distribution area.
4. The method for controlling three-phase imbalance in a low-voltage distribution area as described in claim 1, characterized in that, Real-time monitoring of the three-phase imbalance and load rate of the target low-voltage distribution area, and real-time three-phase imbalance control of the adjustable equipment in the target low-voltage distribution area based on the three-phase imbalance and load rate, including: Real-time monitoring of the three-phase imbalance and load rate of the target low-voltage distribution area; If the three-phase imbalance and load rate of the target low-voltage distribution area meet the first control condition, a first control strategy is generated, and the three-phase imbalance of the controllable equipment in the target low-voltage distribution area is controlled according to the first control strategy. If the three-phase imbalance and load rate of the target low-voltage distribution area meet the second control conditions, a second control strategy is generated, and the three-phase imbalance is controlled on the controllable equipment in the target low-voltage distribution area according to the second control strategy. If the three-phase imbalance and load rate of the target low-voltage distribution area meet the third control condition, a third control strategy is generated, and the three-phase imbalance of the controllable equipment in the target low-voltage distribution area is controlled according to the third control strategy.
5. The method for controlling three-phase imbalance in a low-voltage distribution area as described in claim 4, characterized in that, If the three-phase imbalance and load rate of the target low-voltage distribution area meet the first control condition, a first control strategy is generated, and three-phase imbalance control is performed on the controllable equipment in the target low-voltage distribution area according to the first control strategy, including: If the three-phase imbalance of the target low-voltage distribution area meets the preset risk monitoring requirements and the load rate of the target low-voltage distribution area meets the preset risk monitoring requirements, then the three-phase imbalance and load rate of the target low-voltage distribution area meet the first control condition. A charging strategy is generated based on the rated power of the adjustable equipment in the target low-voltage distribution area and the preset charging power coefficient. According to the charging strategy, the adjustable equipment in the target low-voltage area is charged evenly until the power reaches the preset margin range or the control cycle reaches the preset termination time, thus ending the three-phase imbalance control.
6. The method for controlling three-phase imbalance in a low-voltage distribution area as described in claim 5, characterized in that, If the three-phase imbalance and load rate of the target low-voltage distribution area meet the second control condition, a second control strategy is generated, and three-phase imbalance control is performed on the controllable equipment in the target low-voltage distribution area according to the second control strategy, including: If the three-phase imbalance of the target low-voltage distribution area does not meet the preset risk monitoring requirements and the load rate of the target low-voltage distribution area meets the preset risk monitoring requirements, then the three-phase imbalance and load rate of the target low-voltage distribution area meet the second control condition. Calculate the load current of the adjustable equipment in each target low-voltage distribution area, obtain the adjustable equipment in the target low-voltage distribution area whose load current meets the preset adjustment requirements, and generate a second adjustment strategy for the grid-connected voltage and adjustment current of the adjustable equipment in the target low-voltage distribution area. According to the second control strategy, the discharge of the controllable equipment in the target low-voltage area is evenly distributed until the three-phase imbalance of the target low-voltage area meets the preset risk monitoring requirements, and the three-phase imbalance control ends.
7. The method for controlling three-phase imbalance in a low-voltage distribution area as described in claim 6, characterized in that, If the three-phase imbalance and load rate of the target low-voltage distribution area meet the third control condition, a third control strategy is generated, and three-phase imbalance control is performed on the controllable equipment in the target low-voltage distribution area according to the third control strategy, including: If the three-phase imbalance of the target low-voltage distribution area meets the preset risk monitoring requirements and the load rate of the target low-voltage distribution area does not meet the preset risk monitoring requirements, then the three-phase imbalance and load rate of the target low-voltage distribution area meet the third control condition. Calculate the load current of the adjustable equipment in each target low-voltage distribution area, obtain the adjustable equipment in the target low-voltage distribution area whose load current meets the preset adjustment requirements, and generate a third adjustment strategy for the grid-connected voltage and adjustment current of the adjustable equipment in the target low-voltage distribution area. According to the third control strategy, the discharge of the controllable equipment in the target low-voltage area is evenly distributed until the load rate of the target low-voltage area meets the preset risk monitoring requirements, and the three-phase imbalance control ends.
8. A three-phase imbalance control system for low-voltage distribution areas, characterized in that, The method for controlling three-phase imbalance in a low-voltage distribution area as described in any one of claims 1 to 7 includes: The module includes a data acquisition module, a day-ahead optimization model construction module, a day-ahead three-phase imbalance control module, and a real-time three-phase imbalance control module. The data acquisition module is used to acquire the target low-voltage distribution area grid structure data and the basic parameters of the target low-voltage distribution area adjustable equipment. The day-ahead optimization model construction module is used to construct a day-ahead optimization model based on the target low-voltage distribution area grid structure data and the basic parameters of the target low-voltage distribution area adjustable equipment. The daytime three-phase imbalance control module is used to solve the daytime optimization model based on a preset genetic algorithm, obtain the daytime three-phase imbalance control plan, and perform daytime three-phase imbalance control on the target low-voltage area. The real-time three-phase imbalance control module is used to monitor the three-phase imbalance and load rate of the target low-voltage distribution area in real time, and to perform real-time three-phase imbalance control on the controllable equipment in the target low-voltage distribution area based on the three-phase imbalance and the load rate.
9. A three-phase imbalance control system for low-voltage distribution areas as described in claim 8, characterized in that, The day-ahead optimization model construction module is used to construct a day-ahead optimization model based on the target low-voltage distribution area's grid structure data and the basic parameters of the target low-voltage distribution area's adjustable equipment, including: The system includes a data acquisition unit, an objective function construction unit, a constraint construction unit, and a model construction unit. The control data acquisition unit is used to calculate the first cost and the second cost within the preset control period based on the basic parameters of the controllable equipment in the target low-voltage area, according to the preset control period. The objective function construction unit is used to construct an objective function based on the first cost and the second cost; The constraint construction unit is used to construct several three-phase imbalance control constraints based on the target low-voltage distribution area grid structure data and the basic parameters of the target low-voltage distribution area adjustable equipment. The model building unit is used to construct a day-ahead optimization model based on the objective function and several of the three-phase imbalance control constraints.
10. A three-phase imbalance control system for low-voltage distribution areas as described in claim 8, characterized in that, The real-time three-phase imbalance control module is used to monitor the three-phase imbalance and load rate of the target low-voltage distribution area in real time, and to perform real-time three-phase imbalance control on the controllable equipment in the target low-voltage distribution area based on the three-phase imbalance and the load rate, including: The system comprises a real-time data monitoring unit, a first control unit, a second control unit, and a third control unit. The real-time data monitoring unit is used to monitor the three-phase imbalance and load rate of the target low-voltage distribution area in real time. The first control unit is used to generate a first control strategy if the three-phase imbalance and load rate of the target low-voltage distribution area meet the first control conditions, and to perform three-phase imbalance control on the controllable equipment in the target low-voltage distribution area according to the first control strategy. The second control unit is used to generate a second control strategy if the three-phase imbalance and load rate of the target low-voltage distribution area meet the second control conditions, and to perform three-phase imbalance control on the controllable equipment in the target low-voltage distribution area according to the second control strategy. The third control unit is used to generate a third control strategy if the three-phase imbalance and load rate of the target low-voltage distribution area meet the third control conditions, and to perform three-phase imbalance control on the controllable equipment in the target low-voltage distribution area according to the third control strategy.