Lower hanging type concrete pump pipe fixing device and using method thereof

By using a hanging concrete pump pipe fixing device, which incorporates components such as clamps and elastic support frames, the problem of cumbersome and unstable pump pipe fixing in high-rise buildings has been solved, achieving the effects of stability, simplified operation, and improved construction efficiency.

CN122014915APending Publication Date: 2026-05-12CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
CHINA CONSTR SECOND ENG BUREAU LTD
Filing Date
2026-03-20
Publication Date
2026-05-12

AI Technical Summary

Technical Problem

When pouring concrete in high-rise buildings, the traditional method of fixing pump pipes is cumbersome, time-consuming and labor-intensive, and difficult to fix in narrow spaces, which can easily lead to loosening or breakage of the pump pipes, posing safety hazards. It also cannot effectively buffer pump pipe vibration and affect the stability of the frame.

Method used

The concrete pump pipe fixing device is a hanging type, including a first clamp, a second clamp, a positioning steel plate, an elastic support frame and a fixing plate. The pump pipe is fixed by the clamp, the positioning steel plate and the elastic support frame provide stable support and buffering, and the fixing plate is connected to the floor to achieve the stability and buffering of the pump pipe.

Benefits of technology

It achieves fixed installation without the need for pre-embedding, allows for flexible adjustment of the fixing position, simplifies operation, improves work efficiency, enhances the stability and safety of the pump pipe, reduces construction space restrictions, and lowers construction difficulty.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN122014915A_ABST
    Figure CN122014915A_ABST
Patent Text Reader

Abstract

The invention provides a lower hanging type concrete pump pipe fixing device which comprises a pump pipe penetrating through a preset hole of a floor, and further comprises a first clamping hoop fixedly connected to the side wall of the lower portion of the pump pipe, a second clamping hoop fixedly connected to the side wall of the lower portion of the pump pipe and a third clamping hoop fixedly connected to the side wall of the lower portion of the pump pipe. The second hoop is fixedly connected to the side wall of the upper part of the pump pipe; the positioning steel plate is arranged on the lower portion of the floor, and the pump pipe penetrates through the middle of the positioning steel plate; one end of the elastic supporting frame is movably connected to the side wall of the first clamping hoop, and the other end of the elastic supporting frame is rotationally connected to the lower portion of the positioning steel plate; and the fixing clamping plate is arranged on the floor in a matched mode, the upper portion of the fixing clamping plate is fixedly connected with the second clamping hoop, and the lower portion of the fixing clamping plate is fixedly connected to the positioning steel plate. The device is easy and convenient to install and high in applicability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of construction component technology, and in particular to a hanging concrete pump pipe fixing device and its usage method. Background Technology

[0002] Currently, concrete is typically transported using fixed pump pipes in high-rise buildings, factories, and other construction projects. There is currently no device that can fix vertical concrete pump pipes at the top of pipes that are segmented from each floor.

[0003] When the floor height is high, pump pipe supports are usually erected from the bottom using steel pipes and fasteners, or they can be left unsecured. The former involves a cumbersome and time-consuming scaffolding process, which is difficult to carry out in narrow spaces, while the latter is prone to pump pipe cracking due to the lack of securing measures, posing certain safety hazards, as detailed below: (1) When traditionally supporting pump pipes, due to the limited floor height, the upper section of the pump pipe is often not fixed, or only the reserved opening is filled with materials such as wooden blocks for simple fixation. When pumping concrete for a long time, the pump pipe vibrates and the wooden blocks are easily rubbed off and lose their fixing function. If the pumping is not effectively fixed for a long time, the pump pipe joint will become loose or even break. (2) When the traditional fixed mode uses manual erection of pump pipe frame, the frame needs to be erected at a high height when the floor height is high, otherwise it is difficult to effectively fix the upper pump pipe; (3) The transfer of the traditional fixed form of pump pipe rack requires the removal of the outriggers and scaffolding and then the reconstruction, which is a complicated process that is time-consuming and labor-intensive. (4) In the traditional pump pipe rack, the steel pipe and fastener are rigidly connected, which cannot effectively buffer the vibration of the pump pipe. Long-term pumping will also have a certain impact on the stability of the rack. Summary of the Invention

