High-voltage equipment inspection missing detection prevention method
By introducing integrated inspection data acquisition equipment and a networked monitoring system into the inspection of high-voltage equipment, the problem of missed inspections in high-voltage equipment inspection has been solved, and effective detection of outdoor components and multiple verifications of inspection quality have been achieved.
Patent Information
- Application Number
- CN202511632336.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-10
- Publication Date
- 2026-02-27
AI Technical Summary
In current high-voltage equipment inspections, especially outdoor components such as insulators and tower foundations, there is a lack of effective testing, leading to frequent missed inspections. Furthermore, networked monitoring systems cannot compensate for the shortcomings of manual inspections.
The system employs inspection and data collection equipment, integrating an LCD display, text input module, digital display clock, camera, audio and video storage module, identity reading module, storage module, transmission module, and power module. Combined with a Beidou satellite positioning device, it enables the equipment to take photos, collect videos, and upload information in real time. Multiple verifications are performed using a networked integrated management and monitoring system.
This ensured the completeness of high-voltage equipment inspections, prevented omissions, improved inspection quality and staff responsibility, and enabled effective testing of outdoor components.
Smart Images

Figure CN121583012A_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to a kind of power equipment inspection method, specifically the present application relates to a kind of high-voltage equipment inspection method. BACKGROUND
[0002] Electric energy is formed by extra-high voltage or high voltage after conversion voltage before entering user, and the electric power equipment mainly has transformer substation, substation, ring network cabinet, transformer, insulator and tower foundation etc., and the normal operation of these electric power equipment is the important support to ensure the safe use of electricity for user, in order to maintain the normal operation of equipment, power system inspection is an important link to ensure the safe and stable operation of power grid, usually involves regular inspection of high-voltage equipment, the inspection frequency is generally 1-2 times per month, and the inspection content mainly includes equipment appearance inspection, temperature monitoring, operation function test and identification of abnormal sound or smell, to ensure that the equipment is in normal state;Most of the current high-voltage equipment are installed with networked integrated management monitoring system, and the networked integrated management monitoring system mainly has monitoring host and communication equipment, fire fighting system and environmental power monitoring system, remote vision system, access control system, fire fighting system and environmental power monitoring system, which realizes equipment state monitoring, remote operation and data analysis to reduce the need of on-site inspection;But for the external state inspection and equipment appearance inspection, it is impossible to do so, and the insulator connected with the equipment, the tower foundation and other outdoor components, especially the drainage condition of machine room after heavy rain, the building condition after heavy snow and the influence of nearby construction, etc. cannot be detected;Therefore, manual inspection is essential, and preventing missed inspection is also an important content to avoid laziness. SUMMARY
[0003] The purpose of the present application is to disclose a kind of high-voltage equipment inspection method based on the existing deficiencies, which uses the clock, satellite positioning, audio and video acquisition function and text report function of inspection collection equipment to ensure the inspection quality of staff, and prevents the missed inspection caused by laziness.
[0004] In order to achieve the purpose of the present application, the following technical solutions are disclosed in the present application: A kind of high-voltage equipment inspection method, the method comprises the following steps: Step A. Confirm the inspection destination; Step B. After the staff receives the inspection collection equipment, fill in the number of staff, inspection destination, safety equipment and work order number by using man-machine interface; Step C. After the staff arrives at the inspection destination, take a photo of the inspection object by using the inspection collection equipment, then take a photo of the staff and the aforementioned inspection destination, the photo taken by the inspection collection equipment contains time stamp and address information, then input the place number information manually; Step D. The inspection collection device uploads the collected information to the data center in real time through the self-provided audio and video storage module and networking transmission module, and uploads the collected information to the cloud storage backup.
[0005] The high-voltage equipment inspection anti-missed inspection method, the inspection collection device comprises a liquid crystal display, a text input module, a digital display clock, a camera, an audio and video storage module, an identity reading module, a storage module, a transmission module and a power module; the liquid crystal display and the text input module fill in the number information of the inspection place; the camera is used for collecting video and taking pictures; the identity reading module is used for identifying the identity information of the staff; the storage module stores the collected information; the transmission module is used for uploading the collected information to the data center and the cloud storage; and the power module is used for providing power supply for the liquid crystal display, the digital display clock, the audio and video collection camera module, the audio and video storage module, the text input module, the identity reading module, the storage module and the transmission module.
[0006] The high-voltage equipment inspection anti-missed inspection method, the inspection collection device comprises a Beidou satellite positioning instrument.
[0007] The high-voltage equipment inspection anti-missed inspection method, the inspection collection device further comprises a switch module.
[0008] The high-voltage equipment inspection anti-missed inspection method, the inspection destination comprises a power substation and equipment appearance, a power station and equipment appearance, a ring network cabinet and equipment appearance, a transformer, an insulator, a high-voltage iron tower, a tower foundation and any equipment required for inspection.
[0009] The high-voltage equipment inspection anti-missed inspection method, the collection object of the inspection collection device further comprises a networked integrated management and monitoring system A of the ring network cabinet, a networked integrated management and monitoring system B of the power substation and a networked integrated management and monitoring system C of the power station.
[0010] Through the above disclosure, the beneficial effects of the present application are: The high-voltage equipment inspection and anti-missing inspection method of this invention acquires images and videos of substations and equipment, ring main units and equipment, transformers, insulators, high-voltage towers, tower foundations, and any other equipment to be inspected during inspection operations by setting up an inspection data acquisition device with an LCD display, text input module, digital display clock, camera, audio and video storage module, identity reading module, storage module, transmission module, and power supply module. The acquired images and videos are uploaded to the power data center in real time using the transmission module, and the power data center confirms the inspection quality of the personnel through algorithm matching. This invention can also use the networked integrated management and monitoring system A of the ring main unit, the networked integrated management and monitoring system B of the substation, and the networked integrated management and monitoring system C of the substation for synchronous detection, realizing multiple verification of inspection quality. Attached Figure Description
[0011] Figure 1 This is an inspection diagram of the inspection and data collection device of the present invention; Figure 2 This is a diagram of the built-in module of the inspection and data collection device of the present invention; In the diagram: 1. Data center; 2. Cloud storage; 3. Networked integrated management and monitoring system A; 4. Ring main unit; 5. Inspection and data acquisition equipment; 6. Substation; 7. Networked integrated management and monitoring system B; 8. High-voltage tower; 9. Networked integrated management and monitoring system C; 10. Substation; 11. Beidou satellite positioning device; 12. Digital display clock; 13. Audio and video storage module; 14. Audio and video acquisition camera module; 15. Text input module. Detailed Implementation
[0012] The preferred embodiments of the present invention will be described in detail below with reference to the accompanying drawings, so as to better understand the inventive objectives, features, and advantages of the present invention. It should be understood that the embodiments shown in the drawings are not intended to limit the scope of the present invention, but are merely illustrative of possible implementations of the technical solutions of the present invention.