[0004] To address the aforementioned problems, this invention discloses a hanging concrete pump pipe fixing device, comprising a pump pipe passing through a pre-set hole in the floor, and further comprising: The first clamp is fixedly connected to the lower side wall of the pump pipe; The second clamp is fixedly connected to the upper side wall of the pump pipe; both the first clamp and the second clamp are clamped together and fixed to the pump pipe. A positioning steel plate is installed at the lower part of the floor, and the pump pipe passes through the middle of the positioning steel plate; the positioning steel plate determines the position of the pump pipe. The elastic support frame has one end movably connected to the side wall of the first clamp, and the other end rotatably connected to the lower part of the positioning steel plate; the elastic support frame serves as a buffer. A fixing plate is fitted onto the floor, and the upper part of the fixing plate is fixedly connected to the second clamp. The lower part of the fixing plate is fixedly connected to the positioning steel plate. The fixing plate serves to fix components such as pump pipes and positioning steel plates.

[0005] Preferably, the positioning steel plate includes a second plate body, the second plate body having a second through hole in its center, and the pump pipe passing through the second through hole. The second through hole is located in the center of the second plate body, thus positioning the pump pipe.

[0006] Preferably, the fixing plate includes a U-shaped component that hugs the edge of the floor. A second screw is fixedly connected to the lower part of the U-shaped component. A sliding hole is provided on the second plate, through which the second screw passes and is secured with a nut. The U-shaped component is then clamped onto the floor, and the second screw and nut secure the U-shaped component to the positioning steel plate.

[0007] Preferably, a vertical plate is fixedly connected to the upper part of the U-shaped part, and a first screw is fixedly connected to the side wall of the second clamp. The first screw passes through the vertical plate and is fixed with a nut.

[0008] Preferably, the elastic support frame is provided with a second connecting ear and a third connecting ear at both ends, the side wall of the first clamp is provided with a first connecting ear, and the lower part of the second plate is fixedly connected with a fifth connecting ear. The second connecting ear and the third connecting ear are respectively fitted onto the first connecting ear and the fifth connecting ear. Through the second connecting ear, the third connecting ear, the first connecting ear, and the fifth connecting ear, the elastic support frame is respectively connected to the first clamp and the positioning steel plate.

[0009] Preferably, the sidewall of the second plate is provided with an extended steel plate, the extended steel plate including a first plate, on which a fourth connecting lug is provided, and also an elastic support frame and a first clamp connected to the extended steel plate. The elastic support frame has a second connecting lug and a third connecting lug at each end, and the sidewall of the first clamp has a first connecting lug. The second and third connecting lugs respectively fit onto the first and fourth connecting lugs. That is, other elastic supports and first clamps are also provided, connected to the extended steel plate, improving the overall stability of the device.

[0010] Preferably, one end of the second connecting ear is fixedly connected to a pipe fitting, one end of the third connecting ear is fixedly connected to a telescopic rod, and the other end of the telescopic rod is fixedly connected to a limit block. A first spring and a second spring are respectively provided on both sides of the limit block, and the other ends of the first spring and the second spring abut against the inner wall of the pipe fitting. The first spring and the second spring serve as reciprocating buffers. Furthermore, the elastic support frame can be replaced with a spring damping rod.

[0011] Preferably, the first plate has a first through hole on its edge, and the second plate has a third through hole on its edge. A connecting steel plate is clamped between the edges of the first and second plates, and bolts are inserted into the connecting steel plate, passing through the first and third through holes. The connecting steel plate achieves a fixed connection between the first and second plates.

[0012] Preferably, a buffer rubber pad is provided at the upper end of the first plate and / or the second plate, and the upper end of the buffer rubber pad abuts against the lower end surface of the floor. The buffer rubber pad serves to buffer and reduce shock.

[0013] A method for using a hanging concrete pump pipe fixing device involves first securing a fixing plate to the edge of the floor opening, then installing a positioning steel plate below the floor so that a second screw passes through a sliding hole. After adjusting the second through hole to the correct position for pump pipe pouring, tighten the nut on the second screw to achieve a fixed connection between the limiting steel plate and the fixing plate. Next, insert the first screw on the second clamp onto the vertical plate, insert the pump pipe into the second through hole, and then clamp the second clamp onto the pump pipe. Finally, fix the first clamp to the lower side wall of the pump pipe, and install an elastic support frame between the first clamp and the positioning steel plate. In addition, if the lower part of the pump pipe is too long, an additional first clamp can be added to the lower part of the pump pipe, and an extension steel plate can be added to the edge of the positioning steel plate. The additional first clamp and the extension steel plate are also fixed using an elastic support frame.

[0014] The beneficial effects of this invention are as follows: 1. No pre-embedding is required; the lower-hanging bracket, which is fixed to the reserved opening through a fixing plate, serves as a pump pipe fixing device. 2. By using connecting steel plates to increase or decrease the number of supports, the range of support under the bracket can be adjusted according to changes in floor height; 3. The combination of standardized pump pipe clamps and elastic support frames acts as a buffer, ensuring stable installation; 4. Simple to operate and easy to move, improving work efficiency. The position of the fixing clamp can be flexibly adjusted, and it is less affected by the limitation of construction space. Attached Figure Description

[0015] Figure 1 This is a three-dimensional schematic diagram of the present invention; Figure 2 This is a cross-sectional schematic diagram of the present invention; Figure 3 This is a top view of the second clamp of the present invention; Figure 4 This is a top view of the first clamp of the present invention; Figure 5 This is a cross-sectional schematic diagram of the elastic support member of the present invention; Figure 6 This is a schematic diagram of the extended steel plate of the present invention; Figure 7 This is a schematic diagram of the fixing plate of the present invention; Figure 8 This is a schematic diagram of the positioning steel plate of the present invention.

[0016] List of reference numerals in the attached diagram: 1. First clamp; 2. Pump pipe; 3. Elastic support frame; 4. Extended steel plate; 5. Connecting steel plate; 6. Fixing plate; 7. Positioning steel plate; 8. Second clamp; 9. Buffer rubber pad; 10. First screw; 11. First connecting lug; 31. Second connecting ear; 32. Pipe fitting; 33. First spring; 34. Limiting block; 35. Second spring; 36. Telescopic rod; 37. Third connecting ear; 41. First plate; 42. Fourth connecting ear; 43. First through hole; 61. U-shaped piece; 62. Vertical plate; 63. Second screw; 71. Second plate; 72. Second through hole; 73. Sliding hole; 74. Fifth connecting ear; 75. Third through hole. Detailed Implementation

[0017] The present invention will be further illustrated below with reference to the accompanying drawings and specific embodiments. It should be understood that the following specific embodiments are for illustrative purposes only and are not intended to limit the scope of the invention. It should be noted that the terms "front," "rear," "left," "right," "up," and "down" used in the following description refer to directions in the accompanying drawings, and the terms "inner" and "outer" refer to directions toward or away from the geometric center of a specific component, respectively.

[0018] like Figures 1 to 8 As shown, a hanging concrete pump pipe fixing device includes a pump pipe 2, which is used for pumping concrete. The pump pipe 2 passes through a pre-set hole in the floor to pump concrete to the construction area below the floor. It also includes: The first clamp 1 is fixedly connected to the lower side wall of the pump pipe 2. The first clamp 1 has a two-part structure and is fixed to the side wall of the pump pipe 2 by bolts and nuts. The second clamp 8 is fixedly connected to the upper side wall of the pump pipe 2. Similarly, the second clamp 8 is also a two-part structure, which is fixed to the side wall of the pump pipe 2 by bolts and nuts. Positioning steel plate 7 is set at the bottom of the floor. Positioning steel plate 7 is a square piece, and the size of positioning steel plate 7 is larger than the size of the floor opening. Pump pipe 2 passes through the middle of positioning steel plate 7. The elastic support frame 3 has an axial dimension that can be changed. One end of the elastic support frame 3 is movably connected to the side wall of the first clamp 1, and the other end of the elastic support frame 3 is rotatably connected to the lower part of the positioning steel plate 7, providing support and buffering to ensure the stable installation of the pump pipe 2. The fixing plate 6 is fitted onto the floor, meaning the fixing plate 6 is fixed to the floor. The upper part of the fixing plate 6 is fixedly connected to the second clamp 8. The connection between the fixing plate 6 and the second clamp 8 enables the fixing plate 6 to support and fix the pump pipe 2. The lower part of the fixing plate 6 is fixedly connected to the positioning steel plate 7, thus fixing the positioning steel plate 7.

[0019] The positioning steel plate 7 includes a second plate body 71, and a second through hole 72 is provided in the middle of the second plate body 71. The pump pipe 2 passes through the second through hole 72. The second through hole 72 is provided to allow the pump pipe 2 to pass through.