[0013] Combined with appendix Figure 1 Alternatively, the high-voltage equipment inspection and leak prevention method described in section 2, the method comprising the following steps: Step A. Confirm the inspection destination, which includes substation 6 and its equipment appearance, substation 10 and its equipment appearance, ring main unit 4 and its equipment appearance, transformers, insulators, high-voltage iron tower 8, tower foundations and any equipment that needs to be inspected; Further, the collection object of the inspection collection device 5 also includes the networked integrated management and monitoring system A3 of the ring network cabinet 4, the networked integrated management and monitoring system B7 of the transformer substation 6 and the networked integrated management and monitoring system C9 of the transformer station 10; during the inspection process, the staff can take pictures with the aid of the foregoing networked integrated management and monitoring system and match the time, place and staff with the data center 1 to increase the prevention of missing inspection; The inspection collection device 5 includes a liquid crystal display, a character input module 15, a digital display clock 12, a camera, an audio and video storage module 13, an identity reading module, a storage module, a transmission module and a power module; the liquid crystal display and the character input module 15 fill in the number information of the inspection place; the camera is used for collecting video and taking pictures; the identity reading module is used for identifying the identity information of the staff; the storage module stores the collected information; the transmission module is used for uploading the collected information to the data center 1 and the cloud storage 2; the power module is used for providing power for the liquid crystal display, the digital display clock 12, the audio and video collection camera module 14, the audio and video storage module 13, the character input module 15, the identity reading module, the storage module and the transmission module; the inspection collection device 5 also includes a switch module for starting the device; the inspection collection device 5 includes a Beidou satellite positioning instrument 11; Step B. After the staff receives the inspection collection device 5, the staff fills in the number of staff, the inspection destination, the safety equipment and the work order number by using the human-computer interface; Step C. After the staff arrives at the inspection destination, the staff takes pictures of the inspection object by using the inspection collection device 5, then the staff takes pictures with the foregoing inspection destination, the pictures taken by the inspection collection device 5 contain time stamp and address information, then the staff manually inputs the place number information; Step D. The inspection collection device 5 uploads the collected information to the data center 1 in real time by using the self-provided audio and video storage module 13 and the networked transmission module, and simultaneously uploads the collected information to the cloud storage 2 for backup.
[0014] The preferred embodiments of the present application have been described in detail above, but it should be understood that, after reading the above description of the present application, those skilled in the art can make various modifications or improvements within the scope of the present application. These equivalent forms also fall within the scope defined by the appended claims of the present application.
[0015] The part not described in detail in the present application is the prior art.
Claims
1. A method for preventing missed inspections during high-voltage equipment inspection, characterized by: The method includes the following steps: Step A. Confirm the inspection destination; Step B. After receiving the inspection data collection equipment (5), the staff will fill in the number of staff, inspection destination, safety equipment and work order number using the human-machine interface. Step C. After arriving at the inspection destination, the staff takes photos of the inspection object through the inspection data collection device (5), and then the staff takes a group photo with the aforementioned inspection destination. The photos taken by the inspection data collection device (5) contain timestamps and address information, and then the staff manually inputs the location number information. Step D. The inspection and collection equipment (5) uploads the collected information to the data center (1) in real time through its built-in audio and video storage module (13) and network transmission module, and at the same time uploads the collected information to the cloud storage (2) for backup.
2. The method for preventing missed inspections during high-voltage equipment inspection according to claim 1, characterized in that: The inspection data collection device (5) includes an LCD display, a text input module (15), a digital display clock (12), a camera, an audio and video storage module (13), an identity reading module, a storage module, a transmission module, and a power module; the LCD display and the text input module (15) are used to fill in the number information of the inspection site; the camera is used to collect video and take pictures; The identity reading module is used to identify the identity information of the staff; the storage module stores the collected information; the transmission module is used to upload the collected information to the data center (1) and cloud storage (2); the power module provides power to the LCD display, digital display clock (12), audio and video acquisition camera module (14), audio and video storage module (13), text input module (15), identity reading module, storage module and transmission module.
3. The method for preventing missed inspections during high-voltage equipment inspection according to claim 2, characterized in that: The inspection and data collection equipment (5) includes a Beidou satellite positioning device (11).
4. The method for preventing missed inspections during high-voltage equipment inspection according to claim 2, characterized in that: The inspection and data collection equipment (5) also includes a switch module.
5. The method for preventing missed inspections during high-voltage equipment inspection according to claim 1, characterized in that: The inspection destinations include substations (6) and their equipment appearance, substations (10) and their equipment appearance, ring main units (4) and their equipment appearance, transformers, insulators, high-voltage towers (8), tower foundations and any equipment that needs to be inspected.
6. The method for preventing missed inspections during high-voltage equipment inspection according to claim 5, characterized in that: The inspection data collection device (5) also collects data from the networked integrated management and monitoring system A (3) of the ring network cabinet (4), the networked integrated management and monitoring system B (7) of the substation (6), and the networked integrated management and monitoring system C (9) of the substation (10).