[0020] The fixing plate 6 includes a U-shaped component 61, which hugs the edge of the floor. The U-shaped component 61 allows the fixing plate 6 to be initially set on the floor, and this setting also facilitates the adjustment of the position of the fixing plate 6. The lower part of the U-shaped component 61 is fixedly connected to a second screw 63, which is vertically downward and fixed by welding. The second plate 71 is provided with a sliding hole 73, which is a long through hole. The second screw 63 passes through the sliding hole 73 and is fixed with a nut. During installation, the fixing plate 6 is pre-clamped with the edge of the hole, and then the positioning steel plate 7 is lifted from bottom to top so that the second screw 63 passes through the sliding hole 73. The nut is used to engage the second screw 63 so that the nut supports the positioning steel plate 7. Then, the positions of the fixing plate 6 and the positioning steel plate 7 are further adjusted so that the second through hole 72 is in the designed position. Finally, the nut is tightened to make the fixing plate 6 and the positioning steel plate 7 firmly fixed on the floor.

[0021] A vertical plate 62 is fixedly connected to the upper part of the U-shaped part 61, and a first screw 10 is fixedly connected to the side wall of the second clamp 8. The first screw 10 passes through the vertical plate 62 and is fixed with a nut. The first screw 10 and the second clamp 8 are connected by welding or thread to ensure the stability of the connection. Welding is preferred. After the first screw 10 passes through the vertical plate 62, the vertical pipe 2 passes through the second through hole 72. After the second clamp 8 is fixed on the pump pipe 2, a nut is used to clamp and fix the vertical plate 62 on the second screw 10.

[0022] The elastic support frame 3 is provided with a second connecting ear 31 and a third connecting ear 37 at both ends, the first clamp 1 is provided with a first connecting ear 11 on its side wall, and the lower part of the second plate 71 is fixedly connected with a fifth connecting ear 74. The second connecting ear 31 and the third connecting ear 37 are respectively fitted onto the first connecting ear 11 and the fifth connecting ear 74. A rotating shaft is inserted at the connection point to realize the rotational connection. The rotating shaft uses a bolt with a smooth section, which has the advantage of being easy to use.

[0023] The side wall of the second plate 71 is provided with an extended steel plate 4, which increases the overall working area. During installation, depending on the on-site construction equipment, the extended steel plate 4 and the positioning steel plate 7 can be pre-connected together, or the positioning steel plate 7 can be pre-installed and then the extended steel plate 4 can be installed and finally fixed. The extended steel plate 4 includes the first plate 41, which is provided with a fourth connecting ear 42, and is also provided with an elastic support frame 3 and a first clamp 1 connected to the extended steel plate 4. The two ends of the elastic support frame 3 are respectively provided with a second connecting ear 31 and a third connecting ear 37. The side wall of the first clamp 1 is provided with a first connecting ear 11. The second connecting ear 31 and the third connecting ear 37 are respectively fitted on the first connecting ear 11 and the fourth connecting ear 42, and a rotating shaft is inserted through the connection.

[0024] One end of the second connecting ear 31 is fixedly connected to the pipe fitting 32, and one end of the third connecting ear 37 is fixedly connected to the telescopic rod 36. The other end of the telescopic rod 36 is fixedly connected to the limit block 34. A first spring 33 and a second spring 35 are respectively provided on both sides of the limit block 34, and the other ends of the first spring 33 and the second spring 35 abut against the inner wall of the pipe fitting 32. The springs on both sides enable the telescopic rod 36 to return to its original position after reciprocating motion. In addition, the springs also serve as a buffer. Furthermore, the elastic support frame 3 can be replaced with a spring damping rod or similar component, which, in addition to buffering, also has a shock absorption function.

[0025] The first plate 41 has a first through hole 43 on its edge, and the second plate 71 has a third through hole 75 on its edge. The edges of the first plate 41 and the second plate 71 are clamped together by a connecting steel plate 5. There are two connecting steel plates 5, which clamp the first plate 41 and the second plate 71 from the top and bottom. Bolts are inserted through the connecting steel plates 5 and pass through the first through hole 43 and the third through hole 75. With the help of bolt nuts, the first plate 41 and the second plate 71 are fixedly connected.

[0026] A buffer rubber pad 9 is provided at the upper end of the first plate 41 and / or the second plate 71. The upper end of the buffer rubber pad 9 abuts against the lower end of the floor, which plays a role in buffering and shock absorption.

[0027] The technical means disclosed in this invention are not limited to those disclosed in the above embodiments, but also include technical solutions composed of any combination of the above technical features.

Claims

1. A hanging concrete pump pipe fixing device, comprising a pump pipe (2), wherein the pump pipe (2) passes through a pre-set hole in the floor, characterized in that, Also includes: The first clamp (1) is fixedly connected to the lower side wall of the pump pipe (2); The second clamp (8) is fixedly connected to the upper side wall of the pump pipe (2); Positioning steel plate (7), the positioning steel plate (7) is set at the lower part of the floor, and the pump pipe (2) passes through the middle of the positioning steel plate (7); An elastic support frame (3) is provided, one end of which is movably connected to the side wall of the first clamp (1), and the other end of which is rotatably connected to the lower part of the positioning steel plate (7). A fixing plate (6) is fitted on the floor, and the upper part of the fixing plate (6) is fixedly connected to the second clamp (8), and the lower part of the fixing plate (6) is fixedly connected to the positioning steel plate (7).

2. The under-hanging concrete pump pipe fixing device according to claim 1, characterized in that: The positioning steel plate (7) includes a second plate body (71), a second through hole (72) is provided in the middle of the second plate body (71), and the pump pipe (2) passes through the second through hole (72).

3. The under-hanging concrete pump pipe fixing device according to claim 2, characterized in that: The fixed plate (6) includes a U-shaped part (61) and the U-shaped part (61) hugs the edge of the floor. The lower part of the U-shaped part (61) is fixedly connected to a second screw (63). The upper part of the second plate (71) is provided with a sliding hole (73). The second screw (63) passes through the sliding hole (73) and is fixed with a nut.

4. The under-hanging concrete pump pipe fixing device according to claim 3, characterized in that: The upper part of the U-shaped part (61) is fixedly connected to a vertical plate (62), and the side wall of the second clamp (8) is fixedly connected to a first screw (10). The first screw (10) passes through the vertical plate (62) and is fixed with a nut.

5. A hanging concrete pump pipe fixing device according to claim 2, characterized in that: The elastic support frame (3) is provided with a second connecting ear (31) and a third connecting ear (37) at both ends, the first clamp (1) is provided with a first connecting ear (11) on its side wall, and the lower part of the second plate (71) is fixedly connected with a fifth connecting ear (74). The second connecting ear (31) and the third connecting ear (37) are respectively fitted on the first connecting ear (11) and the fifth connecting ear (74).

6. The under-hanging concrete pump pipe fixing device according to claim 2, characterized in that: The second plate (71) has an extended steel plate (4) on its side wall. The extended steel plate (4) includes a first plate (41). The first plate (41) has a fourth connecting ear (42) and is also provided with an elastic support frame (3) and a first clamp (1) connected to the extended steel plate (4). The elastic support frame (3) has a second connecting ear (31) and a third connecting ear (37) at both ends. The first clamp (1) has a first connecting ear (11) on its side wall. The second connecting ear (31) and the third connecting ear (37) are respectively fitted onto the first connecting ear (11) and the fourth connecting ear (42).

7. A hanging concrete pump pipe fixing device according to claim 5 or 6, characterized in that: One end of the second connecting ear (31) is fixedly connected to a pipe fitting (32), and one end of the third connecting ear (37) is fixedly connected to a telescopic rod (36). The other end of the telescopic rod (36) is fixedly connected to a limiting block (34). A first spring (33) and a second spring (35) are respectively provided on both sides of the limiting block (34), and the other ends of the first spring (33) and the second spring (35) abut against the inner wall of the pipe fitting (32).

8. A hanging concrete pump pipe fixing device according to claim 6, characterized in that: The first plate (41) has a first through hole (43) on its edge, and the second plate (71) has a third through hole (75) on its edge. The edges of the first plate (41) and the second plate (71) are clamped together by a connecting steel plate (5). Bolts are inserted through the connecting steel plate (5) and pass through the first through hole (43) and the third through hole (75).

9. A hanging concrete pump pipe fixing device according to claim 6, characterized in that: The upper end of the first plate (41) and / or the second plate (71) is provided with a buffer rubber pad (9), the upper end of which abuts against the lower end of the floor.